(19) |
|
|
(11) |
EP 2 851 468 B1 |
(12) |
EUROPEAN PATENT SPECIFICATION |
(45) |
Mention of the grant of the patent: |
|
05.04.2017 Bulletin 2017/14 |
(22) |
Date of filing: 23.09.2014 |
|
(51) |
International Patent Classification (IPC):
|
|
(54) |
Mounting assembly for a rail
Montageanordnung für eine Schiene
Ensemble de montage pour rail
|
(84) |
Designated Contracting States: |
|
AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL
NO PL PT RO RS SE SI SK SM TR |
(30) |
Priority: |
23.09.2013 NL 2011485
|
(43) |
Date of publication of application: |
|
25.03.2015 Bulletin 2015/13 |
(73) |
Proprietor: HTM Personenvervoer N.V: |
|
2511 CJ Den Haag (NL) |
|
(72) |
Inventors: |
|
- Van Buuren, Bas Christiaan
2729 CE Zoetermeer (NL)
- Van Buuren, Andreas Jozef Petrus Stephanus
2492 SP Den Haag (NL)
|
(74) |
Representative: Geurts, Franciscus Antonius |
|
Octrooibureau Vriesendorp & Gaade B.V.
Koninginnegracht 19 2514 AB Den Haag 2514 AB Den Haag (NL) |
|
|
|
Note: Within nine months from the publication of the mention of the grant of the European
patent, any person may give notice to the European Patent Office of opposition to
the European patent
granted. Notice of opposition shall be filed in a written reasoned statement. It shall
not be deemed to
have been filed until the opposition fee has been paid. (Art. 99(1) European Patent
Convention).
|
BACKGROUND OF THE INVENTION
[0001] The invention relates to a mounting assembly for mounting a rail to a concrete foundation
of a railbed. Several mounting assemblies are used distributed along the length of
the rail for securing the rail to the concrete foundation. The concrete foundation
keeps the rails properly positioned.
[0002] A railbed with a concrete foundation is used for tram tracks, wherein apart from
the tram other road traffic should also be able to pass the railbed without being
hindered by the rails. For that purpose a concrete upper layer and a thinner asphalt
layer in which the rails are recessed, are disposed over the concrete foundation.
[0003] A known mounting assembly comprises a mounting part on which the rail sits, and two
anchor bolts with a broadened head and thread which with the head downwards and the
thread upwards are poured into the concrete foundation. After the concrete has hardened
the threads protrude from the concrete foundation through holes in the mounting part.
Tensioning clamps are placed over the threads which clamps engage onto the foot of
the rail. The tensioning clamps are secured by means of nuts that are tightened around
the threads.
[0004] The concrete foundation has a lifespan of over 60 years. On sections of tracks that
are loaded lightest, namely the straight sections of track outside the stops, the
rails have an average lifespan of 30 years. In bends where the rails are laterally
loaded by the wheels, and at stops where the tram wheels exert traction forces and
braking forces on the rails, the rails have a much shorter lifespan of 6 years on
average. After the lifespan the rails are replaced entirely. When replacing the rails
the asphalt layer and the concrete upper layer are broken away using a wrecking hammer
so that the threads of the anchor bolts are exposed again.
[0005] In principle the nuts can be unscrewed when replacing the rails so that the tensioning
clamps come off again. Due the violence of the wrecking hammer however, they may have
been damaged and the threads and the nuts often have been exposed to a corrosive environment
for many years. The anchor bolts that were embedded thus cannot be reused anymore.
As the anchor bolts can no longer be removed from the concrete foundation due to the
broadened head, the concrete foundation also needs to be fully demolished whereas
its technical lifespan has by no means been reached yet. Building up a new concrete
foundation and thus an entirely new railbed, results in a long disruption of tram
services. Sufficient hardening of the new concrete foundation needs to be waited for
in order to prevent that the anchor bolts that were embedded while pouring will rotate
along with the nut.
[0006] EP-A-1.709.249 discloses a mounting assembly for mounting a rail to a concrete foundation of a railbed
according to the preamble of claim 1, and implies a method for building a railbed
by means of such mounting assembly according to the preamble of claim 12.
[0007] The mounting assembly disclosed herein is an alternative to the mounting assembly
that is described herebefore. The assembly known from
EP-A-1.709.249 comprises steel screw bolts with counter-rotating threads at the lower end to which
plastic anchors are formed. The lower ends of the anchors are poured into the concrete
foundation. The assembly is finally mounted to the foundation by means of nuts around
the fine-threaded upper side of the screw bolts.
[0008] It is an object of the invention to provide a mounting assembly for mounting a rail
to a concrete foundation with which during the first construction of the concrete
layer the rails can soon be secured to the hardening concrete.
[0009] It is an object of the invention to provide a mounting assembly for mounting a rail
to a concrete foundation, with which rails, that are successive over time, can be
mounted to the same concrete foundation.
[0010] It is an object of the invention to provide a mounting assembly for mounting a rail
to a concrete foundation of which the components in the concrete foundation can be
reused.
SUMMARY OF THE INVENTION
[0011] According to one aspect the invention provides a mounting assembly for mounting a
rail to a concrete foundation of a railbed according to claim 1.
[0012] The mounting assembly according to the invention can temporarily be suspended from
a rail with the plugs oriented downward. Said rail can be positioned over a basis
of the concrete foundation to be poured. After pouring the concrete foundation the
plugs sit in the hardening concrete. Due to the fixed distance between the head and
the mounting part as provided by the shape-retaining auxiliary pieces, the screws
need not be screwed fully into the plug. Said temporary mounting is easily formed
and released again by hand. The form lock prevents the plugs from rotating along with
the screw to be screwed in from above. The screws are for instance collar-sleeper
screws having a square head that are screwed in mechanically. The shape-retaining
auxiliary piece is removed before tightening the screws. As a result the screws can
already be tightened from the moment the concrete has a sufficient initial hardening
for securing the mounting assembly with the rail thereon. Said initial hardening is
much lower than the hardening required for counteracting that the known anchor bolts
that were embedded while pouring, rotate along. As a result the railbed can be finished
immediately after the initial hardening. When the rail needs to be replaced the screws
can be unscrewed from the plugs from above. The plugs and thus the concrete foundation,
can be reused for another rail, wherein optionally only the properly accessible mounting
part needs to be replaced.
