[0001] The present invention relates to a construction apparatus and a construction method
advantageously applicable to carrying out the construction of various structures including
low buildings and high buildings using the least necessary labor and capable of enabling
the construction work to be carried out regardless of weather conditions.
[0002] In constructing a multistory building, a conventional construction method erects
columns for all the stories, lifts up the component members of the multistory building
preassembled on the ground including slabs by lifting machines including cranes, and
then joins the component members to the columns. Another conventional construction
method stacks up stories one on another by completing a lower story, and then lifting
the component members of an upper story by lifting machines including cranes and assembling
the component members on the lower story.
[0003] Fig. 1 is an illustration of the latter conventional construction method, in which
the first and second stories of a building have been completed and the third story
is under construction. A worker H standing on the floor of the third story receives
building members S lifted by a crane C, and then the worker H assembles the building
members S by fixing the building members S at predetermined position by suitable means
including welding and bolts.
[0004] J. P. Pat. Provisional Pub. (Kokai) No. 62-244941 proposes a construction method
which completes one story of a building in a plant installed in the first story of
the building by using machines including industrial robots, and then pushes up the
complete story by a distance corresponding to the story height. This procedure is
repeated to complete a multistory building.
[0005] In constructing a multistory building by the foregoing conventional construction
method which erects all the columns first, and then assembles the building components
lifted up by lifting machines and the other conventional construction method which
constructs the stories of a multistory building one by one from the lower stories
to the upper stories required, much time and labor is necessary, the progress of the
construction schedule is dependent on weather conditions, the construction period
is often extended due to various restrictions (for example not to work at night),
and various measures must be taken for the safety of the workers.
[0006] Although the construction method proposed in J. P. Pat. Provisional Pub. (Kokai)
No. 62-244941 solves most of those problems involved in the foregoing conventional
construction methods, this construction method has a problems that the height of the
building is limited by the strength of the supporting members for pushing up a completed
story of the building in view of the weight of the building and so on. Furthermore,
since the weight supported by the supporting members during the construction work
increases with the progress of the construction work and the plant is installed on
the ground floor, it is possible that the stability of the support of the completed
stories against earthquake deteriorates with the progress of the construction work.
[0007] Accordingly, it is an object of the present invention to provide a construction apparatus
and a construction method advantageously applicable to the construction of various
structures including high and low buildings requiring the least necessary labor and
low costs.
[0008] It is another object of the present invention to provide a construction apparatus
and a construction method capable of enabling construction work to be carried out
regardless of weather conditions.
[0009] It is a further object of the present invention to provide a construction apparatus
and a construction method capable of securing sufficient resistance to earthquakes
for a structure under construction.
[0010] In one aspect of the present invention, a construction apparatus comprises a framework
including beams and constructed on a completed structure so as to form a working space
on the underlying completed structure, and extension columns provided on the framework
and capable of being extended from the framework to support the framework above the
completed structure so that the working space may be formed between the framework
and the underlying completed structure. And the extension column may be contracted
to install permanent columns between the lower ends thereof and the completed structure.
[0011] The extension columns provided on the framework are extended simultaneously to elevate
the framework so that a temporary working space is formed between the framework and
the underlying completed structure supporting the extension columns. The extended
extension columns serve as temporary columns during construction work in the temporary
work space over the underlying completed structure. The extension columns corresponding,
respectively, to positions where permanent columns are to be installed are contracted
sequentially one at a time to install the permanent columns sequentially at positions
corresponding to the contracted extension columns. Thus, a working space provided
with the permanent columns is formed under the framework. After a structure to be
constructed in the working space has been completed, the extension columns are extended
again simultaneously to form another temporary working space for constructing the
next upper structure. Since the upper structures are constructed sequentially by extending
and contracting the extension columns to secure a working space, the construction
work can be easily controlled automatically, and the use of the construction apparatus
in combination with automatic construction equipment enables automatic construction
work.
[0012] A roof is formed over the framework and an enclosure is formed around the framework
to shield the working space from the outside. Accordingly, the construction work can
be carried out without being affected by weather conditions and without giving public
nuisance to the environment. The framework and roof of the construction apparatus
may be incorporated into the building as a penthouse.
[0013] The framework may be a temporary framework provided with a temporary roof and a temporary
enclosure, which are the same in function as the foregoing roof and enclosure.
[0014] The extension columns may be hydraulic cylinders, screw jacks, or a rack-and-pinion
mechanism comprising pinions rotatably supported on the framework and rods provided
with racks respectively engaging the pinions.
[0015] Overhead traveling cranes detachably provided with construction robots may be provided
on the framework. In some cases, the traveling cranes and the construction robots
are controlled on a cylindrical coordinate system or a polar coordinate system.
[0016] Lifts each provided with a rotary floor for unloading the cargo at an optional angular
position may be installed in the internal space of the building.
[0017] A control room may be constructed in the upper space of the framework.
[0018] In another aspect of the present invention, a construction apparatus comprises a
framework including beams and installed on a completed structure so as to form a working
space in which an upper structure including permanent columns is to be constructed
on the completed structure, columns erected on and removably supported on the underlying
completed structure, elevating and locking means provided on the framework, capable
of being locked to the columns to hold the framework on the underlying completed structure
and capable of being unlocked to enable the framework to be elevated along the columns
to form a working space between the framework and the underlying completed structure,
and construction means provided on the framework for construction work within the
working space.
[0019] The elevating and locking means provided on the framework are fastened to the columns
supported on the columns to hold the framework firmly on the underlying completed
structure. Since the elevating and locking means are locked to the columns during
construction work within the working space, the vibration resistance of the construction
apparatus can be sufficiently secured throughout the construction work.
[0020] In forming another working space over the next upper structure, the elevating and
locking means are unlocked, the framework is elevated along the columns to form another
working space, and then the elevating and locking means is locked again to the columns.
When the elevating and locking means are locked to the columns, the columns serve
as members for forming the working space to support the framework. Then, permanent
columns are erected one by one in the working space and beams are joined firmly to
the permanent columns by construction means to complete a structure for the next upper
story on the underlying completed structure. Such a construction work including forming
a working space and constructing a structure is repeated to construct structures for
the upper stories sequentially.
[0021] Thus, the construction work is advanced upward in steps by alternately repeating
the elevation and locking of the framework to form working spaces sequentially. In
thus carrying out the construction work by regularly advancing the working space upward
in the foregoing manner and constructing a structure by using the construction means
provided on the framework, the elevation of the framework and the operation of the
construction means can be easily controlled automatically, and the construction apparatus,
in cooperation with automatic construction equipments, enables automatic construction
work.
[0022] The framework is provided with a covering for covering the working space to shield
the working space from the outside, and hence the construction work can be carried
out regardless of weather conditions without giving public nuisance to the environment.
[0023] Furthermore, the columns are provided with racks respectively, and the elevating
and locking means are provided with pinions respectively. The combination of the columns
and the elevating and locking means may be a screw and rod mechanism, a center hole
jack mechanism or a hydraulic jack mechanism.
[0024] The construction means include column erecting robots, column welding robots, beam
welding robots and external wall installing robots.
[0025] The columns may be either temporary columns or permanent columns.
[0026] The framework may be provided with traveling cranes and construction robots mounted
on the traveling cranes. In some cases the traveling cranes and the construction robots
are controlled on a cylindrical coordinate system or a polar coordinate system.
