[0001] This application pertains to a method of constructing an underwater fill (i.e. so
as to form an artificial island, causeway, breakwater, etc.) and to apparatus adapted
to carry out the method. More particularly, the application pertains to a method of
constructing an underwater fill so as to increase the density of the underwater fill
pile, increase the angle of inclination of the pile side slopes and improve the fill's
ability to resist erosion. The apparatus is used to withdraw water from the underwater
fill pile as fresh fill is added to the pile.
[0002] Artificial islands, causeways, breakwaters and other civil engineering structures
are constructed using well-known underwater fill techniques. Typically, particulate
fill material such as sand or sand-silt is excavated at an underwater site termed
the "borrow pit" and then dumped at an underwater construction site at which the particular
structure is desired. Usually, very large quantities of fill material must be excavated
and dumped at the underwater construction site in order to accumulate an adequate
base to support whatever structures may be desired above the surface of the water.
For example, if it is desired to build a causeway, then sufficient underwater fill
must be dumped at the construction site to form an above-water surface upon which
a road or railbed of desired width may be constructed. Similarly, if it is desired
to build an artificial island, then sufficient fill must be deposited at the underwater
construction site to yield an island having an above-water surface area adequate to
support whatever buildings or equipment may be required to satisfy the contemplated
end use of the island.
[0003] Masses of particulate fill dumped at an underwater site tend to form underwater fill
piles shaped like truncated cones. It has been found that the side slopes of such
piles typically form an angle of about three to five degrees with respect to the horizontal.
It is the relatively shallow side slope inclination of the underwater fill pile which
necessitates dumping massive quantities of fill material at the underwater construction
site in order to accumulate an underwater base which will yield the desired above-water
surface area.
[0004] Suppose, for example, that it is desired to construct an artificial island in fifteen
meters of water such that the island surface is circular, one- hundred meters in diameter
and projects two metres above the surface of the water. It can easily be shown that
about 1,300,000 cubic metres of fill material would be required to construct the island
if its sides slope at about five degrees with respect to the horizontal. Approximately
three to four months would be required to construct the island using conventional
dredging techniques.
[0005] Clearly, the time required to construct an island or other underwater structure could
be reduced if the amount of fill material required could be reduced. Reduced construction
time is of particular interest with respect to Arctic construction projects since
climatic conditions in the Arctic permit construction operations to be carried out
for at most three months of the year. The cost of constructing an artificial island
(or other underwater fill) could also clearly be reduced by reducing the amount of
fill material consumed. Concomitant environmental advantages may also be obtained
by reducing the amount of fill material consumed, since the size of the borrow pit
could be minimized, along with the surface area of the underwater bed upon which fill
material must be deposited to yield the desired structure.
[0006] Obviously, the amount of material required to construct an underwater fill may be
reduced so as to yield the aforementioned advantages by steepening the angle of inclination
of the pile side slopes with respect to the horizontal. For example, if the artificial
island discussed in the above example could be constructed with side slopes angled
at fifteen degrees with respect to the horizontal, then only about 370,000 cubic metres
of fill material would be required. Stated another way, less than one-third as much
fill material, requiring only about one-third as much time to excavate and deposit,
would be required to construct the island with fifteen degree side slopes as opposed
to five degree side slopes. If the island was to be constructed in thirtyfive metres
of water (as opposed to fifteen metres of water), then an island with fifteen degree
side slopes would consume less than twenty percent as much fill material and construction
time as an island having five degree side slopes. Indeed, the amount of fill and time
required to construct an island having fifteen degree side slopes in thirty-five metres
of water is roughly the same as would be required to construct a conventional island
(having five degree side slopes) in only fifteen metres of water.
[0007] The difficulty, of course lies in overcoming the natural tendency of particulate
fill material to accumulate in piles having three to five degree side slopes when
deposited underwater during conventional construction operations. The state of the
art is such that it is currently considered impractical to use underwater fill techniques
to construct artificial islands in Arctic water deeper than about fifteen meters,
since the shallow (i.e. about three to five degree) angle of inclination of the fill
pile side slopes necessitates excavation and dumping of more material than can be
handled during the short Arctic construction season. Where large working platforms
are required in deeper Arctic water (i.e. up to about thirty-five metres), current
practice is to utilize a costly structure (about $l50,000,000) resting on a sand filled
berm about ten meters high formed with conventional underwater fill techniques.
[0008] The present invention provides a method and apparatus for constructing an underwater
fill which overcomes the foregoing disadvantages, facilitating construction of underwater
fills having side slopes inclined at angles significantly greater than five degrees
with respect to the horizontal, thereby greatly reducing the amount of fill material
and time required.
