Background of the Invention
[0001] The present invention relates to an apparatus and method for drilling a pilot bore
hole along an underground arcuate path between two surface locations, and then enlarging
the pilot bore hole for installing a conduit therein, such as pipe, casing, cable,
or a pipeline.
[0002] Heretofore, directional drilling apparatus has been provided for drilling an underground
pilot bore hole along an arcuate path between two surface locations, and then enlarging
the pilot bore hole for receiving a product conduit, such as a pipeline therein. A
common apparatus and method has utilized a drill pipe string of a relatively small
diameter less than two inches (2") with a drill bit thereon forming a relatively small
diameter pilot bore hole, which is followed by a relatively large diameter washover
pipe such as around five inches (5") in diameter or more, in concentric relation to
the drill string and having cutting blades on the leading end thereof for enlarging
the initial pilot bore hole. Upon completion of the pilot bore hole as enlarged by
the washover pipe, the drill string has been removed and the washover string then
connected to a reamer at the exit end for pulling the reamer and connected product
conduit along the initial bore hole for reaming to a desired diameter to receive the
product conduit.
[0003] Thus, the method and apparatus employed heretofore for forming a pilot bore hole
normally has included two separate cutting or drilling steps prior to the reaming
operation, the first cutting step being the drilling of a small diameter bore hole
from a drill bit with a relatively small diameter light weight drill string, and the
second cutting step resulting from an enlarging of the bore hole by the washover string
in concentric relation to the drill string. Thereafter, the reaming operation has
taken place to enlarge the pilot bore hole to receive the product conduit or pipe.
[0004] Heretofore, a relatively small diameter drill pipe string of around one and three-fourths
inches (1-3/4") in diameter has been utilized for such pilot bore holes as it was
found desirable to have a relatively lightweight drill pipe or string, particularly
when drilling under streams where sand and clays are normally encountered with water
also being present at times. Under the weight of the drill string, the drill string
could sink under certain conditions and it was accepted as common practice in the
industry to employ a relatively small diameter drill string in order to keep the weight
of the entire drill string at a minimum and to provide flexibility. Such a small diameter
drill pipe string thus necessitated the use of a separate washover string in order
to provide the necessary strength for the subsequent reaming operation and pulling
of the production conduit through the enlarged bore hole.
[0005] The utilization of two separate cutting steps or procedures for forming the pilot
bore hole prior to the reaming operation results in a costly operation.
[0006] Other directional drilling apparatus and methods for underground arcuate bores or
openings not employing a washover pipe following the drill string have utilized other
types of reamers or cutters which enlarge the initial pilot bore hole by a cutter
or reamer moving in the same direction as the initial drill pipe string forming the
pilot bore hole.
Summary of the Invention
[0007] This invention is directed to an apparatus and method for drilling in one direction
of travel a pilot bore hole along an underground arcuate path between two earth surface
locations, and then enlarging in an opposite direction of travel the initial pilot
bore hole for receiving a product conduit therein. The apparatus and method utilized
to accomplish this comprise two separate cutting operations, the first being a pilot
bore drilled by a conventional drill pipe string but utilizing at least for a majority
of the drill pipe section an increased diameter of around three and one-half inches
(3-1/2") which increases the strength of the pipe string as compared with common industry
practice heretofore. The increased strength drill string thus eliminates the necessity
of having a separate washover string as the increased drill string strength is adequate
for the torsional or rotational stresses developed in the subsequent reaming operation
and pulling of the production conduit through the enlarged bore hole.
[0008] The drill string is thrust along a predetermined arcuate path to form an initial
pilot bore hole of a relatively small diameter, such as around five inches (5"), for
example. After the drilling of the initial pilot bore hole and exit of the drilling
string from the exit surface opening, a reamer and connected production conduit are
attached to the drill string, and the drill string is then pulled back through the
pilot bore hole in an opposite direction of travel with the reamer enlarging the bore
hole to a diameter sufficient to receive the production conduit therein. The enlarged
opening may be around thirty inches (30") in diameter for a production conduit, such
as a pipeline, around twenty inches (20") in diameter thereby providing a five inch
(5") annulus between the production conduit and the enlarged opening.
[0009] In order to provide the desired flexibility in the leading end pipe section of the
drill string, such as is desirable when relatively soft formations are encountered,
the leading end pipe section having the drill bit thereon may be provided of a diameter
smaller than the diameter of the regular drill string sections, or a different wall
thickness or different type of material may be utilized for the leading pipe
'section to provide the desired flexibility. Preferably, the drill string sections
except for the leading pipe sections are over around three inches (3") in diameter
and sections of three and one-half inches (3-1/2") in diameter have been found satisfactory.
The leading drill pipe section of this invention is preferably below three inches
(3") in diameter. Thus, the leading drill pipe section or sections may be provided
with an increased flexibility and the length of the leading end section may be varied.
