[0001] The present invention relates generally to metal refining, and more specifically,
to consumable ingot electrodes therein.
[0002] Consumable ingot electrodes are used in various metallurgical processes for controlling
metallurgical properties. For example, in vacuum arc remelting (VAR), a consumable
electrode is lowered into a crucible maintained under vacuum for controlling the melting
thereof. In electroslag remelting or refining (ESR), a consumable electrode is lowered
into a crucible, which may have a gas environment, for electrical resistance heating
and melting in a corresponding slag for refining the electrode material.
[0003] In both embodiments, it is desirable to measure the changing weight of the electrode
as it is consumed for in turn controlling corresponding process parameters. This is
typically accomplished by using a loadcell system which supports not only the electrode
itself, but also the lowering mechanism attached thereto. Accordingly, the weight
of the electrode itself is determined after subtracting extraneous loads measured
by the loadcell corresponding with the various equipment attached to the electrode.
[0004] For example, portions of the lowering equipment are necessarily attached to the electrode
and move therewith. This may include a hydraulic ram, or ball screw, or both. Various
hoses may be also attached to the lowering mechanism for providing cooling water or
inert gas. And, since the crucible typically defines a pressure vessel maintained
under vacuum or under gas pressure, suitable seals must be provided between the lowering
mechanism and the access port at the top of the crucible over which a substantial
pressure difference is maintained. This pressure drop is variable during operation
and introduces a variable additional force measured by the loadcell which must be
removed in determining the actual weight of the electrode itself.
[0005] An improved form of electroslag refining is disclosed in U.S. Patent 5,160,532-Benz
et al in which a circumferentially segmented, cold induction guide (CIG) is disposed
at the bottom of the electroslag crucible, and includes a drain orifice through which
the refined melt may be drained for further use. For example, the melt may be discharged
through a gas atomizer for spray forming the melt atop a suitable preform.
[0006] It is desirable to accurately control both the drain rate from the crucible for spray
forming the preform, as well as controlling the melt rate of the electrode as it is
consumed during the electroslag refining process. However, the typical loadcell weighing
systems described above necessarily introduce extraneous measured loads in addition
to the weight of the electrode itself which requires various corrections for isolating
solely the electrode weight.
[0007] Accordingly, it is desired to provide an improved electrode weighing mechanism which
reduces or eliminates extraneous loads in weighing the electrode.
[0008] A consumable electrode is suspended by a stub. The stub includes upper and lower
hangers between which is vertically mounted a loadcell for weighing the electrode
attached to the lower hanger. An electrical conductor is joined between the upper
and lower hangers for carrying electrical current therebetween to power the electrode
without damaging the loadcell.
[0009] The invention, in accordance with preferred and exemplary embodiments, together with
further objects and advantages thereof, is more particularly described in the following
detailed description taken in conjunction with the accompanying drawings in which:
Figure 1 is a schematic representation of an electroslag refining apparatus including
an electrode weighing stub in accordance with an exemplary embodiment of the present
invention.
Figure 2 is an exploded view of the electrode weighing stub illustrated in Figure
1 in accordance with an exemplary embodiment of the present invention.
Figure 3 is a partly sectional, elevational view of the stub illustrated in Figures
1 and 2.
Figure 4 is a horizontal sectional view through the weighing stub illustrated in Figure
3 and taken along line 4-4.
[0010] Illustrated schematically in Figure 1 is an electroslag refining apparatus 10 including
an electrode weighing mechanism or stub 12 in accordance with an exemplary embodiment
of the present invention. The stub 12 is configured for directly weighing a consumable
ingot electrode 14 in situ during the electroslag refining thereof as it is consumed
from its lower tip end which decreases its length and weight.
[0011] But for the stub 12 itself, the electroslag refining apparatus 10 may have any conventional
configuration and operation such as that disclosed in U.S. Patent 5,160,532. For example,
the apparatus 10 includes a water-cooled copper crucible 16 which defines a pressure
vessel in which is provided under suitable pressure an inert gas 18 such as argon
from a suitable gas supply 20. Disposed at the bottom of crucible 16 is a water-cooled,
induction heated, circumferentially segmented, guide 22 having a center drain 24 therein.
One or more induction heaters 26 in the form of hollow, water-cooled coils surround
the lower end of the guide and the drain and are electrically powered by a power supply
28.
[0012] The electrode is attached to the lower end of the stub 12. An elevator 30 has a vertically
translatable output rod 32 which extends through a suitable seal in the top of the
crucible and is removably fixedly joined to the top of the stub 12 for lowering and
raising the electrode 14 as required during the electroslag refining process.
