[0001] The present invention relates to methods of installing submarine cold water conduits,
for instance for use with power plants such as Ocean Thermal Energy Conversion (OTEC)
power plants.
[0002] The high cost and dwindling supply of easily obtainable fossil fuels has created
an intense interest in alternative sources of energy. One such alternative energy
source involves utilisation of the temperature differential between warm surface seawater
and cooler subsurface seawater. This general concept is known as ocean thermal energy
conversion or "OTEC".
[0003] In the operation of an OTEC power plant, warm surface seawater is used to vapourise
a working fluid. The vapour is used to drive turbine generators in much the same way
as steam is used to drive turbine generators to produce electricity. After the vapour
has passed through the turbines, cool subsurface seawater is used to condense the
vapour, thereby completing the working fluid cycle. The cool subsurface seawater required
for the process is located roughly 500 to 1000 metres (1500 to 3000 feet) below the
water surface, depending on the latitude of the OTEC power plant. In many OTEC power
plants, it is necessary to pump large quantities of this cool subsurface seawater
to the surface. To accomplish this it is envisioned that a long pipe commonly referred
to as a "cold water conduit" will be used, the conduit extending down from the surface
to a depth of roughly 500 to 1000 metres (1500 to 3000 feet). It is anticipated that
the cold water conduit must be approximately 1.5 to 40 metres (5 to 120 feet) in diameter
for OTEC power plants of 1 to 400 MW, respectively.
[0004] The need for such a huge conduit presents several severe problems. The conduit must
be fabricated, installed, and secured so that it will be able to withstand tremendous
dynamic current loads. Other problems involve the method of installing such a large
conduit and maintaining its position with respect to an OTEC plant located on the
surface.
[0005] Prior art techniques for laying pipelines on the ocean floor include methods of installation
which encompass the use of a barge and stringer arrangement or the use of an underwater
sled which either place the pipeline on or bury it in the ocean floor. In the past,
structurally mounted pipelines were either used at shallow depths or were secured
to a support structure above the water surface and then the support structure and
the pipeline were jointly lowered to the ocean floor. Prior art techniques have been
able to lay pipelines measuring 41 cm (16 inches) in diameter to depths of 610 metres
(2000 feet), though some pipelines as large as 9.1 metres (30 feet) in diameter have
been installed in shallow water. It is believed that the use of a marine railway system
to guide a pipeline to these depths and thereafter to support the pipeline on the
railway system has heretofore never been. attempted. Prior art has not been able to
install pipelines at depths necessary for use with an OTEC power plant. These depths
were previously inaccessible by prior art means.
[0006] According to the present invention there is provided a method of installing a submarine
cold water conduit, characterised by the steps of:
installing and securing at least one railway track means to an underwater land formation,
and
installing and securing a cold water conduit to the railway track means.
[0007] A method embodying the invention and described hereinbelow involves installing and
securing a marine railway system on a floor (more particularly a sloping floor) of
a body of water such as an ocean, the system extending from a depth of about 500 to
1000 metres (1500 to 3000 feet) to an OTEC power plant located on a platform in several
hundred feet of water, or built on the shoreline. Subsequently, the marine railway
system is used for installing and securing a cold water conduit to the floor of the
body of water.
[0008] An advantage of the method described below is that it can be used to install a submarine
pipeline to 1000 metres (3000 feet) water depths by remote methods and techniques
which do not require underwater divers beyond 300 metres (1300 feet) water depths.
Yet another such advantage is the reduction of environmental forces, i.e. forces due
to wind, current, waves, etc., on the installation operation and maintenance of the
system. Another such .advantage is that a submarine pipeline can be installed at depths
heretofore inaccessible. A further such advantage is the possibility of using larger
than ever before coldwater conduits for OTEC power plants.
[0009] Further, the embodiment of the invention described below also minimises harm to the
marine ecological system since it requires minimal disturbance of the ocean floor.
All underwater operations can be monitored by the use of underwater cameras, which
minimises the need for underwater personnel. The installation process can proceed
from shallow waters thereby reducing environmental forces on the working vessels used
and the installation operation.
