[0001] The present invention relates to pumping fluids in well bores, and is concerned in
particular but not exclusively with methods for use in connection with cementing operations
in tubular structures in well bores, and components for use in such methods.
[0002] Operations occuring in the drilling of bores for wells such as oil, gas or water
wells, include the cementing into the bore of a hollow cylindrical steel casing formed
of a series of lengths of casing known as casing joints, joined together to give a
continuous casing known as a casing string. The cementing process normally occurs
at the end of drilling of each stage of the bore of the well, or formation as the
bore is known. When a stage of the well has been drilled as far as possible without
danger of collapse of the formation, the drill string is removed and is replaced by
a casing string having an outer diameter less than the formation. During the removal
of the drill string and insertion section by section of the casing string, the formation
is maintained by the weight of a packing fluid containing for example barium sulphate
among other constituents. This fluid is pumped down the drill and up to the surface
during drilling to carry away the cuttings, cool the bit and hold back the pressure
from the formation(among other functions), and is retained in the formation while
the casing is placed in the bore.
[0003] When the casing string is in position it is cemented in place by pumping down the
hollow centre of the casing a cementing fluid which usually comprises a cement and
water slurry. The cementing fluid displaces the packing fluid and passes out of the
casing string at the bottom of the bore and is forced back up the outside of the casing
string to displace packing fluid from the annular space between the outer wall of
the casing and the inside of the bore. The bottom of the casing is terminated by an
element known as a float shoe or float valve resting at the bottom of the formation.
[0004] Ideally, just sufficient cementing fluid is pumped into the casing to fill the annular
space around the casing back to the required height(which may be to the top of the
formation) with virtually no cement in the bottom of the inside of the casing. This
operation is attempted by placing in the casing string above a calculated quantity
of cementing fluid a fluid displacement plug which is driven along the casing string
by pumping a displacement fluid under pressure behind the plug. The displacement fluid
may be similar to the packing fluid, for example a slurry of water, barium sulphate
and other materials. Thus the cementing fluid is carried along in front of the plug
and the displacement fluid behind the plug is pumped under pressure to drive the plug
along.
[0005] Considerable skill is required during the cementing operation to decide when to stop
pumping the displacement fluid behind the plug so as to stop the operation as nearly
as possible when the plug has just reached the bottom of the casing string. If pumping
continues after the plug reaches the bottom of the casing string, displacement fluid
is pumped beyond the end of the casing string to displace the cementing fluid from
its proper position around the outside of the casing and also to cause damaging mixing
with the cementing fluid so preventing proper setting of the cement. Such an occurence
is known as overdisplacement. If the converse occurs, and pumping is discontinued
before the plug reaches the bottom of the casing, the cement sets in the casing and
has to be drilled out again at a later stage before the next stage of drilling the
formation can commence. Clearly such extra drilling is time consuming and expensive.
[0006] In order to attempt to estimate when the displacement plug should have reached the
bottom of the casing, the present practice is to calculate the volume of displacement
fluid needed to be pumped into the casing to fill the hollow inside of the casing
and to carry the plug to the bottom, and then to make an estimate of the volumetric
efficiency of the displacing pump and the overall integrity of the displacing system(i.e.
valves, casing, joins and so on). It is then attempted to pump in the calculated volume
of displacement fluid by counting pump strokes and relating the count to the estimated
performance of the pump, endeavouring to make allowance for leakage in the pipes,valves
and other parts of the pumping system.
[0007] Premature grounding of the plug can be detected by detecting a surge of pressure
in the surface pumping system, but by that time the damage has usually taken place
by overdisplacement of the cementing fluid. It is known practice to detect the occurence
of unwanted activity in a well bore by detecting a pressure change in the pumping
system, and this is used for example to detect a blocked jet in the cleaning fluid
supply to a drilling head, or to detect a cave-in or other fault in a formation. However,
such prior use of monitoring the pressure in the pumping system has only detecting
unwanted accidental occurences after the stage when damage has occured.
[0008] During the cementing process,if the displacement plug does not seat and seal at the
float valve when the precalculated total displacement volume has been pumped, then
it is common practice to stop displacement for fear of overdisplacing the cement.
