[0001] The building industrialization has allowed the erection of industrial buildings and
perfecting the prefabrication of structures and stopper panels, but the same application
criterium as not been achieved in the design and construction of residential buildings
of any type such as one-family houses, detached houses, terraced houses, few-story
buildings and to the construction of non-residential buildings such as hospitals,
schools, hotels, etc.
[0002] A system which only employs prefabricates in the total construction of the desired
type of building is required in order to reach this degree of application.
[0003] With the application of the aforementioned system we want to achieve the following
targets:
- Design rapidity
- Possibility of adapting the system to different projects
- Homogeneity in making the structural mixtures able to grant the declared characteristics
that are the prerogatives of a prefabricated elements system
- Fast assembly of all the elements
- Possibility of making different types of new housing conglomerates in a short time
- Capability of the system to resist seismic stress
- Certainty of making a realistic expenses
- Possibility of designing different types of residential buildings and also of buildings
for non-residential uses. One-family house, terraced houses, two/three/four-family
houses, few-story and up to 8-story buildings with apartments of different sizes,
hospitals, schools, office district and trading center buildings.
ELEMENTS OF THE SYSTEM
FOUNDATION BEAMS MADE OF CONCRETE
[0004]
FIG.1 Rectilinear beam
FIG.2 Angular beam
FIG.3 T beam
FIG.4 Cross beam
SELF-SUPPORTING PANELS MADE OF STRUCTURAL LIGHT CONCRETE
[0005]
FIG.5 Panel with longitudinal groove-and-tongue joints
FIG.6 Panel with longitudinal female-female dap joints
FIG.7 Panels with longitudinal male-male dap joints
FIG.8 Panel with groove-and-tongue joint with seating for lintel
FIG.9 Panel with tongue-and-groove joint with seating for lintel
FIG.10-Panel with male-male dap joint with seating for lintel
FIG.11-Lintel for doors and windows
FIG.12 Lintel for balcony
FIG.13 Panel for window sill
FIG.14-Composition of outside wall with windows
FIG.15 Angular panel
FIG.16- T-shaped panel
FIG.17- Cross panel
FIG.18- Panel for vertical passage of ducts
FIG.19- Panel with opening for sewage or for housing the heating system radiators
FIG.20- Panel for vertical and horizontal passage of ducts
ELEMENTS FOR PARTITION WALLS
[0006]
FIG.21 Panel with groove-and-tongue joint
FIG.22 Panel ½FIG.21 with groove-and-tongue joint
FIG.23 T-shaped panel with springers for doors lintels
FIG.24 Reduced (smaller) panel with shutter springer for lintel
FIG.25 Lintel
FIG.26 Vertical masonry structure for door
FIG.27 Panel as FIG.21 with vertical masonry structure on the longitudinal axis
FIG.28 Panel as FIG.21 with openings for ducts passage
SLAB ELEMENTS
[0007]
FIG.29- Element with one span with incorporated curb
FIG.30 Element with two spans with incorporated curb
FIG.31- Element with one span with curb and cantilevered slab for balcony
FIG.32 Element with two spans with curb and cantilevered slab for balconies
Fig.33 Element with one span with no incorporated curbs
Fig.34- Element with two spans with no incorporated curbs
[0008] Some elements can also be made with a size half in width
ELEMENTS FOR PEAKED ROOF
[0009]
FIG.77-Triangular element with flat slab and double-pitch sloping roof with insulation system
and incorporated tiles
FIG.78 Triangular elements with slab with two spans and double- pitch sloping roof, with
insulation system and incorporated tiles
ELEMENTS FOR TWO-FLIGHT STAIRS
[0010]
FIG.41- Plan of the stairs
FIG.42 Element with incorporated steps and landing for first flight (plan)
FIG.43 Element without steps for first flight (plan)
FIG.44 Element with incorporated steps and landing for first flight (longitudinal section)
FIG.45 Element without steps for first flight (longitudinal section)
FIG.46 Element with incorporated steps and landings for second flight (plan)
FIG.47 Element without steps for second flight (plan)
FIG.48 Element with steps and landing for second flight (longitudinal section)
FIG.49 Element without steps for second flight (longitudinal section)
FIG.50 - Longitudinal sectional view of the stairs for out of the ground three-storey buildings
FIG.51-Cross section of the element with steps and landing FIG.42
FIG.52 Cross section of the element without steps FIG.43
FIG.53-Cross section of the element with steps and landing FIG.46
FIG.54- Cross section of the element without steps FIG.47
FIG.55- Cross section of the element for third flight with steps and landing
FIG.56- Cross section of the element for third flight without steps
FIG.57- Cross section of the element for fourth flight with steps and landing
FIG.58- Cross section of the element for fourth flight without steps
FIG.59- Cross section of the element of the last storey above FIG 57
FIG.60- Cross section of the element of the last storey above FIG.58
ELEMENTS FOR THREE-FLIGHT STAIRS WITH ELEVATOR SHAFT
[0011]
FIG.61 Element with first, second and third flight
FIG.62 Element without steps with landing, to be coupled with FIG.61
FIG.63 Element with fourth, fifth and sixth flight coupled with element FIG.62
FIG.64 Plan of the three-flight stairs with elevator shaft
FIG.65 Plan of the base of the elevator shaft
FIG.66 Section of the stairs FIG.64 with elevator shaft
FIG.67.Elements for elevator shaft
DESCRIPTION OF THE ELEMENTS WHICH COMPOSE THE SYSTEM
[0012] All of the elements are made of structural light concrete, composed of expanded clay
grains with different diameters, thoroughly washed sand and water in the correct ratio
in order to obtain concrete which is consistent, processable, compact and semi-impermeable.