[0010] The invention will now be further described, by way of illustrative and non-limiting
example, with reference to the accompanying drawings, in which like reference numerals
designate like items throughout, and in which:
Figure 1 is an elevational view of a type of underwater land formation with which
the invention can be practiced;
Figure 2 is an elevational view of the land formation shown in Figure 1, showing the
installation of a bench mark pile;
Figure 3 is an elevational view of the land formation shown in Figure 1, showing the
installation of a deadman template;
Figure 4 is an elevational view of the land formation shown in Figure 1, with the
deadman template and a track pulldown cable in place;
Figure 5 is an elevational view of the .land formation shown in Figure 1, showing
a step of attaching a section of a track to a down slope railway leader;
Figure 6 is an elevational view of the land formation shown in Figure 1, showing a
step of lowering the track into position;
Figure 7 is an elevational view of the land formation shown in Figure 1, with the
track in place and a pile installation rig positioned thereon;
Figure 8 is an elevational view of the land formation shown in Figure 1, showing a
step of securing and levelling the track to the land formation;
Figure 9 is an elevational view of the land formation shown in Figure 1, showing a
step of lowering a first section of a cold water conduit section onto the track;
Figure 10 is an elevational view of the land formation shown in Figure 1, with the
cold water conduit in position;
Figure 11 is an elevational view of the completed cold water conduit of Figure 10
in combination with a discharge pipe and OTEC power plant;
Figure 12 is a side elevational view of the deadman template;
Figure 13 is a top view of the deadman template;
Figure 14 is a side elevational view of the down slope railway leader;
Figure 15 is a top view of the track section;
Figure 16 is an end elevational view of a track section;
Figure 17 is a detailed top view of a track pile guide section;
Figure 18 is a view taken along a line 18-18 in Figure 17;
Figure 19 is a side elevational view of the base of the rail mounted pile installation
rig;
Figures 20A and 20B are front and side elevational views of the pile installation
rig;
Figure 21 is a side elevational view of a section of the cold water conduit;
Figure 22 is a view taken along a line 22-22 in Figure 21; and
Figures 23 to 26 show an alternative method of positioning the track.
[0011] Figure 1 shows a body of water 11 having a downwardly sloping bottom 12 and a surface
13 on which is floating a surveying vessel 14. The vessel 14 is fitted with equipment
well known in the art for obtaining accurate geotechnical and mapping data for the
purpose of locating the best site along which to install a marine railway system.
[0012] Figure 2 shows a derrick barge 15 installing a bench mark pile 16 using a pile driver
17 suspended by a cable 18. Before installation of the bench mark pile 16 in the bottom
12, the chosen path of a track of the marine railway system may be cleared and/or
levelled from the shoreline to the bench mark pile 16, in preparation for installing
the marine railway system.
[0013] Figures 3 and 4 show the installation of a deadman template 19 atop the bench mark
pile 16. The template 19 is installed at approximately the depth to which a cold water
conduit is to extend. As shown in Figures 12 and 13, the template 19 has a plurality
of pile guides or sleeves 60, one of which (62) is inverted. The inverted pile guide
62 is slid over the bench mark pile 16. A second cable 22 is threaded through a template
pulley or sheave 61 (not shown in Figure 13) before the template 19 is lowered into
the water 11.
[0014] The pulley 61 is attached to the template 19 for the purpose of using it as an aid
in the installation of the marine railway system. It allows the derrick barge 15 to
anchor and work in shallow water and yet install the railway system to the desired
depth. An auxiliary vessel 20 is used to run the cable 22, herein referred to as the
track pulldown cable 22, upslope of the template 19. An anchor 21 is attached to the
end of the track pulldown cable 22 and a float 25 is attached to the anchor 21 or
pulldown cable 22 for retrieval at a later time.
[0015] Thereafter, the pile driver 17 installs other template piles 26 needed to secure
the template 19 to the sloping bottom 12. Figures 12 and 13 show the template 19 as
having a plurality of template pile guides 60 and grout bags 63 attached thereto.
Each template pile guide 60 receives a pile 26, driven into place by the pile driver
17. After all the piles 16 and 26 are in place, and the template 19 is levelled, the
piles are secured to the template 19 by means well known in the art, preferably by
pumping grout into the pile guides 60.
[0016] Referring to Figures 5 and 6, a track installation barge or vessel 30 have been coupled
to the derrick barge 15 and moved upslope of the template 19. The track installation
vessel 30 contains successive track sections which are designated 31A, 31B, 31C, etc.
The sections 31A, 31B, 31C, etc., once joined, comprise the track (31) of the marine
railway system. The track pulldown cable 22 have been retrieved and a down slope railway
leader 70 has been releasably attached to the cable 22. The derrick barge 15 is used
to lift and position the railway leader 70 and the first track section 31A so that
they may be secured together above the surface 13 of the water.
[0017] Note that it is not essential to install the template 19. The down slope railway
leader 70 can be releasably attached to the cable 22 which in turn is pulled out and
away from the work vessels by an auxiliary vessel 20 and thereafter set on the bottom
12. This alternative method is shown in Figures 23 to 26 and is preferred when the
path of the track 31 is smooth enough to permit its use.
[0018] The railway leader 70 is shown in Figure 14. It includes a cable attachment means
71 to releasably attach the track pulldown cable 22, a pulley or cold water conduit
pulldown sheave 72 with a guide 73, a cold water conduit pulldown cable 35 reeved
therethrough, a cable conduit 74, track attachment means 75 for securing the leader
70 to the adjacent track section 31A, and a base 76 to which all the above are rigidly
attached.
