| (19) |
 |
|
(11) |
EP 0 404 991 A1 |
| (12) |
EUROPEAN PATENT APPLICATION |
| (43) |
Date of publication: |
|
02.01.1991 Bulletin 1991/01 |
| (22) |
Date of filing: 29.06.1989 |
|
| (51) |
International Patent Classification (IPC)5: E01B 1/00 |
|
| (84) |
Designated Contracting States: |
|
AT BE CH DE ES FR IT LI NL SE |
| (71) |
Applicant: British Steel plc |
|
London SE1 7SN (GB) |
|
| (72) |
Inventor: |
|
- Hodgson, William H
Keswick
Cumbria (GB)
|
| (74) |
Representative: Broughton, Clifford David (GB) |
|
British Steel Corporation
Head Office
9 Albert Embankment GB-London SE1 7SN GB-London SE1 7SN (GB) |
|
| |
|
| (54) |
Laying rail sleepers |
(57) In a method of laying channel-section rail sleepers one or more tubular ballast-filled
bags (1) are disposed so as to nest within the channelled section and are sandwiched
between the sleeper and an elongated tray (2). The whole assembly is dragged beneath
the track on the tray to replace a sleeper previously withdrawn, the tray then being
withdrawn from under the ballast-filled sleeper whereby to minimise any infill ballasting
and subsequent tamping.
|

|
[0001] This invention relates to the laying of sleepers e.g. laying steel sleepers as replacements
for those in wood or concrete. Hitherto, such references have involved the need for
special tamping arrangements for ensuring that the additional ballast adequately 'fills'
around and within the (channel-section) steel sleeper. It is an object of this invention
to mitigate this need.
[0002] From one aspect this invention comprises a method of laying channel-section rail
sleepers, in which one or more tubular ballast-filled bags are disposed so as to nest
within the channelled section and are sandwiched between the sleeper and an elongated
tray, and in which the whole assembly is dragged beneath the track on said tray to
replace a sleeper previously withdrawn, the tray then being withdrawn from under the
ballast-filled sleeper whereby to minimise any infill ballasting and subsequent tamping.
[0003] Preferably, two ballast-filled bags are used to minimise the risk of level irregularities
and the bags are preferably laid on the tray with the sleeper, e.g. a steel sleeper,
laid on top of it. The bag filling may be effected on site, and this may be achieved
by drawing the bag, sealed at one end, over a firm tube, introducing ballast into
the tube whilst upstanding on the tray and then withdrawing the tube from the bag
and sealing the head of the bag. Two adjacent bags may be filled in this way in the
manner of 'sausages' i.e. they may be interconnected by a tie instead of being separate
entities.
[0004] In order that the invention may be fully understood one embodiment thereof will now
be described, by way of example, with reference to the accompanying drawings, in which:-
Figure 1 is a perspective view of the tray on which two ballast-filled bags have been
sited; and
Figure 2 shows the channel-section sleeper laid over the bags ready for insertion
in the track.
[0005] Referring to the drawings two ballast-filled bags 1 are laid on a steel tray or sledge
2 having upstanding edges on its sides and at one end from which a hook 3 extends.
The bags may be of plastic netting and may conveniently have been filled on site by
the method described above using a withdrawable tube.
[0006] A channel section steel sleeper 4 is then laid over the bags (Figure 2) such that
they nest in the channel.
[0007] This assembly is now ready for use in replacing old sleepers. In particular, the
old wooden sleeper (say) is unbolted from the rails and pulled out sideways. The new
assembly is then dragged through the opening thus created, the new steel sleeper is
bolted to the rail and the sledge is then pulled out from beneath, leaving the bagged
ballast in situ. With the bags having been filled with sufficient ballast to fill
the steel sleeper and make up any difference in height between the wood and the steel
sleepers, the track only requires 'boxing-in' with loose fill ballast. Any future
tamping will be regular and not special for steel sleepers.
1. A method of laying channel-section rail sleepers, characterised in that one or
more tubular ballast-filled bags (1) are disposed so as to nest within the channelled
section and are sandwiched between the sleeper (4) and an elongated tray (2) and in
which the whole assembly is dragged beneath the track on said tray to replace a sleeper
previously withdrawn, the tray then being withdrawn from under the ballast-filled
sleeper whereby to minimise any infill ballasting and subsequent tamping.
2. A method according to Claim 1, characterised in that two ballast-filled bags are
equidistantly spaced along the length of the sleeper.
3. A method according to Claim 1 or Claim 2, characterised in that the bag or bags
are laid on the tray, the sleeper then being laid on top.
4. A method according to Claim 1 or Claim 2 characterised in that the bag or bags
are laid in the channel or trough of the sleeper, the tray is then laid on top and
the assembly inverted before introduction under the track.
5. A method according to any one of Claims 1 to 4, characterised in that each bag
is filled by drawing said bag over a firm tube, introducing the ballast into the tube
and withdrawing the tube from the bag and sealing same.
6. A method according to any one of Claims 1 to 5, characterised in that each bag
is made from plastics netting.
7. A method according to any one of Claims 1 to 6, characterised in that the tray
has upstanding edges on its sides and at one end.