[0027] Lifts for lifting up construction materials may be installed in the internal space
of the structure, and each lift may be provided with a rotary floor to unloaded the
construction materials selectively at a desired position.
[0028] A control room may be constructed in the upper space of the framework.
[0029] In a further aspect of the present invention, a construction apparatus comprises
a framework placed on a completed structure of a building under construction to form
a working space for construction work including installing permanent columns, elevating
means provided on the framework and capable of extending downward from the framework
to elevate the same and to serve as temporary columns for forming the working space
over the completed structure of the building, locking mechanism provided on the lower
ends of the elevating means and removably fitting the completed structure of the building,
and construction means provided on the framework for construction work in the working
space.
[0030] The locking mechanism is fitted with the upper ends of the permanent columns prior
installed the underlying completed structure of the building.
[0031] The holding means is provided on the framework and capable of extending downward
from the framework to position and hold the permanent columns installed upright in
the working space at the upper ends thereof.
[0032] The permanent column has an engaging portion at the upper end thereof and the holding
means have a fitting portion at the lower end thereof opposite to the upper end of
the permanent column for positioning each other.
[0033] The permanent column has an engaging portion at the upper end thereof.
[0034] The permanent column has a fitting end portion at the lower end thereof fitting the
engaging portion of the other permanent column prior installed the underlying completed
structure of the building.
[0035] The locking mechanism have a fitting portion at the lower end thereof opposite to
the upper end of the permanent column to engaging the engaging portion of the permanent
column for positioning each other.
[0036] The framework can be positioned correctly relative to the completed structure of
the building and the framework is restrained from lateral movement relative to the
completed structure by the engagement of the fitting portion of the locking mechanism
provided on the lower ends of the elevating means serving as the temporary columns
and the engaging portion formed in the upper ends of the permanent columns of the
underlying completed structure of the building, so that the framework can be supported
securely on the completed structure of the building under construction and the earthquake
resistance of the framework during the construction work is improved.
[0037] The framework is elevated by downwardly extending the elevating means serving as
the temporary columns to form the working space, the permanent columns are installed
in the working space by the construction means, the permanent columns is firmly positioned
one at a time by extending the holding means, and the permanent columns and beams
previously attached to the permanent columns or attached to the permanent columns
in the working space are joined firmly to complete the structure of an upper story
on the underlying previously completed structure of the building.
[0038] After completing the structure of the upper story, the framework is elevated again
by the elevating means to start constructing the structure of the next upper story.
[0039] Thus, the framework is elevated repeatedly to form working spaces sequentially for
the upper stories to proceed with sequentially constructing the upper stories from
the lower to the upper stories. Such regular upward shift of the working space and
the construction within the working space facilitate the automated control of elevating
the framework, driving the holding means and the operation of the construction means,
and enables automated construction work using automatic construction machines.
[0040] The fitting end portions formed on the lower ends of the permanent columns, and the
engaging portions formed in the upper ends of the permanent columns bring the permanent
columns for the upper structure into alignment with the permanent columns of the underlying
structure in installing the permanent columns for the upper structure, so that the
permanent columns for the upper structure are joined correctly and easily to those
of the underlying structure.
[0041] Since the fitting portions formed on the lower ends of the holding means engage the
engaging portions formed in the upper ends of the permanent columns, the permanent
columns are positioned easily and held stably, the support of the framework is reinforced
and hence the earthquake resistance of the framework during the construction is improved.
[0042] In a further aspect of the present invention, a construction method comprises steps
of elevating a framework formed on a completed structure by simultaneously extending
a set of extension columns provided on the framework to form a working space in which
the next upper structure is to be formed; sequentially contracting the extension columns
to sequentially form spaces for receiving permanent columns between the framework
and the underlying completed structure and setting up the permanent columns in the
spaces; extending beams between the permanent columns; carrying out construction work
in a working space formed by the permanent columns and the beams; and repeating the
foregoing sequential steps to advance the construction work upward story by story
to complete a building.
[0043] In still a further aspect of the present invention, a construction method comprises
steps of elevating a framework constructed on a completed structure to form a working
space over the underlying completed structure; locking the elevated framework to the
underlying completed structure; sequentially setting up permanent columns in the working
space; extending beams between the fixed permanent columns; carrying out construction
work in a working space formed by the permanent columns and the beams; unlocking the
framework from the completed structure; and repeating the foregoing sequential steps
to advance the construction work upward story by story to complete a building.
Figure 1 is a pictorial view of assistance in explaining a conventional construction
method;
Figures 2(A) to 2(F) are schematic perspective view of assistance in explaining the
principle of a construction apparatus in a first embodiment according to the present
invention;
Figures 3(A) and 3(B) are fragmentary sectional views of essential portions of extension
columns (extension means) and holding mechanisms employed in the construction apparatus
embodying the present invention;
Figure 4 is an illustration showing the construction apparatus in the first embodiment
according to the present invention as applied to practical construction work;
Figures 5(A) to 5(G) are schematic perspective views of assistance in explaining the
principle of a construction apparatus in a second embodiment according to the present
invention;
Figure 6 is a partially cutaway schematic perspective view of the construction apparatus
in a second embodiment according to the present invention as applied to an actual
construction work;
Figure 7 is a schematic sectional view taken in Fig. 6;
Figures 8(A) to 8(F) are schematic perspective views of assistance in explaining the
principle of a construction apparatus in a third embodiment according to the present
invention;
Figure 9 is a schematic perspective view of a construction apparatus in the third
embodiment according to the present invention as applied to a practical construction
work;
Figure 10 is a schematic plan view of an essential portion of the construction apparatus
shown in Fig. 9;
Figure 11 is a sectional view taken on line XI-XI in Fig. 10;
Figure 12 is a sectional view taken on line XII-XII in Fig. 10;
Figure 13 is a sectional view taken on line XIII-XIII in Fig. 10; and
Figure 14 is a plan view taken in the direction of an arrow XIV in Fig. 10.
[0044] The principle on which a construction apparatus in a first embodiment according to
the present invention is based will be described with reference to Figs. 2(A) to 2(F).
The construction apparatus shown in Figs. 2(A) to 2(F) by way of example comprises,
as principal components, a framework 3 (either permanent or temporary) constructed
on a previously completed structure of a building 10 to form a working space 14 between
the framework 3 and the underlying structure, and extension columns 1 provided on
the framework 3, capable of extending downward from the framework 3 to serve as temporary
columns for forming the working space 14 between the framework 3 and the underlying
structure. And the extension columns 1 may be capable of being individually contracted
to form a space 15 between the lower end thereof and the underlying structure of the
building 10 for receiving a permanent column 6 therein. The framework 3 is provided
with a roof 16 to cover the working space 14.
[0045] In this example, four extension columns 1 are hydraulic cylinders each having a rod
2. The stroke of the rod 2 is slightly greater than the story height of a structure
to be constructed on the underlying structure of the building 10.
[0046] Each of the extension column 1 may be, as shown in Fig. 3(A), a combination of a
rod 2 provided with a rack 20 along the entire length thereof, a sheath 13 fixed to
the framework 3 and slidably receiving the rod 2 therein, and a pinion 21 rotatably
supported on the sheath 13 and engaging the rack 20 to extend or contract the rod
2 along the sheath 13 or may be, as shown in Fig. 3(B), a combination of a rod 2 externally
provided with a helical thread 22, and a sheath 13 internally provided with a helical
groove 23 engaging the helical thread 22 of the rod 2, which is similar to a screw
jack. The rod 2 is extended or contracted by rotating the rod 2 relative to the sheath
13.
