[0001] This invention relates to a method of constructing a modular bridge across a span
and to apparatus for use in such. a method.
[0002] In military operations, it is desirable, if not essential, to have a capability for
allowing heavy ground equipment, such as tanks, to cross difficulties in terrain.
Such difficulties may include gaps formed by ditches, canals and rivers. Although
the construction of a bridge for light vehicles is comparatively straight forward,
providing a bridge which is capable of supporting a tank is of considerably greater
difficulty.
[0003] EP-A-0081388 discloses a modular bridge comprising at least one intermediate bridge
module and two end bridge modules, each of the bridge modules comprising two longitudinal
main girder structures and an intermediate deck having a deck surface, the main girder
structures being foldably connected one along each side of the deck and being foldable
from an operative position in which the main girder structures offer extensions of
the deck surface on either side of the deck for use to a closed position in which
the main girder structures are folded beneath the deck, the main girder structures
of the end bridge modules being longitudinally tapered in depth when seen from a side
of the module in its operative position, the main girder structures of the intermediate
module(s) not being so tapered, wherein each of the end bridge modules and the intermediate
bridge module(s), are connected to form a bridge.
[0004] EP-A-0081388 discloses the construction of such bridge by putting up a.building frame,
having upwardly facing rollers, on the first bank of the span to be crossed. A preliminary
beam is assembled on the frame and pushed outwards towards the bank. The bridge assembly
is assembled progressively on the frame, behind the preliminary beam, with the beam
being attached to the leading module. The preliminary beam has at its outer end a
jacking unit with support rollers so that, when the jacking unit reaches the far bank
of the span, it may rest on it and allow the assembly of beam and bridge to roll across
the span, the bridge assembly is then lowered onto the bank and the beam withdrawn
back through the bridge assembly. This procedure is illustrated in Figures 23A to
23F of EP-A-0081388.
[0005] EP-A-0075671 discloses a demountable non-opening bridge comprising discrete channel-section
modules and ana H-section launching girder, wherein modules comprise a central part
and two wing parts, the wing parts comprise box-section track girders, the two wing
parts are downwardly hinging below the central part for transportation, in the laying
of the bridge the launching girders are assembled and made first, whereafter the various
modules are coupled together and pushed over the launching girder and the launching
girder remains in the bridge as a bearing element.
[0006] EP-A-0075671 discloses the construction of such a bridge by the joint use of a laying
vehicle having a cantilever arm and a four-tonne crane. The laying vehicle moves to
the bank of the span to be crossed with a launching girder ramp (or end) member already
in position on guide rollerscf the cantilever arm. The cantilever arm comprises a
pinion to advance the ramp member over the span by means of a co-operating rack. The
crane delivers launching girder inner sections which are coupled up and advanced.
Once the launching girder has reached the required length, a second launching girder
ramp (end) member is coupled up. The cantilever arm of the laying vehicle is lowered
so that the launching girder is then supported by its own hydraulically deployable
feet. A ramp (end), bridge module is now lifted by the crane onto the launching girder.
Inner (intermediate) bridge modules are coupled up and drawn over the launching girder
by means of a block and tackle and reversing roller. The final module is a further
ramp (end) module. The hydraulic feet are then retracted. This construction sequence
is as illustrated in Figure 6 of EP-A-0075671.
[0007] EP-A-0075611 also discloses the use of a single laying vehicle combining the capabilities
of the laying vehicle and crane described above. It is equipped both with a cantilever
arm and with a four-tonne crane.
[0008] The present invention enables the construction of a modular bridge across a span
without the requirement for specialist vehicles. Furthermore, it is desirable for
bridges of this type to be capable of being built quickly, even at night, by few men.
[0009] According to a first aspect of the present invention, there is provided a method
of constructing a modular bridge across a span, the method comprising placing at least
a first trestle on the home bank of the span, placing a first module of a modular
launching rail on the trestle, connecting one or more subsequent launching rail modules
to the launching rail being formed, placing a first bridge module on the launching
rail, connecting one or more subsequent bridge modules to the bridge being formed,
booming out the launching rail across the span and launching the bridge across the
span along the launching rail.
[0010] The first trestle preferably has one or more rollers for supporting the launching
rail, the rollers desirably being drivable to move the launching rail over the beam
of the first trestle. The first trestle also preferably comprises one or more rollers
for supporting the bridge modules.
[0011] A trestle suitable for use in the above method of construction forms a second aspect
of the invention, according to which there is provided a trestle comprising a support
beam lockably movable, on one or more guide- posts, towards and away from the ground
on which the trestle is located, means for supporting a bridge launching rail on the
beam in such a way that the rail can move over the beam, means for supporting a bridge
module on the beam in such a way that the bridge module can move over the beam and
means for moving the rail over the beam.
[0012] The launching rail is preferably of inverted-T shaped configuration. This configuration
allows the effective use of lateral guide means, for the launching rail, to be positioned
on the trestle. The lateral guide means for the launching rail may comprise retractable
pinch wheels. Because of the use of a trestle it is a simple matter also to provide
lateral guide means for the bridge modules, which may comprise one or more vertically
mounted guide rollers. In addition, the trestle may comprise means for selectively
restraining the launching rail during construction: the selective restraining means
desirably comprise retractably hooks.
[0013] It is a preferred feature of the first trestle that it comprises means for adjusting
the level of the trestle.