[0013] The electrode 14 is joined to a power supply 34 through one or more electrical leads
joined to the output rod 32 for carrying electrical current through the stub 12 to
the electrode 14. A suitable slag is disposed in the bottom of the crucible and is
electrically resistively heated by current flow from the electrode 14 into the crucible
16 which is also joined to the power supply 34 by another electrical lead.
[0014] During operation, the slag in the crucible is heated by resistance heating thereof
which in turn melts the lower, tip end of the electrode 14, with the melt therefrom
being refined by the liquid slag as it drops by gravity to the bottom of the crucible
atop the guide 22. The molten slag floats atop the refined ingot melt, and corresponding
solidified skulls are formed along the inner surface of the crucible and guide for
maintaining the purity of the refined melt during operation. The melt is drained from
the orifice 24 by controlling the induction heating thereof by the surrounding induction
heater 26, and therefore skull thickness, with the melt being discharged through a
gas atomizer 36 which sprays the melt atop a preform 38 for building thereatop successive
layers of the refined melt which solidify thereon.
[0015] As the electrode 14 is consumed during operation, its weight correspondingly decreases.
Accordingly, by weighing the electrode in situ inside the crucible 16 during the electroslag
refining process, that weight may be used in precisely controlling the entire refining
process, including the discharge flowrate of the melt from the drain 24 in the subsequent
spray forming operation.
[0016] In accordance with the present invention as initially illustrated in Figure 1, the
stub 12 is an assembly of components sized and configured to fit within the crucible
for directly weighing the electrode 14 during operation as it is consumed. The weighing
stub 12 also provides an electrical current path to the electrode 14 for the large
electrical current flow required for electrical resistance heating of the molten slag
for melting the electrode tip.
[0017] The stub 12 is illustrated in more detail in exploded view in Figure 2. The stub
includes an upper head or hanger 40, and lower head or hanger 42 disposed vertically
below the upper hanger and configured for fixedly suspending the electrode 14. A loadcell
44 is mounted vertically between the upper and lower hangers for weighing the electrode
attached to the lower hanger during operation.
[0018] The loadcell 44 may have any conventional form such as the S-configuration illustrated
in Figure 2 for measuring the amount of vertically directed load between its upper
and lower legs. The S-configuration provides a middle leg which undergoes bending
upon application of vertical tensile loads across the loadcell, with the bending stress
being measured by strain gages thereon which are electrically joined to a remote weighing
scale 45 in the preferred form of a suitable electrical circuit. An exemplary loadcell
is commercially available from Hardy Instruments, of San Diego, California under model
No. HI LPT5K.
[0019] At least one, and preferably several electrical conductors 46 are fixedly joined
between the upper and lower hangers for carrying electrical current therebetween to
power the electrode during operation, while bypassing the loadcell 44 for preventing
damage thereto.
[0020] In the preferred embodiment illustrated in Figures 2 and 3, the loadcell is pivotally
joined to both the upper and lower hangers for preventing undesirable bending moments
across the loadcell so that it may be disposed primarily under tensile loads between
the upper and lower hangers. This is done by using a pair of coaxial upper and lower
bolts 48,50 which threadingly engage the corresponding upper and lower legs of the
loadcell 44.
[0021] In the exemplary embodiment illustrated in Figure 3, the upper hanger 40 is in the
form of an annular copper plate or disk and includes a vertical center trunnion 52
extending integrally upwardly therefrom for lifting the stub and attached electrode.
The outer configuration of the trunnion 52 may have any conventional form for engaging
a complementary socket in the lower end of the elevator rod 32 illustrated in Figure
2 for providing a removable connection thereat. With the trunnion engaging the elevator
rod 32, the entire stub and electrode may be lowered or lifted as desired by the elevator.
[0022] As shown in Figures 2 and 3, the lower hanger 42 is preferably a solid rod having
a lower end defining a weld prep 54 configured for welding the electrode 14 thereto
at a suitable weld bead 56. The lower hanger 42 is preferably formed of stainless
steel for both its electrical conductivity and its ability to be repeatedly welded
in turn to a series of electrodes 14 as they are consumed and then removed from the
lower hanger 42 by grinding away the previous weld bead 56.
[0023] As shown in Figure 3, the upper bolt 48 extends downwardly through the trunnion 52
and is pivotally joined or seated therein in a spherical bearing 58 mounted in a corresponding
spherical seat. The head of the upper bolt 48 is preferably recessed in a counterbore
in the top of the trunnion 52, and the lower, distal end of the upper bolt threadingly
engages the upper leg of the loadcell 44 to fixedly join the loadcell to the upper
hanger 40 with pivotal capability.
