[0001] The present invention relates to batch heating of billets or ingots in industrial
furnaces.
[0002] In such heating a final homogeneous temperature throughout the heated material is
often the objective. For example, to ensure that subsequent machining is effective
and to avoid damage to the material due, among other things, to shearing forces during
such machining, the difference between the surface temperature of the material and
the temperature at its centre must in many cases not exceed a particular predetermined
value.
[0003] The required final temperature of the material can be achieved by controlling the
temperature of the furnace atmosphere so that it asymptotically converges to the required
final temperature. This convergence is normally controlled by means of a control regulator
which controls the heating power introduced into the furnace and which uses the temperature
of the furnace atmosphere as an input variable. This provides effective control of
the furnace temperature for the purpose of obtaining the required final temperature
in the material quickly.
[0004] However, it is difficult to know the time at which the temperature is sufficiently
homogeneous throughout the heated material. The reason for this is that on the one
hand the surface of the material comparatively quickly assumes approximately the same
temperature as the furnace atmosphere. On the other hand, the centre temperature of
the material takes a longer time to approach the temperature of the furnace atmosphere,
due to heat conduction. Since no cheap and at the same time effective method of measuring
the temperature in the centre of the material is known, empirically determined heating
times have hitherto had to be relied upon to ensure that the temperature differences
in the billet or ingot are not too large when the heating process is interrupted.
[0005] The drawback of such an approach is that a very good margin must be provided to ensure
that temperature differences inside the material do not become too large, which is
why the heating time often becomes unnecessarily long. The reason for this is, among
other things, that the actual conducting of the process gives rise to several sources
of uncertainty and that the original temperature distribution in the material is often
not fully known. This results in increased energy and time consumption, with the accompanying
increases in costs and environmental pollution. Moreover, suSch long heating times
may result in damage to the material, e.g. due to exaggerated oxidation, which naturally
increases the cost of the method and complicates it.
[0006] The present invention solves the above problems.
[0007] The present invention thus relates to a method for heating billets or ingots in an
industrial furnace by means of at least one burner, in which furnace the heating power
continuously introduced into the furnace is controlled by means of a regulator whose
input parameter is the temperature of the furnace atmosphere, which temperature is
measured by means of a temperature measuring device, wherein the regulator is caused
to control the heating in at least one first heating step and a subsequent second
temperature equalising step, and is characterised in that the instantaneous heating
power is measured continuously, in that the derivative of the heating power with respect
to time is calculated continuously, and in that the heating is interrupted when a
primary condition, namely that this derivative falls within a predetermined interval,
is met, provided that the heating at this time is in the subsequent second temperature
equalising step.
[0008] The invention will now be described in detail with reference to an exemplary embodiment
of the invention and the attached drawings, in which:
- Figure 1 shows a general view of an industrial furnace in which the method of the
invention is applied; and
- Figure 2 shows a collection of four explanatory and simplified graphs which explain
the method of the invention.
[0009] Figure 1 shows an industrial furnace 1 in which an ingot 2 is arranged to be heated
batchwise. However, it should be realised that the method of the invention can also
be used in furnaces where slabs and billets of different types are heated. The method
of the invention is advantageously also used for batch heating of a plurality of ingots,
billets or slabs simultaneously.
[0010] The industrial furnace 1 comprises at least one burner 3, which heats the atmosphere
of the furnace 1. The burner or burners 3 may, for example, be driven by means of
a gaseous or liquid fuel and air or oxygen gas as oxidant, but other operating configurations
may also be used. A particularly preferred burner is a so-called oxyfuel burner whose
oxidant consists of at least 80% oxygen gas.
[0011] At least one temperature measuring device 4, which measures the temperature of the
furnace atmosphere and feeds it as an input parameter to a regulator 5 of the PID
type (Proportional, Integral, Derivative), is also arranged in the furnace 1. This
regulator 5 generates an output signal in the form of a desired heating power of the
burner or burners 3. The output signal is fed to a flow regulator 6 which converts
the required heating power to a certain flow of fuel and oxidant, which flow is fed
from the flow regulator 6 to the burner or burners 3.
[0012] The output signal from the regulator 5 is generally less volatile than the resultant
flow from the flow regulator 6, since the flow regulator 6, unlike the regulator 5,
must take into consideration, among other things, the operating limitations of the
burner or burners 3. The flow resulting from the flow regulator 6 thus constitutes
an approximation of the ideal output signal of the regulator 5.
[0013] The burner or burners 3 heat(s) the furnace atmosphere, which in turn heats the ingot
2.