[0014] In a preferred aspect of the method, a second trestle is placed on the home bank
to take a proportion of the load of the modules. The second trestle will desirably
be of similar construction to the first trestle, except that it is not necessary for
it to be provided with retaining means such as hooks or means for moving the rail
over the beam, such as powered rollers.
[0015] Each bridge module is preferably substantially described in EP-A-0081388 in that
it comprises two longitudinal main girder structures and an intermediate, deck having
a deck surface, the main girder structures being foldably connected one along each
side of the deck and being foldable between an operative position in which the main
girder structures offer extensions of the deck surface on either side of the deck
for use and a closed position in which the main girder structures are folded beneath
the deck.
[0016] A bridge formed of such modules will normally comprise two end modules, in each of
which the main girder structures are longitudinally tapered in depth when seen from
the side of the module and at least one intermediate module in which the main girder
structures are not so tapered.
[0017] Some preferred features of modules suitable for use in the method of the present
invention are the same as or closely similar to the preferred features of the modules
disclosed in EP-A-0081388. Thus, it is desirable that the main girder structures be
box girder structures; that each main girder structure comprise at least one lifting
attachment on a surface offering the extension of the deck surface; that each of the
lifting attachments be recessed; that each main girder structure comprise at least
one lifting attachment on a surface which is facing a corresponding surface of the
other main girder structure when the module is in the operative position; that the
deck comprise two lip portions and that each of the main girder structures comprise
a shoulder portion, each of which lip portions stays on a respective one of the shoulder
portions when the module is in the operative position; and/or that the module further
comprise a bracing means between the main girder structure for bracing the module
when in the operative position.
[0018] In EP-A-0081388, the disclosed bracing means comprised steel bracing wires. In a
preferred module suitable for use in the present invention, the bridge modules preferably
comprise bracing arms, one end of each of which is pivotably attached either to a
main girder structure or to the deck surface, and the other end of which is receivable
in a slide in the other of the main girder structure and the deck. Preferably, the
bracing arm is pivotably attached to a main girder structure and receivable in a slide
in the deck.
[0019] A further preferred feature of a bridge module usable in the present invention concerns
means for joining adjacent bridge modules. In EP-A-0081388, joining plates are provided
at each end of each of the intermediate bridge modules and at the inner end of each
of the end modules. Each joining plate would be provided with a hole to receive a
pin when joining plates of adjacent bridge modules are placed together. So much is
similar with the present case. In the prior disclosure, however, pairs of joining
plates would be provided at one end of the bridge module and would be adapted to lie
either side of single joining plates of adjacent bridge modules. A pin would be manually
inserted through the resulting laminate of joining plates to hold the modules together.
In the present case, there are two improvements to this structure. First, the arrangement
of joining plates is hermaphrodite in nature. It therefore does not matter which way
round the intermediate bridge modules are. Secondly, means may be provided for remotely
inserting a pin through a laminate of joining plates, each of which is provided with
a pin-receiving hole. Such means may take the form of a bell-crank lever, adapted
to be operable from the side of a bridge module when in position on the launching
rail and arranged to move a pin through a laminate of joining plates. By this arrangement,
it is not necessary for a man to go underneath the bridge during construction, thereby
saving time.
[0020] A preferred feature of the method of the invention involves the use of means for
altering the angle of approach offered by one or both of the end bridge modules. Such
means may take the form of a hydraulically operable articulating ram for moving a
tapered portion of the end bridge module with respect to a connecting portion of the
module, which is adapted to connect to the end module to an adjacent intermediate
module. One or more filling elements may be inserted in the end module so that the
hydraulic cylinders can be relaxed after articulation.
[0021] It is particularly appropriate for further module bracing means, in addition to or
instead of those described previously, to be provided. To this end, each bridge, comprising
a number of modules, may be provided with a sub-frame for bracing frame for (a) bracing
the bridge in the open position and (b) supporting the bridge on the launching rail
so that it can be boomed out across the span. A sub-frame may be provided at each
end of a bridge, preferably being located at the inner end of each of the end modules.
Each sub-frame preferably has a pair of rollers, one for bearing on each flange of
the inverted T-section of the launching rail.
[0022] For a better understanding of the present invention, and to show how it may be put
into effect, reference will now be made by way of example to the accompanying drawings,
in which:-
Figures lA, 1B and 1C show side elevation, plan and end views of an intermediate launching
rail module;
Figures 2A, 2B and 2C show side elevation, plan and end views of an end launching
rail module;
Figures 3A, 3B and 3C show side elevation, plan and end views of a bearing pad for
use in conjunction with an end module of a launching rail;
Figures 4A, 4B and 4C show side elevation, plan and end views of an intermediate bridge
module in its open position;
Figure 4D shows an end view of the module in its folded position; and
Figure 4E shows a detail of construction of the intermediate bridge module;
Figures 5A, 5B and 5C show side elevation, plan and end views of an end bridge module
in its open position;
Figure 5D shows an end view of such module in its folded position; and
Figure 5E shows a partial underneath view of a folded end module;
Figures 6A, 6B and 6C show side elevation, plan and end views of a sub-frame for bracing
a bridge and for supporting bridge modules on a launching rail;
Figures 7A, 7B and 7C show side elevation, plan and end views of an assembled bridge;
Figure 7D shows an enlarged section on D-D of Figure 7A; and
Figure 7E shows a side elevation view of an alternative configuration of the end of
a bridge;
Figure 8 shows a perspective view of a first embodiment of a first trestle for use
in constructing a bridge;
Figure 8A shows a perspective view of a second embodiment of the first trestle;
Figure 9 shows a perspective view of a first embodiment of a second trestle for use
in constructing a bridge;
Figure 9A shows a perspective view of a second embodiment of the second trestle;
Figures 10A to ION show successive steps in constructing a bridge in accordance with
the invention;
Figures 11A and 11B show steps in completing the construction of the bridge at the
far bank; and
Figures 12A, 12B and 12C show concluding stages of the construction of the bridge
at the home bank.