[0047] When the framework 3 is for temporary use, the framework 3 is formed in a shape similar
in the plan to the shape of the upper surface of the underlying structure of the building
10, for example, a rectangular shape as shown in Figs. 2(A) to 2(F). When the framework
3 is for permanent use, the framework 3 is formed so as to support the roof, not shown,
of a building to be constructed. The extension columns 1 are fixed to the framework
3 so as to support the same on the underlying structure of the building 10.
[0048] A traveling crane 5 is supported on opposite beams 3a and 3b of the framework 3 for
travel along the beams 3a and 3b, and a welding robot 4, for example, is mounted removably
on the traveling crane 5.
[0049] Referring to Fig. 2(A), the rods 2 of the four extension columns 1 are extended simultaneously
to their full length to form the working space 14 between the framework 3 and the
underlying structure of the building 10. In this state, the rods 2 serve as temporary
columns. Then, the rod 2 of one of the extension columns 1 is fully retracted to form
a space 15 for receiving a permanent column 6 between the lower end of the rod 2 and
the underlying structure of the building 10. In this state, the framework 3 is supported
by the other three extension columns 1. In practical application, the construction
apparatus is provided with far more than four extension columns 1 to support the framework
3 by far more than four rods 2, and hence the framework 3 can be supported securely
even if some of the rods 2 are fully retracted.
[0050] Referring to Fig. 2 (B), a permanent column 6 is installed in the space 15 below
the contracted extension column 1. In installing the permanent column 6, the welding
robot 4 is removed from the traveling crane 5 and a column installing robot 9 capable
of gripping the permanent column 6 is mounted on the traveling crane 5 to carry and
install the permanent column 6.
[0051] Then, as shown in Fig. 2(C), the permanent column 6 is fixed firmly to the underlying
structure of the building 10, for example, by welding while the rod 2 of the extension
column 1 presses the permanent column 6 against the underlying structure of the building
10. Then, the rod 2 of another extension column 1 is fully retracted and another permanent
column 6 is installed fixedly on the underlying structure through the same procedure.
Thus, the permanent columns 6 are installed below the four extension columns 1 on
the underlying structure by repeating the same procedure, while the column installing
robot 9 is moved to relevant positions by the traveling crane 5.
[0052] Then, as shown in Fig. 2(D), the column installing robot 9 is changed for a beam
installing robot 12, and then beams 7 are joined to the permanent columns 6 by using
the beam installing robot 12.
[0053] In joining the beam 7 to the permanent columns 6, the beam 7 is extended between
opposite beam joints 8 attached previously to the permanent columns 6, and then the
beam 7 is fixed to the beam joints 8 by suitable means, such as welding or bolting.
[0054] The beam installing robot 12 is moved to relevant positions in joining the all beams
7 to the permanent columns 6.
[0055] Fig. 2(E) shows a stage of the construction work immediately after the completion
of installation of the beams 7. In this example, the beams 7 are joined to the beam
joints 8 by both welding and bolting; that is, first all the beams 7 are installed
between and fastened with bolts and nuts to the beam joints 8 by using the beam installing
robot 12, the beam installed robot 12 is changed for the welding robot 4, and then
the beams 7 are welded to the beam joints 8 by using the welding robot 4. The welding
robot 4 is used also for welding floor slabs to the beams 7.
[0056] Subsequently, all the work necessary for completing the story including installing
external walls 11 (Fig. 2(F)), setting partitions, constructing booths including a
service room, a bathroom and a lavatory, installing utensils and equipments, and hanging
the ceiling, and flooring the slabs is carried out. The floor slabs may be joined
to the beams 7 either after all the permanent columns 6 have been installed or after
some of the permanent columns 6 have been installed.
[0057] Then, as shown in Fig. 2(F), the rods 2 of all the extension columns 1 are extended
simultaneously to form another working space 14 for constructing the next upper story.
Then, the procedure illustrated by Figs. 2(A) to 2(F) is repeated to construct the
next upper structure.
[0058] Thus, the stories of the building are constructed sequentially from the lower stories
to the upper stories to complete the building.
[0059] When the framework 3 is a temporary framework, the construction apparatus is disassembled
and removed after completing the uppermost story to complete the construction work.
When the component members of the extension columns 1, the rods 2 and the framework
3 are the same strength, respectively, as the permanent columns 6 and the beams 7,
the work for disassembling and removing the construction apparatus is simplified because
most of the component members of the construction apparatus can be utilized for the
structure of the uppermost story.
[0060] When the framework 3 is a permanent framework, the component members of the construction
apparatus except the roof, the framework 3 and the extension columns 1 are removed
after constructing the structure of the uppermost story, and then the uppermost story
is finished to complete the construction of the building. If each of the extension
columns 1 is a combination of the sheath 13 and the rod 2 as shown in Fig. 3(B), the
sheath 13 and the rod 2 are designed so that the extension column 1 is equivalent
size and strength to the permanent column 6 when the rod 2 is fully retracted into
the sheath 13.
[0061] Fig. 4 shows a construction apparatus in a first embodiment according to the present
invention as applied to practical construction work, in which parts like or corresponding
to those previously described with reference to Fig. 2(A) to 2(F), 3(F) and 3(B) are
denoted by the same referecne characters.
[0062] Shown in Fig. 4 is the construction apparatus embodying the present invention as
applied to the construction of an annular building 10 requiring the least necessary
workers. An elevator shaft 30 installed an elevator 31 is constructed in the central
space of the building 10 so that the elevator 31 can transport construction materials
including permanent columns 6 and beams 7.
[0063] When a framework 3 is a temporary framework, the framework 3 is formed in a shape
substantially the same in the horizontal projection as the horizontal section of the
building 10. A control room 32 is constructed on the framework 3.
[0064] When the framework 3 is a permanent framework, the framework 3 and a roof 16 formed
on the framework 3 are incorporated into the building 10. In this case, the control
room 32 is constructed in a space under the roof 16.
[0065] Cylindrical buildings and semispherical buildings facilitate the accurate control
of construction robots by using a control system under a cylindrical coordinate system
or a polar coordinate system, which enables the building to be constructed at a reduced
construction cost.
[0066] An operator operates a controller 33 including a computer and installed in the control
room 32 to carry out all the steps of the construction work previously described with
reference to Figs. 2(A) to 2(F) automatically.
[0067] A truck 34 loaded with permanent columns 6 is lifted to a story under construction
by the elevator 31 from the ground, the permanent columns 6 are carried and installed
sequentially at predetermined positions below extension columns 1 by a column installing
robot 9 mounted on a traveling crane 5 (Fig. 2(B)), and then the permanent columns
6 are welded to the upper ends of the permanent columns 6 of the underlying story
at positions near the floor slabs 35 by a welding robot 4.
[0068] A truck 36 loaded with beams 7 is lifted to the story by the elevator 31 from the
ground, the beams 7 are installed fixedly between the opposite beam joints 8 of the
permanent columns 6 by a beam installing robot 12.
[0069] The floor of the elevator 31 is rotatable through an angle of 360° to direct the
trucks 34 and 36 in a desired direction so that the trucks 34 and 36 are able to move
to a desired position suitable for installing the permanent columns 6 and the beams
7.
[0070] After all the permanent columns 6 and all the beams 7 have been thus installed in
place, construction work necessary for the story including attaching external wall
panels 11 by means of quick fasteners 37, flooring the floor slabs 35 and hanging
the ceiling is carried out by construction robots mounted on the traveling cranes
5.