[0014] Figure 2 shows four principal and simplified, explanatory graphs in which the scale
of the X-axis is identical for all four graphs and indicates the time. At the time
T
0, the ingot 2 is fed into the furnace 1.
[0015] The heat treatment is divided into two steps, herein referred to as a first heating
step and a second heating step, or alternatively a second temperature equalising step,
respectively. During the heating step the power of the burner 3 is relatively high,
the purpose of which is to heat the furnace atmosphere quickly. During the temperature
equalising step, the power is continuously controlled by means of the PID regulator
5 for the purpose of achieving a sufficiently uniform temperature distribution in
the ingot 2 as quickly as possible.
[0016] The top graph shows the time development for the temperature T
furnace in the atmosphere of the furnace 1, the temperature T
surface on the surface of the ingot 2, and the temperature T
centre in the centre of the ingot 2. The desired final temperature T
ref is also shown as a dotted horizontal line. In the present embodiment the temperature
T
furnace of the furnace atmosphere is higher than the surface temperature T
surface of the ingot 2 when the ingot 2 is introduced into the furnace 1. Thus, the temperature
T
furnace of the furnace atmosphere initially drops as a result of the cooling effect of the
ingot 2, then increases again after a certain time as a consequence of the heating
power from the burner or burners 3.
[0017] The top but one graph shows the time development for the power P instantaneously
discharged by the burner or burners 3, and a straight horizontal line P
cond that represents an interruption condition. As shown in the graph, the heating power
P of the burner or burners 3 is set during the heating step to a relatively high,
constant level. The purpose of this is to increase the temperature T
furnace and the temperatures of the ingot 2 quickly before the temperature equalising step,
which begins at the time T
1.
[0018] During the temperature equalising step, P is controlled by the PID regulator 5, with
T
furnace as input parameter, which in turn controls through its output signal the flow regulator
6, in turn controlling the flow of fuel and oxidant to the burner or burners 3 for
the purpose of obtaining the desired final temperature T
ref as quickly as possible. When T
furnace has stabilised sufficiently close to T
ref, it may be concluded that the surface temperature T
surface of the ingot 2 and its centre temperature T
centre have also reached sufficient, and sufficiently homogeneous, temperatures.
[0019] T
furnace is therefore measured and fed as an input parameter to the PID regulator 5, which
in turn, by controlling the flow regulator 6, indirectly controls the heating power
P. The purpose of this control is, in a conventional manner, to cause T
furnace to approach the desired final temperature T
ref as effectively as possible.
[0020] The bottom graph shows the time development for the accumulated thermal energy PAck
given by the burner or burners 3, together with a straight horizontal line PAck
cond, which represents an interruption condition.
[0021] The top graph shows that the surface temperature T
surface of the ingot 2 and its centre temperature T
centre increase at different rates during the heating. Due to heat conduction, T
surface increases more quickly than does T
centre. Due among other things to different furnace configurations and different dimensions
of the heated material, this difference in heating is of varying preponderance. However,
a common feature is that at the time T
2, when the ingot 2 is removed from the furnace 1, it is desirable for the difference
between T
surface and T
centre to be less than a certain predetermined value to avoid the problems described above
in subsequent machining steps.
[0022] Instead of allowing the heating process to run for such a long time as to guarantee
adequate temperature equalisation, the present invention solves this problem by examining
the behaviour of the curve P.
[0023] Accordingly, the value P is observed continuously and its time derivative dP/dt is
calculated.
[0024] The instantaneously discharged power P of the burner or burners 3 can be measured
in several different ways. Firstly, P can be measured indirectly by observing the
output signal of the regulator 5. In this case an ideal, desired value is obtained
for P, which does not necessarily correspond to the power actually discharged instantaneously
at a certain moment. On the other hand, this ideal value is a measure of the desired
burner power given the current development of furnace temperature T
furnace. For reasons described in detail below, this method of measuring P in certain embodiments
is therefore preferred according to the present invention. Secondly, the power P can
be measured by measuring the flow from the flow regulator 6, either by means of a
flow meter or by reading off the flow directly from the flow regulator 6. This alternative
measuring method gives a measured value which more closely corresponds to the power
actually discharged instantaneously from burner or burners 3, but on the other hand
contains more noise relative to the desired power calculated by the regulator 5.