[0023] Referring now to the drawings, Figures 1A to 1C and Figures 2A to 2C show the modules
from which the launching rail used in the invention is built up. Figures lA, 1B and
1C show an intermediate launching rail I, which is of a length of 19 feet 6 inches
(5.94 metres) which ensures that the launching rail modules are compatible for transport
with the ISO 6.1 metres (20 feet) container system. Each intermediate launching rail
module weighs about 0.8 tonnes and comprises a longitudinal upstanding member 3 which
carries, at its lower edge, a pair of flanges 5 and 7. The intermediate launching
rail module thus has the configuration of an inverted-T. Each is provided with a tension
connection for connection to a bridge module, as will be described later.
[0024] At the upper and lower edges of each of each intermediate launching rail module 1
is a row of joining lugs for connecting the module with an adjacent module. The upper
row of lugs is designated by reference numeral 9 and the lower row by reference numeral
11. The joining lugs are so positioned that each intermediate launching rail module
1 is hermaphrodite in nature and can therefore connect with any other module. Horizontal
pins (not shown) can be inserted through aligned holes in cooperating rows of joining
lugs in adjacent launching rail modules.
[0025] An end launching rail module 13 is shown in Figures 2A, 2B and 2C. The left-hand
end of the module in Figures 2A and 2B is equipped with upper and lower rows of joining
lugs 15 and 17, corresponding to the rows of joining lugs 9 and 11 described above
for the intermediate launching rail module 1. The end launching rail module 13 comprises
a tapered (when viewed from the side) longitudinal member 19 in the place of the longitudinal
member 3 described for the intermediate launching rail module 1. The end launching
rail module 13 also has lower flanges 21 and 23 and, in this respect, is also of a
generally inverted-T shaped section. The right-hand end of the end launching rail
module 13 shown in Figures 2A and 2B is equipped with opposed horizontally projecting
studs 25 and 27 on opposite sides of the module. One use of the studs 25 and 27 is
to engage with a bearing pad 29, shown in Figures 3A, 3B and 3C. The bearing pad 29
is shown in outline in Figures 2A and 2B. The purpose of the bearing pad 29 is to
distribute the load of a bridge, when formed on the launching rail, on the bank of
a span. There will be one bearing pad 29 at each end of the bridge. The pads 29 conform
to the profile of the toe of the bridge and therefore present their upper surfaces
as part of the bridge decking in use.
[0026] Each of the launching rail modules is of a lightweight hollow construction of rectangular
section. The depth and width of each module is such that it can be accommodated beneath
a bridge formed from bridge modules, which will now be described.
[0027] As can be seen from Figures 4A, 4B and 4C, which illustrate an intermediate bridge
module 31 in its open state, the modules envisaged for use in the present invention
are substantially the same as those disclosed in EP-A-0081388, the disclosure of which
is incorporated by reference into this application. Each intermediate bridge module
31 comprises a centre decking 33 and left and right main girder structures 35 and
37 which can pivot about a respective axis 39 or 41 (Figure 4C) to adopt the folded
configuration shown in Figure 4D for the purposes of transport.
[0028] The decking 33 for each intermediate module 31 is formed of six generally planar
decking members 33a to 33f (Figure 4B), each side of which has a li
p 43 (Figure 4E) which, in the open position of the module, bears on a shoulder 45 of
the adjacent main girder structure 35. A support arm 47 extending from the main girder
section 35 bears the pivotal connection between the decking 33 and the main girder
structure 35.
[0029] Pivotally mounted on each of the main girder structures 35 and 37 is a respective
bracing arm 49 or 51, whose free end engages in a respective slide 53 or 55 (Figures
4B) at the underneath of the centre deck 33. The bracing arms 49 and 51 move in their
respective slides 53 and 55 during folding and unfolding of the intermediate bridge
modules 31.
[0030] Recessed lifting points 57 and 59 are provided in each main girder structure. When
it is desired to unfold a bridge module from its folded (transport) position shown
in Figure 4D to its deployed, open position shown in Figures 4A, 4B. and 4C, the module
is simply lifted by means of a crane using a sling attached at the lifting points
57 and 59. The main girder structures 35 and 37 will swing of their own accord out
from under the deck 33. The unfolding of the intermediate bridge modules is described
in detail in EP-A-0081388 and will not be repeated here, but it should be noted that
the length of the sling can be chosen so that the line of action passes almost through
the centre of gravity of the cross section of the intermediate bridge modules as they
are unfolded. In this way, the load on the sliding bracing arms 49 and 51 and their
stops which are mounted in slides 53 and 55 is minimised. Shock absorbers can additionally
be fitted to reduce shock load.