[0009] The inventor believes that the angle of inclination with respect to the horizontal
at which particulate fill may accumulate during construction of a conventional underwater
fill pile is limited by forces generated during construction of the fill. Such forces
are believed to originate in the potential energy of the fill material dumped onto
the pile, to develop within the pile and to act essentially radially outwardly against
the pile side slopes as the pile is-formed. In particular, the inventor believes that,
during construction, fresh fill material dumped onto the accumulating underwater fill
pile tends to compress "pore water" trapped in the interstices between adjacent particles
of fill within the pile. Since water is virtually incompressible, the pore water tends
to flow radially outwardly from the centre of the accumulating pile, to escape therefrom
at the side slope interface between the pile and the surrounding water. It is believed
that the escaping pore water subjects the pile side slopes to forces which tend to
knock the side slopes down (or at least tend to flatten the side slopes). The inventor
believes that the side slope inclination of the fill pile may be increased by countering
the aforementioned forces. To that end, the inventor proposes that, during construction
of the underwater fill, water be withdrawn from the pile in controlled fashion and
at a rate approximately equal to the rate at which pore water would otherwise be forced
out of the pile by fresh fill dumped onto the accumulating fill pile. It is believed
that this will minimize the afore-mentioned forces and thus allow the underwater fill
pile to accumulate with side slopes much steeper than those conventionally obtained.
[0010] Further benefits are believed to be attainable if the water withdrawal operation
is effected such that water is drawn into the accumulating fill pile at the interface
between the developing side slopes of the pile and the surrounding water. That is,
although it is desirable to minimize the flow of water out from the sides of the pile,
it is more desirable to stop the outward flow of water altogether and even more desirable
to reverse the flow so that water flows into the sides of the accumulating fill pile,
thereby supporting the pile side slopes as they are formed and consequently enabling
the formation of a steeper, more dense pile. In particular, it is believed that the
density of the underwater fill may be significantly increased by drawing water thereinto
as aforesaid. Increased density is desirable in underwater fill construction since
any post-construction shaking of a loosely formed underwater fill may cause settling
or even a catastrophic failure (ie. collapse) of the fill. The accumulating pile also
has an improved capability to resist erosion at the regions from which water is withdrawn.
[0011] The foregoing theoretical discussion is not to be taken as limiting the invention
- it is presented only to assist those skilled in the art in understanding the invention.
Because the underlying theories are not well settled, the inventor has developed several
statements of characterization for the invention which differ only in the way they
express the underlying theory. For example, the invention may be characterized as
being directed to a method of relieving water pressure within an underwater fill during
construction of the fill, comprising withdrawing water from the underwater fill as
fresh fill is added thereto, such that the work done on water withdrawn from the underwater
fill is approximately equal to the energy introduced into the underwater fill by the
combined action of fill material dumped onto the pile and water set in motion by the
material as it settles onto the pile. The invention may alternately be characterized
as being directed to a method of relieving water pressure within an underwater fill
during construction of the fill, comprising withdrawing water from the underwater
fill as fresh fill is added thereto, such that water flow out from the pile side slopes
is minimized, stopped or reversed. Alternatively, the invention may be characterized
as being directed to a method of increasing the side slope inclination of an underwater
fill pile, comprising withdrawing water from the pile as fresh fill is added thereto.
As a further alternative, the invention may be characterized as being directed to
a method of increasing the packing density of particulate fill deposited in an underwater
pile, comprising withdrawing water from the pile as fresh fill is added thereto.
[0012] In accordance with the preferred embodiment of the invention, apparatus adapted to
carry out the afore- mentioned methods comprises a perforated conduit, a pumping means
for pumping water, and a closed conduit for water communication between the perforated
conduit and the pumping means. Operation of the pumping means causes water to be withdrawn
from underwater fill surrounding the perforated conduit. The withdrawn water is passed
through the perforated conduit and through the closed conduit for ultimate discharge
from the pumping means.
[0013] Advantageously, a moveable sealing means is provided for sealing a selected portion
of the perforated conduit to prevent water communication through the selected portion.
The perforated conduit is perforated over at least a portion of its length and the
sealing means is preferably moveable with respect to the perforated portion so as
to permit pore water communication through a selected portion of the perforated portion.
The perforations in the perforated conduit are selectably sized to prevent substantial
passage of fill particles into the perforated conduit.
[0014]
Figure 1 is a fragmented plan view of an apparatus for constructing an underwater
fill in accordance with the invention.
Figure 2 is a cross sectional illustration of a portion of the apparatus of Figure
1, taken with respect to lines II-II of Figure 1.
