[0001] The present invention relates to the production of cast metal articles, and more
specifically, to an apparatus and a method for holding a mold that is being filled
and for transferring a mold filled with molten metal from a pouring station while
moving an empty mold onto said pouring station.
[0002] In the manufacture of cast metal articles such as railway wheels, it is important
from a cost savings and energy savings point of view to produce such wheels as rapidly
as possible while maintaining the accuracy necessary to produce near finish castings.
A typical wheel casting plant layout is shown in U. S. Patent No. 2,999,281. A cope
or top mold section is placed on top of a drag or bottom mold section to form a complete
mold. Usually the mold is a reusable graphite mold. When the completed mold is moved
along a conveyor to a pick up station adjacent the pouring station, a pick-up crane
is used to lift the mold and place it on the pouring station above the pouring tank.
The mold is located above the pouring tank because a bottom pressure pouring method
is used to inject the molten metal into the mold. The ladle containing the molten
metal is placed within a pouring tank. The pouring tank is capable of being pressurized
with air, thereby forcing the molten metal upwardly through a refractory pouring tube
into the bottom of the mold.
[0003] Prior to filling the mold, the mold must be held in place, usually by air cylinders
which extend downwardly to contact the cope. Further, a mold stopper assembly must
be lowered, again by air cylinder, over the stopper hole in the mold. Finally, a riser
height control mechanism must be lowered into the mold riser whereby the height of
the molten metal in the riser is determined and hence the pouring operation is automatically
controlled. These three mechanisms, the hold down cylinders, the mold stopper and
the riser height control mechanism, were previously located on the mold set down crane
legs used to pick up the filled mold and transfer it to the mold set down location
from where the mold would continue for processing along conveyors.
[0004] The mold set down crane and the mold pick up crane are each comprised of a column
assembly having two legs, and both column assemblies are mounted on a single top frame
assembly. Such top frame assembly is capable of lateral movements along secondary
girders, which secondary girders themselves comprise a crane assembly mounted on main
girders giving the secondary girders the capability of moving longitudinally with
relation to the pouring station. Because of the mounting of the pick up crane and
set down crane on a single top frame assembly, their lateral movements along the secondary
girders are simultaneous and of equal lateral dimension.
[0005] In the pouring sequence of the previously known arrangement, a mold just filled with
molten metal is at the pouring station and a second, empty mold is at the mold pick
up location. The mold hold down assembly, mold stopper and riser height control are
attached to the set down crane, and, after pouring is completed, are raised from the
mold. The set down crane then raises the filled mold while the pick up crane raises
an empty mold. The frame assembly supporting both cranes is moved laterally along
the secondary girders. The filled mold is placed at the set down location by the set
down crane and the empty mold is placed at the pouring station by the pick up crane.
The set down crane and the pick up crane are then moved via their frame assembly laterally
along the secondary girders. When the set down crane reaches the pouring station,
the mold hold down assembly and riser height control are lowered to the empty mold
and the pouring operation begins. The mold stopper is lowered after the mold has been
filled.
[0006] It is an object of the present invention to provide an improved pouring station mold
handling arrangement.
[0007] Viewed from a first aspect the invention provides a pouring assembly for use in the
manufacture of cast metal articles, said assembly comprising a mold transfer apparatus
including a top frame movable along a bridge structure and two sets of depending legs,
and a pouring tank located at a pouring station under the bridge structure, said pouring
tank being capable of being pressurized to permit the upward pouring of molten metal
therefrom into a mold positioned thereabove, one set of said depending legs of said
mold transfer apparatus being adapted to move an empty mold from a pick up location
to said pouring station, and the second set of depending legs of said mold transfer
apparatus being adapted simultaneously to move a filled mold from said pouring station
to a set down location, wherein said bridge structure includes means arranged to hold
said mold at said pouring station whereby filling of an empty mold may begin shortly
after such is positioned at said pouring station.
[0008] In accordance with the invention there are significant time savings as compared with
earlier arrangements wherein the mold holding mechanism is mounted to the set down
crane since with the inventive arrangement filling of the mold may commence before
the set down crane is returned to the pouring station.
[0009] In a preferred embodiment the bridge member further includes a mold stopper closing
mechanism and a riser height control, and a mold filled with molten metal is moved
from the pouring station by the set down crane after the mold hold down assembly,
the mold stopper closing mechanism and the riser height control are lifted from the
mold. The filled mold is moved from the pouring station by the set down crane while
an empty mold is moved to the pouring station by the mold pick up,crane. However,
since the mold hold down assembly, the mold stopper closing mechanism and the riser
height control are not attached to the set down crane, but rather are attached to,
for example, secondary girders of the bridge structure, shortly after the empty mold
is plaoedat the pouring station,the mold hold down assembly, the mold stopper and
the riser height control can be lowered onto the mold. The pouring operation can therefore
begin before the set down crane is returned to the pouring station. In a preferred
embodiment the time savings per casting is about 8 seconds, which, in a plant normally
producing 1,000 castings in a 24 hour period, can increase production to about 1,100
castings in a 24 hour period, a 10% increase.
[0010] Viewed from a second aspect the invention provides a method of producing cast metal
articles comprising moving a mold transfer apparatus between first and second positions
thereof whereby to move a mold filled with molten metal from a pouring station to
a set down station and simultaneously to move an empty mold from a pick up station
to said pouring station, and thereafter returning said apparatus to the first position
thereof for subsequent like transfer operations, wherein each empty mold is held at
said pouring station and filling thereof with molten metal is commenced before said
transfer apparatus is returned to its first position.
