BACKGROUND OF THE INVENTION
1. Field of the Invention
[0001] The present invention relates to a gas booster in which connected in series are a
large-in-diameter piston to be reciprocatingly driven by pressurized fluid such as
compressed air and a small-in-diameter plunger inserted into a plunger chamber, a
low-pressure gas introduced into the plunger chamber being boosted according to the
sectional area ratio of the piston to the plunger.
2. Description of the Prior Arts
[0002] A hydraulic clamp is commonly adopted as the fluid-pressure clamp for fixing a die
to a fixed base such as an injection molding machine. The hydraulic clamp is indeed
superior in capability of yielding a strong clamping force with a high-pressure oil
of approx. 250 kgf/cm², which allows the clamping device to be compacted. However,
it also allows the oil to leak, although very small in amount, from the high-pressure
oil sealing packing, causing the atmosphere to be contaminated therewith. For this
reason, the hydraulic clamp has a limit in accomplishing the demand of ultra-cleaning,
which is growing pronouncedly in recent years.
[0003] The present inventor has previously devised a clamping system as described below
with a view to satisfying both the demand of cleaning mentioned above and the compacting
of the fluid-pressure clamp. The clamping system is a technique that a compressed
air of approx. 5 kgf/cm² supplied from an air compressor is boosted to approx. 40
kgf/cm² by a gas booster and the resulting high-pressure air is used as a working
fluid for the fluid-pressure clamp.
[0004] The above-mentioned gas booster is so arranged that a gas pump is driven by a pneumatic
piston engine, which is disclosed in U.S. Patent No. 4,042,311 or No. 4,812,109 previously
proposed by the present inventor.
[0005] More specifically, in this gas booster, an engine chamber is provided above the pneumatic
piston, to or from which engine chamber compressed air is supplied and discharged
by a supply/discharge switching means, while a plunger smaller in diameter than the
pneumatic piston is provided so as to downwardly protrude from the pneumatic piston,
and a plunger chamber is provided below the plunger, with a first check valve for
gas intake and a second check valve for gas discharge both connected to a lower portion
of the plunger chamber.
[0006] The gas booster operates in such a manner that the downward fluid pressure acting
on the pneumatic piston from the engine chamber surpasses the upward discharge reaction
force acting on the plunger from the plunger chamber to thereby downwardly drive the
pneumatic piston; therefore, at the time of high load, when a specified time period
has elapsed since the startup of the gas pump so that the discharge pressure has increased
to a sufficient extent, the piston and the plunger are driven to descend at low speed.
The resulting descending inertia force of the piston at the time of high load is so
small that when compressed air is discharged from the engine chamber by the supply/discharge
switching means at a time point when the piston has descended almost to the bottom
dead point, the piston will be immediately turned over to an ascending return stroke.
[0007] In contrast to this, at the time of low load when the discharge pressure is low,
the piston and the plunger are driven to descend at high speed; therefore, the descending
inertia force of the piston is so great that even though the piston is turned over
to the ascending return stroke almost at the bottom dead point, the piston will downwardly
overrun the bottom dead point for high load, making the descending stroke of the plunger
excessively extend.
[0008] In connection with the technical background as described above, a prior art known
by the present inventor is such that the depth dimension of the plunger chamber is
set so as to be slightly deeper than the descending stroke of the plunger at the time
of low load to thereby prevent the plunger from colliding against the bottom wall
of the plunger chamber at a final period of the descending stroke of the first piston.
[0009] The prior art mentioned above has the following problem.
[0010] That is, when the gas pump is at high load, the bottom dead point of the piston is
elevated higher than it is at the time of low load, causing the clearance between
the bottom wall of the plunger chamber and the bottom end of the plunger to be increased.
This in turn causes the compressibility of the plunger chamber to be reduced, with
the result that the amount of discharged gas is reduced to an extent of the decrement
in the compressibility. The gas booster, as a consequence, is long in the pressure
boosting time.
SUMMARY OF THE INVENTION
[0011] An object of the present invention is therefore to reduce the boosting time.