Any reduced diameter drill pipe section or sections are preferably removed at the
surface location adjacent the exit opening prior to the attachment of the reamer and
production conduit to the drill string. Thus, a constant diameter drill string may
be provided for pulling the reamer and following product conduit through the pilot
bore hole in a reverse or opposite direction of travel.
[0010] Under certain conditions it may be desirable, such as for relatively long arcuate
paths, to provide drill pipe sections in the drill string of an increasing strength
from the leading end thereof to the power means for thrusting the drill bit and/or
rotating the drill string in the reaming operation. The increased strength pipe sections
compensate for the increasing friction of the drill string along its length. Drill
pipe sections having an increased strength may be provided independently of any increased
flexibility, if desired. In some situations, it may be desirable to have less flexibility
on the leading end drill pipe sections.
[0011] Another feature of this invention utilizes an in-hole hydraulic motor positioned
within the leading drill string section for rotating the drill bit, such as might
be desirable where relatively hard formations are encountered. When a leading pipe
section for the drill bit is provided utilizing the in-hole hydraulic motor, the longitudinal
axis of the drive shaft for rotating the drill bit is parallel to but offset from
the longitudinal axis of the drill string. This offset results in the deviation or
deflection of the drill bit a predetermined amount in the desired direction of travel
as the leading pipe section rides along the surface of the pilot bore hole formed
by the drill bit opposite the desired direction of deviation.
[0012] An object of this invention is to provide an apparatus and method in which a conventional
drill string comprising a plurality of drill pipe sections is thrust along an arcuate
path to the desired surface exit opening, and then a reamer and production conduit
are pulled, upon connection to the drill string, back through the pilot bore hole
in a minimum of time.
[0013] A further object is to provide a drill string for drilling the pilot bore hole having
a leading pipe section with an increased flexibility for drilling through relatively
soft formations, or for utilizing various lengths of leading drill pipe sections as
may be desired.
[0014] Another object is to provide a drill string for drilling the pilot bore hole having
drill pipe sections of increasing strength to compensate for the increasing friction
of the drill string along the pilot bore hole.
[0015] An additional object is to provide in a drill string for drilling the pilot bore
hole an in-hole hydraulic motor for rotating the drill bit relative to the drill string,
and having its rotational axis parallel but offset from the longitudinal axis of the
drill string to provide a desired deflection or deviation to the drill bit.
[0016] Another object is to provide a spud bit for drilling a bore hole having a novel shape
particularly adapted for use with discharge nozzles for a high velocity drilling fluid.
[0017] Other objects, features, and advantages of this invention will become more apparent
after referring to the following specification and drawings.
Description of the Invention
[0018]
FIGURE 1 is a perspective schematic cross-section of the initial drilling operation
in drilling an inverted arcuate pilot hole or bore from an earth entry opening to
an earth exit opening and utilizing the apparatus and method of the present invention;
FIGURE 2 is a perspective schematic cross-section similar to Fig. 1 but showing the
enlarging of the initial pilot bore hole by a reamer and the pulling of the production
conduit and reamer therethrough by the initial drill string;
FIGURE 3 is a schematic side elevation, partly in section, of the entrance end of
the pilot bore hole showing the thrust and rotating device for the drill string;
FIGURE 4 is an exploded view of a crossover sub for connecting adjacent drill string
lengths or sections of different diameters;
FIGURE 5 is a schematic side elevation of the leading end of the drill string showing
a deflecting spud bit for forming the initial pilot bore hole shown in Fig. 1;
FIGURE 5A is an end elevation of the spud bit shown in Fig. 5;
FIGURE 6 is a schematic side elevation of the end of the drill string connected to
a reamer and production conduit at the exit opening of the small diameter pilot bore
hole for pulling the reamer and production casing through the enlarged opening formed
by the reamer; and
FIGURE 7 is a schematic cross-section showing a modified drill bit arrangement in
which an in-hole motor driven by drilling fluid is utilized, such as may be required
for certain types of formations or bore hole lengths.
[0019] Referring now to the drawings for a better understanding of our invention, reference
is made to Fig. 1 in which an arcuate pilot bore hole is illustrated at B extending
along an underground path shown at P. Path P extends from an earth surface entrance
opening 0 to an earth surface exit opening E underneath an obstruction shown as a
river R.
[0020] While exit opening E is shown as a surface exit opening in the drawings, the terms
"exit opening", "surface exit opening" or "surface location" as used in the specification
and claims shall be interpreted as including an opening beneath the surface at which
a product conduit is connected to the drill string to be pulled through the bore hole,
such as an underground cable.
[0021] A drill string indicated generally at 10 includes a leading end pipe section 10A
of a small diameter, an adjacent end section 10B of an intermediate diameter, and
following pipe sections 10C of uniform diameter. Drill string 10 is utilized to drill
small diameter pilot bore hole B along path P. A plurality of lengths or sections
of pipe string 10 are normally positioned adjacent entrance opening 0 such as shown
at 10C in broken lines in Fig. 1.