Overdisplacement of cement,or to be more specific unintentionally displacing all of
the mixed cement outside of the casing, gives rise to many problems and is a situation
that drilling supervisors try to avoid. In being too cautious of overdisplacement,
underdisplacement sometimes occurs, whereby too much cement is left inside the casing.
The rig time involved in drilling out an excessive amount(i.e. up to about 5,000 ft.)
of set cement from time to time can be costly to the operator. There is no practical
and accurate subsurface method or equipment being used in the industry to determine
the overall volumetric efficiency of the displacing system prior to seating the plug
while cement displacing is in progress.
[0009] Another form of cementing operation in which similar problems arise is the operation
of cementing the bottom of a well bore at a stage of the drilling operation itself.
When, in presently known methods, it is desired to cement the bottom of a well bore
after a stage of drilling has been completed (but before a casing string is inserted),
cement is pumped down the hollow centre of the drill pipe or string and is forced
back up the outside of the drill pipe in a similar manner to that described for a
casing string. At present the cement is forced down the drill pipe by a following
displacement fluid, but no plug is used to separate the cement and the displacement
fluid. After the cement has been pumped into position (so far as can be estimated
by the techniques described above) the drill pipe is withdrawn, leaving the cement
at the bottom of the well bore to set as required.
[0010] In addition to the problems of overdisplacement and underdisplacement described previously
with regard to cementing casing'strings, the pumping of cement through a drill pipe
brings an additional problem. When the pumps are turned off before withdrawing the
drill pipe, the weight of cementing fluid around the outside of the drill pipe is
greater than the weight of displacement fluid inside the drill pipe, and often this
causes the cementing fluid to flow back down the outside of the drill pipe and up
into the hollow centre of the drill pipe. This effect, known as a "U-tube" effect,
may result in cement remaining in the drill pipe after withdrawal, with consequent
difficulties of operation in subsequent drilling.
[0011] It is a main object of the present invention to provide a method (and components
for use in such a method) of carrying out cementing operations in well bores in tubular
structures such as casing strings or drill pipes in which the risk of overdisplacement
or underdisplacement of cementing fluid is reduced or eliminated.
[0012] It is another object of the invention, in certain aspects thereof, to provide a method
(and components for use in such a method) of cementing the base of a well bore by
pumping cementing fluid down a drill pipe, in which the risk of significant return
of cementing fluid into the drill pipe is reduced or eliminated.
[0013] In accordance with the present invention there is provided a method of monitoring
the pumping of fluid along a tubular structure in a bore of a well, comprising the
steps of driving a movable plug member along a tubular structure in a bore of a well
by a pumping system pumping fluid under pressure behind the plug member, interrupting
the passage of the plug member along the tubular structure by an obstruction means
placed at a known distance along the tubular structure, and detecting a surge of pressure
in the pumping system resulting from the said interruption of the movement of the
plug member to indicate the position of the plug member at the time of detection of
the pressure surge.
[0014] The plug member may conveniently be formed by a fluid displacement plug suitable
for displacing cementing fluid along the tubular structure. For convenience in the
subsequent description the plug member will sometimes be referred to as a plug.
[0015] By way of example, the tubular structure may comprise the hollow cylindrical structure
used to drive a drill during the drilling process and known as a drill pipe or drill
string. As a further example, the tubular structure may comprise a hollow cylindrical
structure used to line a completed or partly completed well bore and known as a casing
string. Tubular structures such as drill pipes and casing strings are generally referred
to in the field of drilling as "tubulars" and the present invention finds use in operations
in such "tubulars".
[0016] The interruption of the plug movement is conveniently a momentary check of the movement
of the plug which may be may not bring the plug to rest before resuming its movement
under the build up of pressure.
[0017] The method described has particular use in the cementing processes set out above,
and may be used merely to give an indication that a displacement plug is approaching
the bottom of a casing string or drill pipe, or, as will be described hereinafter,
to calibrate the pumping system. Conveniently the method may be used both to give
a forewarning of the end of the displacement process and to calibrate the system.
[0018] In this specification it is to be appreciated that the term fluid means any liquid,
semi-liquid slurry or other flowable material of the kind used in pumping operations
in well bores. The invention has application in many kinds of land or off-shore oil,
gas or water wells and many different fluids are used in such systems.