[0013] In one embodiment at the lower side facing the plug, the second coupling member comprises
a slot below the mounting opening, wherein at the upper side facing the mounting part,
the first coupling member comprises a first broadening extending into the slot, wherein
transverse to the centre line the first broadening has a noncircular contour. Due
to the noncircular contour rotation of the plug relative to the mounting part is blocked
within the slot.
[0014] In one embodiment thereof the slot is elongated and has two parallel inner surfaces,
wherein the first broadening has two parallel outer surfaces for abutting the inner
surfaces. Due to the outer surfaces abutting the inner surfaces a firm form lock is
effected that may be free of play.
[0015] In one embodiment at the lower side facing away from the mounting part the plug is
provided with a second broadening. The second broadening constitutes an anchoring
of the plug deep into the concrete foundation, as a result of which already at the
initial hardening, the concrete foundation is amply capable of withstanding the tensile
forces exerted by the screws.
[0016] In one embodiment thereof, transverse to the centre line, the second broadening has
a noncircular contour, so that in addition to the form lock with the mounting part
it is also counteracted within the concrete foundation that the plugs rotate along.
[0017] In one embodiment the second broadening has an anchoring surface facing the mounting
part and being transverse to the centre line. In that way it can be counteracted that
the concrete foundation ruptures along the plugs.
[0018] In one embodiment the plug has a straight bush having a circle-cylindrical smooth
outer surface up to the second broadening. The concrete will then hardly adhere to
the plugs and the plugs are free to make a short stab in the hardening concrete without
consequences to the later retaining force. As a result it is possible to allow trams
to drive slowly over the rails although the concrete foundation has not yet hardened
and the screws are not yet tightened.
[0019] In one embodiment the plugs are made of synthetic material, preferably polyamide.
[0020] In one embodiment the mounting part comprises a mounting member for supporting the
rail and a separate underlying plate below the mounting member, wherein the underlying
plate is provided with the second coupling members. After exposing the old concrete
foundation, for instance by breaking the old concrete upper layer away, a selection
can be made which of these components can be reused for securing a new rail.
[0021] In one embodiment thereof the underlying plate comprises a straight and smooth undersurface
for partial accommodation in the concrete foundation. The straight and smooth undersurface
leaves a flat recess in the concrete foundation in which later on an identical or
slightly smaller underlying plate can easily be fitted.
[0022] In one embodiment the underlying plate is made of synthetic material, preferably
polyamide.
[0023] In one embodiment thereof the auxiliary pieces engage onto the foot of the rail,
so that they simultaneously ensure the temporary suspension from the rail, which is
ended when removing the auxiliary pieces.
[0024] In one embodiment thereof the foot of the rail comprises two opposite end edges and
the mounting part and the auxiliary pieces jointly confine the end edges, so that
a sideward shifting of the mounting assembly relative to the rail is counteracted.
[0025] In one embodiment the auxiliary pieces are provided with a passage for the screw,
wherein the passage towards the rail is opened for sideward insertion of the auxiliary
piece towards the rail. The auxiliary piece can thus easily be placed and subsequently
be removed again, without the rail being a hindrance.
[0026] In one embodiment the mounting part comprises a straight undersurface for supporting
the foot of the rail, wherein the auxiliary pieces are provided with a straight support
surface for the head which surface extends parallel to the undersurface.
[0027] In one embodiment the mounting part comprises a straight undersurface for supporting
the foot of the rail, wherein beyond the foot of the rail the straight undersurface
merges into concave lowerings, wherein the auxiliary pieces are provided with a convex
lower side fitting in the concave lowerings. The form fit ensures a properly secured,
temporary positioning of the auxiliary pieces relative to the mounting part.
[0028] In one embodiment the auxiliary pieces comprise auxiliary bushes around the screws
which bushes at the upper side abut the heads of the screws and which at the lower
side abut the mounting part, wherein at the lower side the screws extend into the
plugs and keep the coupling members in coupling cooperation. The auxiliary bushes
can be temporarily disposed for ensuring the coupling cooperation of the coupling
members while the mounting assembly is still suspended over the basis of the concrete
foundation to be poured. The auxiliary bushes ensure that the screws only need to
be partially screwed in. This can be done manually.
[0029] In one embodiment the mounting part is provided with an auxiliary clamp for engagement
onto the rail, wherein the coupling assembly is capable of being suspended from the
rail.
[0030] According to a second aspect the invention furthermore provides a method for building
a railbed by means of a mounting assembly for mounting a rail to a concrete foundation
of the railbed according to claim 12.
[0031] Said initial hardening is much lower than the hardening required for counteracting
that the known anchor bolts that were embedded while pouring, rotate along. In that
way the construction of the railbed can be finished immediately following initial
hardening.
[0032] In one embodiment thereof the mounting assembly comprises shape-retaining auxiliary
pieces between the mounting part and the heads of the screws which keep the heads
at a fixed distance from the mounting part, wherein at the lower side the screws extend
in the plugs and keep the coupling members in coupling cooperation, wherein the method
comprises the pouring of the concrete foundation with the auxiliary pieces around
the screws, and removing the auxiliary pieces prior to tightening the screws into
the plugs from above.
[0033] The auxiliary pieces are temporarily disposed to ensure the coupling cooperation
of the coupling members while the mounting assembly is still suspended over the basis
of the concrete foundation to be poured. The auxiliary bushes ensure that the screws
only need to be partially screwed in. This can be done manually.
