[0001] The invention relates to a method and device for compensating for crane boom deformation
during load lifting and placing.
[0002] It is known that a crane boom deforms relative to its unloaded condition when lifting
a load, this deformation being proportional to the load. Optimizing the capacity of
a crane boom requires that these deformations be taken into account.
[0003] Problems may result especially in lifting and placing a load. Fig. 3 depicts a crane
boom 1 of a crane in the unloaded condition, a load 2 to be lifted being secured to
the crane hook. To achieve lifting, the lifting force F
lift, which counteracts the force resulting from the weight of the load, F
L, is gradually increased. Only when the force F
lift exceeds the force F
L is the load lifted from the ground. When the lifting force F
lift is still somewhat less than the force F
L incurred by the weight of the load, considerable forces act on the crane boom 1 even
though the load 2 to be lifted is still fully on the ground. This results in deformation
of the crane boom 1 as is illustrated in Fig. 4a. The deformation of the crane boom
1 caused by the lifting force results in an increase in the horizontal distance of
the boom jib away from the fulcrum point of the upper structure, this distance generally
being termed radius or length of jib.
[0004] Fig. 4b depicts vectorially the forces acting on the load 2 when the boom is deformed
in such manner. Due to the increased radius of the crane boom 1, the force F
lift which acts on the load is composed of a vertical component F
lift, for overcoming the weight force F
L incurred by the load, and a horizontal component F
p. When lifting force F
lift is sufficient to overcome the force incurred by the weight of the load, the force
F
P acting in the horizontal direction results in the load swinging upon being lifted.
This may result in hazardous situations when e.g. unloading concrete wall elements
from a truck since the lifted load has uncontrolled movement and, thus, becomes a
hazard to man and equipment in the vicinity. Also, such a situation requires a greater
force F'
lift to be generated by the hoisting mechanism in order to lift the load. This is greater
than the lesser force F
lift which would be required if the lifting force is applied in a purely vertical direction
by a boom which is not shifted laterally by such deformation as illustrated in Figure
4a.
[0005] Similar undesirable effects occur when placing the load. As illustrated in Fig. 5,
the crane boom 1, supporting a lifted load, is deformed as it is just about to place
the load. This is shown at A in Fig. 5. When load is placed and the force acting on
the load 2 from the crane boom 1 is then slowly reduced, this results in the crane
boom 1 translating into its non-deformed unloaded condition, as identified by B in
Fig. 5. To unhook or release the load, the jib of the boom 1 needs to be repositioned
directly above the load 2 since, otherwise, the crane hook on release would tend to
swing once released. However, the situations in placing the load are generally not
as critical or dangerous as in lifting the load since the friction force of the load
at the moment of placement prevents the load itself from swinging.
[0006] To compensate for the deformation of the boom during lifting and placing of a load,
the crane operator must change the angle of the boom 1 by actuating the elevating
mechanism 3 in order to compensate for the increase or decrease in radius resulting
from deformation. Thus, the operator would compensate by elevating the boom during
lifting and compensate the reduced deformation of the boom when placing the load by
lowering the boom. Since operation of the crane boom must always be as near optimum
as possible, and the deformation of the crane boom may be considerable as a result
of the high forces involved, proper compensation is important for lifting and placing
a load.
[0007] In these compensating actions, i.e. elevating and lowering the boom, the crane operator
acts as the controller. The flow of information in such a compensating action is illustrated
in Fig. 6. The crane operator observes the working area and takes note, e.g. when
lifting a load, of the momentary radius of the crane boom in the unloaded condition.
This serves as the target value for him for the radius of the boom in the complete
elevating procedure. A device for limiting the loading moment (LML) shows him the
information obtained via sensors as to the actual condition of the boom, it being
particularly the information regarding the radius that is of importance to him, this
serving as the actual value for his controlling response. In addition, other values
as regards the actual condition of the crane could also be displayed to be likewise
taken into account in compensating the situation. For this purpose the crane operator
needs to always keep an eye on the working area, in addition to noting the displayed
actual values, to keep a check on the effect of his actions.