[0013] An optimal structural light concrete composition could be:
Cement: Rck 425 375 Kg/mc
Sand: 0-3 mm 470 Kg/mc
Expanded clay: 0 3-8 mm 0,850 mc
Water: 160 1/mc
[0014] The absorbed water depends on the absorbing power of the expanded clay which can
be evaluated to be 50-60 1/mc
[0015] Metal formworks placed on vibrating surfaces or (depending on the type of elements)
formworks placed vertically - with vibrating devices on the walls if one wants smooth
and not float finished walls - are required for making the element.
FOUNDATION BEAMS
[0016] The foundation beams
FIG.1-FIG.2-FIG.3-FIG.4- are made of normal concrete with vibrated 3 ql/mc cement.
[0017] The size will be determined by the load incidence and the ground and subsurface resistance.
In order to illustrate this system these elements can for example have the following
dimensions: cm 50x50h with a cm 10x5 upper rectangular dap joint and groove-and-tongue
joint at the extremity (which changes according to the foundation height) which in
our case we hypothesize to be cm . 5-20-5. This element rests on an underpinning which
lays perfectly flat horizontally and which has an impression as wide as the foundation
beam. The element in section shows four holes on both the upper and lower parts; in
fact, no. 8 35x3 mm pipes with end flanges, which measure 60x8 mm, are buried in concrete
to allow the passing of the steel tie rods used for tightly consolidating the various
elements of the foundation. To consolidate the perpendicular elements, you have to
insert the steel tie rods either through the inside or outside holes. The steel tie
rods are composed of steel rods threaded at the end. The tightening will occur by
means of hexagon nuts which are very high.
[0018] The variable length of the elements is required to avoid that the joints of the panels
ever coincide with the joints o the foundations.
SELF-SUPPORTING PANELS MADE OF STRUCTURAL LIGHT CONCRETE
[0019] The panels (
FIG.1-FIG.2-FIG.3) have been designed for environments with an inside finished height of 2.70 meters
but can also be of a different height if needed.
[0020] The panel can have these measures: width 1.20 m, thickness 0.30 m, height 2.75 m
(slab substructure) plus a border with a height of 0.25 m or more (this depends on
the height of the slab) a width of 1.20 m and a thickness of 5 cm. which allows the
curb of the slab to be covered without any other additions. The same series can also
be without border.
[0021] If used in an earthquake zone, the panels, which are obviously reinforced, will have
stronger reinforcements depending on the seismicity of the area.
[0022] The panels
FIG.1,FIG.2,FIG.3, as you can see from the list of elements which compose the system, have different
dap joints to facilitate the coupling when there is an incompatibility problem of
the dap joint profile as per the windows and the doors. The coupling profiles are
slightly trapezoidal.
[0023] In order to face the problem of the openings, different elements are foreseen. The
panels
FIG.8,FIG.9 and
FIG.10 have dap joints for the lintels
FIG.11.and
FIG.12. These lintels have the same dap joint to the right and to the left with a width
of 10 cm and a length of 20 cm per side. On the upper part there is always a channel
of cm. 10x5 in depth to seat the profile beneath the slab curb, and the border as
for the panels in the case of the lintel of
FIG.11 .The lintel of
FIG.12 does not have the border because it will be used when a slab element with aggregate
for making a balcony
FIG.31 or
FIG.32 is used.
[0024] There is also the panel
FIG.13 for a 120 x 100h sill.
[0025] 35x3 mm. steel pipes with flanges at the ends are buried in all the panels for tie
rods passing. Every section of the panel has 4 pipes, two in the upper part in the
lintel area and two in the lower part one at 10 cm. from the base and the other at
70 cm. from the base.