Figure 3 is a schematic illustration showing how multiple units of the apparatus of
Figure 1 may be deployed to construct an artificial island.
Figures 4 through 9 are enhanced side sectional illustrations of a portion of the
apparatus of Figures 1 and 3, taken with respect to line IV-IV of Figure 3, and illustrate
the operation of the apparatus of Figure 1 during successive stages of construction
of an underwater fill.
Figure 10 illustrates an alternative form of the apparatus of Figure 2.
[0015] Figure 1 illustrates apparatus 10 for withdrawing water from an underwater fill during
construction of the fill. Reference numeral 12 indicates the surface of the water
beneath which the construction operation is carried out. Reference numeral 14 indicates
the seabed upon which particulate fill such as sand 16 is deposited as hereinafter
described to construct the underwater fill.
[0016] Apparatus 10 includes a plurality of perforated conduits 18 arranged in spaced, substantially
parallel configuration, a pumping means such as pump 20 and a normally submerged closed
conduit comprising conduit portions 22, 24 and 26 which facilitate water communication
between perforated conduits 18 and pump 20. As hereinafter explained in greater detail,
pump 20 (which may be mounted upon a floating platform 28) draws water through perforated
conduits 18 and through conduit portions 22, 24 and 26 for discharge from pump outlet
30. (Preferably, the discharge from pump outlet 30 is directed as far away from the
underwater construction site as possible to minimize forces acting upon the accumulating
underwater fill pile.) Selected portions of perforated conduits 18 are exposed (as
hereinafter explained) to the accumulating underwater fill pile such that operation
of pump 20 causes water to be withdrawn from underwater fill surrounding the exposed
portions of perforated conduits 18 for passage through conduit portions 22, 24, 26
and discharge from pump outlet 30.
[0017] Advantageously, to minimize damage which may be caused by relative motion between
floating platform 28 and the seabed 14, conduit portion 22 takes the form of a flexible
hose. Such flexibility also simplifies movement of conduit portions 24, 26 and perforated
conduits 18 as hereinafter described. Conduit portion 24 may advantageously take the
form of a rigid pipe-like "header" having a plurality of conduit portions 26 depending
therefrom as illustrated in Figure 1. Conduit portions 26 may also be of rigid pipe-like
construction, capable of telescoping over perforated conduits 18 as hereinafter described.
Header 24 may conveniently be about 30 metres long and have depending therefrom about
twenty conduit portions 26, each spaced about 1.5 metres apart, with an equal number
of perforated conduits 18.
[0018] Initially, the portion of the apparatus comprising header 24, conduit portions 26
and perforated conduits 18 is suspended from cables 32 and lowered to seabed 14 from
platform 28 by means of winches 34. Cables 32 are left slack once the apparatus reaches
the seabed and sufficient fill has accumulated around the base of the apparatus to
hold it upright. Cables 32 and winches 34 serve as a "remote manipulator means" for
remotely moving conduit portions 26 with respect to perforated conduits 18 as hereinafter
described. The weight of the apparatus causes anchoring means in the form of spikes
36 at the base of each of perforated conduits 18 to penetrate seabed 14 and hold the
apparatus in position until it becomes covered by sand as hereinafter described. Structural
integrity is provided by base plate 40 (Figure 2) connector plates 37 which interconnect
the ends of perforated conduits 18 opposite header 24. Valves 38 provided between
each of conduit portions 26 and header 24 may be selectively closed to prevent water
communication between header 24 and the associated conduit portion 26 and perforated
conduit 18, in the event of a rupture or other occurrence resulting in a significant
loss of pressure necessitating isolation of the remainder of the apparatus to prevent
degradation of overall performance.
[0019] Further details of the construction and operation of perforated conduits 18, header
24 and conduit portions 26 will now be provided with reference to Figure 2, which
is a cross sectional illustration taken with respect to line II-II of Figure 1.
[0020] As may be seen in Figure 2, anchoring spike 36 protrudes from a base plate 40 which
is releasably attached to the base 42 of perforated conduit 18 by connecting means
such as shear pins 44. Base plate 40 limits the depth to which conduit portion 18
may penetrate seabed 14.
[0021] Perforated conduit 18 is of generally cylindrical construction and has perforations
46 extending over a substantial portion of its length. Perforations 46 are sized to
prevent substantial passage of fill particles into perforated conduit 18. For example,
if the underwater fill is to be constructed from typical uniform Delta sand in which
about 90% of the sand grains are from .1 to .4 millimetres in diameter, perforations
46 may be provided by a number 70 or number 100 (A.S.T.M. standard) wire mesh screen
48 (ie. screen 48 would in such case have apertures about .2 millimetres on a side).