[0031] As can be seen in Figure 4C the intermediate bridge modules 31 is provided with a
recovery sling 61, which comprises wires each. attached to a lower portion of a surface
of a respective one of the main girder structure 35 and 37 which is inwardly facing
when the module is open, the wires terminating in a common ring 63, which is accessible
from above the centre deck. To close the intermediate module 31, the module is simply
picked up by a crane acting at the ring 63.
' Of its own accord, the module will fold to the position shown in Figure 4D. Again,
the general principle of the folding process is described in EP-A-0081388 and will
not be repeated here.
[0032] As for the dimensions of the intermediate bridge module, it is again 19 feet 6 inches
in length (5.94 metres) to be compatible with the ISO 6.1 metre (20 feet) container
system. When the module is in its folded condition, it is 8 feet (2.44 metres) in
width, again to be compatible with the ISO container requirements, but in its open
position the total width of the intermediate bridge module 31 is 13 feet 5 inches
(4.1 metres), which is a sufficient width for carrying such heavy vehicle as tanks.
Each of the main girder structures 35 and 37, over which the tracks of the tanks pass,is
40.5 inches (1.03 metres) in height (in the open position) and 39 inches (1 metre)
in width (again in the open position).
[0033] Successive bridge modules are coupled together by means of nesting hermaphrodite
joining plates 65, 67, 69 and 71, through holes in which a pin can be inserted. The
nests of joining plates are arranged to be at the corners of the main girder structures
35 and 37. It will be appreciated that the most difficult nest for a pin to be passed
through is the lower, inner nest, at which the joining plates 67 are located in Figures
4C. To obviate the need for a man to climb under the bridge during construction, a
remote pin shooting apparatus 69 is provided. The pin shooting apparatus comprises
a bell-crank lever 71, one end of which projects for the operator's use at the outer
edge of the main girder structure 35, and the other end of which connects with a pin
73 to push the pin through a nest of joining plates 67 (and 65 of the next module).
Pins through upper joining dowels can be inserted by a man on the deck 33 of the bridge
module 31.
[0034] The tapered end bridge module 75 shown in Figures 5A to 5D has many features in common
with the intermediate bridge module 31, but differs in that the main girder structures
77 and 79 are tapered when seen from the side, when the module is in its open (deployed)
position. The end module 75 again comprises a deck 81, but this time only five deck
members 81a to 8le are provided. The deck member at the fully tapered end of the end
module 75 (the right-hand in Figures 5A and 5B) is missing: its place is taken in
the fully assembed bridge by the bearing pad 29. The deck section 81e nearest the
fully tapered end is provided with a connection 83 for connecting the module to the
launching rail, as will subsequently be described.
[0035] As with the intermediate bridge module 31, the end bridge module 75 can be opened
from a closed position (shown in Figures 5D and 5E) to an open position (shown in
Figures 5A, 5B and 5C) by lifting the end module 75 at recessed lifting points 85
and 87 on the deck-extension surfaces of the main girder structures 77 and 79 by means
of a crane. A recovery sling (not shown) for the reverse operation is also provided.
Opening and closing the end modules 75 is again very similar to the process described
in
EP-A-0081388 and will not be repeated here.
[0036] Bracing arms 89 and 91 each attached to a respective main girder structure (.77 or
79) by a pivot extend towards and terminate in slides 93 and 95 under the lower surface
of the deck 81. Their purpose is the same as for the intermediate bridge module 31.
Joining plates 94, 96, 97 and 99 are also correspondingly positioned for joining the
end bridge modules 75 to its adjacent intermediate bridge module 31. A pin shooting
mechanism 101 is again provided.
[0037] A difference between the end bridge module 75 and the intermediate bridge module
31 is that the end bridge module 75 is articulated by way of a pivot 103 at a lower
portion of the end bridge module adjacent where it is connected to an intermediate
bridge module 31. The articulation means that the end bridge module is split into
a ramp section 105 and a joining section 107. The ramp section 105 can be moved relative
to the joining section 107 by means of a hydraulic piston and cylinder arrangement
109 mounted at the joining end of each main girder structure 77 and 79. At one extent
of the articulation (used when the bridge is being assembled on the launching rail
and boomed out across the span it is to bridge) the upper surface of the deck 81 is
level. This is shown by the discontinuous lines in Figure 5A. At the other extent
of the articulation, the lower surfaces of the main girder structures 77 and 79 are
level. This is usually, though not exclusively, the position adopted when the bridge
is in use for carrying traffic. This configuration is shown in solid lines in Figure
5A. In such a configuration, there will be a gap 111 above the point of articulation
at the pin 103. The gap 111 can be filled in use by a deck compression unit 113, which
is a planar narrow deck extension unit. Hydraulic pressure in the piston and cylinder
arrangement 109 can be relaxed once the deck compression unit is in place.
[0038] The maximum overall dimensions for the end bridge module 75 are the same as for the
intermediate bridge module 31.
[0039] Figures 6A, 6B and 6C show an inter-trackway bracing frame. One of these is located
under the deck at each end of the bridge formed from end and intermediate bridge modules
75 and 31 and allows the bridge to be supported on a launching rail, formed from launching
rail end and intermediate modules 13 and l, during booming out.