[0071] After the story has been completed, the rods 2 of the extension columns 1 are extended
simultaneously to form a working space for construction work to construct the next
upper story. Then the next upper story is constructed in the same manner as described
above.
[0072] When the framework 3 is a temporary framework, the construction apparatus and the
control room 32 are removed after the completion of construction of the uppermost
story, and then a roof is constructed.
[0073] When the component parts of the construction apparatus are the same strength as the
permanent columns 6 and the beams 7, those component parts may be incorporated into
the uppermost story of the building 10. The roof 38 constructed on the framework 3
may also he used a permanent roof to be incorporated into the building 10 if the strength
of the roof 38 is the same as those of the permanent one.
[0074] When the framework 3 is a permanent framework, the control room 32 and tie components
of the construction apparatus except the framework 3, the roof 16 and the extension
columns 1 are disassembled and removed after completing the uppermost story. If required,
the equipment of the control room 32 including the controller 33 are removed and the
control room 32 may be left as it is as the uppermost story of the building 10.
[0075] When the framework 3 is a temporary framework, the framework 3 is covered with the
temporary roof 38 and enclosed with a temporary enclosure 39 to arrest noise generated
by the construction work, to prevent the influence of environmental radiowaves and
electromagnetic waves on electrical communication between the controller 33 installed
in the control room 32 and the construction equipment including the construction robots
and to shield the control room 32 and the working space 14 from rain and wind.
[0076] When the framework 3 is a permanent framework, the framework 3 is covered and enclosed
with the roof 16 having an enclosure hanging from the periphery of the roof 16 for
the same purposes as those of the temporary roof 38 and the temporary enclosure 39.
[0077] Providing the roof 16 and the enclosure for the permanent framework 3, or the temporary
roof 38 and the temporary enclosure 39 for the temporary framework 3 with a soundproof
capability and a radiowave and electromagnetic wave intercepting capability enables
maintaining the working environment in a satisfactory condition and prevents the uncontrolled
operation of the computer of the controller 33 and the construction robots.
[0078] If the maximum length of the extension columns 1, namely, the length of the extension
columns 1 when the rods 2 are fully extended, may be such as corresponding to twice
the story height of the building 10 or greater, permanent columns having a length
corresponding to twice the story height of the building 10 or greater can be installed.
[0079] The foregoing construction apparatus embodying the present invention has the following
advantages.
[0080] The sequential progress of the construction from the lower to upper stories of a
building by extending and contracting the extension columns to secure a working space
for each story facilitates the automated control of the construction work and the
use of automatic construction equipment for automated construction work.
[0081] The possibility of using the components of the construction apparatus including the
permanent framework in combination with the permanent roof and the permanent extension
columns which are used for the construction work enhances the economic effect of the
construction apparatus and equipment investment efficiency.
[0082] Shielding the working space by the roof and the enclosure enables the regular progress
of the construction work regardless of weather conditions.
[0083] The automation of the construction work and the elimination of the influence of weather
conditions on the construction work enable uninterrupted day-and-night construction
work to shorten the construction period remarkably.
[0084] Whereas the plant employed in carrying out the previously proposed construction method
must support the enormous weight of a whole building structure throughout the construction
period and hence the previously proposed method is applicable only to the lower light
weight buildings, the construction apparatus of the present invention is applicable
to the higher heavy weight buildings and can be fabricated at a reduced cost because
the extension columns of the construction apparatus of the present invention support
only the temporary or permanent roof, the temporary or permanent framework, the temporary
enclosure and the control room including the control equipment.
[0085] The principle on which a construction apparatus in a second embodiment according
to the present invention is based will be described with reference to Figs. 5(A) to
5(G) prior to the description of the construction apparatus in a second embodiment.
[0086] The construction apparatus comprises, as the essential components, a framework construction
103 installed above a completed structure of a building 110 to form a working space
114 in which permanent columns 106 are installed and the construction work is carried
out over the completed structure of the building 110, guide posts 140 removably supported
on the completed structure of the building 110, elevating and locking mechanisms 150
provided on the framework construction 103 to lock the framework 103 to the guide
posts 140 so that the framework construction 103 can be fixed to the completed structure
of the building 110 and to elevate the framework construction 103 in forming the working
space 114 between the framework construction 103 and the completed structure of the
building 110, extension devices 101 provided on the framework construction 103 and
capable of extending downward to press the permanent columns 106 against the completed
structure of the building 110, and construction equipments for the construction work
in the working space 114. The construction equipments include a column welding robot
104, a column installing robot 109, a beam welding robot 112, and a wall installing
robot, not shown. The framework construction 103 may be provided with a cover 116
for covering the working space 114. Each of the guide posts 140 is provided longitudinally
with a rack 141. Each of the elevating and locking mechanisms 150 comprise a pinion
151 engaging the rack 141.
[0087] In a typical example of the construction apparatus shown in Figs. 5(A) to 5(G), four
extension devices 101 are hydraulic cylinders each having a rod 102 capable of moving
by a stroke slightly greater than the story height of the building 110. The hydraulic
cylinders may be substituted by the device shown in Fig. 3(A) or 3(B).
[0088] The shape of the framework 103 is substantially the same in the plan as that of the
top surface of the building 110. In this example, the framework 103 is rectangular
in the plan. The extension devices 101 are attached to the framework 103, respectively,
at the four corners of the same.
[0089] A traveling crane 105 is mounted on the opposite frame members 103a and 103b of the
framework 103, and one of the construction equipments, for example the column installing
robot 109, is held on the traveling crane 105.
[0090] The guide posts 140 are set upright, fastened temporarily at the lower ends thereof
to beams of the completed structure of the building 110, and slidably received through
guide rings 131 provided on pairs of frame members 103c and 103d, respectively. The
racks 141 are welded to the guide posts 140 in suitable pitches so as to extend longitudinally
along the guide posts 140, respectively.
[0091] The pinions 151 are provided on the frame members 103d so as to engage the racks
141. Each pinion is driven by a driving source such as a motor. The rack 141, the
pinion 151 and the driving source constitute the elevating and locking mechanism 150.
[0092] Each of the elevating and locking mechanisms 150 may be a screw rod mechanism, a
center hole jack mechanism or a hydraulic jack mechanism.
[0093] Thus, the framework 103 of the construction apparatus is held securely relative to
the completed structure of the building 110 by the engagement of the pinions 151 of
the elevating and locking mechanisms 150 with the racks 141 fixed to the guide posts
140 supported on the completed structure of the building 110. The firm connection
of the elevating and locking mechanisms 150 and the guide posts 140, namely, the engagement
of the racks 141 and the pinions 151, secures sufficient resistance to vibration,
for example earthquakes, for the construction apparatus.
[0094] The framework 103 is elevated by driving the pinions 151 of the elevating and locking
mechanisms 150 to form the working space 114 over the completed structure of the building
110, and the rods 102 of the extension columns 101 are fully retracted to form spaces
115 for receiving permanent columns 106 directly below the rods 102 as shown in Fig.
5(A). The permanent columns 106 are installed, respectively, in the spaces 115 by
the column installing robot 109 as shown in Fig. 5(B).