Preferably, perforated conduit 18 is perforated over about 1.5 metres of its length,
the perforated portion commencing at base 42 and extending upwardly therefrom. A perforated
tube 50 attached to base 42 and having apertures much larger than those in screen
48 provides internal support for screen 48.
[0022] As may be seen in Figure 2, conduit portion 26 has a sleeve-like portion comprising
an outer wall 49 and an inner wall 51, which portion is slidable telescopically over
perforated conduit 18. A "sealing means" in the form of tough rubber or elastomeric
skirt 52 is fitted around and overlaps the lower end of each conduit portion 26 to
prevent water communication through the portion of perforated conduit 18 which is
covered by the afore-mentioned sleeve-like portion of conduit portion 26 and skirt
52. The portion of skirt 52 which overlaps the end of conduit portion 26 is drawn
tightly against the immediately adjacent outer surface of perforated conduit 18 by
the suction created by pump 20 and thus facilitates sealing of a selected portion
of perforated conduit 18 so as to prevent water communication through that selected
portion.
[0023] When the apparatus is initially lowered to seabed 14, perforated conduits 18 are
telescoped inside the afore-mentioned sleeve-like portions of conduit portions 26,
leaving no portion of perforated conduits 18 exposed beneath sealing means and thereby
precluding water communication through the system. As hereinafter explained in greater
detail, fill material deposited at the underwater construction site accumulates around
the base of perforated conduits 18, thereby firmly holding the apparatus in position
on seabed 14. When perforated conduits 18 are thus anchored on seabed 14, winches
34 may be operated to slowly raise cables 32, header 24 and conduit portions 26, thereby
slidably raising skirts 52 with respect to anchored perforated conduits 18 to expose
a selected portion of each of perforated conduits 18 to the surrounding fill material.
A "wedge means" such as the locking dog assembly comprising dog member 54 and annular
shoulder 56 permits raising of conduit portions 26 with respect to perforated conduits
18, but precludes subsequent lowering of conduit portions 26. Conduit portions 26
and skirts 52 may thus be selectively incrementally raised with respect to perforated
conduits 18 to expose progressively larger sections of perforated conduit 18 to the
surrounding fill as the underwater construction operation progresses.
[0024] Eventually, as conduit portions 26 and skirts 52 are further raised with respect
to perforated conduits 18, internal shoulder 58 of conduit portion 26 contacts the
opposing internal shoulder 60 of perforated conduit 18, thereby preventing further
upward movement of conduit portion 26 and skirt 52 with respect to perforated conduit
18. Further operation of winches 34 after shoulders 58, 60 come into contact so as
to subject the apparatus to further upward forces, will eventually cause shear pins
44 to shear, thereby freeing the apparatus from base plate 40, which is disposable
and remains buried in the underwater fill. Advantageously, conduit portions 26 and
perforated conduits 18 may have a slight inverted conical taper (not discernible in
the drawings) to ease their withdrawal from the accumulating fill pile. The apparatus
may then be raised slowly to the surface as underwater construction operations continue,
to serve its purpose of withdrawing water from the accumulating fill pile in the region
beneath the interface between the fill pile and the surrounding water and of drawing
water into the fill pile at that interface.
[0025] A flexible "development conduit" 62 extends from header 24 inside conduit portions
26 to the bottom of perforated conduit 18. The end 64 of development conduit 62 is
left open and is anchored to base 42 by means of bracket 66. Development conduit 62
facilitates "development" of fill in the region surrounding perforated conduit 18
as hereinafter described to purge that region of finer particulate matter which might
clog perforated conduit 18 and to improve water flow through said region to the interior
of perforated conduit 18.
[0026] Figure 3 is a top view which illustrates how multiple units of apparatus like that
shown in Figure 1 may be deployed at a construction site to construct an artificial
island. A fixed working platform 68 may be positioned at the desired centre of the
island (presuming that the island, when completed, will be of approximately circular
shape). Particulate fill material to be deposited at the underwater construction site
is supplied, in the form of a slurry, to platform 68 through dredge pipe 70. Multiple
units of apparatus like that described above are deployed from a series of floating
platforms 28 along the desired shoreline of the finished island (indicated in Figure
3 by broken line 72). Cables 74, 76 tether floating platforms 28 (from which the apparatus
is deployed) to fixed platform 68 and to remote anchors (not shown).
[0027] Figures 4 through 9 are a series of side sectional illustrations taken with respect
to line IV-IV of Figure 3 which show successive stages of operation of the apparatus
which has been described with reference to Figures 1 and 2.
