[0001] The invention relates to a method for the production of a steel plate concrete floor,
comprising the pouring of concrete mortar onto a steel plate which, for the purpose
of increasing the adhesion between concrete and steel, is provided beforehand with
anchoring elements projecting from the plane of the steel plate.
[0002] Prefabricated steel plate floor elements produced by this method are known. The steel
plate is U-shaped in cross-section, with a flat bottom. Owing to the self-weight of
the prefab element and the effective load expected, the bottom side of the floor elements
will be subjected to a tensile load. Although the tensile load is absorbed up to a
certain value by the steel plate, the maximum permissible span of the floor elements
will be limited on account of the fact that concrete can absorb only a very low tensile
load. The maximum permissible span of the prefab elements produced with steel plate
can be increased by using a thicker steel plate.
[0003] The object of the invention is to provide a method such as that indicated in the
preamble which leads to steel plate concrete floors which can span a considerable
length without the concrete being subjected to too great a tensile load under the
influence of the weight of the floors themselves and the effective load, and without
the deformations standing in the way a practical use.
[0004] For this purpose, according to the invention one or more elements of elastic material
such as steel which will bond to the concrete are subjected to a tensile load in the
lengthwise direction of the steel plate. In order further to improve the bending resistance
in the lengthwise direction, it is highly preferable for the steel plate to have a
wavy or crenellated profile at right angles to the lengthwise direction.
[0005] Before the concrete mortar is poured, pipes for recessing channels in the concrete
are placed over the steel plate in the lengthwise direction thereof, tensioning elements
are guided through the channels before or after pouring of the concrete mortar, and
said tensioning elements are placed under a tensile load after setting of the concrete,
the ends of the tensioning elements being anchored in the set concrete. Said tensioning
elements can be, for example, bars, wires or bunches of wires which can be made of
steel or glass such as fibres which may or may not be embedded in epoxy resin, plastic
such as aromatic polyamide filaments which may or may not be embedded in epoxy resin,
or carbon fibres which may or may not be embedded in epoxy resin.
[0006] Parallel rectilinear tensioning elements which are pre-tensioned can be fitted at
different levels in the thickness of the concrete. The same or better results can,
however, be achieved with fewer tensioning elements if the tensioning elements extend
in a wavy form through the concrete, the wave valleys being situated approximately
halfway between the places where the floor is to be supported permanently in a building.
[0007] The steel plate can also be subjected to a tensile load in the lengthwise direction
before the concrete mortar is poured by, for example, applying tensile forces to the
ends. After setting of the concrete, the forces are removed from the ends.
[0008] The method according to the invention could be applied to the production of prefab
floor elements, but it is pre-eminently suitable for application to construction itself
for the production of extended floors, for example with a total length of 40 metres
and spans of, for example, 10 metres. For this, the steel plate is supported at at
least two opposite-lying edges by supporting elements of a building and between them
by a number of temporary additional bearing elements such as screw jacks, the concrete
mortar is poured onto the steel plate serving as the formwork element, and the above-mentioned
additional bearing elements are removed after setting and pre-stressing of the concrete.
[0009] The anchoring elements are preferably made of studs rolled into the steel plate.
These studs prevent the steel plate and the concrete from shifting relative to each
other. The inside of the studs can be used at the bottom side of the floors for suspending
ceilings, lines of cables and pipes and the like.
[0010] The invention will now be explained with reference to the figures.
Figure 1 shows a perspective view of a floor produced according to the invention,
in which the concrete is shown partially cut away.
Figure 2 shows a longitudinal section through a building under construction with a
floor according to the invention.
[0011] The floor shown in Figure 1 has a steel plate 1 with a crenellated profile extending
at right angles to the lengthwise direction thereof, on which a layer of concrete
2 is poured. In order to improve the adhesion of the concrete to the steel plate,
the latter is provided with projecting anchoring elements in the form of studs 3 rolled
into the steel plate.
[0012] Before the concrete mortar is poured, form- retaining pipes 4 or the like are fitted
over the steel plate in the lengthwise direction of the profile, through which tensioning
elements 5 are guided before or after pouring of the concrete mortar. After setting
of the concrete the tensioning elements 5 are pre-tensioned, and the ends of the tensioning
elements are anchored in the concrete by means of anchoring elements 6. Resin or mortar
is injected into the pipes 4 for the purpose of anchoring and/or protection.