[0025] The next but bottom graph shows the time development for dP/dt, as well as two straight
horizontal lines dP/dP
cond1, dP/dP
cond2, which together represent an interruption condition. As will be realised from the
combination of the next but top and next but bottom graphs, dP/dt is initially approximately
zero in the present exemplary embodiment, then passes from the first heating step
and into the PID control phase, i.e. the second heating step, via a not necessarily
continuous transition at the time T
1. During this phase the derivative dP/dt will vary according to the PID control of
P.
[0026] Surprisingly, it has been found that empirically based conditions for dP/dt can be
formulated, thus making it possible to estimate, very accurately, the time T
2 at which the heating process can be interrupted and the ingot 2 can be removed from
the furnace 1 for subsequent machining steps without heating ingot 2 for an unnecessarily
long time, whilst at the same time achieving sufficient temperature homogeneity in
the ingot 2.
[0027] Correspondingly, time T
2 is selected according to the present invention as the time at which a primary condition
is met, in other words the time at which dP/dt falls within a certain predetermined
interval [dP/dP
cond1, dP/dP
cond2], determined on the basis of experience and dependent on a number of factors such
as the dimensions and shape of the heated material, the furnace type, the number of
burners, the characteristics of the regulator 5 and the flow regulator 6, desired
maximum temperature difference between T
surface and T
centre and so on. The interval [dP/dP
cond1, dP/dP
cond2] is preferably symmetrical around dP/dt = 0.
[0028] To prevent the heating process from being interrupted too early, it must also be
ensured that the method has reached the temperature equalising second heating step.
According to an exemplary embodiment this can be done by ensuring that two secondary
conditions are met simultaneously.
[0029] A first secondary condition is that the absolute value of P must be below a certain
first predetermined value P
cond. It is preferable for this first predetermined value P
cond to be selected so that it is below the value of P during the initial phase or an
early phase, between T
0 and T
1, to prevent the heating process from being interrupted already during the first heating
step.
[0030] A second secondary condition is that the total thermal energy supplied, PAck, must
exceed a certain second predetermined value PAck
cond. This second predetermined value PAck
cond is selected to prevent premature interruption of the heating process, preferably
so that it exceeds the minimum quantity of energy which is theoretically required
to heat the ingot 2 to the desired final temperature distribution with the desired
minimum temperature homogeneity and with a heating efficiency suitable for the system.
[0031] It is realised that the purpose of the second secondary condition is to prevent premature
interruption of the heating process and that this purpose is achieved by not allowing
such interruption to take place before a minimum quantity of thermal energy has been
supplied. Approximate and/or indirect measures of PAck can thus be used to determine
whether the second secondary condition has been met or not. For example, the time
from the beginning of the heating process may be measured, and given that P, as a
function of time, is approximately known, this time can be used as an approximate
and indirect measure of PAck. Similarly, many other metrics can be used to determine,
approximately and/or indirectly, whether the second secondary condition has been met,
for example the position of fuel valves, measured fuel pressures, etc.
[0032] The total thermal energy supplied, PAck, is preferably measured indirectly by measuring
the total quantity of fuel introduced into the furnace 1 since heating began.
[0033] When both secondary conditions are met, it is certain that the heating method is
in the temperature equalising phase between T
1 and T
2, i.e. in the second temperature equalising step. During this phase, the furnace 1
is in a form of dynamic thermal equilibrium. The temperature of the furnace wall has
thus been largely stabilised, as has the degree of thermal losses through the wall.
In principle, the flue gases maintain a constant temperature and flow. In practice
it is mainly the ingot 2 that changes temperature during this temperature equalising
phase. In other words, the dependence between P and T
centre is relatively direct, which is why the PID control of P has a relatively clear, and
delayed, effect on the variation of T
centre. Conversely, because the PID control is a predictable process under uniform conditions,
the variation in P induced by the PID control will depend on the variation over time
in T
centre, and also on the instantaneous value of T
centre. Because of these relations, it has been found that it is possible to use the value
of dP/dt to predict when the value of T
centre will exceed a certain value.
[0034] This can be realised by considering a somewhat simplified expression of the total
power supplied P
tot expressed as a function of the surface area A of a heated ingot, the thermal conductivity
of the heated material λ, the distance ΔD between the surface of the material and
its centre, and the temperature difference ΔT between the surface and the centre,
and at the above described dynamic equilibrium, i.e. when the surface temperature
of the heated material has reached the final temperature in the furnace:
in which P
material and P
losses, respectively, are those proportions of the total power supplied that are transferred
to the material in the form of thermal energy and that disappear from the system in
form of losses, respectively.