[0028] Figure 4 illustrates how working platform 68 may be suspended above the water surface
12 and fixed with respect to seabed 14 by means of legs 78 which extend from the underside
of platform 68 into seabed 14. (Alternatively, platform 68 may be a floating, tethered
platform.) Figure 4 also illustrates one of the floating platforms 28 upon which pump
20 and winches 34 are mounted. In Figure 4, header 24, conduit portion 26 and perforated
conduit 18 have just been lowered on cable 32 to seabed 14 such that spike 36 penetrates
seabed 14, anchoring the apparatus in position such that perforated conduits 18 are
upstanding on seabed 14 and resting on their respective base plates 40. As previously
described, the apparatus is initially deployed with perforated conduits 18 telescoped
inside conduit portions 26, leaving no portion of perforated conduits 18 exposed beneath
skirts 52. Particulate fill material (excavated from the borrow pit) is supplied as
a slurry to working platform 68 through dredge pipe 70 and is discharged from platform
68 onto seabed 14 as indicated by arrows 80. The particulate fill material 16 may
be seen in Figure 4 accumulating beneath platform 68 in a pile having shallow (ie.
3° - 5°) sloped sides. Since it takes some time to accumulate a sufficient base of
fill on seabed 14 before operation of the apparatus can be commenced effectively,
the excavation/discharge operation may be ongoing as platforms 28 are positioned and
the apparatus deployed therefrom to the position shown in Figure 4.
[0029] Particulate fill material is dumped onto seabed 14 from dredge pipe 70 until the
lower portion of perforated conduit 18 has been covered with fill material to a depth
of about 1.5 meters as depicted in Figure 5. Reference numeral 82 illustrates the
conventional shallow (ie. about 3° - 5°) angle with respect to seabed 14 at which
the particulate fill material accumulates. Once perforated conduit 18 has been buried
as aforesaid winch 34 is activated to raise cable 32, header 24 and conduit portion
26 to expose about a .5 metre length of perforated conduit 18 to the surrounding fill.
The fill region immediately surrounding the exposed portion of perforated conduit
18 is then "developed" with pump 20 and development conduit 62 by periodically reversing
the operation of pump 20 to cause water to surge alternately inwards and outwards
through the exposed mesh of screen 48 into the surrounding fill material. This action
removes from the region of conduit 18, through conduit 62, finer fill material which
might clog screen 48 and generally enhances the ability of the surrounding fill region
to pass water toward the exposed portion of perforated conduit 18. After the surrounding
fill region has been adequately developed (the time required to do so being heavily
dependent upon the characteristics of the fill material) pump 20 is operated so as
to withdraw water from the fill region surrounding the exposed section of perforated
conduit 18, through perforated conduit 18, and conduit portions 26, 24, 22 for discharge
from pump 20. Such pumping continues as long as fill is being discharged from dredge
pipe 70 onto the accumulating fill pile.
[0030] Figure 6 depicts a later stage at which sufficient fill material has been discharged
from dredge pipe 70 to form a fill pile about 3 - 4 metres deep in the vicinity of
perforated conduit 18. In Figure 6, winch 34 has been further activated to raise cable
32, header 24 and conduit portion 26 so as to gradually increase the portion of perforated
conduit 18 which is exposed to the surrounding fill. Pump 20 continues to operate
to draw water from the region surrounding the exposed portion of conduit 18, into
the interior of conduit 18 and thence through conduit 18, conduit portion 26, header
24 and flexible conduit 22 for discharge from pump outlet 30. Winch 34 is periodically
operated as fill material accumulates above the exposed section of perforated conduit
18 to incrementally raise conduit portion 26 and skirt 52 with respect to perforated
conduit 18 so as to maintain about one to two metres of fill material above the exposed
section of perforated conduit 18. As pump 20 continues to operate, water is withdrawn
from the region of the fill pile surrounding the exposed section of conduit 18 and
is also drawn into the fill pile at the interface between the pile and the surrounding
water, thereby offsetting the forces previously mentioned, facilitating steepening
of the pile side slopes (as shown at 84) and the formation of a denser pile having
improved erosion resistance at the waterline. As may be seen in Figure 6, withdrawal
of water from the region surrounding the exposed section of perforated conduit 18
results in a transition in the angle of the pile side slope from the relatively shallow
angle shown at 82 to the preferred, relatively steep angle shown at 84.