[0019] There is also provided in accordance with the present invention a method of calibrating
a pumping system for pumping fluid along a tubular structure in a bore of a well comprising
the steps of driving a fluid displacement-plug along a tubular structure in a bore
of a well from a known reference position by pumping displacement fluid under pressure
behind the plug, interrupting the passage of the plug along the tubular structure
at a known distance from the said reference position, detecting a surge of pressure
in the pumping system resulting from the interruption of the passage of the plug,
and measuring a working parameter of the pumping system from the time of plug movement
from the said reference position to the time of detection of the said pressure surge
to provide a measure of the said working parameter related to a known volume of displacement
fluid corresponding to the said known distance along the tubular structure.
[0020] Conveniently the said known reference position of the plug is constituted by the
top of the tubular structure at the surface of the bore, so that the working parameter
of the pumping system is measured from the time that the plug is inserted in the tubular
structure and the pumping operation started. Usually the measurement of working parameter
referred to will be a count of pump strokes. It will be appreciated that once a relationship
has been established in operating conditions between a count of pump strokes and a
volume of displacement fluid which has taken the plug to the obstructing means, it
is a simple matter to calculate how many further pump strokes will be needed to carry
the plug the remaining distance to the bottom of the tubular structure, or other required
position.
[0021] In accordance with one particular aspect of the invention there is provided a method
of carrying out a cementing operation in a bore of a well comprising the steps of
forcing cementing fluid along a tubular structure by a fluid displacement plug driven
along the tubular structure by a pumping system pumping a displacement fluid under
pressure behind the plug, interrupting the passage of the plug along the tubular structure
by an obstruction means placed at a known distance along the tubular structure, detecting
a surge of pressure in the pumping system resulting from the said interruption of
the plug movement to indicate the position of the plug, and terminating the cementing
operation in dependence upon the detection of the said pressure surge.
[0022] There is further provided in accordance with the present invention a tubular component
for use in a tubular structure in a bore of a well, the tubular component having obstruction
means for interrupting passage through the tubular component of a plug member during
pumping of fluid through the tubular component.
[0023] Where the tubular structure comprises a casing string, the tubular component may
consist of a casing joint, which term means a length of casing adapted to be joined
with other lengths of casing to form a casing string for use in a bore of a well.
Where the tubular structure comprises a drill pipe, the tubular component may consist
of a corresponding joint of the drill pipe or string. Hereinafter such tubular components
will be referred to generally as tubular joints or merely as joints.
[0024] In one particularly preferred form of the obstruction means for use in a drill pipe,
the obstruction means may have a shape such as to allow a fluid displacement plug
to move past the obstruction means under the force of displacement fluid behind the
plug, but such as to prevent return of the plug back up the drill pipe under the force
of cementing fluid displaced outside the drill pipe. Such a use of an obstruction
means embodying the invention may be used to reduce or avoid the "U-tube" effect described
hereinbefore as a disadvantage of known cementing operations.
[0025] In some aspects of the invention an obstruction means may be used in a cementing
operation in a drill pipe or other tubular structure as set out in the previous paragraph
without being used to determine a finishing time for the cementing operation.
[0026] Thus in accordance with a different aspect of the invention there is provided a method
of depositing cement in a bore of a well comprising the steps of forcing cementing
fluid along a tubular structure by a fluid displacement plug driven along the tubular
structure by a pumping system pumping a displacement fluid under pressure behing the
plug, and driving the plug past an obstruction means placed in the tubular structure
at or in the region of the bottom of the well bore and having a shape such as to prevent
or inhibit return of the plug along the tubular structure past the obstruction means.
[0027] There is further provided in accordance with the present invention in this aspect
a tubular component for use in a tubular structure in a bore of a well, the tubular
component having obstruction means shaped to allow passage through the tubular component
of a fluid displacement plug during pumping of fluid through the tubular component,
but shaped to prevent or inhibit return of the plug past the obstruction means under
the influence of fluid displaced from the tubular structure by the plug.
[0028] Preferably the obstruction means is adapted for disposal after the said interruption
of the cement displacement plug, conveniently the obstruction means being adapted
for disposal after the cementing process by drilling out of the obstruction means.