[0019] A typical track section 31A is shown in Figures 15 to 18, which show conduits 80A
and 80B (or any other similarly shaped body having a length much greater than its
width) on each side of the track section 31A, running the length of the section 31A,
and defining its width. A plurality of supports 81 rigidly connect the two conduits
80A and 80B. A rail 82 of T-shaped cross-section is rigidly connected along the top
of each conduit 80A and 808, or two parallel rails are provided per track 31. The
cable conduit 74 is positioned between the conduits 80A and 80B and runs the length
of the track section 31A. Attached to each section 31A, 31B is a track pile guide
section 84. Although only one track pile guide section 84 (Figure 17) is shown, it
should be understood that any necessary and reasonable number could be used with any
one track section 31A, 31B etc. Each track pile guide section 84 is shown to have
two track pile guides, sleeves or tubes 83.
[0020] The track sections 31A, 31B, 31C, etc. are successively attached as the pulldown
cable 22 is used to pull the joined track sections 31A, 31B, 31C, etc. towards the
template 19. Those sections 31A, 31B, 31C, etc. already joined define the track 31
and can be flooded or pressurised as required to maintain the desired track attitude
to avoid collapse due to the enormous external pressure exerted on closed bodies at
great depths. Care must also be taken to feed or pay out the cable 35 while pulling
the track 31 with the pulldown cable 22. In the event of bad weather, the assembled
track 31 can be set on the bottom 12 until conditions improve. Once the whole track
31 has been tacked together and threaded with the cable 35, the cable 22 is used to
pull the track 31 and railway leader 70 towards the template 19. At this point in
the installation process the pulldown cable 22 extends from the track installation
vessel 30 to the template sheave 61 and one end of the cable 22 is attached to the
down slope railway leader 70 at the cable attachment means 71. The cold water conduit
pulldown cable 35 extends from the track installation vessel 30 to the cold water
pulldown sheave 72 and through the cable conduit 74, and after leaving the upslope
end of the conduit 74 it extends back to one of the barges 15 and 30.
[0021] Figures 7 and 8 show a pile installation rig 40 attached to the cable 35 and thereafter
lowered onto the track 31 from the derrick barge 15. Figures 19, 20A and 20B show
that the pile installation rig 40 is positioned on the track 31 so that it rests on
and is slidably engaged by the rails 82. The rig 40 has a base 40A and a guide and
reaction member 40B. The base 40A is a dolly-like member that is guided by the rails
82 and on which surface-activated brakes 98, of well known type, are mounted. The
guide and reaction member 40B is attached to the base 40A and is composed of supports
92 and a torque motor 93 used to screw in track piles 34 through the track pile guide
tubes or sleeves 83. (However, dpending on soil conditions, a hammer (not shown) may
be mounted to drive in the piles). Figure 8 shows the pile installation rig 40 proceeding
down the railway track 31 installing the track piles 34 to grade. The track 31 is
then levelled with jacks (not shown) which are attached to the pile installation rig
40. Thereafter, each pile 34 (shown in Figure 8) is secured to the pile sleeve or
guide 83 in a manner well known in the art, preferably with the placement of grout
in the guides 83 which secure the track 31 to the bottom 12.
[0022] The cold water conduit pulldown cable 35 is used to pull the pile installation rig
40 downslope (i.e. downwardly along the sloping bottom 12) to continue the installation
of the track piles 34 until all necessary track piles 34 are installed. Upon completion,
the pile installation rig 40 is retrieved by pulling it upslope (i.e. upwardly along
the sloping bottom 12) to the upper end of the track 31, releasing it from the track
31, and hoisting it back aboard the barge 15 or 30.
[0023] Referring to Figures 9 and 10, the track pulldown cable 22 has been released and
pulled back to the derrick barge 15. The track installation barge 30 has been removed
and a materials barge containing a first section or inlet 50A of a cold water conduit
50 is brought alongside the derrick barge 15. The first section 50A of the cold water
conduit 50 is releasably connected to the cold water conduit pulldown cable 35. The
cable 35 is used to pull the conduit sections 50A, 50B, 50C, etc., into place once
they have been lowered onto the track 31 and slidably engaged with the rails 82. Mechanical
brake means (not shown), which are attached to each of the cold water conduit sections
50A, 50B, 50C, etc., can be engaged from the surface and are used to secure each section
of the cold water conduit 50 to the track 31 once in position. The cable 35 is then
released from the cold water conduit 50. The brake means could comprise any of the
following systems; an explosive pin, a mechanically driven wedge, or the use of chemicals
to create a metal to metal bond.