[0031] As more fill material is added to the underwater fill pile, winch 34 is further periodically
operated to increase the length of perforated conduit 18 which is exposed to the surrounding
fill, thus increasing the fill region from which water is withdrawn. Eventually, shoulders
58, 60 (Figure 2) come into contact with one another and further operation of winch
34 to raise conduit portion 26 with respect to perforated conduit 18 ruptures shear
pins 44, thereby freeing perforated conduit 18 from base plate 40. As illustrated
in Figure 7, the freed assembly is drawn slowly upward through the fill pile as more
fill is added thereto, always maintaining about one to two metres of fill above the
uppermost exposed portion of perforated conduit 18 so that continued operation of
pump 20 results in water withdrawal from the accumulating fill pile in the region
about one to two metres beneath the region of transition from the relatively shallow
slope 82 to the desired steeper slope 84.
[0032] Figure 8 illustrates a still further advanced stage at which conduit portion 26 has
been withdrawn from the fill pile to protrude above the water surface 12 while perforated
conduit 18 remains buried beneath the surface of the fill pile and pump 20 continues
to operate as the final portion of fill material required to break surface is discharged
onto the fill pile through dredge pipe 70. Continued operation of pump 20 at this
stage is believed to enhance the resistance of the developing fill shoreline to erosion
by wave lapping and scouring until sandbags or other reinforcing means can be positioned.
After the fill pile has broken surface to the required height, the apparatus is disassembled
and removed and the shoreline protected as shown at 86 in Figure 9 to leave the finished
underwater fill 88.
[0033] Figure 10 illustrates an alternate form of the apparatus shown in Figure 2. This
alternate form eliminates conduit portions 22 and 24 and includes an integral pump,
thereby allowing greater flexibility in placement of the apparatus. Cable 102 protrudes
through the upper end 104
'of apparatus 100 and is connected to a sealing means 106. Sealing means 106 includes
an inner conduit 108 with seals 110, 112 fixed at the upper and lower ends thereof.
[0034] Seals 110, 112 provide a watertight seal against the inner surface of conduit 114.
Conduit 114 is made long enough to extend from the base to the top of the pile, and
is perforated over the entire length to be covered by fill material. (Initially some
lateral support - not shown - must be provided to hold conduit 114 upright until sufficient
fill has accumulated around the base of conduit 114 to support the conduit.) Seals
110, 112 subdivide the inner portion of conduit 114 into upper, central and lower
compartments 116, 118 and 120.
[0035] Pump 122 may be positioned in lower compartment 120 or in central compartment 118.
Pump 122 is operated to draw water through the pump intake 124 and through the perforated
portion of conduit 114 surrounding lower compartment 120 into and through inner conduit
108 for discharge into upper compartment 116 from which the water flows outward through
the perforated portion of conduit 114 encircling upper compartment 116 and into the
surrounding water.
[0036] When apparatus 100 is initially placed on seabed 14 inner conduit 108 and seals 110,
112 are positioned so that the base of lower seal 112 is about one metre above the
base 126 of conduit 114. Once fill has accumulated on seabed 14 to a depth of about
1.5 metres (illustrated, for example, at 128) pumping may commence. As further fill
is deposited on the accumulating pile conduit 108, seals 110, 112 and pump 122 may
be incrementally raised on cable 102 to maintain about one to two metres of fill above
the uppermost end of lower compartment 120. (As conduit 108 and seals 110, 112 are
raised, the volume of lower compartment 120 increases while the volume of upper compartment
116 correspondingly decreases.) Once the fill has been completed cable 102, conduit
108, seals 110, 112 and pump 122 are withdrawn from conduit 114 which remains in place.
[0037] As will be apparent to those skilled in the art in the light of the foregoing disclosure,
many alterations and modifications are possible in the practice of this invention
without departing from the spirit or scope thereof. Accordingly, the scope of the
invention is to be construed in accordance with the substance defined by the following
claims.
1. A method of relieving water pressure within an underwater fill during construction
of said fill, comprising withdrawing water from said underwater fill as fresh fill
is added to said underwater fill, such that the work done on water withdrawn from
said underwater fill is approximately equal to the energy introduced into said underwater
fill by said fresh fill and by water set in motion by said fresh fill.
2. A method of relieving water pressure within an underwater fill during construction
of said fill, comprising withdrawing water from said underwater fill as fresh fill
is added to said underwater fill, so that water flow from within said underwater fill
to the water surrounding said underwater fill is minimized.
3. A method of relieving water pressure within an underwater fill during construction
of said fill, comprising withdrawing water from said underwater fill as fresh fill
is added to said underwater fill, so that water surrounding said underwater fill flows
into said fill.