[0008] In such a compensating procedure it is necessary that the crane operator has sufficient
experience. Otherwise, uncontrolled and, thus, hazardous operating conditions may
easily arise in lifting the load. The crane operator needs to observe several displays
at the same time whilst operating various control levers to suitably control the hoisting
or lifting mechanism for lifting the load, and suitably track the elevating mechanism
to compensate for deformation of the crane boom. This puts a considerable strain on
the crane operator, who is required to simultaneously observe various displays and
operate the various control levers, so that he may no longer be able to fully concentrate
at all times on the working area. This increases the chances that hazardous operating
conditions may arise. This may result in danger for man and machines in the vicinity
when a load is lifted.
[0009] An object of the present invention is to provide a method and device for compensating
the deformation of a crane boom upon lifting and placing of a load by which safety
in crane operation may be enhanced.
[0010] In accordance with the invention, a controller device is provided which receives
data pertaining to the sensed deformation of the crane boom, as well as a target value
for the position of the crane boom. From these two input variables, i.e. the target
value for the position of the crane boom and the actual value of crane boom deformation
as measured or established from measured variables, suitable control signals are established
by a controller device which signal or control at least one positioner for the crane
boom. The crane boom is, thus, maintained in a suitable position during lifting or
placement of a load, substantially in its target position.
[0011] For example, for an ever-increasing lifting force and a corresponding increasing
deformation of the crane boom, resulting in an increased radius, the position of the
crane boom is modified so that the target position of the crane boom, more particularly
of the crane boom jib, remains substantially unchanged. The jib of the crane boom
is thereby maintained plumb above the load to be lifted without any horizontal displacement,
irrespective of the magnitude of the momentary lifting force. More particularly, the
angle of elevation of the crane boom may be adjusted by the boom elevating mechanism
so that the crane boom jib remains plumb above the load to be lifted even with increasing
curvature of the crane boom.
[0012] It is also possible to maintain the angle of elevation of the crane boom constant
and to alter, e.g., the length of the crane boom or the position of the crane carriage.
The controlling action may also be achieved by modifying concurrently several manipulated
variables such as, e.g., the length of the crane boom and the angle of elevation,
as long as it is achieved during lifting or placement of a load that the jib of the
boom always remains substantially directly above the load which is standing on the
ground despite changes in boom condition resulting from the lifting forces.
[0013] In detecting the deformation of the crane boom, the measured values of various sensors
may be employed. In this respect it is of particular advantage to employ the following
sensors: a position transducer arranged at the jib of the crane boom for measuring
at the lower end the momentary angle of elevation of the crane boom jib; a position
transducer disposed on the crane boom jib and measuring the momentary angle of elevation
of the crane boom jib; a linear transducer for measuring the overall length of the
crane boom; a pressure transducer on the elevating mechanism, especially on the elevating
cylinder; a transducer for measuring the load or change in load of a single section
(i.e., a telescoping section of the boom), such as one or more strain gauges or a
load sensing roller arranged at the upper end of the crane boom and located on the
upper end of the elevating jib for measuring the force acting momentarily on the jib
of crane boom. It is possible thereby to make use of the data provided by all of the
above sensors in detecting the deformation or radius of the crane boom. In addition,
of course, use may be made of further data sensed by further sensors of the crane
or crane boom to support the controlling action.
[0014] It is also possible to detect the deformation of the crane boom with but one of the
aforementioned sensors or with any combination thereof. Thus, the deformation of the
crane boom may be detected e.g. by making use only of the data of a position transducer
on the underside or in the lower region of the boom, a position transducer on the
upper side or in the upper region of the crane boom and a linear transducer which
senses the overall length of the crane boom. As an alternative it is also possible
to use the data of other sensors for the controlling action from which the actual
deformation of the crane boom may be detected. This may also be done e.g. by means
of the data of a pressure transducer on the elevating cylinder or a linear transducer
for detecting the length of the crane boom as a whole. In addition, for this purpose
use may be made of the data furnished by a position transducer in the upper or lower
region of the crane boom, it also being possible to detect the data relevant to controlling
the deformation of the crane boom by making use of a combination of the aforementioned
sensors.