In other arrangements however the obstruction means may be adapted for disposal in
other ways, for example it may be adapted to disintegrate, or to be displaced as soon
as it has performed its function of interrupting the cement displacement plug. In
yet other arrangements the obstruction means may be constructed to remain in the tubular
joint permanently or semi-permanently after it has effected interruption of the plug.
[0029] It is preferred that the said tubular component or joint has along at least a portion
of its length an inner diameter less than the inner diameter of the tubular structure
in which the component is adapted to be coupled in operation. The said lesser inner
diameter may be provided along the whole length of the tubular joint, but it can be
that the obstruction means is provided by a portion of the tubular joint having a
lesser inner diameter than the inner diameter of the remainder of the tubular joint.
Most conveniently, the obstruction means is provided by a lining along at least part
of the inner surface of the tubular joint of a material different from the material
of the wall of the tubular joint, the material of the lining being chosen to allow
easy removal if necessary by drilling out at a later stage of operation, for example
after the cementing process is completed. Examples of preferred materials for obstruction
means are natural or synthetic rubber, or synthetic plastics material,and conveniently
the material is bonded to the wall of the tubular joint.
[0030] In other forms of the tubular component according to the invention, the obstruction
means may comprise projections extending inwardly from the wall of the tubular component,
for example, flanges, studs, lugs, fluting or other projections.
[0031] In accordance with one preferred arrangement according to the invention, as an alternative
to or in addition to the lining mentioned above, the obstruction means may comprise
a web, spider or other form of bridging member extending across the tubular component
and adapted to interrupt the passage of the plug member through the tubular component,
but adapted to be broken by the plug member so as to allow the plug member to proceed
past the bridging member after the said interruption. Conveniently the bridging member
comprises a moulded rubber cross positioned across the tubular component at the upper
end thereof. Such a rubber cross may be arranged to be breakable by a fluid displacement
plug driven by a pressure of displacement fluid in the range 600 to 800 p.s.i. (lbs/sq.
inch), conveniently 700 p.s.i.
[0032] Embodiments of the invention will now be desribed by way of example with reference
to the accompanying drawings in which:-
Figures 1 and 2 are diagrammatic sections showing a casing joint embodying the invention,
Figure 1 showing the joint positioned in a well bore during a cementing operation;
Figures 3 and 4 show corresponding diagrammatic sections of a drill pipe during a
cementing operation; and
Figures 5a and 5b show in diagrammatic form a modified tubular component including
a rubber bridging member.
[0033] In Figure 1 there is shown a well bore or formation 11 cut in rock or other ambient
material 12 and terminating at a base 13 of the formation. Within the bore 11 is a
casing string indicated generally at 14 and composed of a number of casing joints
of which 4 are shown at 15, 16, 17 and 18. The casing joints are interconnected by
threaded sleeves 19, and the bottom casing joints 18 is
terminated by a float shoe or float valve 20.
[0034] The formation 11 in Figure 1 is shown at stage at which the drill string(not shown)
has been removed after drilling a stage down to the base 13, and the casing string
15 has been inserted in the bore 11 to leave between the outer surface of the casing
string 15 and the inner
:surface of the formation 11 an annular space 21 initially filled with a packing fluid
22. Inside the casing string 14 has been pumped a calculated volume of cementing fluid
23 which has been forced down the casing string 14 by a displacement plug 24 driven
along the casing string 14 by a displacement fluid 25 behind the plug 24. As shown,
the cementing fluid 23 has been forced around the bottom of the float shoe 20 and
back up the annular space 21 to reach a level approximately the same as the level
of cementing fluid 23 within the casing string 14. At this stage the pressure detected
at the surface by monitoring the pressure in the pumping system changes from an initial
negative pressure to a positive pressure as the cement fluid in the annular space
21 passes the cement fluid in the inside of the casing string 14.
[0035] Connected in the casing string 14 is a casing joint 16 embodying the present invention
and including an obstruction means formed by an inner rubber lining 26 extending along
part of the length of the casing joint 26. As shown in Figure 2, the lining 26 extends
along most of the length of the casing joint 16, and provides an inner diameter at
the lining of lesser diameter than the inner diameter of the casing 16 at top and
bottom portions 27 and 28. The inner diameter of the casing joint 16 at the regions
27 and 28 is conveniently the same inner diameter as for other casing sections in
the stage of the casing string.