[0022] As pointed out above, drill string pipe sections utilized heretofore in association
with a separate washover pipe string have been of a diameter around one and three-fourths
inches (1-3/4") since the washover string was relied upon for rotation of the reamer
and pulling of the production conduit. However, the present invention eliminates the
washover pipe and instead, provides a higher strength drill pipe string having a diameter
of three and one-half inches (3-1/2"). Such an increased diameter provides a stiffer
pipe string than used heretofore.
[0023] Under certain types of conditions encountered such as relatively soft formations,
it is desirable to have a smaller, more flexible leading end section on drill string
10 in order to achieve easily the necessary or desired deflection. As shown in Fig.
1, sections 10C are of the normal or regular diameter of three and one-half inches
(3-1/2"). However, leading section 10A is formed of a smaller diameter pipe and is
around two and three- quarters inches (2-3/4") in diameter, while pipe section 10B
is of an intermediate diameter of two and seven- eighths inches (2-7/8"). By using
a drill string with two or more graduated diameters, different length pipe sections
may be easily utilized as might be desirable under certain conditions, and this has
been found to be particularly useful where relatively soft ground conditions are encountered
where a smaller, more flexible leading end pipe section is desirable for obtaining
the desired deflection necessary to follow arcuate path P.
[0024] While increased flexibility is obtained by having pipe sections 10A and 10B of a
smaller diameter than sections 10C, it is to be understood that sections 10A and 10B
could, if desired, provide increased flexibility by other means, such as by being
made of a more flexible high strength material without being of a reduced diameter,
or by having a different wall thickness without any change in external diameter.
[0025] It is also desirable for a relatively long arcuate path P to have trailing pipe sections
of the drill string of a strength greater than the leading pipe sections. During a
thrust action, the drill string is pushed from the entrance opening 0 along the bore
hole B, and portions of the length of the drill string are in contact with the surface
of the bore hole B during the pushing action thereby to generate sliding frictional
resistance which has to be overcome. The greater the length of the drill string, the
greater the amount of sliding friction. Likewise, upon rotation of the drill string
during a reaming action, the torsional or rotational stresses in the drill string
are higher at the power source providing rotation. Thus, it is desirable to have drill
pipe sections adjacent the power source of an increased strength. It may be desired
to have drill pipe sections of graduated increasing strength from the drill bit end
to the power source. Further, it may not be desirable to have the diameter of the
drill string greater than around three and one-half inches (3-1/2"), or to have the
leading pipe sections of an increased flexibility. Under such conditions, the strength
of the drill pipe sections, particularly those sections adjacent the power means for
thrusting the drill bit along a relatively long arcuate path P, such as over five
hundred feet (500') in length, are preferably of an increased strength. Such increased
strength could be provided, for example, by making the pipe sections of high strength
materials or increasing the wall thickness of such pipe sections. The utilization
of drill pipe sections with different strengths thereby eliminates the necessity of
having a separate washover pipe following the drill string in concentric relation,
as a specific drill string section can be designed for the specific strength required
at its location in a drill string.
[0026] As shown in Fig. 3, an inclined ramp is shown at 12 and has a hydraulic motor 14
mounted on a carriage 16 for axial movement along a suitable guideway on ramp 12,
such as by a suitable pulley or cog wheel 18 moving along a taut cable 20, for example.
Motor 14 may be used, selectively, to rotate a connecting shaft 22 which is connected
at one end to a joint 24 attached to section 10C of drill string 10, thereby to rotate
drill string 10, if desired. Shaft 22 is connected at its other end to a swivel 26
which is in turn connected to a hose 28 through which a suitable drilling fluid is
circulated. Carriage 16 reciprocates back and forth as drill pipe sections are added
by making and breaking joint 24.
[0027] Drilling mud circulated through hose 28 is supplied to the drill pipe and out suitable
fluid passageways (not shown) at the drill bit for possible return to a sump shown
at 30 adjacent the end of entrance opening 0 which receives the drilling fluid and
cuttings from the drilling operation. A suitable hose shown at 32 returns the drilling
fluid or mud for removal of the cuttings, and again providing drilling fluid to hose
28 as is well known in the art.
[0028] Drill string 10 is standard and normally made up of a plurality of drill pipe sections
which are added to the drill pipe string at connector 24. The pipe sections are advanced
in the earth by advancing hydraulic motor 14 connected to a suitable source of hydraulic
fluid (not shown) down ramp 12.
[0029] Leading small diameter pipe section 10A has a spud bit 34 on its leading end. Spud
bits of various types are well known generally in the art for directional drilling
or the like. However, spud bit 34 as shown in Figs. 5 and 5A is particularly adapted
in the present invention for discharging a high velocity drilling fluid from its leading
end at a location closely adjacent the formation thereby to obtain a highly effective
excavating action to advance the drill string. It is important to note that spud bit
34 preferably discharges fluid in a direction parallel to the axis of the drill string
as shown by the arrows in Fig. 5. For this purpose, spud bit 34 has a flat or planar
forward end portion 34A, an inclined intermediate planar end portion 34B leading from
forward end portion 34A to form a ramp, and a rear planar shoulder 34C. An arcuate
shoe or wear plate 35 is secured to the outer periphery of pipe section 10A adjacent
rear shoulder 34C. It is noted that bore hole B has a diameter larger than the maximum
diameter of any portion of the drill string moving through the hole.