[0015] To enhance the quality of the controlling action it may be of advantage to obtain
the deformation values of the crane boom on the basis e.g. of families of characteristics
detected by testing prior to actual use of the crane.
[0016] The aforementioned combinations of the individual sensors are cited merely as exemplary
embodiments, it being possible to make use of other sensors for measuring specific
variables, whereby then the total deformation of the crane boom may be sensed from
the combination of the variables detected by these sensors.
[0017] In one embodiment of the invention the deformation of the crane boom may be detected
by the actual value of the radius of the crane boom being sensed by one or more suitable
sensors. It is also possible as described above, to detect the magnitude of the momentary
deformation or radius of the crane boom from individual or several measured variables
of the crane, such as the actual boom length or actual boom elevation, in conjunction
with the momentary lifting force. In general, each and every individual measured variable
or combination of measured values may be used to determine the deformation of the
crane boom from which it may be detected how the deformation or radius of the crane
boom has changed. This then provides a measure of the horizontal spacing between the
standing load and boom jib.
[0018] In addition to the measured values serving to detect the deformation of the crane
boom, the controller device may also be furnished advantageously with even further
values, such as the desired rate and direction of movement of the hoisting or lifting
mechanism. This manipulated variable may be entered by the crane operator via a control
lever. From the desired rate of the hoisting mechanism the controller is able to detect
the deformation time profile that the crane boom will probably have and, thus, suitably
control the positioner of the crane boom to maintain the latter in its target position.
[0019] For the target value for the position of the crane boom it is preferred to use the
radius of the boom immediately prior to placement of a load or immediately prior to
lifting a load, the crane boom jib in each case being located plumb above the load
without any lateral displacement. When the controlling action is in accordance with
this target value, the conditions of the crane boom in lifting or placing a load as
shown in Figs. 4 and 5 may be avoided. It is also possible, however, to take the position
of the crane boom on activation of the controller device as the target value. It would
then be the task of the crane operator to make sure that the controller device is
activated at a suitable moment in time, i.e. when the boom jib is precisely above
the load.
[0020] The signals output by the controller device are preferably those with which the positioner
of the crane boom, such as the elevating mechanism of the crane may be controlled,
so that the rate of change in the angle of elevation of the crane boom, and also the
direction of the change in the angle of elevation, may be controlled via the rate
and direction of movement of the elevating mechanism. As a result, the horizontal
departure of the crane boom jib from the target position, the position plumb above
the load, may be controlled. For example, in the operating condition as shown in Fig.
4a, in which the crane boom jib is no longer located plumb above the load to be lifted,
the elevating mechanism can be controlled so that the angle of elevation of the crane
boom is increased, thereby returning the jib of the crane boom to a position which
is plumb above the load to be lifted.
[0021] It is further of advantage to control the hoisting mechanism as the crane boom positioner,
i.e. by controlling the hoisting mechanism so that the rate and/or direction of movement
of the hoisting mechanism is controlled. In this arrangement the controlling action
may be done, for example, in conjunction with the control of the elevating mechanism,
as described above, so that the complete lifting or placement action of a load is
controlled so that no jerking movements or undesirable side swinging movements of
the load occur.
[0022] It is also possible to control automatically only one variable, or only certain variables
of a positioner as noted above, whereby other control variables may be defined directly
by the crane operator, such as detecting whether the hoisting mechanism is to implement
a lifting or lowering movement. The controller device needs only to receive suitable
input variables from which the deformation or actual departure of the crane boom from
a target condition may be sensed in order to determine therefrom suitable control
signals which are then output to bring the crane boom, more particularly the crane
boom jib, to the desired position.