[0024] As shown in Figures 21 and 22, each conduit section 50A, 50B, 50C etc., has at least
two saddle supports 90. Each saddle support 90 extends approximately the width of
the track 31 and has a concave top side 91 to which are mounted pads (not shown) upon
which the cold water conduit 50 rests.
[0025] The cable 35 is a continuous loop cable which runs from the derrick barge 15 through
the cable conduit 74, through the cold water pulldown sheave 72 and then back to the
derrick barge 15. Once the conduit section 50A is pulled into position, it is secured
to the track 31, the cable 35 is released from the conduit inlet section 50A and the
next conduit section 50B is releasably attached thereto. Each successive conduit section
is lowerred onto the track 31 and pulled into position by the cold water pulldown
cable 35. Figure 11 shows the completed installation of the cold water conduit 50,
and also shows a discharge conduit 100 and a shelf-mounted OTEC fossil or nuclear
power plant 102 upon which the necessary pumps are located.
1. A method of installing a submarine cold water conduit, characterised by the steps
of:
installing and securing at least one railway track means (31) to an underwater land
formation (12), and
installing and securing a cold water conduit (50) to the railway track means (31).
2. A method according to claim 1, wherein the track means (31) comprises two substantially
parallel rails (82).
3. A method according to claim 1 or claim 2, wherein the underwater land formation
(12) is first surveyed to obtain geotechnical and mapping data.
4. A method according to claim 1, claim 2 or claim 3, wherein the cold water conduit
(50) is installed and secured to the track means (31) in sections (50A, 50B etc).
5. A method according to claim 4, wherein the submarine cold water conduit (50) is
installed on a sloping underwater land formation (12) constituting the bottom of a
body of water, the method comprising the steps of:
a) attaching a first section (31A) of the marine railway track means (31) to a track
pulldown cable (22),
b) rigidly fastening successive sections (31B etc.) of the marine railway track means
(31) to the first section (31A) of the railway track means until the marine railway
track means is attached together while simultaneously threading each track section
with a cold water conduit pulldown cable (35) and thereafter pulling the track pulldown
cable (22) with a cable pulling means,
c) lowering the track means (31) onto the underwater land formation (12),
d) securing the track means (31) to the underwater land formation (12) with track
piles (34) using a pile installation rig means (40),
e) releasably attaching the conduit pulldown cable (35) to a first (50A) or subsequent
(50B etc.) section of the cold water conduit (50) and pulling it into position on
the track means (31) using the conduit pulldown cable (35),
f) securing the cold water conduit section (50A, 50B etc.) to the track means (31)
by a brake means and repositioning the conduit pulldown cable (35), and
b) repeating steps (e) and (f) for each cold water conduit section (50A, 50B etc.)
until all the conduit sections are in place.
6. A method according to claim 5, comprising an initial step of installing, levelling
and securing a deadman template (19) to a downslope area of the sloping underwater
land formation (12).
7. A method according to claim 6, wherein the step of installing, levelling and securing
the deadman template (19) comprises the steps of:
a) installing a bench mark pile (16) with a pile driver (17),
b) placing the deadman template (19) having a pulley (61) reeved with the track pulldown
cable (22) atop the bench mark pile (16) by slidably fitting a template pile guide
(62) over the bench mark pile (16),
c) installing a pile (26) in each of a plurality of template pile guides (60),
d) levelling the template (19) with grout bags (63), and
e) securing the piles (26) to the template (19) with securing means.
8. A method according to claim 5, claim 6 or claim 7, wherein an elongate down slope
railway leader (70) is attached in the vicinity of one end thereof to the track pulldown
cable (22) and is secured to the first section (31A) of the railway track means at
its other end.
9. A method according to any one of claims 5 to 8, wherein the track pulldown cable
(22) is releasably attached.
10. A method according to any one of claims 5 to 9, wherein the step of lowering the
railway track means (31) onto the underwater land formation (12) comprises the step
of pressurising or flooding the track means to maintain proper track means attitude.
11. A method according to any one of claims 5 to 10, wherein the step of securing
the railway track means (31) to the underwater land formation (12) with track piles
(34) using a pile installation rig means (40) comprises the steps of:
a) installing the piles (34) to grade through a series of pile sheaves (83) attached
to the track means (31);
b) levelling the track means (31) with jacks attached to the pile installation rig
means (40), and
c) securing the piles (34) to the pile sheaves (83) with securing means.
12. A method according to any one of claims 4 to 11, wherein each cold water conduit
section (50A, 50B etc.) has at least one saddle support (90) and pads attached thereto.
13. A method according to any one of the preceding claims, wherein the railway track
means (31) is completely fabricated above water and thereafter installed and secured
to the underwater land formation (12).