[0024] Correspondingly, the lower bolt 50 extends upwardly from the lower hanger 42 and
is pivotally joined or seated therein in an identical spherical bearing 58. The head
of the lower bolt 50 is therefore fixedly joined to the lower hanger with pivotal
capability, and the upper, distal end of the lower bolt threadingly engages the lower
leg of the loadcell 44 coaxially with the upper bolt. In this way, the loadcell 44
is pivotally joined at its opposite upper and lower legs to the corresponding upper
and lower hangers.
[0025] The weight of the electrode 14 is directly carried by the lower hanger 42 and in
turn through the single lower bolt 50 into the loadcell 44, which in turn is suspended
to the upper hanger 40 by the single upper bolt 48. In this way, the loadcell 44 is
directly mounted to the electrode through the lower hanger 42 and directly measures
the weight of the electrode 14, except for the intervening components supported by
the lower bolt 50 whose weight is a constant which may be suitably removed from the
total weight detected by the loadcell.
[0026] As initially shown in Figure 2, the weighing stub 12 preferably also includes an
upper shield or case 60 fixedly joined to and extending below the upper hanger 40.
The upper case is preferably arcuate or semi-tubular, and formed of copper for providing
a low resistance electrical conducting path from the copper upper hanger and trunnion.
[0027] Correspondingly, a lower case 62 is fixedly joined to the lower hanger 42 and extends
upwardly therefrom and adjacent to the upper case 60. The lower case 62 is also preferably
arcuate or semi-tubular and is complementary with the upper case 60 for collectively
surrounding the loadcell 44. The lower case 62 adjoins the upper case 60 coaxially
therewith and is separated therefrom by a gap 64 extending vertically and horizontally
therebetween in opposite pairs to collectively define a segmented tubular enclosure
around the loadcell.
[0028] The tubular or cylindrical cases 60,62 not only surround the loadcell 44 for protection
thereof, but also define integral extensions of the upper and lower hangers, respectively
for carrying the high electrical current required for powering the electrode 14. Like
the upper case 60, the lower case 62 is also preferably copper having low electrical
resistance, and both provide relatively large cross sectional areas for carrying current
with the respective hangers.
[0029] As shown in Figures 3 and 4, a plurality of the electrical conductors 46 are preferably
fixedly joined at opposite ends thereof to the respective upper and lower cases 60,62
for carrying the electrical current therebetween. Each conductor 46 is preferably
flexible in its lateral direction by being formed of a plurality of thin gauge copper
wires braided together. The opposite ends of the conductors 46 may be suitably clamped
to the corresponding casings using a bus bar and several mounting bolts as desired.
[0030] The several conductors 46 are preferably disposed circumferentially between the upper
and lower cases across the two vertical portions of the gap 64 to carry the substantial
electrical current from the upper hanger 40 to the lower hanger 42 and in turn to
the electrode 14 welded to the lower hanger. The electrical current is supplied to
the stub 12 through the elevator rod 32 and its connection to the trunnion 52 in a
continuous and relatively large cross sectional area current path.
[0031] The lateral flexibility of the conductors 46 allows relatively free vertical movement
between the upper and lower hangers for reducing or eliminating weighing errors during
operation. This may be simply effected by calibrating the loadcell 44 after complete
assembly of the stub 12 to a zero initial weight without the attached electrode 14,
or to the actual weight of the electrode 14 when attached.
[0032] The bifurcated construction of the upper and lower hangers 40,42 and their attached
cases 60,62 allows the direct mounting of the loadcell 44 vertically therebetween
for more accurately weighing the electrode 14 as it is consumed during operation.
The pivoted upper and lower bolts further protect the loadcell from undesirable bending
moments which may occur upon lateral movement of the electrode 14 as it is transported
and moved during operation.
[0033] It is also desirable to further protect the loadcell 44 against excess tension loads
therein which might occur, for example, in the event the electrode 14 sticks during
operation as the elevator attempts to raise the electrode. Accordingly, the loadcell
44 illustrated in Figure 3 forms part of a primary loadpath between the upper and
lower hangers, and a secondary loadpath is provided in parallel with the primary loadpath
with a predetermined amount of backlash sized to supplant the primary loadpath upon
excess load on the lower hanger.