4. A method of constructing an underwater fill, comprising the steps of:
(a) depositing fill at an underwater site; and,
(b) as fresh fill is deposited at said site, withdrawing water from fill previously
deposited at said site such that the work done on water withdrawn from said fill is
approximately equal to the energy introduced into fill deposited at said site by said
fresh fill and by water set in motion by said fresh fill.
5. A method of constructing an underwater fill, comprising the steps of:
(a) depositing fill at an underwater site; and,
(b) as fresh fill is deposited at said site, withdrawing water from fill previously
deposited at said site so that water flow from within said deposited fill to the water
surrounding said deposited fill is minimized.
6. A method of constructing an underwater fill, comprising the steps of:
(a) depositing fill at an underwater site; and,
(b) as fresh fill is deposited at said site, withdrawing water from fill previously
deposited at said site so that water surrounding said deposited fill flows into said
deposited fill.
7. A method of increasing the side slope inclination of an underwater fill pile, comprising
withdrawing water from said pile as fresh fill is added to said pile.
8. A method of increasing the packing density of particulate fill deposited in an
underwater pile, comprising withdrawing water from said pile as fresh fill is added
to said pile.
9. A method as defined in claim 7 or 8, wherein the rate of water withdrawal from
said pile is such that the work done on water withdrawn from said pile is approximately
equal to the energy introduced into said pile by said fresh fill and by water set
in motion by said fresh fill.
10. Apparatus for withdrawing water from an underwater fill, comprising:
(a) a perforated conduit;
(b) pumping means for pumping water; and,
(c) a closed conduit for water communication between said perforated conduit and said
pumping means;
whereby operation of said pumping means withdraws water from underwater fill surrounding
said perforated conduit for passage through said conduits and discharge from said
pumping means.
11. Apparatus as defined in claim 10, further comprising moveable sealing means for
sealing a selected portion of said perforated conduit to prevent water communication
through said selected portion.
12. Apparatus as defined in claim 11, wherein said perforated conduit is perforated
over at least a portion of its length and wherein said sealing means is moveable with
respect to said perforated portion to permit pore water communication through a selected
portion of said perforated portion.
13. Apparatus as defined in claim 10, 11 or 12, wherein perforations in said perforated
conduit are selectably sized to prevent substantial passage of fill particles into
said perforated conduit.
14. Apparatus as defined in claim 10, 11 or 12, wherein perforations in said perforated
conduit are between about .1 mm. to about .2 mm. in diameter.
15. Apparatus as defined in claim 10, 11 or 12, wherein said perforated conduit is
tapered to facilitate withdrawal of said perforated conduit from fill surrounding
said perforated conduit.
16. Apparatus as defined in claim 10, 11 or 12, wherein said closed conduit is flexible
over at least a portion of its length.
17. Apparatus as defined in claim 10, 11 or 12, further comprising closeable valve
means for preventing water communication between said perforated conduit and said
closed conduit.
18. Apparatus as defined in claim 10, 11 or 12, wherein said closed conduit is connected
to one end of said perforated conduit and further comprising, at the opposite end
of said perforated conduit, anchoring means for anchoring said opposite end at the
site of said underwater fill.
19. Apparatus as defined in claim 10, 11 or 12, wherein said closed conduit is connected
to one end of said perforated conduit and further comprising, at the opposite end
of said perforated conduit:
(a) anchoring means for anchoring said opposite end at the site of said underwater
fill; and,
(b) shearable connecting means for connecting said anchoring means to said opposite
end;
whereby said perforated conduit may be withdrawn from fill surrounding said perforated
conduit by imposing a withdrawal force on said perforated conduit sufficient to shear
said connecting means.
20. Apparatus as defined in claim 12, further comprising wedge means for wedging said
sealing means in a selected position.
21. Apparatus for withdrawing water from an underwater fill, comprising:
(a) a plurality of perforated conduits arranged in spaced, substantially parallel
configuration;
(b) pumping means for pumping water; and,
(c) a closed conduit for water communication between said perforated conduits and
said pumping means;
whereby operation of said pumping means withdraws water from underwater fill surrounding
said perforated conduits for passage through said perforated conduits and through
said closed conduit and discharge from said pumping means.
22. Apparatus as defined in claim 21, further comprising, moveable sealing means for
sealing a selected portion of each of said perforated conduits to prevent water communication
through said selected portions.
23. Apparatus as defined in claim 22, wherein said perforated conduits are perforated
over at least a portion of their respective lengths, and wherein said sealing means
are moveable with respect to said perforated portions to permit pore water communication
through selected portions of said perforated portions.