[0023] Since embodiments are possible in which a plurality of input variables are applied
to the controller device, such as the actual value of the angle of the boom, the actual
value of the length of the boom, the measured lifting force and the like, and furthermore,
a plurality of output variables need to be output from the controller device, such
as the direction and rate of movement of the hoisting mechanism and the direction
and rate of change of the actual position of the elevating mechanism, it is of advantage
to use a fuzzy controller. This kind of control may be appreciated as a kind of fuzzy
expert system, the control response of which may be defined in a quasi-natural language
on the basis of linguistic expressions, one exemplary definition of the controlling
action being e.g.:
WHEN radius of the jib position is rather large AND lifting is rapid
THEN raise the boom angle quickly AND lift the load slowly
[0024] By way of explanation, the preceding logical statement relates to a situation wherein
a large control deviation, such as a long radius, occurs, and the crane operator further
dictates that lifting is to be achieved at a relatively high rate. In this situation,
the fuzzy controller device would output control signals which prompt a fast change
in the radius to the target position, such as a fast increase in the angle of elevation
of the crane boom relative to the horizontal, and at the same time the hoisting mechanism
is controlled so that the rate at which the load is to be lifted is made to be relatively
slow, i.e. slower than defined by the crane operator. In a situation as set forth,
it may even be necessary that the load is lowered at moments, rather than raised,
in order to control deformation of the boom.
[0025] In general, a fuzzy control action is composed of a plurality of such linguistic
conditions for describing the various possible control actions. Collectively, such
control actions comprise the control algorithm. For implementing such a controlling
action, recourse may be made to the experience of the crane operator who, as already
mentioned, needs to implement boom elevating and lowering actions manually in the
usual manner.
[0026] An apparatus in accordance with the invention for compensating for the deformation
of a crane boom in lifting or placing a load comprises a positioner for positioning
the crane boom so that it may be maintained substantially in a target position, i.e.,
so that the crane boom jib exhibits substantially no horizontal displacement from
a target position. Further, a measuring device, or a combination of several measuring
devices, is provided in a controller device for detecting the deformation of the crane
boom for defining a target value for the crane boom position. The positioner for the
crane boom is coupled to the controller device so that the target position of the
crane boom may be set by the controller device from the defined target and actual
values.
[0027] Preferably the device for measuring or detecting the deformation of the crane boom
is a sensor, or a combination of several sensors, capable of measuring or detecting
the radius and/or curvature of the crane boom, as indicated above.
[0028] Sensors may be provided which measure, e.g., the boom length, the angle of elevation
of the boom, or the actual lifting force acting on the crane boom. It is not necessary,
of course, as already mentioned above, that all of the aforementioned sensors are
used. It is possible that only one or more sensors are used in combination for measuring
or detecting the deformation of the crane boom.
[0029] In a preferred embodiment, the elevating mechanism of the crane is used as the positioner
for controlling the position of the crane boom and maintaining the boom at a target
position. In such an embodiment the rate and/or direction of the change in the angle
of elevation of the crane boom may be adjusted in order to maintain the target position.
It is likewise possible to use the hoisting mechanism of the crane for the controlling
action. It is also possible to make use of the elevating mechanism and hoisting mechanism
in combination for suitably maintaining the target position of the crane boom, such
as by adapting the lifting force produced by the hoisting mechanism in lifting a load
to the momentary position of the elevating mechanism so that no excessive or jerking
deformation of the crane boom may occur.
[0030] Preferred embodiments of a method and apparatus in accordance with the invention
will now be discussed with reference to the accompanying drawings in which:
Fig. 1 is a block diagram representing the control loop in accordance with the invention;
Fig. 2 is a flow diagram of the information in accordance with the invention for controlling
the deformation of the crane boom;
Fig. 3 is an illustration of an unloaded crane boom to which a load is secured,
Fig. 4a is an illustration of a loaded crane boom applying a lifting force to a load,
wherein the lifting force has not increased to a magnitude sufficient to actually
lift the load;
Fig. 4b is a force diagram representing the forces occurring at the load as shown
in Fig. 4a;
Fig. 5 is an illustration of a loaded crane boom directly after having placed a load
as well as of an unloaded crane boom; and
Fig. 6 is a flow diagram of the information for conventionally elevating or lowering
the crane boom by the crane operator.