[0035] In the case of dynamic equilibrium, P
losses is built up from two components. Firstly, losses occur in the form of thermal energy
in the outgoing flue gases. These are approximately linear as a function of P
tot. Secondly, other losses occur which are approximately constant over time where there
is dynamic equilibrium, since the temperature conditions are approximately constant
over time in the furnace, besides inside the heated material itself, as described
above.
[0036] Furthermore, A, λ and ΔD are approximately constant throughout the heating process,
which is why P
material is essentially a function of ΔT. In fact, it has been found that in the case of the
dynamic equilibrium described above, the derivative of P
material with respect to time is approximately a linear function of ΔT, referred to below
as F(ΔT).
[0037] In other words, the following applies under dynamic equilibrium:
in which k
1 and k
2 are constants and since F(ΔT) is an approximately linear function. Since T
surface is known and constant when the dynamic equilibrium described above prevails, the
time derivative of P
tot can thus be used to approximately calculate the temperature T
centre in the centre of the heated material.
[0038] Finally, since the specific operating conditions may vary somewhat, it has been found
that it is easier to use empirically based interruption conditions than mathematically
calculated conditions. The above derivation is therefore intended mainly to explain
the principle behind the present invention.
[0039] In Figure 2, the dotted surface illustrates the area in which both secondary conditions
are met. At the time T
2 the primary condition is also met, and the heating may thus be interrupted.
[0040] Because of the operating conditions, that actually vary, and the generally varying
conditions that prevail during heating of material in industrial furnaces, the PID
control of P will have a relatively high variance. As described above, this variance
will be somewhat higher if P is measured at the flow regulator 6 rather than at the
regulator 5.
[0041] In other words, P will generally vary as a relatively smooth function as the negative
derivative increases during the period between T
1 and T
2, but with a noise component of varying intensity. Whenever applicable, this noise
component can be filtered off by averaging P over a number of measuring points that
depends on the current application, preferably at least 10 measuring points. It is
also possible, and preferable, to have the number of points used in the formation
of the mean value vary as a function of how high the variance of P currently is. Thus,
more points are used in the formation of the mean value at high instantaneous variance,
and reversely fewer points at low instantaneous variance. For example, the variance
may be lower during the beginning of the temperature equalising second heating step
and higher during its final stage. For the sake of clarity, and to give an example,
a mean value has been formed over 10 historical measuring points for P in the next
but bottom graph of dP/dt.
[0042] Moreover, there may be greater justification, for example, in forming a mean value
over more points if P is measured at the flow regulator 6. The flow of fuel and oxidant
controlled by the flow regulator 6 contains a further noise component relative to
the output signal generated by the regulator 5, as described above. One reason for
this is that the flow regulator 6 controls the burner or burners 3, in certain applications,
to heat the furnace 1 by an on/off procedure. This may, for example, depend on the
fact that the burner or burners 3 has (have) a minimum power which exceeds the heating
power prescribed by the PID regulator 5, which heating power is to be discharged to
the furnace atmosphere at a certain given occasion. In this case, for example, the
flow regulator 6 controls the burner or burners 3 to be switched on for a certain
period of time after which it (they) are switched off and then repeat(s) this process
so that the mean power emitted will be that prescribed by the PID regulator 5 during
each given period of time. This method is called pulse width modulation.
[0043] It is also possible for the flow regulator 6 to use constant times for the switched-on/switched-off
position, respectively, and instead to vary the power of the burner or burners 3 during
the switched-on position, thereby achieving the same correct average heating power.
This is called pulse height modulation.
[0044] Other modulation techniques are also possible, for example a combination of pulse
width modulation and pulse height modulation, to achieve an average instantaneous
heating power which corresponds to that prescribed by the PID regulator 5 during a
certain given period of time.
[0045] When such a modulation is used, combined with measurement of P at the flow regulator
6, it is also possible, advantageously, to average the curve P over a number of measuring
points in order to arrive at a corresponding continuous function from which dP/dt
can be determined. In the same manner as above, at least 10 measuring points are preferably
used for the mean value formation, but it is also preferable to vary the number of
measuring points as a function of the variance of P. For example, the modulation will
very likely be greater or more prevalent during the final stage of the heating process,
when T
centre approaches its desired final temperature.
[0046] In the present exemplary embodiment, the regulator 5 is of the PID type, but it should
be realised that also other types of regulators can be used when applying the method
of the present invention. In such cases the criteria of the present invention for
interrupting the heating may need to be modified to suit the prevailing conditions.