SHORT DESCRIPTION OF THE DRAWINGS
[0034] The invention will be elucidated on the basis of a number of exemplary embodiments
shown in the attached drawings, in which:
Figure 1 shows an isometric side view of a railbed in which a rail on a mounting assembly
according to a first embodiment of the invention is accommodated;
Figure 2 shows an isometric side view of a partially exploded part of the mounting
assembly according to figure 1;
Figure 3 shows an isometric bottom view of the part of the mounting assembly according
to figure 2;
Figure 4 shows an isometric side view of the tram rail and the mounting assembly in
a preparatory stage of constructing the railbed;
Figure 5 shows an exploded view of a mounting assembly for the rail according to a
second embodiment of the invention; and
Figure 6 shows an isometric view of the mounting assembly according to figure 5 in
mounted condition.
DETAILED DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 shows a railbed 1 of which parts have been cut out in the figure in order
to show the final stage of its construction. The railbed 1 comprises a compacted and
levelled sand layer 10 and on top of it a concrete foundation 11. A tram track has
been accommodated in the railbed 1 of which track only one rail 20 is shown in figure
1. The rails 20 are connected to each other by means of distributed steel transverse-rods.
If the railbed 1 is located in a street, when finishing the railbed 1 a concrete upper
layer 12 which is approximately 13 centimetres thick and a thinner asphalt layer 13
which is approximately 7 centimetres thick, are disposed on the concrete foundation
11 of which asphalt layer the top surface is flush with the top side of the rails
20 so that other traffic can also drive over the railbed 1. Between the concrete foundation
11 and the upper layer 12 a thin separation layer 14 is disposed as a result of which
the upper layer 12 can separately be broken away from the foundation 11.
[0036] The rails 20 have a foot 21 mounted to mounting assemblies 30 according to a first
embodiment of the invention that are regularly distributed along the length, and only
one of which is shown in figure 1. Figures 2 and 3 show exploded views of the mounting
assembly 30. Figures 5 and 6 show a mounting assembly 230 according to a second embodiment
of the invention. The embodiments will be further elucidated below.
[0037] As also shown in figure 3 the mounting assembly 30 comprises a rectangular underlying
plate 31 of synthetic material, in this example polyamide (nylon). Parallel to each
other the flat underlying plate 31 comprises a straight and smooth upper surface 32
and a straight and smooth undersurface 33. In the underlying plate 31 two continuous
circular holes 34 are formed, which at the lower side merge into wider, recessed slots
35 having a rounded rectangular contour.
[0038] The mounting assembly 30 furthermore comprises two identical synthetic plugs 40,
in this example made of polyamide. The plugs 40 comprise a straight bush 41 having
coarse internal thread 45, a broadening 42 at the upper side, the broadening having
two parallel levellings 43 that fit within the long sides of the recessed slots 35,
and a spout 44 fitting in the circular holes 34 of the underlying plate 31. At the
lower side the plugs 40 comprise an anchor 47 in the shape of a broadening having
a straight undersurface 48 at the lower side, two parallel levellings 49 at the sides,
and two anchoring surfaces 50 at the upper side which extend perpendicular to the
longitudinal direction of the plugs 40.
[0039] As shown in figures 1 and 3 the mounting assembly 30 comprises a synthetic mounting
member 60, in this example made of polyamide. The mounting member 60 comprises an
elongated straight bearing surface 61, which for the larger part is covered by a flat
cork rubber 80. At the ends the bearing surface 61 merges into a lowering 62 for accommodation
of a synthetic wedge 90, in this example made of polyamide. Over its entire length
the lowering 62 has a constant concave cross-section. The mounting member 60 is provided
with supports 63 extending above the bearing surface 61 for sideward support of the
wedge 90. The mounting member 60 is solid or, in order to save on material, hollow
on the inside and filled with a honeycomb structure which is open at the lower side
facing the underlying plate 31.
[0040] The mounting assembly 30 comprises two guide members 100 placed at the ends of the
bearing surface 61, the guide members having a U-shaped passage 101 to two continuous
holes 64 that are in line with the holes 34 in the underlying plate 31. At the side
facing the outside, the guide members 100 are provided with wedgeshaped part for cooperation
with the wedge 90. The foot 21 of the rail 20 contacts the cork rubber 80 and is secured
thereto using tensioning clamps 110 that by means of resilient outer ends engage onto
the upper side of the foot 21. The position of the tensioning clamps 110 can be set
by sliding the wedge 90 relative to the guide member 100. The tensioning clamps 110
are each secured and pre-biassed using collar-sleeper screws 120 that are inserted
through the tensioning clamps 110, the guide member 100 and the holes 34 in the underlying
plate 31 and are tightened in the plugs 40. The collar-sleeper screw 120 comprises
a head 121 having a square upper side and a circular collar engaging onto the tensioning
clamps 110. The collar-sleeper screw 120 furthermore comprises a smooth rod section
122 and an external thread 123 having a coarse pitch corresponding with the internal
thread 45 in the plugs 40.
[0041] Figures 5 and 6 show a mounting assembly 230 according to a second embodiment of
the invention. The parts corresponding with the first embodiment are provided with
the same reference numbers in the figures. Below the differences from the first embodiment
are discussed.
[0042] The mounting assembly 230 comprises two identical synthetic plugs 240, in this example
made of polyamide. The plugs 240 comprise a straight bush 241 having the coarse internal
thread 45, the broadening 42 at the upper side, the broadening having two parallel
levellings 43 that fit within the long sides of the recessed slots 35, and a spout
44 fitting in the circular holes 34 of the underlying plate 31. The plugs 240 comprise
a straight cylindrical circumferential wall in which an external thread 246 in the
shape of a groove that is recessed relative to the smooth circumferential wall. On
the external thread 246 a synthetic anchor 247 is screwed, in this example made of
polyamide. The anchor 247 has a hexagonal circumferential surface 249 and at the lower
side is closed by means of a straight lower wall 248.