[0036] Conveniently the lining 26 is of natural or synthetic rubber and is bonded to the
interior of the steel casing joint 16. By way of example,where the outer diameter
of the casing joint 16 is 30in., the thickness of the lining 26 may be 2½ in. For
example where the inner diameter of the casing joint 16 in the regions 27 and 28 is
26½ in. , the inner diameter at the lining 26 may be 21½ in. Further by way'of example
the length of the casing joint 16 may be 120in., and the length of the lining 26 may
be about 19in.
[0037] As shown in Figure 1 the displacement plug 24 comprises a central metal core 29,
for example of aluminium, carrying four rubber cone-shaped sealing members 30 which
are of a diameter such as to press outwardly against the inner surface of the casing
string 14, and effect a seal therewith.
[0038] When the plug 24 reaches the lining 16 it experiences a momentary check or interruption
to its movement along the casing string 14 while the pressure in the displacement
fluid 25 rises sufficiently to carry the plug 24 past the lining 24 and onwards down
the casing string 14. The extent of this interruption to the plug movement, for example
as to whether the plug comes to rest or merely slows in its movement, will depend
upon the depth of the lining 26, and the resilience or design of the cones 30 on the
plug 24. The effect of the interruption of the plug movement is a pressure surge in
the pumping system which is detected at the surface pumping equipment.
[0039] In operation the method of the embodiment of the invention shown operates in the
following manner. Firstly there is deposited into the casing string 14 the quantity
of cementing fluid 23 which is calculated to provide the required height of cement
up the outer annular space 21. Next there is inserted in the top of the casing string
14 the displacement plug 24, and the plug is driven down the casing string 14 by pressure
of the displacement fluid 25. The number of strokes of the pumping apparatus (not
shown) is counted from the start of the movement of the plug 24 from the top of the
casing string 14 (constituting a known reference position) and the pressure in the
pumping system at the surface is monitored until the pressure surge is detected which
results from the interruption of the plug movement by the obstruction means 26. Conveniently
at this stage the pumping operation can be stopped and the required relationship between
the number of pump strokes counted and the volume of displacement fluid pumped (calculated
from the known distance of the lining 26 from the surface)is determined. This calibration
factor is then-applied to the volume of displacement fluid required to fill the remainder
of the casing string 14 down to the float shoe 20(previously calculated from the known
length of the casing string 14)to give a number of pumping strokes required to complete
the operation. The pumping is then restarted and continued for the required number
of strokes, which brings the plug 24 to seat and seal on the float shoe 20.
[0040] The cementing fluid is then left to harden around the outside of the casing string
14, and the stage of casing is completed. When the next stage of drilling is to commence
the new, narrower, drill bit is lowered down the inside of the casing string, and
is easily able to drill away the lining 26, which is made of material suitable to
allow easy removal at this stage. As in conventional drilling operation, the drill
bit then drills through the float shoe 20 and through the small amount of cement remaining
at the base 13.
[0041] It is to be appreciated that the method and apparatus according to the invention
which has been described finds many uses outside the specific example of cementing
a casing stage which has been described. For example, well cementing may be used to
line, seal, locate or strengthen a formation at critical points along the bore, or
for example in repairing damage to an operating well. The present invention finds
application in these situations. Such repair work is known as secondary cementing
whilst the cementing process described in the specific example is known as primary
cementing.
[0042] An example of another such cementing process will now be described with reference
to Figures 3 and 4.
[0043] In Figure 3 there is shown a well bore or formation 111 cut in rock or other ambient
material 112 and terminating at a base 113 of the formation. Within the bore 111 is
a drill string indicated generally at 114 and composed of a number of drill joints
of which three are shown at 115, 116 and 118. The drill joints are interconnected
by threaded portions 119, and the bottom drill joint is terminated by a drill head
shown diagrammatically at 120.
[0044] The formation 111 in Figure 3 is shown at a stage at which the drill string 114 is
to be removed from the bore after there has been deposited at the base 113 of the
bore cementing fluid 123. Between the outer surface of the drill string 114 and the
inner surface of the formation 111 is an annular space 121 initially filled with a
packing fluid 122. Inside the drill string 114 has been pumped a calculated volume
of cementing fluid 123 which has been forced down the drill string 114 by a displacement
plug 124 driven along the drill string 114 by a displacement fluid 125 behind the
plug 124. The cementing fluid 123 has been forced (through apertures not shown) around
the bottom of the drill head 120 and back up the annular space 121 to reach a level
approximately the same as the level of cementing fluid 123 within the drill string
114.