[0031] Referring now to Fig. 1 there is illustrated an embodiment of a control loop in accordance
with the invention whereby the crane operator is able to switch the controller in
and out of circuit and to define merely manipulated variables or target variables
for the direction and/or rate of movement of the hoisting mechanism for the controller.
The crane operator is thus able, e.g., via a single control lever for the hoisting
mechanism, to affect lifting and placing of a load with the controller device controlling
the boom so that the crane boom jib is always maintained above the load (at the target
position) and no horizontal shifting of the jib occurs which, as described above,
may result in hazardous swinging when lifting a load.
[0032] The controller 10 as shown in Fig. 1 receives input of data representing actual values
of variables as measured by sensors 12 which define the actual condition of the boom.
Useful data may be provided by sensors which measure the curvature or radius of the
boom; the angle of elevation of the boom, more particularly the angle of elevation
at the upper and lower ends of the boom, respectively; the boom length; the forces
acting on the boom; or the pressure existing at the elevating cylinder. The actual
value of the angle of elevation of the boom and the actual value of the length of
the boom are particularly useful values.
[0033] In this arrangement the values measured by the sensors are first transferred to a
boom monitor 14 which may also handle additional functions, such as load moment limiting
(LML). Boom monitor 14 then applies the values as measured by the sensors and, where
necessary, further processed, to the controller 10. At this stage certain features
may already be extracted from the measured values, for example, in making use of characteristics
or suitable computations.
[0034] The boom monitor 14 may further record the actual values of the boom characteristics
measured by the sensors upon activation of the controlling action, such as the sensed
radius, as the target values to which the subsequent controlling action is to respond.
It is likewise possible, as evident from Fig. 1, to record the target value in a separate
memory MEM 16. In this arrangement the target value may be recorded, e.g., upon activating
the controller. It is also possible, however, to store the target value automatically
upon sensing the load or upon lifting the load. This may be done, e.g., as soon as
a freely selectable tensile force (e.g. 50 KG) is exceeded. It is the difference between
this stored target value and the measured actual value of the radius - the error -
that is applied to the controller.
[0035] Input from the operator is provided manually by levers and switches or the like,
identified collectively at 18 in Figure 1. Signals for operator input of movement
direction, rate of movement, etc., and activation or de-activation of the controller
may be thus input. From the input variables the controller detects, by means of the
fuzzy control algorithm specified by linguistic expressions, the output variables
for controlling the hoisting mechanism and/or the elevating mechanism and/or the telescoping
mechanism. Signals controlling the direction and/or rate of change are output, as
shown at 10a and 10b to the hoisting mechanism, and/or at 10c and 10d to the elevating
mechanism. Such control may also be applied by the controller to a telescoping mechanism
(not shown). The hoisting mechanism influences the deformation of the boom via the
lifting force applied to the lifting cable supported by the boom. The elevating mechanism
sets or adjusts the angle of elevation of the boom. In this arrangement the length
of the boom or the angle of elevation must always be adjusted or controlled so that
the momentary deformation of the crane boom resulting from the changing load is compensated
in each case so that the jib of the crane boom has substantially no horizontal departure
from its target position.
[0036] Referring now to Fig. 2 there is illustrated a flow diagram of the information in
an operation for compensating for boom deformation in accordance with the invention.
The working area is firstly observed by the crane operator. When the crane operator
sees that, e.g., a load is to be lifted, he activates the controlling action and defines
a manipulated value for the hoisting mechanism via a control lever. The controlling
action receives as additional input data representing the actual values detected by
the sensors for the deformation of the boom, which are transferred from the boom monitor
by, for example, a CAN bus, to the controlling action.