[0012] To accomplish the foregoing object, the present invention provides a gas booster
constructed as follows. A first cylinder bore, a plunger bore smaller in diameter
than the first cylinder bore, and a second cylinder bore are formed in this descending
order. A first piston inserted into the first cylinder bore and a plunger inserted
into the plunger bore are connected so as to extend vertically while a second piston
is inserted into the second cylinder bore. To or from an engine chamber formed between
the top wall of the first cylinder bore and the first piston, a pressure fluid is
supplied or discharged by a supply/discharge switching means. A plunger chamber is
formed between the plunger and the second piston while a cushion chamber is formed
between bottom wall of the second cylinder bore and the second piston. A first check
valve for gas intake and a second check valve for gas discharge are connected to an
internal lower portion of the plunger chamber. The cushion chamber and the outlet
of the second check valve are connected to each other with a communicating passage.
The second piston is prevented from moving upward in excess of a set extent by means
of a stopper.
[0013] The gas booster according to the present invention operates as follows.
[0014] With the load at low level, the pressure of the outlet of the second check valve
and that of the plunger chamber are so low that the first piston and the plunger are
driven to rapidly descend, causing a great descending inertia force of the first piston.
On this account, at a final period of the descending stroke, the bottom end of the
plunger comes into contact with the second piston, and subsequently the plunger pushes
the second piston down against the gas pressure of the cushion chamber. On the other
hand, when the plunger is turned over to ascend, the second piston returns to the
ascending position from the descending position with the pressure of the cushion chamber.
[0015] As the plunger repeats the above-described up-down strokes, the pressure of the outlet
of the check valve gradually increases. The descending speed of the first piston decreases
accordingly, so that the inertia force of each of the first piston and the plunger
becomes smaller when they descend, causing the overrun of the bottom end of the plunger
to gradually decrease. With the decreasing overrun, the height level of the second
piston is elevated by the pressure acting from the cushion chamber to the second piston
to thereby eliminate or reduce the clearance between the bottom end of the plunger
and the second piston. This contributes to maintaining the compressibility of the
plunger chamber at a great value.
[0016] Since the gas booster of the present invention is constructed and operates as described
above, the amount of gas discharge can be increased over the whole range from low
load to high load by increasing the compressibility of the plunger chamber at the
time of high load, thus allowing the pressure boosting time to be reduced.
[0017] Moreover, since the descending travel of the plunger can be cushioned by compressing
operation of the cushion chamber, the descending travel is gradually decelerated such
as to result in small colliding force due to collision between the plunger and the
second piston. In consequence, the gas booster produces only low level vibrations
and noise.
BRIEF DESCRIPTION OF THE DRAWINGS
[0018]
Figs. 1 to 3 show a first embodiment of the present invention,
Fig. 1 is a longitudinal sectional view of a gas booster;
Fig. 2 is an operation explanatory view of a piston engine of the booster;
Figs. 3 are operation explanatory views of a gas pump of the booster;
Fig. 4, showing a second embodiment of the present invention, is a segmentary view
illustrating a brake means of a first piston;
Figs. 5 and 6 show a third embodiment of the present invention,
Fig. 5 is a view equivalent to Fig. 4;
Fig. 6 is a view equivalent to Fig. 2; and
Fig. 7, showing a fourth embodiment of the present invention, is a view equivalent
to Fig. 4.
DESCRIPTION OF THE PREFERRED EMBODIMENTS
(First Embodiment)
[0019] Figs. 1 to 3 show a first embodiment of the present invention.
[0020] Referring to Fig. 1, a gas booster, designated by numeral 1, comprises a pneumatic
piston engine 2 to generate reciprocating linear movement by making use of compressed
air, and a plunger type gas pump 3 to be driven by the engine 2 to boost the gas.
[0021] The engine 2 has an engine body 4 for converting the pressure energy of compressed
air into power, to or from which engine body 4 compressed air is supplied or discharged
by a supply/discharge switching means 5. These engine body 4 and supply/discharge
switching means 5 are fastened to the gas pump 3 with a plurality of tie rods 6.
[0022] The engine body 4 is constructed as follows.