[0095] As shown in Fig. 5(C), the permanent column 106 is positioned correctly since the
rod 102 of one of the extension columns 101 is extended slightly to press the permanent
column 106 at the upper end 106a thereof against the upper end of a corresponding
member of the completed structure of the building 110, and then the lower end of the
permanent column 106 is welded to the upper end of the corresponding member of the
completed structure of the building 110 by the welding robot 104 held on the traveling
crane 105.
[0096] Although the stroke of the rods 102 of the extension columns 101 may be as small
as a value sufficient to press the permanent columns 106 against the completed structure
of the building 110, the stroke is set as large as the story height of the building
110 to enable the extension columns 101 to serve as temporary columns for supporting
the framework 103 on the completed structure of the building 110 in this embodiment.
[0097] Then, as shown in Fig. 5(D), the adjacent permanent column 106 is installed and fixed
in place in the same manner. Then, as shown in Fig. 5(E), beams 107 previously joined
to the adjacent permanent columns 106 so as to extend toward each other are welded
together by the welding robot 112 held on the traveling crane 105. It is also possible
to place a beam 107 having a length corresponding to the span between opposite beam
joints attached to the opposite sides of the adjacent permanent columns 106 and to
weld the beam 107 to the beam joints by the welding robot 112.
[0098] The foregoing construction procedure is repeated to complete the skeleton of an upper
story on the previously completed structure of the building 110 by fixedly installing
all the permanent columns 106 and joining together the beams 107 as shown in Fig.
5(F). Subsequently, the guide posts 140 are raised to positions shown in Fig. 5(G),
and then finishing work necessary for completing the story is carried out to complete
the upper story. The finishing work includes setting external walls 111 on the skeleton
(Fig. 6), installing partitions, constructing booths including a service room, a bathroom
and a lavatory, installing utensils and equipments, flooring the slabs and hanging
the ceiling.
[0099] After completing the story, the elevating and locking mechanisms 150 are driven to
elevate the framework 103 as shown in Fig. 5(A) to form a working space 114 for constructing
the next upper story. The next upper story, similarly to the underlying story, is
constructed by carrying out the steps of the construction procedure as illustrated
in Figs. 5(A) to 5(G). The construction procedure is repeated a number of times corresponding
to the number of stories of the building 110 to construct upper stories on the lower
stories one by one. After the uppermost story of the building 110 has thus been completed,
the construction apparatus including the framework 103 and the extension columns 101
is disassembled and removed, and then finishing work necessary for completing the
uppermost story is carried out to complete the building 110.
[0100] When the extension columns 101 and the framework 103 are formed of members equivalent
strength to or superior one to those forming the permanent columns 106 and the beams
107, the extension columns 101 and the framework 103 may be used as the components
of the uppermost story, which simplifies the work for disassembling and removing the
construction apparatus.
[0101] Fig. 6 is a perspective view showing the construction apparatus in the second embodiment
as applied to practical construction, in which parts like or corresponding to those
previously described with reference to Figs. 3(A), 3(B) and 5(A) to 5(G) are denoted
by the same reference characters, and Fig. 7 is a schematic sectional view of assistance
in explaining the function of the construction apparatus shown in Fig. 6.
[0102] Shown in Fig. 6 is a building 110 having the shape of a polygonal cylinder. Elevators
are installed in elevator shafts formed in the internal space of the building 110
to transport construction materials including permanent columns 106 and beams 107.
[0103] A framework 103 is constructed in a shape substantially the same in the plan as the
building 110 and covered with a cover 116. A control room 132 is formed in a space
covered with the cover 116.
[0104] An operator operates a controller 133 including a computer and installed in the control
room 132 for the automatic control of the construction work illustrated in Figs. 5(A)
to 5(G).
[0105] The permanent columns 106 provided with the beams 107 are transported from the ground
to a story under construction by the elevator, not shown, installed sequentially at
positions directly below the fully retracted rods 102 of the extension columns 101
by a column installing robot 109 and welded sequentially to the upper end of the permanent
columns 106 of the underlying story by a column welding robot 104. The beams 107 of
the adjacent permanent columns 106 are welded together by a beam welding robot 112.
[0106] After all the permanent columns 106 have been thus installed in place and all the
corresponding beams 107 have been welded together, construction work necessary for
completing the story including setting external walls 111 is carried out by using
construction robots held on the traveling crane 105. After the story has been completed,
elevating and locking mechanisms 150 are driven to elevate the framework 103 to form
a working space for constructing the next upper story. Then the same construction
work is repeated to construct the next upper story. After all the stories of the building
110 have been completed, the construction apparatus and the control room 132 are removed,
and then a roof is constructed on the uppermost story of the building 110.
[0107] The framework 103 applied to the practical construction is provided with the cover
116 consisting of a temporary roof 138 and a temporary enclosure 139 to arrest noise
generated by the construction work, to prevent the influence of environmental radiowaves
and electromagnetic waves on electrical communication between the controller 133 installed
in the control room 132 and the construction equipment including the construction
robots and to shield the control room 132 and the construction space from rain and
wind.
[0108] Providing the cover 116 with a soundproof capability and a radiowave and electromagnetic
wave intercepting capability enables maintaining the working environment in a satisfactory
condition and prevents the uncontrolled operation of the controller 133 and the construction
robots.
[0109] As mentioned above, the extension columns 101, the rods 102 and the framework 103
can be used as the components of the building 110 if the extension columns 101, the
rods 102 and the framework 103 are formed of members equivalent to or superior to
the permanent columns 106 and the beams 107. The temporary roof 138 may be formed
in the same construction as that of the roof of the building 110 to use the same also
as the roof of lhe building 110.
[0110] The guide posts 140 may be removed after completing the uppermost story of the building
110 or may be used as the permanent column of the story after removing the racks 141.
If the guide posts 140 are intended for use as the permanent columns at positions
for the coaxial permanent columns 106, the guide posts 140 may be such as having a
length corresponding to the height of the building 110 and installed, respectively,
or may be sectional guide posts extended section by section with the progress of the
construction work. In latter case, the guide posts may be extended by lifting a sectional
guide post by a crane or the line, inserting the sectional guide post through an opening
160 formed in the temporary roof 138 onto the upper end of the guide post previously
constructed and joining the sectional guide post to the upper end of the guide post.
It is also possible to extend the guide posts by previously setting the temporary
roof 138 at a height sufficient to provide a space for extending the new sectional
guide post, and adding the sectional guide post to the previous existing portion of
the guide post within the working space 114.
[0111] When the guide posts 140 are temporary sectional posts, each of the guide posts 140
may be extended upward by supporting the guide post 140 at a position above the lower
end thereof on a base 142 placed on an auxiliary beam 107a for shifting the guide
post 140, removing a portion of the guide post 140 below the position where the guide
post 140 is supported on the base 142, and joining the removed portion of the guide
post 140 to the upper end of the guide post 140 as indicated by an arrow a in Fig.
7. It is also possible to extend each of the guide post 140 upward by extending the
rods 102 of the extension columns 101 so that the lower ends of the rods 102 are brought
into firm contact with the upper ends of the previously installed permanent columns
106 to transfer the weight supported by the guide posts 140 to the permanent columns
106, driving the elevating and locking mechanisms 150 to shift the guide posts 140
upward relative to the framework 103, and seating the guide posts 140 on bases 142
placed on the beam 107 of the upper story as indicated by an arrow b in Fig. 7.