[0045] Connected at or the near the bottom of the drill string 114 is a drill joint 116
embodying the present invention and including an obstruction means formed by an inner
rubber lining 126 extending along most of the length of the drill joint 116. As shown
in Figure 4, the lining 126 extends along almost all of the length of the joint 116,
and provides an inner diameter at the lining of lesser diameter than the inner diameter
of the joints forming the rest of the drill string 114.
[0046] Conveniently the lining 126 is of generally similar material and configuration to
the lining 26 shown in Figures 1 and 2. However a lower edge 132 of the lining 126
differs from that of the lining 26. The lining 26 of Figure 2 has chamfered edges
at its upper and lower edges. An upper edge 131 of the lining 126 is again chamfered
to allow relatively easy (although interrupted) passage of the plug 124, but the lower
edge 132 of the lining 126 is a square shoulder for preventing return of the plug
124 back up the drill string 114.
[0047] As shown in Figure 3 the displacement plug 124 is generally similar to the plug 24
shown in Figure 1. When the plug 124 reaches the lining 126 it experiences a momentary
check or interruption to its movement along the string 114 while the pressure in the
displacement fluid 125 rises sufficiently to carry the plug 124 past the lining 126.
The effect of the interruption of the plug movement is a pressure surge in the pumping
system which is detected at the surface pumping equipment and is used as described
hereinbefore to determine when the required displacement of cementing fluid has been
achieved.
[0048] In operation the method of the embodiment of the invention shown in Figures 3 and
4 operates in the following manner. Firstly there is deposited into the drill string
114 the quantity of cementing fluid 123 which is calculated to provide the required
depth of cement at the base 113 of the bore 111. Next there is inserted in the top
of the drill string 114 the displacement plug 124, and the plug is driven down the
drill string 114 by'pressure of the displacement fluid 125. When the plug 124 reaches
the bottom of the drill string 114, the pumping system is switched off and the drill
string 114 is withdrawn from the bore 111 leaving the cementing fluid at the base
113 of the bore 111 to harden as required. After the pumping system has been shut
off (during the withdrawing of the drill string), the cementing fluid is prevented
from passing back up the drill string 114 by the plug 124 lodging against the shoulder
at the lower edge 132 of the lining 126.
[0049] In Figures5a and 5b there is shown a modification of the drill joint 116 shown in
Figure 4. In Figures 5a and 5b, elements corresponding to elements in Figure 4 are
indicated by like reference numerals. The modification of the drill joint showing
Figures 5a and 5b consists of the provision at the upper end of the drill joint 116
of a moulded rubber bridging element 133 in the form of a cross which extends across
the drill joint 116 at the top of the rubber lining 126. The purpose of the rubber
cross 133 is to provide additional obstruction means for producing an interruption
of the movement of the displacement plug member 124 (Figure 3) when it reaches the
drill joint 116. In the case of the modification, it is intended that the plug 124
is interrupted in its movement, but then breaks through the rubber cross 133 and continues
its way down the drill joint 116. The rubber cross 133 is conveniently arranged to
be broken by a fluid displacement plug 124 when driven under a pressure of displacement
fluid of about 700 p.s.i. It is to be appreciated that the modification of Figures
5a and 5b may equally well be applied with the embodiments shown in Figures 1 and
2. Also the bridging member 133 may be used alone or in combination with other obstruction
means with a drill joint or other tubular casing member.
1. A method of monitoring the pumping of fluid along a tubular structure in a bore
of a well, including the step of driving a movable plug member along a tubular structure
in a bore of a well by a pumping system pumping fluid under pressure behind the plug
member, characterised by interrupting the passage of the plug member (24, 124) along
the tubular structure (14, 114) by an obstruction means (26,126,133) placed at a known
distance along the tubular structure (14, 114) and detecting a surge of pressure in
the pumping system resulting from the said interruption of the movement of the plug
member (24, 124) to indicate the position of the plug member (24, 124) at the time
of detection of the pressure surge.