[0043] The mounting assembly 230 comprises a separate, shape-retaining auxiliary piece 330
made of synthetic material with which the mounting assembly 230 can temporarily be
suspended from the rail 20. The auxiliary piece 330 comprises a straight undersurface
331 for abutting the straight bearing surface 61 of the mounting member 60, and along
it a concave fitting member 332 that merges into a straight end surface 333. The fitting
member 332 and the straight end surface 333 jointly have a cross-section that is constant
over the length and fit free of play in the lowering 62 and against the projecting
supports 63 in order to enter into a form fit therewith. The undersurface 331 merges
into a parallel and raised engagement surface 334 for abutting the foot 21 of the
rail 20, thus confining the end edge 22.
[0044] The auxiliary piece 330 is provided with a curved inner wall 335 bounding a U-shaped
recess 336. The recess extends through the undersurface 331 up to the fitting member
332. At the upper side the inner wall 335 forms a straight support surface 337 extending
parallel to the undersurface 331.
[0045] Figure 4 shows the mounting assembly 30 according to a first embodiment in a preparatory
stage of constructing the railbed 1, prior to the situation as shown in figure 1.
The mounting assembly 30 is assembled and temporarily attached to the foot 21 of the
rail 20 by means of auxiliary clamps that are not further shown and engage on either
side of the rail 20 onto the upper surface of the foot 21 and that are screwed onto
the bearing surface 61 of the mounting member 60 in order to keep the foot 21 firmly
pressed into the cork rubber 80. The collar-sleeper screws 120 are inserted into a
temporary synthetic auxiliary bush 130 and subsequently only partially tightened in
the plugs 40. In this example the auxiliary bush 130 is made of PVC. The auxiliary
bush 130 is shape-retaining in the longitudinal direction. Inserting and tightening
can be effected using manual power. The auxiliary bushes 130 then press on the guide
members 100 and keep the guide members 100, the mounting member 60 and the underlying
plate 31 on top of each other free of play. With the broadening 42 at the upper side
the plugs 40 are kept free of play in the recessed slots 35 at the lower side of the
underlying plate 31. As a result the mounting assembly 30 forms one unity free of
play, that in the desired final arrangement is able to hang from the foot 21 of the
rail 20.
[0046] In the preparatory stage as shown in figure 4 the sand layer 10 has been laid, compacted
and levelled. Concrete slabs 152 having concrete blocks 151 thereon have been placed
on the sand layer 10. Atop the concrete blocks 151 adjustment wedges 153 have been
placed on which the rails 20 sit. The parts of the mounting assemblies 30 have been
brought into the above-mentioned bond free of play by means of the temporary auxiliary
bushes 130. The mounting assemblies 30 with the plugs 40 are freely suspended over
the sand layer 10. The rails 20 have been accurately brought at the desired final
height by means of the adjustment wedges 153.
[0047] Subsequently the concrete foundation 11 is poured as shown in figure 1. The upper
surface of the concrete foundation 11 sits at the level of the heads of the blocks
151 and the bearing plates 31 are halfway sunk into the concrete foundation 11. After
sufficient initial hardening of the concrete foundation 11, the collar-sleeper screws
120 including the temporary auxiliary bushes 130 are unscrewed so that the rails 20
can locally be lifted in order to remove the adjustment wedges 153. Subsequently the
wedges 90 and the tensioning clamps 110 are placed. Finally the collar-sleeper screws
120 without the auxiliary bushes 130 are mechanically screwed into the plugs 40 until
the tensioning clamps 110 are at the desired pre-bias. For that purpose a set screwing
moment is used. If the railbed 1 is located in a street, synthetic protective covers
that are not shown are furthermore secured over the tensioning clamps 110 and arranged
over the concrete foundation 11 the separation layer 14, the concrete upper layer
12 and the asphalt layer 13. The concrete then remains free from the rail 20 by sticking
a layer of foam band 15 to it.
[0048] Due to the pressure of time, the concrete foundation 11 only just has sufficient
initial strength in order to remain in the final bond when tightening the collar-sleeper
screws 120. That is why the plugs 40 have been inserted into the underlying plate
31 rotation-fixedly in order to prevent that they rotate along in the hardening concrete.
It is even possible for trams to ride over the rails 20 even before the initial strength
has been achieved, as the weight of the trams will still be borne by the adjustment
wedges 153. The rails possibly being pushed in locally, which leads to a small stab
of the plugs 40 in the concrete, only results in the broadening 47 at the lower side
of the plugs 40 being inserted deeper over the stab and returning again without causing
damage to the concrete along the straight bushes 41. As a result sufficient concrete
remains present above the broadening 47 in order to take the tensile force of the
collar-sleeper screws 120 in the end.
[0049] Figure 6 shows the mounting assembly 230 according to the second embodiment in the
preparatory stage of constructing the railbed 1. The mounting member 60 with the cork
rubber 80 thereon is placed under the foot 21 and two auxiliary pieces 330 with the
fitting members 332 have been laid in the lowerings 62. The collar-sleeper screws
120 have been inserted into the plugs 240 through the U-shaped recesses 336 and tightened
by hand until the heads 121 firmly abut the straight support surface 337. The whole
thus is suspended from the rail 20 free of play. After the poured concrete foundation
11 has acquired sufficient initial hardening the collar-sleeper screws 120 are partially
unscrewed so that the auxiliary pieces can be removed from the rail 20. After placing
the tensioning clamps 110 the collar-sleeper screws 120 are finally mechanically screwed
into the plugs 240 until the tensioning clamps 110 are at the desired pre-bias.
[0050] The lifespan of a straight rail at a distance from a stop is approximately 30 years.
Rails in bends and at stops wear much faster than that and have a lifespan of for
instance only 6 years, as a result of which they need to be replaced more often. When
replacing the rails 20 in a street a hydraulic wrecking hammer will break away the
concrete upper layer 12 and the asphalt layer 13 as a result of which the heads 121
of the collar-sleeper screws 120 below the synthetic protective covers become accessible
again. After unscrewing the collar-sleeper screws 120 the rails 20 can be removed
and be replaced by new rails 20.