[0112] The guide posts 140 of the construction apparatus in the second embodiment support
only the framework 103, the cover 116 and the construction equipments mounted on the
framework 103, which are far less in weight than those supported by the plant constructed
on the ground in accordance with the construction method proposed in J. P. Pat. Provisional
Pub. (Kokai) No. 62-244941. Accordingly, the construction apparatus of the present
invention is applicable to the construction of buildings unlimited in height and has
a sufficiently high earthquake resistance.
[0113] The construction apparatus in the second embodiment has the following advantages.
[0114] The framework of the construction apparatus is held securely on a completed structure
of a building during the construction work for constructing the next upper structure
on the completed structure and hence the framework is sufficiently resistant to earthquakes
throughout the construction period because the framework is locked securely to the
guide posts firmly supported on the completed structure by the elevating and locking
mechanisms during the construction work for constructing the next upper structure
on the completed structure.
[0115] The sequential upward shift of the working space formed under the framework by the
cooperative operation of the elevating and locking mechanisms and the guide posts
facilitates the automated control of the construction work and enables the advantageous
application of automatic construction equipments to the construction work.
[0116] The working space covered with the cover enables the construction work to be carried
out regardless of weather conditions.
[0117] The construction apparatus saves labor, and enables the uninterrupted day-and-night
execution of the construction work, so that the construction period is shortened remarkably
and the efficiency of the construction equipments is improved.
[0118] Principle on which a construction apparatus in a third embodiment according to the
present invention is based will be described with reference to Figs. 8(A) to 8(F).
[0119] Basically, a construction apparatus of the third embodiment of the present invention
comprises a framework 203 placed on a completed structure of a building 210 under
construction to form a working space 214 for construction work including installing
permanent columns 206, elevating mechanisms 207 provided on the framework 203 and
capable of extending downward from the framework 203 to elevate the same and to serve
as temporary columns for forming the working space 214 over the completed structure
of the building 210, locking mechanism provided on the lower ends of the elevating
mechanism 207 and removably fitting the completed structure of the building 210, and
construction machines provided on the framework 203 for construction work in the working
space 214. A holding mechanisms 201 are provided on the framework 203 and capable
of extending downward from the framework 203 to position and hold permanent columns
206 installed in the working space at the upper ends thereof. Construction machines
include a traveling crane 205, construction robots, such as a column installing robot
209, a beam installing robot 291, external wall setting robot 292 and a welding robot
204.
[0120] The locking mechanisms are fitted with the upper ends of the permanent columns 206
prior installed the underlying completed structure of the building 210. Practically,
the permanent column 206 has a conical recess 206y at the upper end thereof and the
holding mechanism 201 has a conical projection 202x at the lower end thereof opposite
to the upper end of the permanent column 206 for positioning each other. And the permanent
column 206 has a conical recess 206y at the upper end thereof. The permanent column
206 has a conical projection 206x at the lower end thereof fitting the conical recess
206y of the other permanent column 206 prior installed the underlying completed structure
of the building 210. And the locking mechanism have a conical projection 208x at the
lower end thereof opposite to the upper end of the permanent column 206 to engaging
the conical recess 206y of the permanent column 206 for positioning each other. It
is also possible to change the conical projections 202x, 206x and 208x for conical
recesses and the conical recesses 206y for conical projections or to change the conical
recesses 206y for simple holes.
[0121] In an example shown in Figs. 8(A) to 8(F), the two holding mechanism 201 are provided
diagonally opposite to each other on the framework 203, and the two elevating mechanisms
207 are provided diagonally opposite to each other on the framework 203. However,
a practical construction apparatus is provided with more than two holding mechanisms
201 and more than two elevating mechanisms 207.
[0122] The holding mechanism 201 is a hydraulic actuator having a rod 202 slidably received
in a cylinder for projection and retraction. Each holding mechanism 201 may be constructed,
instead of the hydraulic actuator, such as shown in Fig. 3(A) or Fig. 3(B).
[0123] The elevating mechanism 207 comprises a hollow shaft, a post 208 having a length
slightly longer than twice the story height of the building 210 and received slidably
in the hollow shaft, and a hydraulic device, not shown, for moving the post 208.
[0124] The post 208 of each elevating mechanism 207 is provided on the lower end thereof
with a conical projection 208x. Each permanent column 206 is provided in the upper
end thereof with a conical recess 206y fitting the conical projection 208x, and a
conical projection 206x similar to the conical projection 208x of the post 208 on
the lower end thereof. A conical projection 202x similar to the conical projection
206x is formed on the lower end of the rod 202 of the holding mechanism 201. The conical
projections 208x of the posts 208, the conical projections 206x of the permanent columns
206 and the conical projections 202x of the rods 202 are capable of engaging the conical
recesses 206y of the permanent columns 206.
[0125] The holding mechanisms 201 and the elevating mechanisms 207 are attached to the framework
203 having a shape in plan substantially the same as the shape of the upper surface
of a completed structure of the building 210 (a rectangular shape, in the example
shown in Figs. 8(A) to 8(F)) respectively at the four vertical edges thereof. In a
practical construction apparatus embodying the present invention, the holding mechanisms
201 and the elevating mechanisms 207 are attached at appropriate intervals to the
periphery of a framework similar to the framework 203.
[0126] A traveling crane 205 is mounted on the opposite beams 203a and 203b of the framework
203, and a column installing robot 209 is held removably on the traveling crane 205.
[0127] In placing the framework 203 on the completed structure of the building 210, the
conical projections 208x of the posts 208 of the elevating mechanisms 207 are fitted
in the conical recesses 206y of the permanent columns 206 of the underlying completed
structure of the building 210 to position the framework 203 correctly relative to
the underlying completed structure of the building 210. The engagement of the conical
projections 208x and the conical recesses 206y restrains the posts 208 from lateral
movement to support the framework 203 stably so that the earthquake resistance of
the framework 203 is improved. In the example shown in Figs. 8(A) to 8(F), the two
elevating mechanisms 207 are disposed diagonally opposite to each other, and hence
the support of the framework 203 seems unstable. However, in a practical construction
apparatus embodying the present invention, far more than two elevating mechanisms
are arranged at appropriate intervals to support the framework 203 stably.
[0128] The hydraulic devices of the elevating mechanisms 207 are driven to project the posts
208 downward, and thereby the framework 203 is elevated to form the working space
214 over the completed structure of the building 210 as shown in Fig. 8(A). In this
state, spaces 215 for receiving the permanent columns 206 are formed directly below
the retracted rods 202 of the holding mechanisms 201.
[0129] Then, as shown in Fig. 8(B), the column installing robot 209 installs a permanent
column 206 in the space 215 directly below the rod 202 of the holding mechanism 201
so that the conical projection 206x formed on the lower end of the permanent column
206 is received in the conical recess 206y formed in the upper end of the permanent
column 206 of the underlying completed structure of the building 210. Even if the
conical projection 206x is deviated slightly from the conical recess 206y in installing
the permanent column 206, the conical projection 206x and the conical recess 206y
can be closely engaged by applying a small pressure to the permanent column 206. Therefore,
the column installing robot 209 need not be controlled highly accurately, which facilitates
the installation of the permanent column 206.