[0023] A first piston 8 is inserted into a first cylinder bore 7 via a packing 10 so as
to be hermetically and vertically slidable. Between a top wall 7a, i.e. a first end
wall of the first cylinder bore 7, and the first piston 8 there is provided an engine
chamber 9. When compressed air is supplied to the engine chamber 9, the first piston
8 is driven toward the bottom dead point. In contrast to this, when compressed air
is discharged from the engine chamber 9, the first piston 8 is allowed to return toward
the top dead point.
[0024] The supply/discharge switching means 5, having a supply/discharge valve 13, serves
to make the engine chamber 9 selectively connect to a supply port 14 or a discharge
port 15 via the supply/discharge valve 13. The supply port 14 is connected to an air
compressor 17 via a pressure reducing valve 16. The discharge pressure of the compressor
17 can be set in the range from 5.0 to 9.9 kgf/cm². The discharge port 15 is open
to the outside. The supply/discharge valve 13 is so arranged as to be switchable between
supply position X and discharge position Y (see Fig. 2) for compressed air via a pilot
valve 18.
[0025] The plunger type gas pump 3 is constructed as follows.
[0026] A plunger bore 20, smaller in diameter than the first cylinder bore 7, is formed
below the first cylinder bore 7 in series. A plunger 21 is inserted into the plunger
bore 20 via a packing 22 so as to be hermetically and vertically movable, the top
thereof being coupled to the first piston 8. Below the bottom end 21a of the plunger
21 there is provided a plunger chamber 23. To a lower portion of the chamber 23, the
outlet 24b of a first check valve 24 for gas intake and the inlet 25a of a second
check valve 25 for gas discharge are connected. Further, the compressor 17 is connected
to the inlet 24a of the first check valve 24.
[0027] When the first piston 8 is driven to descend, the plunger bottom end 21a goes into
the plunger chamber 23 to increase the internal pressure, thereby pushing a valve
member 26 of the first check valve 24 to be closed and simultaneously pushing a valve
member 27 of the second check valve 25 to be opened, so that the compressed air increased
in pressure is discharged from the outlet 25b. Conversely, in the ascending return
stroke, the valve member 26 is pushed open by the pressure of the inlet 24a of the
first check valve 24, so that a compressed air of approx. 5 kgf/cm² is introduced
into the plunger chamber 23, its pressure causing the plunger 21 to return the first
piston 8 to ascend. The above-described strokes will be repeated until the discharged
compressed air finally reaches at least 40 kgf/cm² pressure.
[0028] A concrete arrangement of the supply/discharge switching means 5 is now described
with reference to Fig. 1 and Fig. 2. The left half of Fig. 2 and the whole Fig. 1
each show an initial state of the descending drive stroke of the first piston 8 while
the right half of Fig. 2 shows an initial state of the ascending return stroke of
the same first piston 8.
[0029] The supply/discharge valve 13 is so constructed that a cylindrical supply/discharge
valve member 30 is inserted into a supply/discharge valve casing 29 fixed to the upper
portion of the top wall 7a of the first cylinder bore 7. The supply/discharge valve
member 30, when pushed up, switches to the supply position X in the left half of Fig.
2 and, when pushed down, to the discharge position Y in the right half of Fig. 2.
[0030] The supply port 14 is communicated with the discharge port 15 via a filter 37, a
supply actuation chamber 33, inside of a supply-side valve seat 29a, a working chamber
32, inside of a discharge-side valve seat 29b, a discharge chamber 34, a discharge
hole 38, and an outlet chamber 39, in this order. The outlet chamber 39 is internally
provided with a muffler 40. Further, the supply actuation chamber 33 is communicated
with a discharge actuation chamber 35 via a cylinder bore 30d of the valve member
30. The discharge actuation chamber 35 is partitioned from the discharge chamber 34
by an O-ring 42.
[0031] As shown in the left half of Fig. 2, when the supply/discharge valve member 30 is
pushed up switchedly to the supply position X, a supply actuation pressure-receiving
surface 30a provided at a lower portion of the valve member 30 leaves apart from the
supply-side valve seat 29a, so that the supply actuation chamber 33 and the working
chamber 32 are communicated with each other, while a discharge-side pressure-receiving
surface 30b provided at a mid-height portion of the supply/discharge valve member
30 is seated on the discharge-side valve seat 29b to seal the space between the working
chamber 32 and the discharge chamber 34.