For example, it may also be necessary to examine the second derivative with respect
to time of the heating power curve in the case where a regulator used can bring about
a build-up of the furnace temperature, where the derivative of the heating power is
zero once or several times before the furnace temperature eventually approaches its
final value.
[0047] The present invention thus provides a method that enables a heating process to be
interrupted with greater certainty in an industrial furnace when there is sufficient
temperature uniformity in the material, without the need to continue the heating process
for an unnecessarily long period, with the associated drawbacks in terms of long heating
times, high energy costs and material damage. Moreover, the investment cost for applying
the present invention to existing industrial furnaces is low, because sensors or corresponding
devices required to measure or observe emitted power and furnace temperature are often
already installed. In these cases it is therefore sufficient to implement the actual
interruption condition, which can be achieved at relatively low cost.
[0048] Exemplary embodiments have been described above. However, the invention may be varied
without departing from the concept of the invention. The present invention must not
therefore be considered to be limited by these exemplary embodiments but can be varied
within the scope of the attached claims.
1. A method for heating billets or ingots (2) in an industrial furnace (1) by means of
at least one burner (3), in which furnace (1) the heating power (P) continuously introduced
into the furnace (1) is controlled by means of a regulator (5) whose input parameter
is the temperature (Tfurnace) of the furnace atmosphere, which temperature (Tfurnace) is measured by means of a temperature measuring device (4), wherein the regulator
(5) is caused to control the heating in at least one first heating step and a subsequent
second temperature equalising step, characterised in that the instantaneous heating power (P) is measured continuously, in that the derivative of the heating power (P) with respect to time (dP/dt) is calculated
continuously, and in that the heating is interrupted when a primary condition, namely that this derivative
(dP/dt) falls within a predetermined interval ([dP/dPcond1, dP/dPcond2]), is met, provided that the heating at this time is in the subsequent second temperature
equalising step.
2. A method according to Claim 1, characterised in that the heating is considered to be in the subsequent second temperature equalising step
if both a first secondary condition, namely that the absolute instantaneous heating
power (P) is below a first predetermined value (Pcond), and a second secondary condition, namely that the total thermal energy (PAck) introduced
into the furnace (1) since the beginning of the heating exceeds a second predetermined
value (PAckcond), are met at the same time as the said primary condition.
3. A method according to Claim 1 or 2, characterised in that the instantaneous heating power (P) at any time is determined indirectly by continuously
measuring the quantity of fuel per unit time introduced into the industrial furnace
(1).
4. A method according to Claim 1 or 2, characterised in that the instantaneous heating power (P) at any time is determined as an ideal and desired
heating power calculated by the regulator (5).
5. A method according to Claim 1 or 2, characterised in that the regulator (5) is caused to control a flow regulator (6), which in turn is caused
to control the heating power supplied to the industrial furnace (1), and in that the instantaneous heating power (P) is determined at any time as the heating power
modulated by the flow regulator (6).
6. A method according to Claims 2, 3, 4 or 5, characterised in that the first predetermined value (Pcond) consists of the heating power emitted into the furnace (1) during an early stage,
or a lower value.
7. A method according to any one of Claims 2 - 6, characterised in that the second predetermined value (PAckcond) consists of the theoretical energy which is at least required to heat the material
(2) to the required final temperature distribution or higher with a heating efficiency
suitable for the system.
8. A method according to any one of the preceding claims, characterised in that the variance over time of the heating power (P) is caused to be reduced by means
of a first mean value formation over several consecutive measuring points, before
calculation of the derivative of the heating power with respect to time (dP/dt).
9. A method according to any one of the preceding claims, characterised in that when pulse width modulation, pulse height modulation or combinations of these are
used to control the heating power (P) introduced continuously into the furnace (1),
a corresponding continuous heating power function is calculated by means of a second
mean value formation over several consecutive measuring points of the heating power
(P), and in that the corresponding continuous heating power function is used to calculate the derivative
(dP/dt).
10. A method according to Claim 8 or 9, characterised in that the first and/or second mean value formation over several consecutive measuring points
make(s) use of at least 10 consecutive points.
11. A method according to Claim 8 or 9, characterised in that the first and/or second mean value formation over several consecutive measuring points
make(s) use of a number of consecutive points where the number of points varies depending
on the instantaneous variance of the heating power over time.
12. A method according to any one of the preceding claims, characterised in that the interval ([dP/dPcond1, dP/dPcond2]) is symmetrical around 0.
13. A method according to any one of the preceding claims, characterised in that the burner (3) is an oxyfuel burner.