[0013] Another possibility of pre-tensioning is the use of virtually rectilinear tensioning
elements running in the lengthwise direction of the steel plate floor virtually parallel
to each other and at different levels in the thickness, which elements are not fitted
in pipes. These tensioning elements are pre-tensioned before the concrete is poured
by applying temporary forces to the ends, and the pre-tensioning is removed from the
ends of the tensioning elements after the setting of the concrete, as a result of
which the concrete is pre-stressed through the adhesion of concrete and tensioning
elements. It goes without saying that all kinds of pre-tensioning combinations are
possible.
[0014] The tensioning elements 5 for pre-tensioning run in a wavy form and, as can be seen
from Figure 2, the wave parts are situated approximately halfway between the fixed
supports 7 of the floor. So long as the concrete has not yet set, temporary bearing
elements 8 such as screw jacks are placed under the floor and are removed after the
concrete has set.
[0015] The method described above is particularly suitable for use in construction for the
production of floors of large dimensions, in particular length dimensions. The steel
plate 1 forms a formwork element and replaces the main reinforcement consisting of
a woven-wire cloth. The pre-tensioned tensioning elements 5 lead to a very great maximum
span length, in particular in conjunction with the profiling of the steel plate. As
a result of this profiling and as a result of the steel plate being made thicker,
less cable is needed.
[0016] Use of the principle of the invention for a prefab floor element is not ruled out.
[0017] It is also possible within the scope of the invention to place the steel plate 1
itself under pretension. In that case fewer or no tensioning elements 5 at all are
needed.
[0018] If the tensioning elements 5 to be pre-tensioned do not run in a wavy form, they
can be fitted at different levels parallel to each other in the concrete. In general,
the steel plate 1 will have no side edges, so that for pouring of the concrete mortar
temporary formwork boards will have to be fitted at the sides of the plate 1.
[0019] It will be clear that the tensioning elements 5 for pre-tensioning and the steel
plate 1 can absorb tensile load at the bottom side of the floor.
[0020] What is of vital importance is that through the use of the invention reinforced concrete
floors can be made for a very great span without woven-wire cloth, with low thickness,
a good bearing capacity, good rigidity and low deformation behaviour.
1. Method for the production of a steel plate concrete floor, comprising the pouring
of concrete mortar onto a steel plate which, for the purpose of increasing the adhesion
between concrete and steel, is provided beforehand with anchoring elements projecting
from the plane of the steel plate, characterised in that one or more elements of elastic
material such as steel which will bond to the concrete are subjected to a tensile
load in the lengthwise direction of the steel plate.
2. Method according to Claim 1, characterised in that the steel plate has a wavy or
crenellated profile at right angles to the lengthwise direction.
3. Method according to Claim 1 or 2, characterised in that before the concrete mortar
is poured, pipes for recessing channels in the concrete are placed over the steel
plate in the lengthwise direction thereof, in that before or after pouring of the
concrete mortar tensioning elements are guided through the channels, and in that the
tensioning elements are placed under a tensile load after setting of the concrete,
and the ends of said tensioning elements are anchored in the set concrete.
4. Method according to Claim 1 or 2, characterised in that, before the concrete mortar
is poured, tensioning elements are fitted, in that said tensioning elements are placed
under a tensile load through the application of tensile forces to the ends of the
tensioning elements, in that during the pouring of the concrete mortar and the setting
of the concrete the tensioning elements remain under a tensile load, and in that the
forces on the ends of the tensioning elements are removed after setting of the concrete,
so that the concrete is pre-stressed through the adhesion between concrete and the
tensioning elements.
5. Method according to Claim 3 or 4, characterised in that the tensioning elements
are bars, wires or bunches of wires which can be made of steel or glass such as fibres
which may or may not be embedded in epoxy resin, plastic such as aromatic polyamide
filaments which may or may not be embedded in epoxy resin, or carbon fibres which
may or may not be embedded in epoxy resin.
6. Method according to Claim 3, 4 or 5, characterised in that the tensioning elements
extend in a wavy form through the concrete, the wave valleys being situated approximately
halfway between the places where the floor is to be supported permanently in a building.
7. Method according to any of the preceding claims, characterised in that the steel
plate is placed under a tensile load before the concrete mortar is poured.
8. Method according to any of the preceding claims, characterised in that the steel
plate is supported at at least two opposite-lying edges by supporting elements of
a building and between them by a number of temporary additional bearing elements such
as screw jacks, in that the concrete mortar is poured onto the steel plate serving
as the formwork element, and in that the above-mentioned additional bearing elements
are removed after setting and pre-stressing of the concrete.
9. Method according to any of the preceding claims, characterised in that the anchoring
elements are studs rolled into the steel plate.