[0032] Conversely to this, as shown in the right half of Fig. 2, when the supply/discharge
valve member 30 is pushed down switchedly to the discharge position Y, the supply
actuation pressure-receiving surface 30a is seated on the supply-side valve seat 29a
so that the space between the supply actuation chamber 33 and the working chamber
32 is sealed while the discharge-side pressure-receiving surface 30b leaves apart
from the discharge-side valve seat 29b so that the working chamber 32 and the discharge
chamber 34 are communicated with each other.
[0033] The pilot valve 18, which is to switch the supply/discharge valve member 30 between
supply position X and discharge position Y, comprises a piston type pilot valve casing
71, a spool 46 fixed to the first piston 8, an O-ring type pressure-introduction valve
seat 48, a pressure-relief valve member 53, and a pressure-relief valve seat 52.
[0034] More specifically, within the upper portion of the supply/discharge valve casing
29 there is provided a cylinder chamber 70a for a pilot cylinder 70, into which cylinder
chamber 70a the pilot valve casing 71 is inserted via an O-ring 72 so as to be hermetically
and vertically movable. Further, a pressure-receiving actuation chamber 70b formed
in confronting relation with the bottom face of the pilot valve casing 71 is communicated
with the discharge actuation chamber 35. The pilot valve casing 71 is adapted to be
driven upward against the urging force of a return spring 73 by virtue of the internal
pressure of the pressure-receiving actuation chamber 70b. A support cylinder 31 downwardly
protruding from the pilot valve casing 71 is inserted into the cylinder bore 30d of
the supply/discharge valve member 30, and the valve seat 48 is mounted from downside
to a lower portion 49 of the support cylinder 31. To the pressure-relief valve seat
52 provided within the upper portion of the pilot valve casing 71, the pressure-relief
valve member 53 is downwardly urged by a valve-closing spring 54 so as to be closed.
A pressure-relief port 51 disposed above the pressure-relief valve member 53 is communicated
with the discharge port 15.
[0035] When the spool 46, which is to descend along with the movement of the first piston
8, is switched from a state in which it is at the top dead point as depicted by solid
line in the left half of Fig. 2 to a state in which it is at the bottom dead point
as depicted by two-dot chain line in the same left half figure, first the pressure-relief
valve member 53 is seated on the pressure-relief valve seat 52, rendering the pressure-relief
port 51 closed, and subsequently the outer circumferential surface of the spool 46
and the inner circumferential surface of the valve seat 48 will leave apart from each
other. Then the compressed air within the supply actuation chamber 33 passes through
the valve-opening clearance between the spool 46 and the valve seat 48, a pilot valve
chamber 45, and a through hole 31a of the support cylinder 31, in this order, so that
it is introduced into the discharge actuation chamber 35 and the pressure-receiving
actuation chamber 70b.
[0036] By virtue of the internal pressure of the pressure-receiving actuation chamber 70b,
the pilot valve casing 71 is elevated against urging force of the two springs 73 and
54, as depicted by solid line in the right half of Fig. 2, causing the valve seat
48 to rapidly leave apart from the spool 46. This in turn causes compressed air to
be rapidly introduced into the discharge actuation chamber 35, the compressed air
serving to strongly push down the supply/discharge valve member 30 switchedly to the
discharge position Y in the right half figure. As a result, the engine chamber 9 is
communicated with the discharge port 15 via a supply/discharge hole 36, the working
chamber 32, the discharge chamber 34, and the discharge hole 38, thus allowing the
first piston 8 to follow the ascending return stroke.
[0037] Incidentally, when the supply/discharge valve member 30 is pushed down, upward back
pressure resistance that the supply/discharge valve member 30 receives will decrease
from one force applied to the pressure-receiving sectional area of the discharge-side
pressure-receiving surface 30b to another applied to the pressure-receiving sectional
area of the supply actuation pressure-receiving surface 30a, on the descending way
of the supply/discharge valve member 30. This arrangement ensures that the supply/discharge
valve member 30 can be reliably switched to the discharge position Y with its descending
speed increased from a midpoint of the descent.