[0051] Depending on the violence required for breaking the concrete upper layer 12 and the
asphalt layer 13 away, parts of the mounting assembly 30, 230 can be replaced during
reconstruction. In particular the underlying plate 31, that is partially sunk into
the concrete foundation 11, can be replaced by one having a smaller perimeter fitting
well within the remaining lowering in the concrete foundation 11. The lowering can
then be cleaned beforehand using for instance a leaf blower or high-pressure sprayer.
In all cases the plugs 40 are left behind in order to be reused. By means of the underlying
plate 31 they have been kept out of the demolition violence. As a result new mounting
holes for repair plugs do not need to be drilled into the concrete foundation 11 or
the entire concrete foundation 11 does not need to be broken away.
[0052] The plugs 40, 240 and the auxiliary pieces 330 of the first embodiment and the second
embodiment can be used independent from each other and thus are interchangeable. For
instance the auxiliary piece 330 of the second embodiment can be used in combination
with the plugs 40 of the first embodiment.
1. Mounting assembly (30; 230) for mounting a rail (20) to a concrete foundation (11)
of a railbed (1), wherein the mounting assembly comprises a mounting part (31, 60)
on which the rail sits, and at least two plugs (40; 240) to be accommodated in the
concrete foundation, wherein the plug has a first coupling member (43) and the mounting
part has a second coupling member (35) for cooperation with the first coupling member,
characterized in that the plugs are provided with an internal channel (45) for accommodating a screw (120)
which is screwed into the plug from above through a mounting opening (34, 64) in the
mounting part, wherein the cooperating coupling members (43, 35) constitute a form
lock that blocks rotation of the plug relative to the mounting part about the centre
line of the internal channel (45), wherein the mounting assembly (30; 230) comprises
shape-retaining auxiliary pieces (130; 330) between the mounting part (31, 60) and
the heads (121) of the screws (120) which keep the heads at a fixed distance from
the mounting part, wherein at the lower side (123) the screws extend into the plugs
(40; 240) and keep the coupling members (43, 35) in coupling cooperation.
2. Mounting assembly (30; 230) according to claim 1, wherein at the lower side facing
the plug (40; 240), the second coupling member (35) comprises a slot (35) below the
mounting opening (34), wherein at the upper side facing the mounting part (31, 60),
the first coupling member (43) comprises a first broadening (42) extending into the
slot (35), wherein transverse to the centre line the first broadening (42) has a noncircular
contour, wherein the slot (35) preferably is elongated and has two parallel inner
surfaces, wherein the first broadening (42) has two parallel outer surfaces for abutting
the inner surfaces.
3. Mounting assembly (30; 230) according to any one of the preceding claims, wherein
at the lower side facing away from the mounting part (31, 60) the plug (40; 240) is
provided with a second broadening (47; 247), wherein transverse to the centre line
the second broadening preferably has a noncircular contour.
4. Mounting assembly (30; 230) according to claim 3, wherein the second broadening (47;
247) has an anchoring surface (50) facing the mounting part (31, 60) and being transverse
to the centre line.
5. Mounting assembly (30) according to claim 3 or 4, wherein the plug (40) has a straight
bush (41) having a circle-cylindrical smooth outer surface up to the second broadening.
6. Mounting assembly (30; 230) according to any one of the preceding claims, wherein
the mounting part (31, 60) comprises a mounting member (60) for supporting the rail
and a separate underlying plate (31) below the mounting member, wherein the underlying
plate is provided with the second coupling members (35), wherein the underlying plate
(31) preferably comprises a straight and smooth undersurface (33) for partial accommodation
in the concrete foundation.
7. Mounting assembly (230) according to any of the preceding claims, wherein the auxiliary
pieces (330) engage onto the foot (21) of the rail (20), wherein the foot of the rail
preferably comprises two opposite end edges (22) and the mounting part (31, 60) and
the auxiliary pieces (330) jointly confine the end edges.
8. Mounting assembly (230) according to any one of the preceding claims, wherein the
auxiliary pieces (330) are provided with a passage (336) for the screw (120), wherein
the passage towards the rail (20) is opened for sideward insertion of the auxiliary
piece towards the rail.
9. Mounting assembly (230) according to any one of the preceding claims, wherein the
mounting part (31, 60) comprises a straight undersurface (61) for supporting the foot
(21) of the rail (20), wherein the auxiliary pieces (320) are provided with a straight
support surface (337) for the head (121) which surface extends parallel to the undersurface
(61).
10. Mounting assembly (230) according to any one of the preceding claims, wherein the
mounting part (31, 60) comprises a straight undersurface (61) for supporting the foot
(21) of the rail (20), wherein beyond the foot (21) of the rail the straight undersurface
(61) merges into concave lowerings (62), wherein the auxiliary pieces (330) are provided
with a convex lower side (332) fitting in the concave lowerings (62).
11. Mounting assembly (130) according to any one of the preceding claims, wherein the
auxiliary pieces (130) comprise auxiliary bushes (130) around the screws (120) which
bushes at the upper side abut the heads (121) of the screws and which at the lower
side abut the mounting part (31, 60), wherein at the lower side (123) the screws extend
into the plugs (40) and keep the coupling members (43, 35) in coupling cooperation.
12. Method for building a railbed (1) by means of a mounting assembly (30; 230) for mounting
a rail (20) to a concrete foundation (11) of the railbed, wherein the mounting assembly
comprises a mounting part (31, 60) on which the rail sits, and at least two plugs
(40; 240) to be accommodated in the concrete foundation, wherein the plug has a first
coupling member (43) and the mounting part has a second coupling member (35) for cooperation
with the first coupling member, characterized in that the plugs are provided with an internal channel (45) for accommodating a screw (120)
which is screwed into the plug from above through a mounting opening (34, 64) in the
mounting part, wherein the cooperating coupling members (43, 35) constitute a form
lock that blocks rotation of the plug relative to the mounting part about the centre
line of the internal channel (45), wherein the method comprises the laying of a sand
layer (10), positioning the rail (20) over the sand layer, suspending the mounting
part (31, 60) from the rail, wherein the plugs (40; 240) are downwardly oriented towards
the sand layer, pouring the concrete foundation (11) so that the plugs are accommodated
therein, and tightening the screws (120) into the plugs (40; 240) from above when
the concrete foundation (11) has acquired its initial hardening but not yet its final
hardening.