[0030] A discharge opening 34D or discharge nozzle which may be threaded within end portion
34A to form opening 34D is provided in the face formed by planar end portion 34A.
Thus, opening 34D is positioned at the leading end of spud bit 34 directly adjacent
the formation to be excavated for discharging a jet of high velocity drilling fluid
therein. The drilling fluid may be pressurized from around one hundred (100) psi to
around two thousand (2000) psi, for example. The longitudinal or discharge axis of
discharge nozzle 34D is parallel to, but offset from, the longitudinal axis of drill
string 10 to aid in deflecting end section 10A in the direction of the offset. Discharge
opening 34D is of sufficient depth such that pressurized fluid is preferably discharged
therefrom in a direction parallel to the longitudinal axis of drill string 10 to erode
and/or excavate the formation. It is apparent that end section 10A may be guided also
by rotation of the drill string through a defined angle. To provide an effective guiding
action, the offset of nozzle or opening 34D, or the offset of the center of the volume
of fluid being discharged in the event more than one discharge opening is utilized,
should be at least greater than around threefourths inch (3/4"). As an example, with
a spud bit having a diameter of five inches (5") as shown in Fig. 5A, nozzle 34D is
around threeeighths inch (3/8") in diameter and offset one inch (1") from the longitudinal
center line of section 10A.
[0031] It may be desirable under certain conditions to have more than one discharge nozzle,
but in any event, the center of the combined jets of drilling fluid being discharged
is parallel to and preferably offset from the longitudinal axis of section 10A in
the desired travel path. The ramp formed by inclined planar end portion 34B, rear
shoulder 34C, and shoe 35 ride along the surface of bore hole B opposite the desired
direction of deviation and aid in guiding pipe section 10A along travel path P. Under
certain conditions it may be desirable to have a ramp to aid in guiding pipe section
10A, such as ramp 34B, extending across the entire leading end of the spud bit without
any separate planar end portion such as shown at 34A. Spud bit 34 thus moves along
path P in a thrusting action without being rotated except for a predetermined partial
rotation to obtain angular orientation to guide pipe section 10A.
[0032] While spud bit 34 has been developed primarily for use in drilling a pilot bore hole
along an arcuate path between two surface locations, it is obvious that spud bit 34
may be utilized for other types of directional or down-hole drilling as well known
in the art.
[0033] Arcuate path P can be controlled or guided without withdrawing of the drill string
from the earth primarily by orientation of spud bit 34 by a partial rotation of the
drill string through a defined angle, but such control may also be dependent on such
factors or parameters, for example, as the thrust on the drill string and the volume
of drilling mud passed to the drill string, as is well known in the art. For further
details concerning the deviation or deflection of the drill string for directional
drilling or the like, as well known in the art, reference is made to U.S. patent no.
2,646,254 dated July 21, 1953 and U.S. patent no. 3,713,500 dated January 30, 1973,
as examples.
[0034] For connecting two pipe sections of different diameters, such as shown in Fig. 4,
a crossover sub indicated generally at 36 is illustrated having a threaded male end
38 adapted to be threaded within a female end 40 on pipe section 10A, and having a
female connection 42 on an opposite end thereof adapted to receive the male threaded
end 44 of adjacent pipe section 10B. A similar crossover sub 42 is provided between
sections 10B and 10C. The diameter of bore B is sufficiently larger than the diameter
of pipe string 10 to provide an annulus to permit the discharge of the drilling fluid
and cuttings from bore B. Utilizing a drill pipe string of a maximum diameter around
three and one-half inches (3-1/2"), bore B may be around five inches (5") in diameter
to provide adequate clearance for the flow of cuttings and drilling fluid from bore
B.
[0035] When leading drill section 10A reaches exit opening E and pilot bore hole B is completed,
it is now necessary to enlarge the pilot bore hole for receiving the production conduit
shown in the drawings as a pipeline 46. The production conduit may be any of several
types of continuous conduit, such as, for example, casing, pipe, cables, or the like,
and more than one production conduit may be installed in enlarged opening D. For this
purpose, a reamer indicated generally at 48 is shown in Fig. 6. Reamer 48 has cutting
teeth 50 thereon and is coupled at 52 to the end of the first drill section 10C of
the uniform diameter of three and one-half inches (3-1/2") for rotation by drill string
10 and motor 14. The end drill pipe section 10A, or at least the drill bit and any
associated instrumentation (not shown), is removed for connection of drill string
10 to reamer 48. It may be desirable to remove both sections 10A and 10B from the
end of the drill string 10 prior to the connection of reamer 48 if it is desired that
drill string 10 be of a uniform diameter and strength for rotating reamer 48 and pulling
production pipe 46 through bore hole B.