[0038] Conversely to the above case, when the spool 46 is switched, along with the ascent
of the first piston 8, from the bottom dead point as depicted by solid line in the
right half figure to the top dead point as depicted by solid line in the left half
figure, first the outer circumferential surface of the spool 46 is brought into sealing
contact with the inner circumferential surface of the valve seat 48, and subsequently
the pressure-relief valve member 53 is made to leave apart from the pressure-relief
valve seat 52 against the valve-closing spring 54 while the discharge actuation chamber
35 is made to be communicated with the discharge port 15 via the through hole 31a
of the support cylinder 31, the valve-opening clearance between the valve seat 52
and the valve member 53, and the pressure-relief port 51. This in turn causes the
supply/discharge valve member 30 to be pushed up by the vertical differential pressure
whereby it is switched to the supply position X in the left half figure. Thus the
engine chamber 9 is communicated with the supply port 14 via the supply/discharge
hole 36, the working chamber 32, and the supply actuation chamber 33, allowing the
first piston 8 to start its descending drive stroke.
[0039] The gas pump 3 is constructed as follows.
[0040] As illustrated in Fig. 1, below the plunger bore 20 there is provided the second
cylinder bore 57 having the same diameter as the bore 20. The second piston 58 confronting
the bottom end 21a of the plunger 21 is inserted into the second cylinder bore 57
via the O-ring 59 so as to be hermetically and vertically movable. Between the second
piston 58 and a plug 60 there is provided the cushion chamber 61. The plug 60 forms
a second end wall of the second cylinder bore 57. The cushion chamber 61 and the outlet
25b of the second check valve 25 are communicated with each other via a communicating
passage 62.
[0041] The second piston 58 is urged upward by a return spring 63 installed in the cushion
chamber 61. A flange 66 provided at a lower portion of the second piston 58 is brought
from downside into contact with a stopper 64 on the circumferential wall of the second
cylinder bore 57 to thereby prevent the second piston 58 from moving upward in excess
of a set extent. A notched groove of the flange 66 forms a throttle 68 of the communicating
passage 62.
[0042] The second piston 58 and the cushion chamber 61, as shown in Fig. 3, operate as follows.
Figs. 3 (a), (b), and (c) show their operation at the time of low load; Fig. 3 (a)
depicts a state where the plunger 21 is at the top dead point, Fig. 3 (b) depicts
a state where the plunger 21 is in the course of descent, Fig. 3 (c) depicts a state
where the plunger 21 has descended to the bottom dead point. Further, Fig. 3 (d) shows
a state where the plunger 21 has descended to the bottom dead point at the time of
high load.
[0043] In the state of Fig. 3 (a), by virtue of the compressed air introduced from the first
check valve 24 into the plunger chamber 23, the plunger 21 has returned to the top
dead point. The second piston 58 is urged upward by the resultant force of the two:
a differential pressure between an upward force due to the compressed air introduced
into the cushion chamber 61 and a downward force due to the internal pressure of the
plunger chamber 23, and an urging force of the return spring 63. Symbol S represents
the stroke tolerance of the second piston 58.
[0044] As shown in Fig. 3 (b), when the plunger 21 descends to thereby increase the pressure
of the plunger chamber 23, the second check valve 25 is opened so that the compressed
air increased in pressure is discharged through its outlet 25b. Then the pressure
acts on the cushion chamber 61 through the communicating passage 62, holding the second
piston 58 at its ascent position.
[0045] At this low-load time, since the pressure of the outlet 25b of the second check valve
25 and that of the plunger chamber 23 are so low that the plunger 21 will be driven
to rapidly descend by the first piston 8 (see Fig. 1 or Fig. 2). Along with this movement,
the bottom end 21a of the plunger 21 is brought into contact with the second piston
58, and subsequently the plunger 21 pushes down the second piston 58 against the pressure
of the cushion chamber 61 and the return spring 63, as shown in Fig. 3 (c). Then the
compressed air within the cushion chamber 61 is further compressed to pass through
the communicating passage 62, pushed out to the outlet 25b of the second check valve
25. Symbol C in the figure represents the down stroke of the plunger 21 in this low-pressure
discharge state.