[0040] The bracing frame 115 also braces the bridge in the open position. Each bracing frame
115 is fitted to one of the end bridge modules 75 and is located in the jaws at the
joining section 107 of each end bridge module 75. The bracing frame 115 consists of
a portal frame 117, on the inside of each upright of which is mounted a flanged wheel
119 or 121 on a horizontal axis for supporting the bridge on flanges of the launching
rail (shown in dotted lines in Figure 6C). Additional supports 123 and 125 extend
outwardly from the uprights to make further engagement with the end bridge module
75. Additional vertical bracing 127 and 129 extends between the supports 123 and 125
on the one hand and the cross member of the portal frame 117 on the other hand.
[0041] Figures 7A to 7E give an overall view of a bridge 131 after construction. The bridge
comprises three intermediate bridge modules 31 and two end bridge modules 75. These
can clearly be seen in the side and plan views of Figures 7A and 7B. Underneath the
deck of the bridge 131 can be seen (in dotted lines in Figure 7B) a launching rail
133, which is itself formed of intermediate modules 1 and end modules 13. A bracing
frame 115 can be seen in position in Figure 7D.
[0042] Figures 7A and 7B show how the bridge 131 would be configured when spanning a gap
between substantially level banks. Both bridge end modules are fully articulated.
On the other hand, in Figure 7E, the end module 75 is not articulated. This reduces
the ramp slope at the end of the bridge and renders it more suitable for use on a
sloping bank.
[0043] Figure 8 shows a trestle 135, which is the subject of one aspect of the invention
and which can be used in accordance with a method of the invention. The trestle 135
comprises a pair of upright guide posts 137 and 139 of rectangular section, between
which is movably and lockably mounted a support beam 141. The support beam 141 is
constructed of two support beam members 143 and 145, interconnected by a number of
spacers 147.
[0044] Each guide post 137 or 139 is mounted on a respective anvil-shaped beam 149 or 151,
which is in turn supported on the respective base plate 153 or 155. Free ends of the
anvil-shaped beams 149 and 151 are spaced from their respective base plate 153 or
155 by means of limit screws 157. The limit screws 157 are manually adjustable to
give longitudinal level adjustment for the trestle 135.
[0045] The support beam 141 moves and is locked with respect to the guide posts 137 and
139 by means of hydraulic piston and cylinder arrangements 159 and 161, one associated
with each guide post. Hydraulic fluid for the piston and cylinder arrangements 159
and 161 are supplied from a trestle hydraulic power pack supply (not shown).
[0046] Between the members 143 and 145 of the support beam 141 are mounted a variety of
rollers. Two of them, 163 and 165, are launching rail support rollers powered by the
trestle hydraulic power pack supply. They are flanged and have a surface with a high
coefficient of friction so that they can drive the launching rail 133 shown in discontinuous
lines in Figures 8 in the direction of the arrow 167, which is the direction of launching
the launching rail 133, and eventually, the bridge 131. The launching rail support
rollers 163 and 165 are centrally disposed along the support beam 141. Above each
of the launching rail support rollers 163 and 165 is a respective retractable pinch
wheel 167 or 169 mounted, like the launching rail support rollers, for rotation about
a horizontal axis. The rotatable pinch wheels 167 and 169 bear upon the upper surfaces
of the flanges 5 and 7 (see Figures lC) of each of the launching rail modules. When
the retractable pinch wheels 167 and 169 are deployed, as shown in Figure 8, they
ensure that the launching rail support rollers 163 and 165 properly grip the launching
rail 133 when driving it. The pinch wheels 167 and 169 can be retracted by hydraulic
piston and cylinder arrangements 171 and 173, respectively.
[0047] Either side of the launching rail support rollers is a pair of bridge support rollers
175 and 177. They are again mounted for horizontal rotation. The pairs of bridge support
rollers 175 and 177 support the lower surfaces of the main girder structures of the
bridge 131, but are not powered. They are therefore passive, low-friction supports.
Lateral guide rollers 179, mounted for vertical non-powered rotation, are position
one either side of the path of the main girder structures of the bridge 131 during
launching.
[0048] Two hydraulically retractable launching rail hooks 181 are mounted on the support
beam 141 and extend in a downstream direction (as far as the direction of launch is
concerned). They terminate in upwardly curved hooked portions. The hooks can pivot
about horizontal axes to bring them out of and into engagement with the protrusions
25 and 27, respectively, (see Figures 2B) of a tapered end module 13 of the launching
rail 133.
[0049] Figure 8A shows an alternative construction of the trestle 135, in which longitudinal
level adjustment is achieved in a different way. The anvil shaped beams 149 and 151
are absent, and instead sloping tie rods or braces 150 and 152 are pivotally attached
at their upper ends each to a respective one of the guide posts 137 and 139 and at
their lower ends each to a respective one of the base plates 153 and 155. The length
of each of the tie rods 150 and 152 can be adjusted in a similar fashion to a turnbuckle,
as will be described later, with reference to Figure 9A.
[0050] A second trestle 183 is shown in Figure 9. Two of these second trestles 183 are used
in the preferred method of construction of the present invention. The second trestle
183 is broadly similar to the first trestle 135 except that (a) the second trestle
183 does not have to be of such heavy construction as the first trestle 135 because,
in use, it does not have to withstand such heavy loading, and (b) the only interaction
between the second trestle 183 and the launching girder 133 is such that the launching
girder 133 is supported by non-powered rollers.