[0036] Drilling mud continues to be supplied through drill string 10 and pipe section 10C
to the cutting area adjacent reamer 48 where it is discharged through suitable perforations
as is well known. Shaft 54 extends from reamer 48 and has an enlarged diameter end
thereof at 56 received within a swivel indicated generally at 50 so that reamer 48
can rotate relative to production pipe 46. An equally satisfactory and effective method
and means could be utilized by a separate threaded sleeve connection between shaft
54 and reamer 48 as shown in Fig. 3 by connector 24. Enlarged end 56 of shaft 54 is
mounted within bearings 58 on opposite sides thereof for transmitting thrust to swivel
50 and to permit relative rotation between reamer 48 and production pipe 46. Preferably
pipe 46 enters the bore hole B without any rotation at all although in some instances
it may be desirable to rotate a production conduit being installed. Swivel body 50
has a clevis defining two spaced arms 60 on the side thereof opposite shaft 54, and
an extension 62 on a sleeve 66 is pivotally connected to arms 60 by pin or bolt 64.
[0037] Sleeve 66 is shown in Fig. 6 threaded onto an end of production pipe 46 which is
formed of a plurality of welded sections as common for pipelines. It is to be understood,
however, as well known in the art, that sleeve 66 could be secured by other means
to a production conduit, such as, for example, by welding, bolted connection, or other
types of threaded connections. Reamer 48 is of a diameter larger than a diameter of
production casing 46 so as to form a suitable annulus 68 in the enlarged diameter
opening D. For example, if production casing or pipe 46 is of a diameter of twenty
inches (20"), reamer 48 may be of a thirty inch (30") diameter to provide a five inch
(5") annulus 68 about the periphery of pipe 46. Annulus 68 may be utilized for cementing
of conduit 46 in position.
[0038] After pipe 46 has been pulled through the enlarged opening D from surface location
at opening 0, sleeve 66 is removed from production casing 46 and production casing
46 may be cemented or secured in position.
[0039] Referring to Fig. 7, a modified form of end section is shown at 10D for an in-hole
motor 70 which is used where relatively hard formations may be encountered. In-hole
motor shown at 70 is positioned within an enlarged diameter end portion 71 of drill
string section 10D and is a hydraulic motor driven by drilling fluid received by the
drill string. The longitudinal axis of the drill string is shown along line 72 while
the longitudinal axis of the rotating drill bit shaft 74 is shown at 76. A drill bit
78 is connected to the end of shaft 74 for rotation therewith. While hydraulic motor
70 is shown schematically in Fig. 7 as being separate and larger than shaft 74, it
is to be understood, as well known in the art, that motor 70 and shaft 74 may be combined
and of a single continuous diameter such as illustrated schematically by shaft 74.
[0040] It is noted that axis 76 is offset from but parallel to axis 72 to aid in deflecting
end section 10D a predetermined amount in the desired direction of travel. While axis
76 is shown as offset above axis 72 in Fig. 7 to deflect end section 10D upwardly,
it may be offset laterally or downwardly by limited rotation of the drill string through
a defined angle if a different path of travel is desired. It is noted that other parameters
may be utilized to aid in the control of direction of the drill string along the desired
travel path P as indicated above for the embodiment shown in Fig. 5, and, in addition,
the speed of rotation of drill bit 78. Enlarged diameter end portion 71 has a beveled
leading end 79 which rides along the surface 80 of bore B opposite the direction of
the offset and as a result of the offset directs bit 78 in the direction of the offset.
The amount of offset along with the other parameters set forth for the embodiment
of Fig. 5, and the speed of rotation of drill bit 78, determine the amount of deviation
or deflection. Motor 70, as well known in the art, has a conventional stator and rotor
with drive shaft 74 connected to the rotor. Drilling fluid passes through the rotor
and stator to effect a rotation of shaft 74 and drill bit 78, as well known in the
art.
[0041] While the bore hole B formed by drill bit 78 is illustrated diagrammatically in Fig.
7 of a diameter not greater than the diameter of enlarged end portion 71, it is to
be understood that the diameter of bore hole B formed by bit 78 is always of a diameter
greater than the diameter of end portion 71 in order to provide a suitable annulus
for the flow of drilling fluid and cuttings from drill bit 78.
[0042] While preferred embodiments of the present invention have been illustrated in detail,
it is apparent that modifications and adaptations of the preferred embodiments will
occur to those skilled in the art. However, it is to be expressly understood that
such modifications and adaptations are within the spirit and scope of the present
invention as set forth in the following claims.