24. Apparatus as defined in claim 21, 22 or 23, wherein perforations in said perforated
conduits are selectably sized to prevent substantial passage of fill particles into
said perforated conduits.
25. - Apparatus as defined in claim 21, 22 or 23, wherein perforations in said perforated
conduits are between about .1 mm. to about .2 mm. in diameter.
26. Apparatus as defined in claim 21, 22 or 23, wherein said perforated conduits are
tapered to facilitate withdrawal of said perforated conduits from fill surrounding
said perforated conduits.
27. Apparatus as defined in claim 21, 22 or 23, wherein said closed conduit is flexible
over at least a portion of its length.
28. Apparatus as defined in claim 21, 22 or 23, further comprising, closeable valve
means for selectably preventing water communication between selected ones of said
perforated conduits and said closed conduit.
29. Apparatus as defined in claim 21, 22 or 23, wherein said closed conduit is connected
across adjacent ends of each of said perforated conduits and further comprising, at
the opposite end of at least one of said perforated conduits, anchoring means for
anchoring said opposite end at the site of said underwater fill.
30. Apparatus as defined in claim 21, 22 or 23, wherein said closed conduit is connected
across adjacent ends of each of said perforated conduits and further comprising, at
the opposite end of at least one of said perforated conduits:
(a) anchoring means for anchoring said opposite end at the site of said underwater
fill; and,
(b) shearable connecting means for connecting said anchoring means to said opposite
end;
whereby said perforated conduits may be withdrawn from fill surrounding said perforated
conduits by imposing a withdrawal force on said perforated conduits sufficient to
shear said connecting means.
31. Apparatus as defined in claim 23, further comprising wedge means for wedging said
sealing means in selected positions.
32. Apparatus as defined in claim 21, 22 or 31, further comprising remote manipulating
means connected to each of said sealing means for remotely moving said sealing means
into selected positions.
33. Apparatus as defined in claim 21, 22 or 23, wherein said closed conduit is connected
across adjacent ends of each of said perforated conduits and further comprising a
base plate connected across the opposite ends of said perforated conduits.
34. A method of relieving water pressure in an underwater particulate fill comprising,
during construction of said fill, the steps of:
(a) spacing a plurality of upstanding, perforated conduits along the desired site
of sloped sides of said fill and on the underwater base of said site;
(b) interconnecting the uppermost ends of each of said perforated conduits with a
closed conduit to facilitate water communication between said perforated conduits
and said closed conduit;
(c) connecting a water pumping means to said closed conduit; and,
(d) operating said pumping means as fresh fill accumulates around said perforated
conduits, thereby withdrawing water from fill surrounding said perforated conduits
for passage through said perforated conduits and through said closed conduit and discharge
from said pumping means.
35. A method as defined in claim 34, further comprising, before said operating step,
sealing portions of said perforated conduits not covered by fill to prevent water
communication through said non-covered portions.
36. A method as defined in claim 34, further comprising sealing portions of said perforated
conduits which are not covered with fill to a depth of about one to two metres to
prevent water communication through said non-covered portions.
37. A method as defined in claim 36, further comprising, after commencement of said
operating step, and as additional fill accumulates around said perforated conduits,
gradually unsealing said sealed portions to maintain a depth of about one to two metres
of fill covering unsealed portions of said perforated conduits.
38. A method as defined in claim 37, further comprising, after the perforated portions
of said perforated conduits have been entirely unsealed, and as additional fill accumulates
around said perforated conduits, gradually withdrawing said perforated conduits from
said fill, while maintaining a depth of about one to two metres of fill covering said
perforated portions.
39. A method as defined in claim 34, 35 or 36 wherein adjacent ones of said perforated
conduits are spaced at least 1.5 metres apart.
40. A method as defined in claim 34, 35 or 36 wherein water withdrawn from fill surrounding
said perforated conduits is discharged at a point remote from the point at which fresh
fill is added to said underwater fill.
41. A method of increasing the packing density of particles accumulated in a water
saturated particulate mass, comprising withdrawing pore water from said mass while
applying a particle-compacting force to said mass.
42. A method as defined in claim 41, wherein said particle-compacting force is applied
by adding additional particles to said mass.
43. A method as defined in claim 42, wherein pore water is withdrawn from said mass
such that the work done on pore water withdrawn from said mass is approximately equal
to the energy introduced into said mass by said additional particles.
44. A method of increasing the packing density of particles accumulated in a water
saturated particulate mass, comprising withdrawing pore water from said mass while
applying inter-particle shear stress within said mass.
45. A method of constructing an underwater fill comprising, as fresh fill is deposited
at the underwater construction site, withdrawing water from fill previously deposited
at said site.