[0051] The second trestle 183 comprises a pair of vertical guide posts 185 and 187 which
movably and lockably support a support beam 189 composed of two parallel girders 191
and 193 between which extend spacing members 195. Each of the guide posts 185 and
187 terminates at its lower end on a respective anvil-shaped member 197 or 199 whose
centre portion rests on a respective baseplate 201 or 203. Adjusting screws 205 allow
for longitudinal level adjustment as with the first roller.
[0052] Either side of the centre of the length of the support beam 189 is a flanged roller
207 or 209, both of which act as launching rail support rollers. Pairs of bridge support
rollers 211 and 123 are provided, as for the first trestle, as are lateral guide rollers
215, which are rotatable about a vertical axis and which limit lateral movement of
the bridge modules 131 during construction of the bridge. Again, the vertical movement
of the support beam 189 towards and away from the ground is provided by a pair of
hydraulic piston and cylinder arrangements 217 and 219, each mounted on a respective
guide post 185 or 187.
[0053] Figure 9A shows an alternative construction of the second trestle 183, in which longitudinal
level adjustment is achieved in a different way. The Figure 9A construction differs
from the Figure 9 construction in the same way that the Figure 8A construction of
the first trestle -135 differed from the Figure 8 construction. The anvil shaped beams
197 and 199 are absent, and instead sloping tie rods or braces 198 and 20.0 are pivotally
attached at their upper ends each to a respective one of the guide posts 185 and 187
and at their lower ends each to a respective one of the baseplates 201 and 203. The
length of each of the tie rods 198 and 200 can be adjusted in a similar fashion to
a turnbuckle. This is achieved, as illustrated by way of example for the tie rod 198,
by each tie rod (198 in this casel comprising an upper tie rod end 198A and a lower
tie rod end 198B, which are formed at the ends that are not pivotally attached to
the guide post 185 or the base plate 201 with left and right hand screw threads, respectively.
(Which has the left thread and which has the right does not matter, as long as there
is one of each.) The threaded ends of the upper and lower tie rod ends 198A and 198B
both engage female-threaded ends of a central tube 198C, which carries a handwheel
198D. The central tube 198C lies along the central axis of the handwheel 198D. By
turning the handwheel 198D, the length of the tie rod 198 can be increased or decreased
in order to keep the guide post near vertical. The same principle applies to the second
embodiment of the first trestle 135 shown in Figure 8A.
[0054] The use of such a levelling means, which comprises a tie rod of adjustable length
extending between and pivotally attached to a guide post and a base plate, has the
following two advantages. First, need for coordinating the adjustment of the two adjusting
screws 205 (Figure 9) - that is, slackening one off before (or while) the other screw
is being extended - is avoided. Secondly, the support beam 189 can be lowered further
in view of the absence of the anvil shaped beams 197 and 199 (Figure 9). This is significant
when jacking down the home bank end of the bridge (see Figures 12A, 12B and 12C),
because the minimum height to which the roller beam can be lowered determines the
amount of upward articulation required on the tapered end ramps of the bridge in order
to lower the launching rail to the ground. By adopting the alternative construction
of Figure 9A, the support beam can be lowered nearer the ground, and the articulation
provided on the bridge end ramp can therefore be significantly reduced.
[0055] To construct a bridge by the preferred method in accordance with the present invention,
it is particularly appropriate to use two hydraulic power packs. One would be positioned
on the bridge under construction and would be used for articulating the bridge end
modules 75 by means of the piston and cylinder arrangements 109. The other power pack
would be located on the home bank and would be for raising and lowering the support
beams 141 and 189 of the first and second trestles 135 and 183 and also for powering
the friction drive rollers 163 and 165 of the first trestle, for moving the retractable
pinch wheels 167 and 169 into and out of position and for moving the launching rail
hooks 181 into and out of position.
[0056] Each portable hydraulic power pack can be powered by an air-cooled diesel engine
of about 10 horsepower (.7.5 kiloWatts) driving a variable displacement pump working
at a pressure of 300 psi (20.
6 MN/m
2). The engine would be provided with hand or inertia start to obviate the need for
batteries. Spare power units could be provided as a precaution against breakdown.
In addition, an emergency hand pump could be provided to enable the bridge to be jacked
down in the event of power failure. Recovery, however, would hardly be feasible with
a manual pump, due to the height to which the bridge has to be jacked.
[0057] Figures lOA to lOG illustrate a method of constructing a bridge in accordance with
the invention. The bridge illustrated is to be built of a total of five bridge modules
(three intermediate bridge modules 71 and two end bridge modules 75) and is capable
of reaching a span of 100 feet (30.5 metres) (nominal). For spans above 100 feet (30.5
metres) to 160 feet (48.8 metres), link reinforcement would be required. However,
as some 95% of gaps in north-west Europe do not exceed 100 feet (30.5 metres), it
is not foreseen that this will be a problem. Before construction proper can begin,
all the components must be brought to the home bank. The components needed are as
follows:
Three intermediate launching rail modules;
Two end launching rail modules;
Three intermediate bridge modules;
Two end bridge modules;
Two end pads;
One powered first trestle;
Two second trestles;
Two inter-trackway bracing frames; and
Two hydraulic power packs.