1. Apparatus for drilling an arcuate underground pilot bore hole along a predetermined
inverted arcuate path between two spaced earth surface locations; said apparatus comprising:
a drill pipe string including a plurality of connected pipe sections extending from
one surface location into a bore entrance opening of the pilot bore hole;
means at said one surface location to apply a thrust on said pipe string;
said drill pipe string having a leading pipe section with a drill bit thereon and
being of a flexibility greater than the other pipe sections; and,
means to circulate drilling fluid during the drilling operation.
2. Apparatus as set forth in claim 1 wherein the increased flexibility of said leading
pipe section is achieved by said leading pipe section being of a diameter less than
the other pipe sections.
3. Apparatus as set forth in claim 2 wherein a crossover sub connects the leading
pipe section with the adjacent pipe section.
4. Apparatus as set forth in claim 2 wherein both the leading pipe section and the
immediately adjacent pipe section have a diameter less than the remainder of the pipe
sections thereby to form a relatively long length flexible end for the drill string.
5. Apparatus as set forth in claim 2 wherein the diameter of the leading pipe section
is less than around three (3) inches and the diameter of the regular drill pipe sections
is more than around three (3) inches.
6. Apparatus for drilling an arcuate underground pilot bore hole along a predetermined
inverted arcuate path between two spaced surface locations in one direction of travel,
and then reaming an enlarged opening along the pilot bore hole in an opposite direction
of travel while simultaneously placing a production conduit therein; said apparatus
comprising:
a drill pipe string including a plurality of threaded connected pipe sections extending
from one surface location into a bore entrance opening of the pilot bore hole, said
string including pipe sections of different strengths and a leading pipe section with
a drill bit thereon;
means at said one surface location applying a thrust on said pipe string in said one
direction of travel to force said pipe string in a thrust action along the arcuate
path in said one direction of travel to an exit opening at the other surface location;
means to circulate drilling fluid through said drill string during the drilling operation;
a reamer connected to said drill string at the other surface location after the pilot
bore hole is drilled between said spaced surface locations to form an enlarged opening
along the pilot bore hole;
a production conduit connected to said reamer and following said reamer through the
enlarged opening formed by the reamer;
said means at said one surface location including means for pulling said drill string,
said reamer, and said production conduit along the enlarged opening in an opposite
direction of travel, said pulling means at said one surface location rotating said
drill string and reamer simultaneously with the pulling action; and
said means to circulate drilling fluid providing drilling fluid for said reamer during
the reaming operation.
7. Apparatus as set forth in claim 6 wherein said pipe sections adjacent said means
applying a thrust are of a greater strength than the pipe section at the leading end
of said pipe string.
8. Apparatus as set forth in claim 6 wherein the drill bit on said leading pipe section
comprises a spud bit.
9. Apparatus as set forth in claim 6 wherein a swivel connects said reamer and said
production conduit to each other to permit relative rotation therebetween.
10. Apparatus for drilling an arcuate underground pilot bore hole along a predetermined
inverted arcuate path between two spaced earth surface locations; said apparatus comprising:
a drill pipe string including a plurality of connected pipe sections extending from
one surface location into a bore entrance opening of the pilot bore hole;
means at said one surface location to apply a thrust on said pipe string;
said drill pipe string having a leading pipe section with a drill bit thereon and
being of a strength less than the pipe sections adjacent said means to apply a thrust;
and
means to circulate drilling fluid through said drill pipe during the drilling operation.
11. Apparatus as set forth in claim 10 wherein said leading pipe section is of a smaller
diameter than the diameter of the pipe sections adjacent said means to apply a thrust.
12. Apparatus as set forth in claim 10 wherein said leading pipe section is of the
same diameter as the remaining pipe sections but has a decreased wall thickness.
13. Apparatus as set forth in claim 10 wherein said leading pipe section is of the
same diameter as the remaining pipe sections but formed of a more flexible high strength
material than at least the majority of the remaining pipe sections.
14. Apparatus for drilling an arcuate underground pilot bore hole along a predetermined
inverted arcuate path between two spaced surface locations in one direction of travel,
and then reaming an enlarged opening along the pilot bore hole in an opposite direction
of travel while simultaneously placing a production conduit therein; said apparatus
comprising:
a drill pipe string including a plurality of threaded connected pipe sections extending
from one surface location into a bore entrance opening of the pilot bore hole, said
string including pipe sections of different strengths and a leading pipe section with
a drill bit thereon;
at least some of the leading pipe sections being of a reduced strength relative to
at least some of the trailing pipe sections, and at least some of the leading pipe
sections being of an increased flexibility relatively to at least some of the trailing
pipe sections;
means at said one surface location applying a thrust on said pipe string in said one
direction of travel to force said pipe string in a thrust action along the arcuate
path in said one direction of travel to an exit opening at the other surface location;
means to circulate drilling fluid through said drill string during the drilling operation;
a reamer connected to said drill string at the other surface location after the pilot
bore hole is drilled between said spaced surface locations to form an enlarged opening
along the pilot bore hole;
a production conduit connected to said reamer and following said reamer through the
enlarged opening formed by the reamer;
said means at said one surface location including means for pulling said drill string,
said reamer, and said production conduit along the enlarged opening in an opposite
direction of travel, said pulling means at said one surface location rotating said
drill string and reamer simultaneously with the pulling action; and
means operatively connecting the production conduit to the reamer;
said means to circulate drilling fluid providing drilling fluid for said reamer during
the reaming operation.