[0037] From these input variables control signals for the movement of the winch of the hoisting
mechanism and/or for the elevating mechanism are output, both of which influence the
position and shape of the boom. Accordingly, the crane operator simply defines a manipulated
value, e.g., rate of lift for desired lifting of a load. The controlling action controlling
the crane boom, such as the elevating mechanism and hoisting mechanism, take into
account the defined manipulated value so that substantially no variation of the radius
of the crane boom occurs. The boom monitor, which may also serve to define or limit
the loading moment, as described above, indicates the measured actual value of the
crane boom to the crane operator.
[0038] Accordingly, the controlling action in accordance with the invention relieves the
crane operator from some of the monitoring tasks typically required of him hitherto
in lifting and placing a load so that he is now able to more fully concentrate on
the working area.
1. A method for compensating for the deformation of a crane boom (1) in lifting or placing
a load (2), comprising
detecting the deformation of the crane boom (1);
applying data representing detected deformation of said crane boom (1) to a controlling
device (10);
applying a target value representing a target position of said crane boom (1) to said
controlling device (10 ); and
outputting signals from said controlling device (10) for controlling at least one
device for positioning said crane boom (1) so that said crane boom (1) is substantially
maintained in its target position.
2. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein deformation of said crane boom (1) is detected by measuring the curvature
of said crane boom (1).
3. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein deformation of said crane boom (1) is detected by measuring the radius
of said crane boom.
4. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein deformation of said crane boom (1) is measured by measuring the angle of
elevation of said crane boom.
5. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein deformation of said crane boom (1) is measured by measuring the length
of said crane boom.
6. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein deformation of said crane boom (1) is measured by measuring the magnitude
of the lifting force acting on said crane boom.
7. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein at least one of the rate of movement and the direction of movement of the
hoisting or lifting mechanism is applied manually to the controller device during
an operation for lifting or placing a load.
8. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein the radius of the crane boom prior to placement or lifting of a load is
used as said target value for said position of said crane boom.
9. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein the radius of said crane boom upon activation of said controlling action
is used as said target value for said target position of said crane boom.
10. The method for compensating for deformation of a crane boom as set forth in claim
1, wherein said at least one device for positioning said crane boom is an elevating
mechanism for said boom, wherein at least one of the rate of movement and the direction
of movement of said elevating mechanism is controlled by the controlling device.
11. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein said at least one device for positioning said crane boom is a hoisting
mechanism, wherein at least one of the rate of movement and the direction of movement
of said hoisting mechanism is controlled by the controlling device.
12. The method for compensating for the deformation of a crane boom as set forth in claim
1, wherein a control algorithm is implemented as a fuzzy controller.
13. A device for compensating for the deformation of a crane boom (1) in lifting or placing
a load (2), comprising
at least one positioner (3) for changing the position of the crane boom (1);
at least one detection device (12) for measuring deformation of said crane boom (1);
means for defining a target value for the position of said crane boom (1); and
a controller (10) connected to said at least one detection device for measuring said
deformation of said crane boom and to said means for defining a target value for said
position of said crane boom, wherein said controller is connected to said at least
one positioner (3) for said crane boom for maintaining said crane boom in its target
position during operation.
14. The device as set forth in claim 13, wherein said at least one device for measuring
said deformation of said crane boom is a device for measuring at least one of the
curvature of said crane boom and radius of said crane boom.
15. The device as set forth in claim 13, wherein said at least one detection device for
measuring said deformation of said crane boom is a device for measuring at least one
of the angle of elevation of said crane boom, the length of said crane boom, and the
force acting on said crane boom.
16. The device as set forth in claim 13 wherein said at least one positioner for said
crane boom is an elevating mechanism (3) which is capable of changing the angle of
elevation of said crane boom.
17. The device as set forth in claim 13, further comprising a hoisting mechanism for lifting
or placing a load, wherein said hoisting mechanism is responsive to said controller
for varying at least one of the rate of movement of said load and direction of movement
of said load.
18. The device as set forth in claim 16, wherein said controller (10) controls at least
one of the rate of change of the elevation of said crane boom and the direction of
change of the elevation of said crane boom.