[0058] All these components could be brought to the site on a total of four 8T trucks which,
in addition to the standard mobile crane would be all the vehicles needed for the
bridge to be constructed. The crane would be expected to have a 3.5 tonne lift at
a 15 feet (4.6 metres) outreach. The crane is designated by reference numeral 221
in Figure 10.
[0059] Using the crane 221 free on wheels, the first trestle 135 is placed close to an parallel
with the home bank. The second trestle 183 is placed parallel to the first trestle
but some 15 feet (4.6 metres) parallel to and behind the first trestle 135. A first
hydraulic power pack 223 is placed near the trestles in such a place that it can service
the hydraulic requirements of the two trestles 135 and 183.
[0060] With the crane 221 being positioned on the centre line of the bridge to be constructed,
and the loaded trucks conveniently positioned alongside, an end launching rail module
13 is placed on two trestles with its toe towards the far bank. An end bearing pad
29 may be in position on the toe of the end launching rail module 13.
[0061] The crane 221 now lifts an intermediate launching rail module 1 into position for
connection behind the end launching rail module 13. Because the intermediate launching
rail modules only weight 0.8 tonnes, it is not necessary for the crane 221 to be chocked
at this stage.
[0062] Figure lOB shows a second intermediate launching rail 1 being brought into position
behind the first intermediate launching rail module 1, to which it is coupled.. At
this point, the launching rail being formed is boomed forward using a friction drive
roller of the first trestle 135. This is done first to keep the centre of gravity
of the launching rail being formed between the first and second trestles 135 and 183.
[0063] A third trestle 225, of identical construction to the second trestle 183, is placed
towards the back of the launching rail being formed. The crane 221 is moved to its
final position, where it is chocked by means of outriggers and jacks, as shown in
Figure lOC. A further intermediate launching rail module 1 is then lifted into position
on the launching rail being formed. Finally, in this stage of the operation, a second
launching rail end module 13 is lifted into position to complete the launching rail.
At this point, the second trestle 183 can be removed, the weight of the launching
rail being entirely supported now by the first and third trestles 135 and 225; it
should be noted that the first power pack 223 continues to service the requirements
of the first and third trestles 135 and 225.
[0064] When the last section (the second end module 13) of the launching rail has been connected,
the launching rail is not boomed forward until a first bridge module (which will be
an end bridge module 75) has been put in position on the launching rail. The positioning
of the end bridge module 75 is shown in Figure lOB. The end bridge module 75 will
have been deployed in its unfolded position before fitting on the launching rail.
At this point, a first roller bracing frame 115 is fitted between the trackways of
the end bridge module 75, which is connected by means of a tension connection at position
W (Fgiure 10E) to the launching rail. Note that the end bridge module 75 is articulated
upwards (in the position shown by the discontinuous lines in Figure 5A) so that the
upper chord is approximately horizontal. In this way the end bridge module 75 is appropriately
aligned for connection to an intermediate bridge module. The launching rail is now
boomed out by 20 feet (6.1 metres) and an intermediate bridge module 31 is connected
to the end bridge module 75, again in its deployed position, connection to the end
bridge module 75 is made by connecting pins. The lower chord outer pins are placed
by hand. The lever mechanism 101 used for sliding the lower chord inner pins into
position obviate the necessity for a man to go underneath the bridge. The upper chord
tension connections can be made by a man standing on the deck. Each time subsequent
intermediate bridge modules 31 are added, the bridge, still connected at point W to
the launching rail, is moved forward the same distance (20 feet (6.1 metres)) by means
of the drive rollers of the first trestle 135.
[0065] During this phase, a second hydraulic power pack 227 is positioned on the bridge
deck and hydraulically connected to the piston and cylinder arrangements 109 of the
end bridge module 75. As building proceeds, the droop of the launching rail can be
counteracted by hydraulic adjustment of the articulation of the end launching rail
module 75. As a further adjustment, the position of the support beam 141 of the first
trestle 135 can be adjusted vertically by means of the hydraulic piston and cylinder
arrangements 159 and 161 of the first trestle 135.
[0066] Figure 10I shows the second end bridge module 75 being connected to the bridge. The
second end bridge module 75 is articulated so that its lower chord is approximately
horizontal. At this point, a second bracing frame is inserted between the trackways.
[0067] At this point, the bridge is ready for launching and jacking down. Because the bridge
has been driven forward as each bridge module 31 or 75 has been added, the far end
of the launching rail will be over the far bank when the second end bridge module
75 is assembled. The launching rail must be driven as far forward as possible until
the projections 25 and 27 of the second end launching rail module 13 are located in
the hooks 181 of the first trestle 135. The bearing pad 29 on the first end launching
rail module 13 can now be landed on the far bank by articulating the first end bridge
module 75 and/or by lowering the support beam 141 of the first trestle
135. The launching rail now becomes a simply supported beam over which the bridge can
be launched. The connection at W is now released and the bridge pushed across the
gap or span by means of a booming vehicle, which could be the crane 221. This is shown
in Figure 10K.