[0130] Then, as shown in Fig. 8(C), the rod 202 of the holding mechanism 201 is projected
slightly so that the conical projection 202x of the rod 202 engage the conical recess
206y formed in the upper end of the permanent column 206 to position and hold the
permanent column 206 in place, and then the permanent column 206 is welded to the
completed structure of the building 210 by the welding robot 204 removably held on
the traveling crane 205. Even if permanent column 206 is misaligned slightly relative
to the rod 202, the permanent column 206 is brought into alignment with the rod 202
by the engagement of the conical projection 202x of the rod 202 and the conical recess
206y of the permanent column 206 when the permanent column 206 is pressed by the rod
202, which facilitates the correct positioning of the permanent column 206. Since
the upper end and the lower end of the permanent column 206 is engaged with the rod
202 and the underlying permanent column, the permanent column 206 is held securely,
the support of the framework 203 is reinforced and hence the earthquake resistance
of the framework 203 during the construction is improved. Subsequently, the other
permanent column 206 is installed and fixed to the underlying permanent column 206
in the same manner.
[0131] Then, as shown in Fig. 8(D), the post 208 of the elevating mechanism 207 is retracted
by driving the hydraulic device of the elevating mechanism 207 to form a space 215
for installing a permanent column 206 directly below the post 208, and then the permanent
column 206 is installed and fixed to the underlying permanent column 206 of the completed
structure of the building 210 in the same manner as that for installing and fixing
the permanent column 206 in the space 215 directly below the rod 202 of the holding
mechanism 201. Then, a permanent column 206 is installed and fixed to the underlying
permanent column 206 at a position diagonally opposite the previously fixed permanent
column 206 as shown in Fig. 8(E).
[0132] In thus setting up the permanent columns 206, beams 260 joined beforehand to the
adjacent permanent columns 206 are welded together at appropriate time by the welding
robot 204 held on the traveling crane 205 as shown in Fig. 8(F). It is also possible
to prepare the beams 260 and the permanent columns 206 separately and to weld each
beam 260 at the opposite ends thereof to beam joints, not shown, attached to the opposite
sides of the adjacent permanent columns 206.
[0133] The foregoing steps of operation of the holding mechanisms 201 and the elevating
mechanisms 207 are repeated for all the permanent columns 206 and the beams 260. After
all the permanent columns 206 and all the beams 260 have thus been set as shown in
Fig. 8(F), all the work necessary for completing the story including installing external
walls 211 (Fig. 9), setting partitions, constructing booths including a service room,
a bathroom and a lavatory, hanging the ceiling, and flooring the slabs.
[0134] Subsequently, the elevating mechanisms 207 are driven again to elevate the framework
203 as shown in Fig. 8(A) to start the construction of the next upper story, in which
the steps shown in Figs. 8(A) to 8(F) are repeated. After all the structures of the
building 210 have been completed from the lower stories to the upper stories, the
construction apparatus including the framework 203 and the holding mechanisms 201
is disassembled and removed, and then the uppermost story is finished to complete
the building 210. When composed of members having strength equivalent to or higher
than the permanent columns 206 and the beams 260, the holding mechanisms 201, the
framework 203 and the elevating mechanisms 207 can be used as the components of the
structure of the uppermost story, which simplifies or enables the omission of disassembling
and removing the construction apparatus.
[0135] Fig. 9 is a schematic perspective view illustrating a construction apparatus of the
third embodiment as applied to a practical construction work, in which parts like
or corresponding to those previously described with reference to Figs. 8(A) to 8(F).
3(A) and 3(B) are denoted by the same reference characters. Fig. 10 is a schematic
plan view of an essential portion of the construction apparatus shown in Fig. 9, Fig.
11 is a sectional view taken on line XI-XI in Fig. 10, Fig. 12 is a sectional view
taken on line XII-XII in Fig. 10, Figure 13 is a sectional view taken on line XIII-XIII
in Fig. 10, and Fig. 14 is a plan view as viewed in the direction of an arrow XIV
in Fig. 10.
[0136] A building 210 shown in Fig. 9 is substantially rectangular in plan.
[0137] An elevator shaft is constructed in the central space of the building 210, and an
elevator is installed in the elevator shaft to transport construction materials including
permanent columns 206 and beams 207.
[0138] The construction apparatus is substantially the same in plan as the building 210.
A framework 203 included in the construction apparatus is provided with a cover 216.
A control room 232 is formed in a space covered with the cover 216.
[0139] The construction apparatus is controlled by a computerized controller 233 installed
in the control room 232 and operated by an operator for automatic execution of the
construction steps shown in Figs. 8(A) to 8(F).
[0140] A plurality of elevating mechanisms 207 are arranged in pairs. Each pair of elevating
mechanisms 207 are disposed adjacently. While one of the elevating mechanisms 207
of each pair is contracted the other is extended. Accordingly, the framework 203 is
supported alternately by one of the elevating mechanisms 207 of each pair and the
other of the same. A hydraulic mechanism 270 for operating the elevating mechanism
207 is disposed on top of the framework 203 to project a post 208 downward from the
framework 203 and to retract the post 208 upward.
[0141] Furthermore, since the post 208 of the elevating machanism 207 is held at all time
by the hydraulic mechanism 270 driving the post 208, the framework 203 is firmly engaged
with the post 208 even if the horizontal force such as the earthquake or the wind
force acts the framework 203, therefore the vibration resistance of this construction
appratus is improved still more.
[0142] Each of permanent columns 206 transported from the ground to a story under construction
by an elevator is transported to and installed at a position specified by the computerized
controller 232 by a column installing robot 209 held on a traveling crane 205, and
then the permanent column 206 is welded to the upper end of a permanent column 206
of the underlying completed structure of the building 210 by a welding robot 204.
Then, beams 260 previously attached to the adjacent permanent columns 206 are welded
together by the welding robot 204.
[0143] Especially, the permanent column 206 is formed higher than one story height, and
attached integrally the beams 260 extending both sides thereof at the upper end and
the lower end of the permanent column 206, respectively. Then in a practical work,
the beam 260 of the upper end of the permanent column 206 is welded the beam 260 of
the lower end of the permanent column 206 which is adjecent to the former, as the
result the construction work of the permanent columns 206 and the beams 260 in the
one story is finished by setting the half number of columns 206 and beams 260, in
considering the column and the beam installation of each story. Therefore, the efficiency
of the construction work is improved in comparing the case which all the columns 206
and the beams 260 is setting in each story.
[0144] After fixedly installing all the permanent columns 206 and all the beams 260, construction
work necessary for completing the story including installing external wall panels
211 is carried out by construction robots held on the traveling cranes 205. Then,
the elevating mechanisms 207 are driven to elevate the framework 203 to construct
a structure for the next upper story. The structure of the next upper story is constructed
by repeating the same steps of construction work. After the structures of all the
stories of the building 210 have been constructed, the construction apparatus and
the control room are removed, and then the roof of the building 210 is constructed.
[0145] The cover 216 provided on the framework 203 consists of a temporary roof 238 and
a temporary enclosure 239. The cover 216 arrest noise generated by the construction
work, prevents the influence of disturbance, such as environmental radiowaves, on
electrical signals given from the computerized controller 233 installed in the control
room 232 to the construction machines including the construction robots, and to shield
the control room 232 and the story under construction from rain and wind.
[0146] As mentioned above, when composed of members having strength equivalent to or greater
than that of the permanent columns 206 and the beams 260, the holding mechanisms 201,
the framework 203 and the elevating mechanisms 207 may be incorporated into the building
210. The temporary roof 238 may be formed of the same materials and in the same construction
as those of the permanent roof of the building 210 to incorporate the temporary roof
238 to the building 210 as the permanent roof.