[0011] A preferred embodiment of the invention will now be described, by way of example
only, with reference to the accompanying drawings, wherein:
Figure 1 is a perspective view in partial cross section of a mold handling system,
and Figure 2 is a side view along line 2-2 of Figure 1 of the mold handling system.
[0012] A pouring station and mold handling system are shown in Figures 1 and 2 of the drawings.
The mold 10 is centrally located at the pouring station, being set atop pouring tank
12 and joined to pouring tank 12 by refractory pouring tube 14. Mold 10 is comprised
of top or cope section 16 and bottom or drag section 18. Usually such molds are of
a permanent composition, utilizing compressed graphite as the refractory material.
[0013] Set down crane 19 comprises a front depending leg 20 and a rear depending leg (not
shown), and pick up crane 25 comprises front depending leg 22 and rear depending leg
62. All said depending legs are supported by top frame assembly 24. Lower section
21 of set down crane front depending leg 20 and a similar lower section of the rear
depending leg (not shown), and lower section 23 of pick up crane front depending leg
22 and lower section 64 of rear depending leg 62 are moveable sections supported by
compressed air cylinders 50 and 51 within each crane. The pairs of lower section 21
and the lower section of crane 19 not shown and lower sections 23 and 64 of crane
25 cooperate to contact and lift a mold assembly 10. Top frame assembly 24 is a beam
arrangement which is adapted to move laterally across intermediate support girders
26. Girders 26 can move longitudinally across main support rails 28 and 30.
[0014] Hanging from intermediate support girders 26 are mold hold down cylinders 32 and
34, usually compressed air type piston cylinders, mold stopper 36, usually also a
compressed air type cylinder with a refractory stopper, and riser height control mechanism
38. The refractory stopper is usually mounted in the mold and not connected to the
cylinder. Riser height control mechanism 38 can be of various types, but usually extend
into the mold riser and, upon the detection of molten metal rising to a preset height,
will generate a signal to end the pouring of the molten metal.
[0015] Upon the movement of frame assembly 24 to the right in Figure 1, set down crane 20
will be aligned with mold 10 at the pouring station. Filled mold 10 will be picked
up by set down crane 20. At the same time, pick up crane 22 will be at a mold pick
up station 40, where it will pick up an empty mold. As top frame assembly 24 moves
left, the filled mold will be set down at the mold set down station 42. At the same
time, pick up crane 22 will be setting the empty mold down at the pouring station,
Hold down cylinders 32, 34, and riser height control 38 will be lowered to the empty
mold, and pouring of molten metal can begin. Mold stopper 36 is lowered after the
mold has been filled. Meanwhile, top frame assembly 24 is moving to the right to prepare
for the pick up of the filled mold at the pouring station by set down crane 20 and
of an empty mold at pick up station 40 by pick up crane 22.
[0016] Two secondary hold down cylinders 52 and 53 are attached to set down crane front
leg 20 and the rear leg (not shown). These cylinders are usually compressed air type
piston cylinders. They are used to hold the full mold closed when being transferred
from the pouring station 12 to the set down position 42.
1. A pouring assembly for use in the manufacture of cast metal articles, said assembly
comprising a mold transfer apparatus including a top frame movable along a bridge
structure and two sets of depending legs, and a pouring tank located at a pouring
station under the bridge structure, said pouring tank being capable of being pressurized
to permit the upward pouring of molten metal therefrom into a mold positioned thereabove,
one set of depending legs of said mold transfer apparatus being adapted to move an
empty mold from a pick up location to said pouring station, and the second set of
depending legs of said mold transfer apparatus being adapted simultaneously to move
a filled mold from said pouring station to a set down location, wherein said bridge
structure includes means arranged to hold said mold at said pouring station whereby
filling of an empty mold may begin shortly after such is positioned at said pouring
station.
2. A pouring assembly as claimed in claim 1 wherein said top frame of said mold transfer
apparatus is mounted on said bridge structure so as to be movable along said bridge
structure.
3. A pouring assembly as claimed in claim 1 or 2 wherein said bridge structure further
includes a mold stopper closing mechanism.
4. A pouring assembly as claimed in claim 3 wherein said mold stopper is mounted on
an air cylinder arranged to extend downwardly from the bridge structure to contact
said mold.
5. A pouring assembly as claimed in any preceding claim wherein said bridge structure
further includes a riser molten metal height control mechanism.
6. A pouring assembly as claimed in any preceding claim wherein each said set of depending
legs includes a lifting cylinder that enables each set of legs to lift a mold.
7. A pouring assembly claimed in any preceding claim wherein said means to hold said
mold at said pouring station includes two air cylinders arranged to extend downwardly
from said bridge structure to contact said mold.
8. A pouring assembly as claimed in any preceding claim wherein said depending legs
adapted to move a full mold to the set down location have secondary hold down air
cylinders adapted to hold a full mold closed during transfer.
9. A method of producing cast metal articles comprising moving a mold transfer apparatus
between first and second positions thereof whereby to move a mold filled with molten
metal from a pouring station to a set down station and simultaneously to move an empty
mold from a pick up station to said pouring station, and thereafter returning said
apparatus to the first position thereof for subsequent like transfer operations, wherein
each empty mold is held at said pouring station and filling thereof with molten metal
is commenced before said transfer apparatus is returned to its first position.
10. A method as claimed in claim 9 wherein said transfer apparatus comprises a moving
frame assembly.
11. A method as claimed in claim 9 or 10 wherein the molten metal is pressure injected
into the bottom of the mold.
12. A method as claimed in any of claims 9 to 11 wherein the filling operation further
comprises placing a riser height control mechanism in the empty mold and closing a
mold stopper.