[0068] With the bridge fully launched, jacking down on the far bank can proceed (Figures
10L, 11A and 11B). The first end bridge module 75 is articulated downwards by using
the second power pack 227 so that the launching rail is relieved of the load of the
bridge. The deck compression unit 113, as shown in Figure 11A, is inserted to transmit
the top chord compressive load. The piston and cylinder arrangements 109 of the first
end bridge module 75 can then be relaxed. Note that, as the ramps of the first end
bridge module 75 are articulated downwards, the launching rail can move downwards
from the roller bracing frame 115, thus relieving rollers 119 and 121 (Figure 6C)
of any load. The second hydraulic power pack 227 can now be disconnected and moved
back along the bridge ready to jack down on the home bank.
[0069] The first stage of jacking down on the home bank (Figure 10M and Figures 12A, B and
Cl involes making a tension connection between the launching rail and the bridge at
point X. The hooks 181 of the.first trestle 135 are retracted to disengage them from
the protrusions 25 and 27 on the second end launching rail module 13. At this point,
the weight of the home bank end of the bridge is borne by the toe of the second end
bridge module 75 on the support beam 141 of the first trestle 135. The ramps of the
second end bridge module 75 are then articulated upwards so that the toe of the second
end launching rail module 13 will be lowered to the ground and into its seating in
a second bearing pad 29, which has been positioned there to receive it. The launching
rail can now support the weight of the bridge while the ramps of the second end bridge
module 75 are articulated upwards to free the first trestle 135, which can be removed
by the crane 221. The tension connection at X is now released and the ramps of the
second end bridge module 75 are articulated downwards at the far end so as to relieve
load on the launching rail and to allow a deck compression unit 113 to be inserted.
[0070] The bridge is now ready for traffic.
[0071] The launching rail remains in the bridge, ready for recovery, which can take place
from either end, due to the symmetrical construction of the bridge.
[0072] It should be noted that if the launching rail is suspended from the tension connection
marked X and from a corresponding one at the other end of the bridge, the lower connecting
pins joining the end launching rail modules 13 to their respective neighbouring intermediate
launching rail modules 1 can be removed. In this way, it is possible to reduce the
end slope of the bridge, or even to have the level deck, by reducing the width of
the deck compression units 113 shown in Figure 5A, if the lower launching rail connecting
pins are also removed.
[0073] It should be mentioned that, to achieve the various tension connections (as mentioned
for points W and X) during construction of the bridge, each end launching rail module
13 and each intermediate launching rail module 1 is provided with a tension connection
for connection to the centre decking of the bridge at the appropriate point.
[0074] The sequence for recovery and dismantling the bridge is essentially the reverse of
the launching sequence. The timing may be comparable.
[0075] It can thus be seen that a bridge of MLC 70 capability can readily be built with
the minimum of specialist equipment and no specialist vehicles. It is anticipated
that a nominal 100 feet (30.5 metres) span could be bridged with the aid of a crane
and six men in less than 30 minutes by night. The 4 metre wide deck presented by the
bridge in use should be sufficient for conveying the majority of ground based military
equipment across the span.
1. A method of constructing a modular bridge across a span, the method being characterised
by comprising placing at least a first trestle (135) on the home bank of the span,
placing a first module (13) of a modular launching rail on the trestle, connecting
one or more subsequent lauching rail modules (1, 13) to the launching rail being formed,
placing a first bridge module (75) on the launching rail, connecting one or more subsequent
bridge modules (31, 75) to the bridge being formed, booming out the launching rail
across the span and launching the bridge across the span along the launching rail.
2. A method as claimed in Claim 1, characterised in that the first trestle comprises
one or more rollers (163, 165) for supporting the launching rail.
3. A method as claimed in Claim 2, characterised in that the launching rail support
rollers (163, 165) are drivable to move the launching rail over the beam of the first
trestle.
4. A method as claimed in Claim 2 or 3, characterised in that the first trestle comprises
one or more rollers (175, 177) for supporting the bridge.
5. A method as claimed in any one of Claims 1 to 4, characterised in.that the first
trestle comprises at least one support beam (141) and at least two guide posts (137,
139) for holding the support beam, the height of the support beam above the ground
being adjustable.
6. A method as claimed in any one of Claims 1 to 5, characterised in that each bridge
module comprises two longitudinal main girder structures (35, 37) and an intermediate
deck (33) having a deck surface, the main girder structures being foldably connected
one along each side of the deck and being foldable between an operative position in
which the main girder structures offer extensions of the deck surface on either side
of the deck for use and a closed position in which the main girder structures are
folded beneath the deck.
7. A method as claimed in any one of Claims 1 to 7, characterised in that it comprises
placing a second trestle (183) on the home bank to take proportion of the load of
the modules.
8. A method as claimed in Claim 7, characterised in that the second trestle comprises
one or more rollers (207, 209) for supporting the launching rail, one or more rollers
(209, 211) for supporting the bridge and lateral guide means (215) for the bridge
modules.
9. A trestle (135) suitable for use in constructing a modular bridge across a span,
the trestle being characterised by comprising a support beam (141) lockably movable,
on one or more guide posts (137, 139), towards and away from the ground on which the
trestle is located, means (163, 165) for supporting a brige launching rail on the
beam in such a way that the rail can move over the beam, means (175, 177) for supporting
a bridge module on the beam in such a way that the bridge module can move over the
beam, and means for moving the rail over the beam.
10. A trestle as claimed in Claim 9 characterised by comprising at least one support
beam and at least two guide posts for holding the support beam, the height of the
support beam above the ground being adjustable.