[0147] Whereas the previously proposed plant installed on the ground floor must support
the increasing enormous weight of a building throughout the construction period, the
posts 208 of the elevating mechanisms 207 of the construction apparatus according
to the present invention support only the framework 203, the cover 216 and the construction
equipments provided on the framework 203. Accordingly, the construction apparatus
has a sufficient earthquake resistance and is applicable to the construction of buildings
unlimited in height.
[0148] The above construction apparatus according to the third embodiment has the following
advantages.
[0149] The engagement of the conical projections of the locking mechanisms provided on the
lower ends of the elevating mechanisms and the conical recesses formed in the upper
ends of the permanent columns positions the framework accurately relative to the completed
structure of the building, prevents the lateral movement of the framework relative
to the completed structure of the building, supports the framework stably and improves
the earthquake resistance of the construction apparatus during the construction.
[0150] The upward progress of the construction work by repeatedly elevating the framework
by the elevating mechanisms to form working spaces sequentially for upper stories
facilitates the automatic control of the construction work and the employment of automated
construction equipments and saves labor.
[0151] The engagement of the conical projections formed on the lower ends of the permanent
columns and the conical recesses formed in the upper ends of the permanent columns
easily brings the permanent columns into alignment with the underlying permanent columns
of the completed structure for the correct connection of the permanent columns even
if the former permanent columns are misaligned slightly with the latter permanent
columns in installing the former permanent columns.
[0152] Since the conical projections formed on the lower ends of the holding means engage
the conical recesses formed in the upper ends of the permanent columns, the permanent
columus are positioned easily and held stably, the support of the framework is reinforced
and hence the earthquake resistance of the framework during the construction is improved.
1. A construction apparatus comprising: a framework constructed above a completed
structure of a building so as to form a working space over the completed structure
and extension columns provided on the framework, capable of extending downward to
support the framework above the completed structure so that the working space may
be formed between the framework and the completed structure.
2. A construction apparatus according to Claim 1, wherein said extension columns are
capable of being contracted to provide space for installing permanent columns on the
completed structure.
3. A construction apparatus according to Claim 1, wherein said framework is provided
with a roof for covering the working space.
4. A construction apparatus according to Claim 1, wherein said framework is a temporary
framework.
5. A construction apparatus according to Claim 4, wherein said framework is provided
with a temporary cover for covering the working space.
6. A construction apparatus according to Claim 1, wherein said extension columns are
hydraulic cylinders.
7. A construction apparatus according to Claim 1, wherein said framework is mounted
with a traveling crane for detachably holding a construction robot.
8. A construction apparatus according to Claim 7, wherein said traveling crane and
said construction robot are controlled on a cylindrical coordinate system.
9. A construction apparatus according to Claim 7, wherein said traveling crane and
said construction robot are controlled on a polar coordinate system.
10. A construction apparatus according to Claim 1, wherein said completed structure
of the building is installed an elevator for transporting construction materials in
the internal space thereof and the elevator has a rotary floor to discharge the construction
materials in an optional direction.
11. A construction apparatus according to Claim 1, wherein a control room is formed
in the upper part of said framework.
12. A construction apparatus comprising:
a framework construction installed above a completed structure of a building so as
to form a working space for construction work including installing permanent columns
over the completed structure;
guide posts detachably held upright on the completed structure of the building;
elevating and locking mechanisms provided on the framework construction to elevate
the framework construction along the guide posts to form the working space over the
completed structure of the building and to lock the framework to the guide posts so
that the framework construction can be fixed to the completed structure of the building;
and
construction means provided on the framework to execute the construction work in the
working space.
13. A construction apparatus according to Claim 12, wherein said framework construction
is provided with a cover for covering the working space.
14. A construction apparatus according to Claim 12, wherein said guide posts are provided,
respectively, with racks, and said elevating and locking mechanisms are provided,
respectively, with pinions engaging the racks.
15. A construction apparatus according to Claim 12, wherein a mechanism comprising
said guide post and said elevating and locking mechanism is of a center hole jack
type.
16. A construction apparatus according to Claim 12, wherein said construction means
includes a column installing robot, a column welding robot, a beam welding robot and
an external wall setting robot.
17. A construction apparatus according to Claim 12, wherein said guide posts are permanent
columns.
18. A construction apparatus according to Claim 12, wherein said guide posts are temporary
columns.
19. A construction apparatus according to Claim 12, wherein a traveling crane is mounted
on said framework construction, and said construction means is held detachably on
the traveling crane.
20. A construction apparatus according to Claim 19, wherein said traveling crane and
said construction means are controlled on a cylindrical coordinate system.
21. A construction apparatus according to Claim 19, wherein said traveling crane and
said construction means are controlled on a polar coordinate system.
22. A construction apparatus according to Claim 12, wherein said completed structure
of the building is installed an elevator for transporting construction materials in
the internal space thereof and the elevator has a rotary floor to discharge the construction
materials in an optional direction.
23. A construction apparatus according to Claim 12, wherein a control room is formed
in the upper part of said framework construction.
24. A construction apparatus comprising:
a framework placed on a completed structure of a building under construction to form
a working space for construction work including installing permanent columns;
elevating means provided on the framework and capable of extending downward from the
framework to elevate the same and to serve as temporary columns for forming the working
space over the completed structure of the building;
locking mechanism provided on the lower ends of the elevating means and removably
fitting the completed structure of the building; and
construction means provided on the framework for construction work in the working
space.
25. A construction apparatus according to Claim 24, wherein said locking mechanism
is fitted with the upper ends of the permanent columns prior installed the underlying
completed structure of the building.
26. A construction apparatus according to Claim 24, wherein holding means is provided
on said framework and capable of extending downward from the framework to position
and hold the permanent columns installed upright in the working space at the upper
ends thereof.
27. A construction apparatus according to Claim 26, wherein said permancnt column
has an engaging portion at the upper end thereof and said holding means have a fitting
portion at the lower end thereof opposite to the upper end of the permanent column
for positioning each other.
28. A construction apparatus according to Claim 24, wherein said permanent column
has an engaging portion at the upper end thereof.
29. A construction apparatus according to Claim 28, wherein said permanent column
has a fitting end portion at the lower end thereof fitting the engaging portion of
the other permanent column prior installed the underlying completed structure of the
building.
30. A construction apparatus according to Claim 28, wherein said locking mechanism
has a fitting portion at the lower end thereof opposite to the upper end of the permanent
column to engaging the engaging portion of the permanent column for positioning each
other.
31. A construction method of constructing a multistory building in ascending order
of stories by sequentially repeating steps of:
simultaneously extending extension columns provided on a framework placed on a completed
structure of the building to form a working space over the completed structure;
sequentially contracting the extension columns one at a time to sequentially form
spaces respectively for receiving permancnt columns therein between the framework
and the completed structure and installing permanent columns in the spaces formed
sequentially;
installing beams between the adjacent permanent columns;
executing construction work in a structure formed by the permanent columns and the
beams to complete the structure; and
sequentially repeating the steps in that order to construct the next upper structure.
32. A construction method of constructing a multistory building in ascending order
of stories by sequentially repeating steps of:
elevating a framework construction placed on a completed structure of the building
to form a working space over the completed structure;
locking the framework construction to the completed structure at an elevated position;
sequentially placing and fixing permanent columns on the completed structure in the
working space;
installing beams between the permanent columns;
executing construction work in a structure formed by the permanent columns and the
beams to complete the structure;
unlocking the framework construction from the completed structure after finishing
construction work;
and
sequentially repeating the steps in that order to construct the next upper structure.