13. Method according to claim 12, wherein the mounting assembly (30; 230) comprises shape-retaining
auxiliary pieces (130; 330) between the mounting part (31, 60) and the heads (121)
of the screws (120) which keep the heads at a fixed distance from the mounting part,
wherein at the lower side (123) the screws extend in the plugs (40; 240) and keep
the coupling members (43, 35) in coupling cooperation, wherein the method comprises
the pouring of the concrete foundation (11) with the auxiliary pieces (130; 330) around
the screws (120), and removing the auxiliary pieces (130; 330) prior to tightening
the screws (120) into the plugs (40; 240) from above.
1. Befestigungsanordnung (30; 230) zur Befestigung einer Schiene (20) an einem Betonfundament
(11) eines Gleisbetts (1), wobei die Befestigungsanordnung ein Befestigungsteil (31,
60), auf welchem die Schiene liegt, und wenigstens zwei Stopfen (40; 240), die in
dem Betonfundament aufgenommen werden sollen, aufweist, wobei der Stopfen ein erstes
Kopplungselement (43) und das Befestigungsteil ein zweites Kopplungselement (35),
das mit dem ersten Kopplungselement zusammenwirkt, aufweist, dadurch gekennzeichnet, dass die Stopfen mit einem internen Kanal (45) zur Aufnahme einer Schraube (120) versehen
sind, die in den Stopfen von oben durch eine Befestigungsöffnung (34, 64) in dem Befestigungsteil
geschraubt ist, wobei die zusammenwirkenden Kopplungselemente (43, 35) einen Formschluss
darstellen, der eine Rotation des Stopfens relativ zum Befestigungsteil um die Mittellinie
des internen Kanals (45) sperrt, wobei die Befestigungsanordnung (30; 230) formbeständige
Hilfsteile (130; 330) zwischen dem Befestigungsteil (31, 60) und den Köpfen (121)
der Schrauben (120) aufweist, die die Köpfe in einem festgelegten Abstand zum Befestigungsteil
halten, wobei an der unteren Seite (123) sich die Schrauben in die Stopfen (40; 240)
erstrecken und die Kopplungselemente (43, 35) in koppelnder Zusammenwirkung halten.
2. Befestigungsanordnung (30; 230) nach Anspruch 1, wobei an der unteren, dem Stopfen
(40; 240) zugewandten Seite das zweite Kopplungselement (35) einen Schlitz (35) unter
der Befestigungsöffnung (34) aufweist, wobei an der oberen, dem Befestigungsteil (31,
60) zugewandten Seite das erste Kopplungselement (43) eine erste Verbreiterung (42)
aufweist, die sich in den Schlitz (35) erstreckt, wobei quer zur Mittellinie die erste
Verbreiterung (42) eine nicht-kreisförmige Kontur aufweist, wobei der Schlitz (35)
bevorzugt länglich ist und zwei parallele innere Oberflächen aufweist, wobei die erste
Verbreiterung (42) zwei parallele äußere Oberflächen aufweist, die an die inneren
Oberflächen angrenzen.
3. Befestigungsanordnung (30; 230) nach einem der vorhergehenden Ansprüche, wobei an
der unteren, dem Befestigungsteil (31, 60) abgewandten Seite der Stopfen (40; 240)
mit einer zweiten Verbreiterung (47; 247) versehen ist, wobei quer zur Mittellinie
die zweite Verbreiterung bevorzugt eine nicht-kreisförmige Kontur aufweist.
4. Befestigungsanordnung (30; 230) nach Anspruch 3, wobei die zweite Verbreiterung (47;
247) eine Ankerfläche (50) aufweist, die dem Befestigungsteil (31, 60) zugewandt ist
und quer zur Mittellinie ist.
5. Befestigungsanordnung (30) nach Anspruch 3 oder 4, wobei der Stopfen (40) eine gerade
Hülse (41) aufweist, die eine kreiszylindrische glatte äußere Oberfläche bis zur zweiten
Verbreiterung aufweist.
6. Befestigungsanordnung (30; 230) nach einem der vorhergehenden Ansprüche, wobei das
Befestigungsteil (31, 60) ein Befestigungselement (60) zum Abstützen der Schiene und
eine separate darunterliegende Platte (31) unter dem Befestigungselement aufweist,
wobei die darunterliegende Platte mit den zweiten Kopplungselementen (35) versehen
ist, wobei die darunterliegende Platte (31) bevorzugt eine gerade und glatte Unterfläche
(33) zur teilweisen Aufnahme in dem Betonfundament aufweist.
7. Befestigungsanordnung (230) nach einem der vorhergehenden Ansprüche, wobei die Hilfsteile
(330) in den Fuß (21) der Schiene (20) eingreifen, wobei der Fuß der Schiene bevorzugt
zwei entgegengesetzte Endkanten (22) aufweist und das Befestigungsteil (31, 60) und
die Hilfsteile (330) zusammen die Endkanten begrenzen.
8. Befestigungsanordnung (230) nach einem der vorhergehenden Ansprüche, wobei die Hilfsteile
(330) mit einem Durchgang (336) für die Schraube (120) versehen sind, wobei der Durchgang
in Richtung der Schiene (20) für ein seitliches Einsetzen des Hilfsteils in Richtung
der Schiene geöffnet ist.