[0034] More specifically, the primary loadpath preferably also includes a steel mounting
block 66 fixedly joined atop the lower hanger 42 as illustrated in Figure 3, such
as being bolted thereto. A cooperating steel mounting plate 68 is disposed in abutment
atop the mounting block 66. The mounting plate 68 includes a central aperture in which
the lower bearing 58 is mounted on the under surface thereof, with the head of the
lower bolt 50 being disposed in a corresponding recess in the upper surface of the
mounting block 66.
[0035] A plurality of compression springs 70, such as the four illustrated in Figures 2-4,
are disposed atop the four comers of the mounting plate symmetrically about the lower
bolt 50 disposed therebetween. A plurality of primary mounting bolts 72 extend through
respective ones of the springs 70, and extend freely through corresponding apertures
in the mounting plate 68. The heads of the bolts sit atop washers on the respective
springs, with their lower distal ends being threadingly engaged in the mounting block
66 for clamping the mounting plate in abutment atop the mounting block 66 which extends
upwardly from the lower hanger 42.
[0036] In order to protect the loadcell 44 from the high electrical current carried through
the upper and lower hangers, the upper and lower bolts 48,50 as illustrated in Figure
3 are preferably electrically insulated from the corresponding upper and lower hangers
40,42. In one embodiment, an electrically insulating washer 74 is disposed in the
counterbore at the top of the trunnion 52 for supporting the seat of the spherical
bearing 58. In this way, the electrical path from the trunnion 52 to the upper bolt
48 is interrupted.
[0037] Correspondingly, additionally electrically insulating washers 76 are disposed between
the bottom of the springs 70 and the top of the mounting plate 68 as illustrated in
Figure 3, with an electrically insulating pad 78 being disposed between the mounting
plate 68 and the mounting block 66 to interrupt the electrical path therebetween.
[0038] In this way, the primary loadpath between the upper and lower hangers includes in
sequence the upper bolt 48, the loadcell 44, the lower bolt 50, the mounting plate
68, the coil springs 70, the primary bolts 72, and the mounting block 66. The coil
springs 70 are preferably sized for collectively carrying the intended weight of the
electrode 14 with little if any additional compression thereof.
[0039] In the event the electrode 14 sticks to the crucible during operation and the elevator
attempts to raise the stub 12, the four springs will experience a load increase and
further compression that will unseat the bottom of the pad 78 from the top of the
mounting block 66 as represented by a vertical relief gap A therebetween shown in
phantom in figure 3. As the springs 70 compress in response to a vertical load exceeding
the weight of the electrode 14 itself, that load is nevertheless still carried by
the loadcell 44 and opens the relief gap A.
[0040] Since the loadcell 44 has a predetermined load limit, it is undesirable to exceed
that limit Accordingly, the secondary loadpath is configured to bypass the primary
loadpath upon excess vertical load through the springs and loadcell, and includes
a plurality of secondary mounting bolts 80 shown in Figures 2-4. The secondary bolts
are arranged in a symmetrical group of four corresponding to the four primary bolts
72. They extend downwardly through corresponding counterbores and apertures in the
upper hanger 40, and have lower distal ends threadingly engaging the mounting block
66 to fixedly attach the secondary bolts thereto.
[0041] Each of the secondary bolts includes an upper enlarged head spaced vertically atop
a corresponding seat in the upper hanger to define a predetermined gap or backlash
B. The backlash between the secondary bolts 80 and the upper hanger 40 is selected
to allow limited additional compression of the springs 70 as vertical loads through
the primary bolts 72 collectively exceed the desired limit for the loadcell 44 and
opens the relief gap A.
[0042] As the mounting block 66 and pad 78 separate during excess compression of the springs
70, the secondary bolts 80 are correspondingly lowered in the upper hanger until the
backlash is depleted and the heads of the secondary bolts contact their respective
seats therein. At this point, the excess vertical loads from the mounting block 66
are carried instead through the four secondary bolts 80 directly into the upper hanger
40 bypassing the four primary bolts and the loadcell 44.
[0043] The loadcell 44 is therefore mounted between the upper and lower hangers for accurately
measuring the weight of the suspended electrode 14, yet vertical loads in excess of
the electrode weight may be bypassed through the secondary bolts 80 directly to the
upper hanger for preventing excess loads through the loadcell and preventing damage
thereto.
[0044] The secondary bolts 80 also provide a convenient manner for locking together the
upper and lower hangers when desired during assembly of the electrode thereto and
prior to insertion of the electrode into the crucible. This may be effected by providing
a corresponding plurality of locking tubes or sleeves 82 around each of the respective
secondary bolts 80 and sized in length to match the available height between the bottom
of the upper hanger and the top of the mounting block when the mounting plate 68 and
its underlying pad 78 are seated in abutment against the top of the mounting block.