15. Apparatus as set forth in claim 14 wherein the majority of the pipe sections in
said pipe string have a diameter over around three (3) inches.
16. Apparatus for drilling an arcuate underground pilot bore hole along a predetermined
inverted arcuate path between two spaced surface locations in one direction of travel,
and then reaming an enlarged opening along the pilot bore hole in an opposite direction
of travel while simultaneously placing a production conduit therein; said apparatus
comprising:
a drill pipe string including a plurality of threaded connected pipe sections extending
from one surface location into a bore entrance opening of the pilot bore hole, said
string including pipe sections of different strengths and a leading pipe section with
a spud bit thereon;
said spud bit having a planar forward end portion forming a flat front face thereof,
said flat face having a discharge opening for receiving and discharging high velocity
drilling fluid directly into the adjacent formation, and an intermediate planar portion
slanting rearwardly from said front face for riding along the surface of the bore
hole;
means at said one surface location applying a thrust on said pipe string in said one
direction of travel to force said pipe string in a thrust action along the arcuate
path in said one direction of travel to an exit opening at the other surface location;
means to circulate drilling fluid through said drill string during the drilling operation;
a reamer connected to said drill string at the other surface location after the pilot
bore hole is drilled between said spaced surface locations to form an enlarged opening
along the pilot bore hole; and
a production conduit connected to said reamer and following said reamer through the
enlarged opening formed by the reamer;
said means at said one surface location including means for pulling said drill string,
said reamer, and said production conduit along the enlarged opening in an opposite
direction of travel, said pulling means at said one surface location rotating said
drill string and reamer simultaneously with the pulling action;
said means to circulate drilling fluid providing drilling fluid for said reamer during
the reaming operation.
17. Apparatus for drilling a pilot bore hole as set forth in claim 16 wherein an arcuate
shoe is secured to the outer periphery of the leading pipe section adjacent said spud
bit for riding along a surface of the bore hole.
18. Apparatus for drilling a pilot bore hole as set forth in claim 17 wherein said
spud bit has a lower planar shoulder adjacent said arcuate shoe for riding along a
surface of the bore hole.
19. A method for drilling an arcuate underground pilot bore hole along a predetermined
arcuate path in one direction of travel between two surface locations, and then enlarging
the pilot bore hole in an opposite direction of travel between the surface locations
to receive a production conduit therein, the bore hole being drilled by a drill pipe-string
of connected pipe sections including a leading drill pipe section of a smaller diameter
than the diameter of at least the majority of the remaining pipe sections, said method
comprising the steps of:
advancing the small diameter leading drill pipe section with a drill bit thereon in
one direction of travel along the arcuate path from a surface entry location to a
surface exit location;
removing the small diameter leading drill pipe section from the drill pipe string
after exit from the exit location;
attaching a reamer and production conduit connected thereto to the drill string at
the exit location after the small diameter leading pipe section has been removed;
pulling the drill string, reamer, and production conduit along the pilot bore hole
from the exit location to the earth entry location in an opposite direction of travel
with the reamer forming an enlarged opening to receive the production conduit;
rotating said drill string and reamer during pulling thereof; and
circulating drilling fluid through said drill string during the drilling and reaming
operations.
20. A method for drilling an arcuate underground pilot bore hole along a predetermined
arcuate path in one direction of travel between two surface locations defining an
entrance and an exit, and then enlarging the pilot bore hole in an opposite direction
of travel between the surface locations to receive a production conduit therein, the
bore hole being drilled by a drill pipe string of connected pipe sections including
a leading drill pipe section of a strength less than the strength of at least the
majority of the remaining pipe sections; said method comprising the steps of:
providing thrusting means at the surface entrance location to advance the drill string
and small diameter leading drill pipe section with a drill bit thereon in one direction
of travel along the arcuate path;
circulating drilling fluid through said drill string during the drilling operation;
removing the small diameter leading drill pipe section from the drill pipe string
after exit from the exit location;
attaching a reamer and production conduit connected thereto to the drill string at
the exit location after the small diameter leading pipe section has been removed;
pulling the drill string, reamer, and production conduit along the pilot bore hole
from the exit location to the entry location in an opposite direction of travel with
the reamer forming an enlarged opening to receive the production conduit;
rotating said drill string and reamer during pulling thereof; and
circulating drilling fluid through said drill string during the reaming operation.