[0026] There are other panels for the stability of the comers, of the tee joints and crossings,
that act as big pillars and facilitate the assembly from the start. These are the
angular panels
FIG.15, the T panel
FIG.16 and the perpendicular cross panel
FIG.17.
[0027] Some panels
FIG.18,FIG.19,FIG.20, have seatings for the passage of ducts, hydraulic and heating systems. They facilitate
the installation and also allow inspection in case of faults, if any.
THE PARTITION WALLS
[0028] The elements for building partitions are made of C.L. composed of expanded clays,
cement, and sand (with reinforcement for some types), properly plastered and gesso
finished. They can be easily stuccoed after the installation.
[0029] The elements are 8:
FIG.21 with groove-and-tongue joint,
FIG.22 half panel with groove-and-tongue joint,
FIG.23 T panel with springer for the lintels of the doors,
FIG.24 reduced panel for lintel springer,
FIG.25 lintel for door,
FIG.26 vertical masonry structures for door to be used in special cases,
FIG.27 panel with vertical masonry structure in the middle,
FIG.28 panel as
FIG.21 with openings for the passage of ducts.
[0030] It is obvious that the construction of a building with prefabricated elements cannot
be made using the same criterium used for conventional buildings, since in our case
everything must be planned respecting some priorities. The partitions must be constructed
at the same time of the supporting structures along the perimeter, so that when the
slabs are installed the partitions are complete being careful that the coplanarity
of the slab positioning plane is respected.
THE SLAB
[0031] The element of the slab, which is part of the system, is composed of a beam, which
is 1.20 m wide, 25 cm. high, or higher when the calculation requires it, and of an
element, which is 0.60 m. wide. Since these elements have an incorporated curb and
the panels are 1.20 m. wide, the joints of the panels will not correspond with the
joints of the slab elements and therefore the continuity of the vertical lines is
interrupted when you compose the slab. The elements of the slab can therefore have
either incorporated curbs or only the reinforcements corresponding to the curbs which
can in this case be made at site. The length can change according to the design with
e 4 to 6 meters span if with only one span. If it has two spans the first span will
be 5 to 6 meters and the second span from 4 to 5 meters.
[0032] In the section it shows 6 plastic pipes with a diameter of 120 - 140 mm or thin steel
pipes with a diameter of 120 mm. They allow the passage of household ducts and of
air conditioning ducts if required. Longitudinally it has male-female profiles,
FIG.36, made of 2 - 2.5 mm steel sheet metal that allows the elements to be placed very
closely. They will then be consolidated by intermittent welds which are 5 cm long
and at 40 - 50 cm. from one another.
[0033] The longitudinal reinforcements made with steel rods with a diameter of 8, 10 mm,
will be made according to the span and the capacity and will be consolidated one to
the other by means of perpendicular bracketings.
[0034] These elements have 6 more holes on the longitudinal side with pipes to allow the
passage of the 20 to 24 mm steel tie rods. The extremities of the tie rods are threaded
so as to allow the use of long nuts to compact the elements. These tie rods strengthen
the slabs and cooperate in the distribution of the loads. Also the joint profiles
FIG.36 cooperate in the distribution of the loads. Any type of floor, to be anchored using
products available on the market, can be installed on the slab surface.
[0035] Beneath the slab, the profiles
FIG.36 are not visible because their lower wing is buried in mix to facilitate the plastering.
The elements can be already plastered and only the stuccoing of the ceiling will be
required in this case.
THE COVERING
[0036] The covering can be of the terrace- or roof-type. If the design foresees a terrace
type of covering, the same slabs will be used with insulating layers, waterproof mantles,
slab leveling layer with normal slope if required, to be installed at site and which
must be suitable for the installation of elements that can be stepped on.
[0037] Two elements have been studied for a roof type of covering:
FIG.77 and
FIG.78 with sloping planes already equipped with insulation and tiles of any type being
careful that mobile elements can be positioned in the joints between the elements:
these mobile elements will be fixed, at the site, above the tiles near the joints.
A waterproof and elastic rubber cement will be put between one element and the other:
this rubber cement must not be damaged by temperature variation.
[0038] These elements also bear the holes of the passage of the tie rods.