9. Befestigungsanordnung (230) nach einem der vorhergehenden Ansprüche, wobei das Befestigungsteil
(31, 60) eine gerade Unterfläche (61) zum Abstützen des Fußes (21) der Schiene (20)
aufweist, wobei die Hilfsteile (320) mit einer geraden Stützfläche (337) für den Kopf
(121) versehen sind, welche Fläche sich parallel zur Unterfläche (61) erstreckt.
10. Befestigungsanordnung (230) nach einem der vorhergehenden Ansprüche, wobei das Befestigungsteil
(31, 60) eine gerade Unterfläche (61) zum Abstützen des Fußes (21) der Schiene (20)
aufweist, wobei jenseits des Fußes (21) der Schiene die gerade Unterfläche (61) in
konkave Vertiefungen (62) übergeht, wobei die Hilfsteile (330) mit einer konvexen
unteren Seite (332) versehen sind, die in die konkaven Vertiefungen (62) passt.
11. Befestigungsanordnung (230) nach einem der vorhergehenden Ansprüche, wobei die Hilfsteile
(130) Hilfsbüchsen (130) um die Schrauben (120) aufweisen, welche Büchsen an der oberen
Seite an die Köpfe (121) der Schrauben angrenzen und an der unteren Seite an das Befestigungsteil
(31, 60) angrenzen, wobei sich die Schrauben an der unteren Seite (123) in die Stopfen
(40) erstrecken und die Kopplungselemente (43, 35) in koppelnder Zusammenwirkung halten.
12. Verfahren zum Bauen eines Gleisbetts (1) mithilfe einer Befestigungsanordnung (30;
230) zum Befestigen einer Schiene (20) an einem Betonfundament (11) des Gleisbetts,
wobei die Befestigungsanordnung ein Befestigungsteil (31, 60), auf welchem die Schiene
liegt, und wenigstens zwei Stopfen (40; 240), die in dem Betonfundament aufgenommen
werden sollen, aufweist, wobei der Stopfen ein erstes Kopplungselement (43) und das
Befestigungsteil ein zweites Kopplungselement (35), das mit dem ersten Kopplungselement
zusammenwirkt, aufweist, dadurch gekennzeichnet, dass die Stopfen mit einem internen Kanal (45) zur Aufnahme einer Schraube (120) versehen
sind, die in den Stopfen von oben durch eine Befestigungsöffnung (34, 64) in dem Befestigungsteil
geschraubt ist, wobei die zusammenwirkenden Kopplungselemente (43, 35) einen Formschluss
darstellen, der eine Rotation des Stopfens relativ zum Befestigungsteil um die Mittellinie
des internen Kanals (45) sperrt, wobei das Verfahren ein Aufbringen einer Sandschicht
(10), ein Positionieren der Schiene (20) über der Sandschicht, ein Aufhängen des Befestigungsteils
(31, 60) an der Schiene, wobei die Stopfen (40; 240) nach unten in Richtung der Sandschicht
ausgerichtet sind, ein Gießen des Betonfundaments (11), so dass die Stopfen darin
aufgenommen sind, und ein Anziehen der Schrauben (120) in die Stopfen (40; 240) von
oben aufweist, wenn das Betonfundament (11) seine Anfangshärtung, jedoch noch nicht
seine endgültige Härtung erreicht hat.
13. Verfahren nach Anspruch 12, wobei die Befestigungsanordnung (30; 230) formbeständige
Hilfsteile (130; 330) zwischen dem Befestigungsteil (31, 60) und den Köpfen (121)
der Schrauben (120) aufweist, die die Köpfe in einem festgelegten Abstand zum Befestigungsteil
halten, wobei an der unteren Seite (123) sich die Schrauben in die Stopfen (40; 240)
erstrecken und die Kopplungselemente (43, 35) in koppelnder Zusammenwirkung halten,
wobei das Verfahren das Gießen des Betonfundaments (11) mit den Hilfsteilen (130;
330) um die Schrauben (120) aufweist, und ein Entfernen der Hilfsteile (130; 330)
vor dem Anziehen der Schrauben (120) in die Stopfen (40; 240) von oben.
1. Ensemble de montage (30 ; 230) pour le montage d'un rail (20) sur une fondation en
béton (11) d'un lit de rail (1), dans lequel l'ensemble de montage comprend une partie
de montage (31, 60), sur laquelle le rail repose, et au moins deux bouchons (40 ;
240) à loger dans la fondation en béton, dans lequel le bouchon a un premier élément
de couplage (43) et la partie de montage a un second élément de couplage (35) pour
la coopération avec le premier élément de couplage, caractérisé en ce que les bouchons sont dotés d'un canal interne (45) pour loger une vis (120) qui est
vissée dans le bouchon par le dessus à travers une ouverture de montage (34, 64) dans
la partie de montage, dans lequel les éléments de couplage coopérants (43, 35) constituent
un verrou de forme qui bloque la rotation du bouchon par rapport à la partie de montage
autour de la ligne centrale du canal interne (45), dans lequel l'ensemble de montage
(30 ; 230) comprend des pièces auxiliaires à retenue de forme (130 ; 330) entre la
partie de montage (31, 60) et les têtes (121) des vis (120) qui maintiennent les têtes
à une distance fixe de la partie de montage, dans lequel sur le côté inférieur (123),
les vis s'étendent dans les bouchons (40 ; 240) et maintiennent les éléments de couplage
(43, 35) en coopération de couplage.
2. Ensemble de montage (30 ; 230) selon la revendication 1, dans lequel sur le côté inférieur
faisant face au bouchon (40 ; 240), le second élément de couplage (35) comprend une
fente (35) sous l'ouverture de montage (34), dans lequel sur le côté supérieur faisant
face à la partie de montage (31, 60), le premier élément de couplage (43) comprend
un premier élargissement (42) s'étendant dans la fente (35), dans lequel transversalement
à la ligne centrale, le premier élargissement (42) présente un contour non circulaire,
dans lequel la fente (35) est de préférence allongée et possède deux surfaces intérieures
parallèles, dans lequel le premier élargissement (42) présente deux surfaces extérieures
parallèles pour buter contre les surfaces intérieures.