21. A method of drilling an arcuate underground pilot bore hole along a predetermined
path between two spaced surface locations utilizing a spud bit on a leading drill
pipe section of a drill string with a discharge nozzle in a leading planar front face
of the bit directly adjacent the formation to be excavated and eroded; said method
comprising the steps of:
advancing the leading drill pipe section of the drill string having the spud bit thereon
with the nozzle in said planar face positioned directly adjacent the formation to
be excavated from a surface entry location to a surface exit location;
and discharging drilling fluid from said nozzle in a jet parallel to but offset from
the longitudinal axis of said drill pipe section to aid in guiding the drill pipe
section along the predetermined path.
22. The method of drilling an arcuate underground pilot bore hole as set forth in
claim 21 and further including the step of providing a predetermined partial rotation
of said leading drill pipe section and said spud bit thereby to change the direction
of offset and the deviation of the leading drill pipe section.
23. Apparatus for drilling a pilot bore hole along a predetermined underground arcuate
path between two spaced surface locations comprising:
a drill pipe string including a plurality of connected drill pipe sections extending
from one surface location into a bore entrance opening of the pilot bore hole and
having a leading pipe section;
means at said one surface location to apply an axial thrust to said pipe string;
means to circulate drilling fluid through said drill pipe string during the drilling
operation; and
a spud bit on the leading pipe section of said pipe string having a leading end face
thereon and fluid discharge nozzle means on said end face for discharging drilling
fluid in a jet offset from the longitudinal axis of said leading pipe section to aid
in guiding the pipe string along the predetermined arcuate path, said leading drill
pipe section and said spud bit adapted to be partially rotated a predetermined amount
to change the deviation of offset of said nozzle means and the deviation of the leading
drill pipe section.
24. Apparatus for drilling a pilot bore hole as set forth in claim 23 wherein an arcuate
shoe is secured to the outer periphery of the leading pipe section adjacent said spud
bit for riding along the surface of the bore hole opposite the desired direction of
deviation.
25. Apparatus for drilling a pilot bore hole as set forth in claim 23 wherein said
spud bit has a lower planar shoulder adjacent said arcuate shoe for riding along the
surface of the bore hole opposite the desired direction of deviation.
26. A method of drilling an arcuate underground pilot bore hole along a predetermined
path between two spaced surface locations utilizing a spud bit on a leading drill
pipe section of a drill string with discharge nozzle means in a leading front face
of the bit directly adjacent to the formation to be excavated and eroded; said method
comprising the steps of:
advancing the leading drill pipe section of the drill string having the spud bit thereon
with said nozzle means in said front face positioned directly adjacent the formation
to be excavated from a surface entrance location to a surface exit location;
discharging dri'lling fluid from said nozzle means in a jet with the center of the
drilling fluid jet being discharged offset from the longitudinal axis of the leading
pipe section to aid in guiding the pipe string along the predetermined arcuate path;
and
providing a predetermined partial rotation of the leading drill pipe section and the
spud bit thereby to change the direction of offset of said nozzle means and the deviation
of the leading pipe section.
27. Apparatus for drilling an arcuate underground pilot bore hole along a predetermined
inverted arcuate path between two spaced surface locations in one direction of travel,
and then reaming an enlarged opening along the pilot bore hole in an opposite direction
of travel for receiving a production conduit therein; said apparatus comprising:
a drill pipe string including a plurality of connected threaded pipe sections extending
from one surface location into a bore entrance opening of the pilot bore hole, the
drill pipe string including a leading pipe section having a spud bit with a leading
front face thereon;
fluid discharge nozzle means on said front face for discharging drilling fluid in
a jet having its center offset from the longitudinal axis of said leading pipe section
to aid in guiding the pipe string along the predetermined arcuate path, said leading
drill pipe section and said spud bit adapted to be partially rotated in a predetermined
amount to change the directional offset of said nozzle means and the deviation of
the leading drill pipe section;
means at said one surface location applying a thrust on said pipe string in said one
direction of travel to force said pipe string in a thrust action along the arcuate
path in said one direction of travel to an exit opening at the other surface location;
means to circulate drilling fluid through said drill string during the drilling operation;
a reamer connected to said drill string at the other surface location after the pilot
bore hole is drilled between said spaced surface locations and after removal of the
spud bit from the drill string;
said means at said one surface location including means for pulling said drill string
and said reamer along the pilot bore hole in the opposite direction of travel to form
an enlarged opening for receiving a production conduit, said pulling means rotating
said drill string and reamer simultaneously with the pulling action.
28. Apparatus for drilling an arcuate underground pilot bore hole as set forth in
claim 27 wherein the leading front face of said spud bit is a planar face extending
in a plane generally transversely of the longitudinal axis of the drill string and
having a plurality of discharge nozzles therein for discharging drilling fluid in
streams directly against the formation, the center of the mass of discharged fluid
being offset from the longitudinal axis of the drill string.
29. Apparatus for drilling an arcuate underground pilot bore hole as set forth in
claim 27 wherein the leading front face of said spud bit is a planar face extending
in a plane generally transversely of the longitudinal axis of the drill string, and
said spud bit has an inclined planar lower surface extending from said planar front
face and adapted to ride along the lower surface of the pilot bore hole.