STAIRS
[0039] Also the stairs with or without elevator are inserted in the system in the view of
total prefabrication. This prefabricated system foresees two- and three-flight stairs
with or without elevator shaft depending on the height of the building, and two-flight
stairs with gallery and elevator if there are 4 apartments per storey (floor). The
stairs form an integral part of the system. The two-flight stairs per floor, illustrated
in the
FIG.41 plan, is composed of one element with incorporated steps and landing for the first
flight
FIG.42 (Plan)
FIG.44 (Longitudinal section),
FIG.51 (Cross section), of one element without steps for first flight
FIG.43 (Plan)
FIG.45 (Longitudinal section),
FIG.52 (Cross section), of one element with incorporated steps and landing for the second
flight
FIG.46 (Plan)
FIG.48 (Longitudinal section),
FIG.53 (Cross section), and of one element without steps for second flight
FIG.47(Plan),
FIG.49 (Longitudinal section),
FIG.54 (Cross section). The elements with steps and the adjacent ones without steps are
consolidated by tie rods that also consolidate the landings of the following flights,
i.e. the top landing of the first flight will be consolidated with the bottom landing
of the second flight.
[0040] The third flight
FIG.55, has a bottom landing to be consolidated with the top landing of the second flight
and a top landing to be consolidated with the bottom landing of the fourth landing
FIG.57.
FIG.50 shows the longitudinal section of two-flight stairs in a three-storey building.
THREE-FLIGHT STAIRS
[0041] The three-flight stairs with elevator shaft are composed of one element
FIG.61 with first, second and third flight and intermediate landings, of element
FIG.62 without steps and landings on the ground and first floors. These two elements are
consolidated one with the other by means of tie rods which pass through flanged pipes.
The last step of the third flight is housed in the seat of landing in
FIG.62 where the seat for the first step of the fourth flight is also located. The element
FIG.68 (cross section) with fourth, fifth and sixth flight with intermediate landings and
following flights, element
FIG.70 without steps with landing for the second floor and following.
[0042] This type of stairs is arranged with an elevator pit which is composed of two elements
that are the subgrade
FIG.65 and the concrete pit element
FIG.67
1. System of prefabricated elements for the construction of buildings, characterized
by a vertical structure composed of panels made of structural light cement which in
turn is made of expanded clay, high resistance cement and sand in the right proportions.
2. System of prefabricated elements as per claim no. 1, characterized by panels having
groove-and-tongue joints, female-female dap joints, male-male dap joints, all slightly
trapezoidal
3. System of prefabricated elements as per claim nos. 1 and 2, characterized by the fact
that the upper part of the panels is equipped with a border which is required in order
to cover the incorporated or made at site curb.
4. System of prefabricated elements as per claim nos. 1, 2, 3 characterized by the fact
that there are three panels, with seatings for lintel, for making the window. One
panel has the seating to the right, one to the left while the third panel has a seating
to the right and one to the left.
5. System of prefabricated elements as per claim nos. 1, 2, 3, 4 characterized by the
fact of having panels with the seating for WP and systems piping that can be easily
inspected.
6. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5 characterized by
the fact of having three different types of panels for making wall knot. The panels
are the following: angular panel, T panel and cross panel.
7. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, characterized
by the fact that all of the elements (panels, window sills, lintels) have flanged
pipes buried into them which are needed for the passage of the tie rods that consolidate
the panels.
8. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7 characterized
by the fact that the slab (horizontal structure) is composed of elements having one
or two spans. The slab has the following characteristics: it is made of structural
light mix as the panels; it has PVC or thin steel sheet metal pipes buried into it;
it has male and female longitudinal metal profiles which can be put close together
and welded; it has a reinforcement that varies according to the load.
9. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, characterized
by the fact that the elements of the slab can have an incorporated curb.
10. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, characterized
by the fact of having a two-flight stair composed of 4 elements, two with incorporated
steps and two without steps, for the ground floor and 4 elements, two with incorporated
steps and two without steps, for the first and following floors.
11. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, 10,
characterized by the fact that three-flight stairs with elevator shaft are used for
prefabricated buildings with three or more storeys. These stairs are composed of 4
elements: one with three flights on the ground floor; one with landing; one with three
flights from the first floor and following floors; one with only one landing from
the first floor and following floors.
12. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, 10 11,
characterized by the fact of having sloping pitch covering elements which are already
equipped with insulation and elements such as tiles of any type.
13. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, 10,
11, 12, characterized by the fact that the covering elements have flanged steel pipes
for the passage of tie rods buried into them crosswise.
14. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, 10,
11, 12, characterized by the fact that the panels can be surface finished in any way
(baked bricks or different type, mosaic finish, plastering, etc.) before installation.
15. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, 10,
11, 12, 13,14, characterized by the fact of having linear, angular, T-shaped and cross-shaped
foundation elements which can be coupled with one another by means of a coupling profile
with rectangular section.
16. System of prefabricated elements as per claim nos. 1, 2, 3, 4, 5, 6, 7, 8, 9, 10,
11, 12, 13, 14, 15, characterized by the fact that the foundation elements have 8
steel pipes buried into them for the passage of the tie rods needed for consolidating
the foundation elements.