3. Ensemble de montage (30 ; 230) selon l'une quelconque des revendications précédentes,
dans lequel sur le côté inférieur faisant face à l'extérieur de la partie de montage
(31, 60), le bouchon (40 ; 240) est doté d'un second élargissement (47 ; 247), dans
lequel transversalement à la ligne centrale, le second élargissement présente de préférence
un contour non circulaire.
4. Ensemble de montage (30 ; 230) selon la revendication 3, dans lequel le second élargissement
(47 ; 247) présente une surface d'ancrage (50) faisant face à la partie de montage
(31, 60) et étant transversale à la ligne centrale.
5. Ensemble de montage (30) selon la revendication 3 ou 4, dans lequel le bouchon (40)
présente une douille droite (41) présentant une surface extérieure lisse cylindrique
et circulaire jusqu'au second élargissement.
6. Ensemble de montage (30 ; 230) selon l'une quelconque des revendications précédentes,
dans lequel la partie de montage (31, 60) comprend un élément de montage (60) pour
supporter le rail et une plaque sous-jacente séparée (31) sous l'élément de montage,
dans lequel la plaque sous-jacente est dotée des seconds éléments de couplage (35),
dans lequel la plaque sous-jacente (31) comprend de préférence une surface inférieure
droite et lisse (33) pour loger partiellement dans la fondation en béton.
7. Ensemble de montage (230) selon l'une quelconque des revendications précédentes, dans
lequel les pièces auxiliaires (330) s'engagent sur le pied (21) du rail (20), dans
lequel le pied du rail comprend de préférence deux arêtes d'extrémité en regard (22)
et la partie de montage (31, 60) et les pièces auxiliaires (330) confinent conjointement
les arêtes d'extrémité.
8. Ensemble de montage (230) selon l'une quelconque des revendications précédentes, dans
lequel les pièces auxiliaires (330) sont dotées d'un passage (336) pour la vis (120),
dans lequel le passage vers le rail (20) est ouvert pour insertion latérale de la
pièce auxiliaire vers le rail.
9. Ensemble de montage (230) selon l'une quelconque des revendications précédentes, dans
lequel la partie de montage (31, 60) comprend une surface inférieure droite (61) pour
supporter le pied (21) du rail (20), dans lequel les pièces auxiliaires (320) sont
dotées d'une surface de support droite (337) pour la tête (121), laquelle surface
s'étend parallèlement à la surface inférieure (61).
10. Ensemble de montage (230) selon l'une quelconque des revendications précédentes, dans
lequel la partie de montage (31, 60) comprend une surface inférieure droite (61) pour
supporter le pied (21) du rail (20), dans lequel au-delà du pied (21) du rail, la
surface inférieure droite (61) fusionne dans des abaissements (62) concaves, dans
lequel les pièces auxiliaires (330) sont dotées d'un côté inférieur convexe (332)
s'insérant dans les abaissements concaves (62).
11. Ensemble de montage (130) selon l'une quelconque des revendications précédentes, dans
lequel les pièces auxiliaires (130) comprennent des douilles auxiliaires (130) autour
des vis (120), lesquelles douilles butent sur le côté supérieur contre les têtes (121)
des vis et butent sur le côté inférieur contre la partie de montage (31, 60), dans
lequel sur le côté inférieur (123), les vis s'étendent dans les bouchons (40) et maintiennent
les éléments de couplage (43, 35) en coopération de couplage.
12. Méthode de construction d'un lit de rail (1) à l'aide d'un ensemble de montage (30
; 230) pour le montage d'un rail (20) sur une fondation de béton (11) du lit de rail,
dans laquelle l'ensemble de montage comprend une partie de montage (31, 60), sur laquelle
le rail repose, et au moins deux bouchons (40 ; 240) à loger dans la fondation en
béton, dans lequel le bouchon a un premier élément de couplage (43) et la partie de
montage a un second élément de couplage (35) pour la coopération avec le premier élément
de couplage, caractérisé en ce que les bouchons sont dotés d'un canal interne (45) pour loger une vis (120) qui est
vissée dans le bouchon par le dessus par une ouverture de montage (34, 64) dans la
partie de montage, dans lequel les éléments de couplage coopérants (43, 35) constituent
un verrou de forme qui bloque la rotation du bouchon par rapport à la partie de montage
autour de la ligne centrale du canal interne (45), dans lequel la méthode comprend
la pose d'une couche de sable (10) le positionnement du rail (20) sur la couche de
sable, la suspension de la partie de montage (31, 60) du rail, dans lequel les bouchons
(40 ; 240) sont orientés vers le bas vers la couche de sable, le versement de la fondation
de béton (11) de sorte que les bouchons soient logés dedans, et le serrage des vis
(120) dans les bouchons (40 ; 240) par le dessus lorsque la fondation en béton (11)
a acquis son durcissement initial mais pas encore son durcissement final.
13. Méthode selon la revendication 12, dans laquelle l'ensemble de montage (30 ; 230)
comprend des pièces auxiliaires (130 ; 230) à retenue de forme entre la partie de
montage (31, 60) et les têtes (121) des vis (120) qui maintiennent les têtes à une
distance fixe de la partie de montage, dans lequel sur le côté inférieur (123), les
vis s'étendent dans les bouchons (40 ; 240) et maintiennent les éléments de couplage
(43, 35) en coopération de couplage, dans lequel la méthode comprend le versement
de la fondation en béton (11) avec les pièces auxiliaires (130 ; 330) autour des vis
(120), et le retrait des pièces auxiliaires (130 ; 330) avant le serrage des vis (120)
dans les bouchons (40 ; 240) par le dessus.
REFERENCES CITED IN THE DESCRIPTION
This list of references cited by the applicant is for the reader's convenience only.
It does not form part of the European patent document. Even though great care has
been taken in compiling the references, errors or omissions cannot be excluded and
the EPO disclaims all liability in this regard.
Patent documents cited in the description