[0046] With the above-described compression operation of the cushion chamber 61, the descending
movement of the plunger 21 is cushioned such that its speed can be gradually reduced,
which contributes to suppressing the impact force due to collision between the plunger
21 and the second piston 58. Also, in this cushioning operation, the flowout speed
of compressed air, which is pushed out of the communicating passage 62 can be reduced
by the flow resistance that the throttle 68 provided in the communicating passage
62 gives, so that the pressure rise ratio of the cushion chamber 61 increases to allow
the descending movement of the plunger 21 to be sufficiently cushioned. Thus the vibrations
and noise of the gas booster can be reduced.
[0047] In contrast to this, in the ascending return stroke, the plunger 21 goes up by virtue
of the pressure of the gas introduced into the plunger chamber 23 from the first check
valve 24. Then the second piston 58 returns from the descent position of Fig. 3 (c)
to the ascent position as shown in Fig. 3 (a).
[0048] The plunger 21 repeats the above-described ascending and descending strokes so that
the pressure of the outlet 25b of the second check valve 25 gradually increases. With
increasing pressure of the outlet 25b, the descending speed of the first piston 8
slows down, causing the inertia force of the first piston 8 and the plunger 21 at
the time of descent to be reduced, with the result of gradually decreasing overrun
of the plunger bottom end 21a. On this account, in the case of high load as in Fig.
3 (d), the descending stroke D of the plunger 21 diminishes as compared with the case
of low load.
[0049] Correspondingly to this operation, the pressure of the cushion chamber 61 also increases
with the increasing pressure of the outlet 25b of the second check valve 25, while
the height position of the second piston 58 at the final period of the discharge stroke
gradually goes up, so that the clearance between the bottom end 21a of the plunger
21 and the second piston 58 is eliminated or reduced. Therefore, the compressibility
of the plunger chamber 23 can be maintained at a great value, with the result of a
large amount of gas discharge even at the time of high load.
[0050] With the arrangement that the return spring 63 is provided which urges the second
piston 58 upward, the second piston 58 can positively be urged against the plunger
bottom end 21a by the return spring 63 even when the gas pressure of the cushion chamber
61 is low at the time of low load, thus allowing the compressibility to be increased.
This enables the gas booster 1 to be increased in compressibility over the entire
region of operation and in average discharge amount.
[0051] Further, there is provided a brake means 75 for decelerating the ascending speed
in the first piston 8 when the first piston 8 has ascended nearly to the top dead
point.
[0052] More specifically, a third cylinder bore 76 is provided on the top wall 7a of the
first cylinder bore 7 above the engine chamber 9. The third cylinder bore 76 is so
formed as to be smaller in diameter than the plunger bore 20. Also, a third piston
77 is hermetically fitted into the third cylinder bore 76 via a packing 78 so as to
be vertically disengageable. The third piston 77, disposed between the plunger 21
and the spool 46, is fitted so as to be movable along with the first piston 8.
[0053] As shown in Fig. 2, at a final period of the upward return movement of the first
piston 8, a brake chamber 79 is formed above the third piston 77 within the third
cylinder bore 76. The brake chamber 79 and the supply port 14 are connected with each
other via a communicating passage 81. An opening/closing means 82 for opening and
closing the communicating passage 81 is composed of a groove 83 formed at the lower
part of the spool 46 and a through hole 84 of the top wall 7a of the first cylinder
bore 7.
[0054] The brake chamber 79 and the opening/closing means 82 operate in the following manner.
[0055] Referring to the right half of Fig. 2, as the first piston 8 ascends from the bottom
dead point as depicted by solid line in the figure to the position as depicted by
dash-and-dot line, the third piston 77 also ascends from the position as depicted
by solid line in the figure to the position as depicted by dash-and-dot line.
[0056] At an early to intermediate period of the ascending movement of the first piston
8, the compressed air within the engine chamber 9 is discharged via the supply/discharge
hole 36, the working chamber 32, the discharge chamber 34, and the discharge hole
38, as shown by two-dot chain lined arrow. The brake chamber 79 is communicated with
the engine chamber 9 while the upper external circumferential surface of the spool
46 serves to close the through hole 84.