2. A method according to Claim 1 applied in calibrating a pumping system for pumping
fluid along a tubular structure in a bore of a well, the method being characterised
by the steps of driving the said plug member (24, 124) along the said tubular structure
(14, 114) in a bore (11,111) of a well from a known reference position by pumping
displacement fluid (25,125) under pressure behind the plug member (24, 124), interrupting
the passage of the plug member (24, 124) along the tubular structure (14, 114) at
a known distance from the said reference position, detecting a surge of pressure in
the pumping system resulting from the interruption of the passage of the plug member
(24, 124), and measuring a working parameter of the pumping system from the time of
plug member movement from the said reference position to the time of detection of
the said pressure surge to provide a measure of the said working parameter related
to a known volume of displacement fluid corresponding to the said known distance along
the tubular structure (14, 114).
3. A method according to Claim 2 characterised in that the said measurement of working
parameter consists of a count of pumping strokes producing the said pumping of displacement
fluid.
4. A method according to Claim 1, 2, or 3 characterised in that the said plug member
(24, 124) comprises a fluid displacement plug member (24, 124) suitable for displacing
cementing fluid (23, 123) along the tubular structure (14, 114), and the step of driving
the movable plug member (24, 124) along the tubular structure (14, 114) includes displacing
cementing fluid (23, 123) along the tubular structure (14, 114) in front of the plug
member (24, 124).
5. A method according to Claim 1 applied in carrying out a cementing operation in
a bore of a well, the method including the step of forcing cementing fluid along a
tubular structure by a fluid displacement plug member driven along the tubular structure
by a pumping system pumping a displacement fluid under pressure behind the plug member,
characterised by interrupting the passage of the plug member (24, 124) along the tubular
structure (14, 114) by an obstruction means (24, 124, 133) placed at a known distance
along the tubular structure (14 , 114),detecting a surge of pressure in the pumping
system resulting from the said interruption of the plug member movement to indicate
the position of the plug member (24, l24),and terminating the cementing operation
in dependence upon detection of the said pressure surge.
6. A method of depositing cement in a bore of a well including the step of forcing
cementing fluid along a tubular structure by a fluid displacement plug member driven
along the tubular structure by a pumping system pumping a displacement fluid under
pressure behind the plug member characterised by driving the plug member (124) past
an obstruction means (126) placed in the tubular structure (114) at or in the region
of the of the bottom (113) of the well bore (lll) and having a shape (132) such as
to prevent or inhibit return of the plug member (124) along the tubular structure
(114) past the obstruction means (126).
7. A tubular component for use in a tubular structure in a bore of a well, characterised
in that the tubular component (16, 116) has obstruction means (26, 126, 133) for interrupting
passage through the tubular component (16, 116) of a plug member (24, 124) during
pumping of fluid (25, 125) through the tubular component (16, 116).
8. A tubular component for use in a tubular structure in a bore of a well, characterised
in that the tubular component (116) has obstruction means (126, 132) shaped to allow
passage through the tubular component (116) of a fluid displacement plug member (124)
during pumping of the fluid (125) through the tubular component (116), but shaped
to prevent or inhibit return of the plug member (124) past the obstruction means (126,
132) under the influence of fluid (123) displaced from the tubular structure (114)
by the plug member (124).
9. A tubular component according to Claim 7 or 8 characterised in that the said tubular
component (16, 116) has along at least a portion of its length an inner diameter less
than the inner diameter of the tubular structure (14, 114) in which the component
(16, 116) is adapted to be coupled in operation, the said lesser inner diameter being
produced by means of a lining (26, 126) along at least part of the inner surface of
tubular component (16, 116).
10. A tubular component according to Claim 9 characterised in that the lining (26)
is formed of a material different from a material of the wall of the tubular component
(16), the material of the lining (26) being chosen to allow easy removal if necessary
by drilling out at a later stage of operation.
ll. A tubular component according to Claim 7, 8, 9 or 10 characterised in that there
is provided a bridging member (133) extending across the tubular component (116) and
adapted to interrupt the passage of the plug member (124) through the tubular component
(116), but adapted to be broken by the plug member (124) and to allow the plug member
(124) to proceed past the bridging member (133) after the said interruption.