[0057] When the first piston 8 goes up nearly to the top dead point, the third piston 77
is brought into sealing contact with the packing 78, thereby partitioning the brake
chamber 79 from the engine chamber 9, while the groove 83 of the spool 46 comes to
confront the through hole 84, thereby making the supply actuation chamber 33 communicate
with the brake chamber 79. Then the compressed air within the supply actuation chamber
33 is introduced from the groove 83 into the brake chamber 79, the pressure of the
compressed air serving to urge the third piston 77 downward. As a result, the ascending
speed of the first piston 8 is decelerated such that the compressed air of the outlet
24b of the first check valve 24 is gradually introduced into the plunger chamber 23,
to thereby increase the intake pressure of the plunger chamber 23. Thus the push-up
force acting from the plunger chamber 23 to the plunger 21 overcomes the push-down
force derived from the brake chamber 79, causing the first piston 8 to move to the
top dead point.
[0058] In this way, as the intake pressure of the plunger chamber 23 increases, the next
discharge amount also increases. The increase in the discharge amount will appear
to be a remarkable advantage at the time of low load when the pressure of the outlet
25b of the second check valve 25 is low. That is, as previously described, the gas
booster 1 operates depending on the balance between the descending drive force, which
acts from the engine chamber 9 onto the first piston 8, and the discharge reaction
force, which acts from the plunger chamber 23 onto the plunger 21, so that the pressure
of the engine chamber 9 will increase as the pressure of the outlet 25b increases.
In other words, the pressure of the engine chamber 9 is lower at the time of low load
than at the time of high load. For this reason, with the low load, the back pressure
resistance within the engine chamber 9 is small and the ascending return time of the
first piston 8, short. As a result of this, the intake pressure of the plunger chamber
23 decreases, the next discharge amount also diminishing. With the brake means 75
of the present invention, however, the next discharge amount can be increased by heightening
the intake pressure of the plunger chamber 23 at the time of low load, so that the
average discharge amount is increased to thereby allow the boosting time for reaching
a set pressure (approx. 40 kgf/cm² in this embodiment) to be reduced. Needless to
say, also with high load, the next discharge amount increases as the intake pressure
of the plunger chamber 23 increases.
[0059] The foregoing first embodiment can be modified as follows.
[0060] The gas booster 1, instead of being arranged in its longitudinal position, may also
be positioned in a lateral or slanting position or in a vertically inverted position.
[0061] The supply/discharge switching means 5 may also be of the type described in the above-mentioned
U.S. Patents No. 4,042,311 or No. 4,812,109 or the like.
[0062] The plunger bore 20 and the second cylinder bore 57 are preferably made into the
same diameter from a viewpoint of their manufacture, but may be of different diameters.
[0063] Below the first piston 8 there may be added a return spring for ascending and returning
the first piston 8.
[0064] It is possible to omit the return spring 63 that has been provided in the cushion
chamber 61. However, since the return spring 63, provided as in the above embodiment,
allows the second piston 58 to be urged into contact with the plunger 21 by the return
spring 63 in the low-load operation, the compressibility at the time of low load becomes
also great to elevate the average compressibility.
[0065] Working fluid of the gas pump 3 may be nitrogen gas or helium gas in place of compressed
air. Further, the gas increased in pressure by the gas pump 3 may be of the kind other
than the one supplied to the engine 2.
[0066] The respective packings 10, 59, and 78 of the cylinder bores 7, 57, and 76 may be
X-rings or U-packings in place of O-rings.
[0067] Fig. 4, Figs. 5 and 6, and Fig. 7 illustrate second to fourth embodiments, respectively,
where like components and members having the same construction as in the first embodiment
are designated by like numerals in principle.
(Second Embodiment)
[0068] In this embodiment, the brake means 75 is modified as follows.
[0069] As shown in Fig. 4, the space between the through hole 84 of the cylinder top wall
7a and the spool 46 is sealed by a packing 86. Further, the opening/closing means
82 is composed of a check valve member 87 and a valve-opening rod 88 protruding downwardly
from the valve member 87. A check valve seat 89 formed from an O-ring is received
by a support cylinder 90 from below.
[0070] When the first piston 8 has ascended nearly to the top dead point, the first piston
8 pushes up the rod 88, causing the check valve member 87 to leave apart from the
O-ring 89. As a result, the compressed air within the supply port 14 is introduced
into the brake chamber 79 via the communicating passage 81.
(Third Embodiment)
[0071] In this embodiment, the brake means 75 is modified as shown in Figs. 5 and 6.
[0072] As in Fig. 4, the space between the spool 46 and the through hole 84 of the cylinder
top wall 7a is sealed by a packing 92. The brake chamber 79 is communicated with the
engine chamber 9 via a throttling clearance 93 formed from a fitting clearance between
the third cylinder bore 76 and the third piston 77.
[0073] The brake chamber 79 and the throttling clearance 93 operate as follows.
[0074] In the right half of Fig. 6, as the first piston 8 ascends from the bottom dead point
as depicted by solid line in the figure to the point as depicted by dash-and-dot line,
the third piston 77 also ascends from the position as depicted by solid line in the
figure to the position as depicted by dash-and-dot line.
[0075] At an early to intermediate period of the ascending movement of the first piston
8, the compressed air within the engine chamber 9 is discharged to outside via the
supply/discharge hole 36, the working chamber 32, the discharge chamber 34, and discharge
hole 38 in this order, as indicated by two-dot chain lined arrow. The brake chamber
79 is open to the engine chamber 9.
[0076] When the first piston 8 has ascended nearly to the top dead point, the third piston
77 is fitted into the third cylinder bore 76 so that the internal pressure of the
brake chamber 79 is increased by virtue of the throttling effect of the throttling
clearance 93. The internal pressure being applied to the top surface of the third
piston 77 as a back pressure, the ascending speed of the first piston 8 is reduced
so that the compressed air at the outlet of the first check valve (not shown) is gradually
introduced into the plunger chamber 23, to thereby increase the intake pressure of
the plunger chamber 23. Then the push-up force acting from the plunger chamber 23
onto the plunger 21 overcomes the push-down force applied from the brake chamber 79,
thus causing the first piston 8 to move up to the top dead point.
[0077] Accordingly, even with low load, the plunger chamber 23 takes in a sufficient amount
of gas to increase the pressure of the plunger chamber 23, so that the next discharge
amount is increased. As a result, the gas booster has a greater average discharge
amount, capable of reducing the boosting time to reach a set pressure (approx. 40
kgf/cm² in this embodiment).
[0078] Moreover, achieving the above-described advantage only requires the third piston
77 to be fitted into the third cylinder bore 76, permitting a simplified construction.
(Fourth Embodiment)
[0079] In this embodiment, the brake means 75 in Fig. 5 and Fig. 6 is further modified as
follows.
[0080] As shown in Fig. 7, the space between the third cylinder bore 76 and the third piston
77 is sealed from each other by a packing 95 while the brake chamber 79 and the engine
chamber 9 are communicated with each other via an exhaust passage 96, in which exhaust
passage 96 there is provided a throttle valve 97 formed from a needle valve.
[0081] With this arrangement, when the first piston 8 ascends nearly to the top dead point
with the third piston 77 hermetically fitted into the third cylinder bore 76, the
internal pressure of the brake chamber 79 is increased by virtue of the throttling
effect of the throttle valve 97, decreasing the ascending speeds of the first piston
8 and the plunger 21. As a result, the intake pressure of the plunger chamber increases
to thereby increase the next discharge amount correspondingly, allowing the boosting
time to be reduced. Moreover, since the exhaust speed from the brake chamber 79 can
be controlled by the throttle valve 97, the brake force applied to the first piston
8 can be finely adjusted advantageously.
[0082] It is noted that the exhaust passage 96 may alternatively be communicated with the
supply/discharge hole 36 or the like instead of being communicated with the engine
chamber 9.
[0083] Although the present invention has been fully described by way of example with reference
to the accompanying drawings, it is to be noted here that various changes and modifications
will be apparent to those skilled in the art. Therefore, unless otherwise such changes
and modifications depart from the scope of the present invention as defined by the
appended claims, they should be construed as included therein.