[0045] The secondary bolts 80 may then be screwed down when desired so that the heads thereof
engage their seats in the upper hanger to clamp together the upper and lower hangers
on the sleeves 82 to bypass the loadcell 44. The locked down secondary bolts 80 prevent
relative vertical movement between the upper and lower hangers and thusly lock together
the two hangers in a rigid assembly during assembly and transport of the stub and
electrode prior to final assembly inside the crucible. The secondary bolts 80 may
then be partially unscrewed to the desired backlash clearance B prior to electroslag
refining so that the loadcell may then be used for accurately measuring the weight
of the electrode 14 as it is consumed.
[0046] As shown in Figure 3, the stub 12 preferably also includes means in the form of a
gas inlet 84 disposed in flow communication with the gas supply 20, or other suitable
source, for providing a coolant, such as the argon gas, inside the upper and lower
cases 60,62 for cooling the loadcell, with the spent gas being discharged through
the vertical and horizontal portions of the gap 64.
[0047] As indicated above, the loadcell 44 is protected both mechanically and electrically
inside the two cases 60,62 and vertically between the two hangers 40,42. The electrical
conductors 46 provide a larger-area current path for the high currents required for
electroslag refining which bypass the electrically insulated loadcell 44. Since heat
is nevertheless a byproduct of the electroslag refining process, the coolant channeled
through the stub effectively cools the loadcell for ensuring a useful life thereof
while maintaining weighing accuracy during operation.
[0048] The primary loadpath through the loadcell, including the spherically mounted bolts
48,50, ensures tensile loading of the loadcell without undesirable bending moments
therein. And, the secondary loadpath provided by the bolts 80 protect the loadcell
from excessive vertical loads therethrough, as well as provides a failsafe or backup
loadpath in the event of separation failure of the loadcell itself.
[0049] Since the loadcell 44 is directly mounted between the upper and lower hangers immediately
adjacent to the electrode 14, it is effective for providing substantially more accurate
weight measurement of the electrode 14 as it is consumed during operation without
undesirable additional loads therethrough which would otherwise require compensation.
[0050] The weighing stub 12 therefore provides a mechanical connection to the electrode
14 for suspending the electrode from the elevator rod 32, while carrying the substantially
high electrical current through the stub to the electrode as required for electroslag
refining. In this configuration, the loadcell does not weigh any other component above
the stub including any portions of the elevator 30 or its output rod 32. Nor, is the
weighing stub 12 subject to measuring errors due to differential pressure between
the inside and outside of the crucible 16.
1. A stub 12 for suspending a consumable electrode 14 inside a crucible 16 comprising:
an upper hanger 40;
a lower hanger 42 for fixedly suspending said electrode;
a loadcell 44 mounted vertically between said upper and lower hangers for weighing
said electrode; and
an electrical conductor 46 joined between said upper and lower hangers for carrying
electrical current therebetween to power said electrode.
2. A stub according to claim 1 wherein said loadcell 44 is pivotally joined to both said
upper and lower hangers 40,42.
3. A stub according to claim 2 further comprising:
an upper case 60 fixedly joined to said upper hanger 40;
a lower case 62 fixedly joined to said lower hanger 42 adjacent said upper case, and
being complementary therewith for collectively surrounding said loadcell; and
said conductor 46 is joined at opposite ends thereof to said upper and lower cases
for carrying said electrical current therebetween.
4. A stub according to claim 3 further comprising a primary loadpath, including said
loadcell 44, between said upper and lower hangers 40,42, and a secondary loadpath
therebetween having backlash sized to supplant said primary loadpath upon excess load
on said lower hanger.
5. A stub according to claim 4 wherein:
said upper hanger 40 includes a vertical trunnion 52 extending upwardly therefrom
for lifting said stub 12 and attached electrode 14; and
said lower hanger 42 includes a weld prep 54 therebelow for welding said electrode
thereto.
6. A stub according to claim 5 further comprising:
an upper bolt 48 extending downwardly through said trunnion 52 and pivotally seated
therein, and fixedly joined to said loadcell; and
a lower bolt 50 extending upwardly from said lower hanger 42 and pivotally seated
therein, and fixedly joined to said loadcell coaxially with said upper bolt for pivotally
joining said loadcell to both said upper and lower hangers.
7. A stub according to claim 6 wherein said upper bolt 48 is electrically insulated from
said upper hanger 40, and said lower bolt 50 is electrically insulated from said lower
hanger 42.
8. A stub according to claim 4 wherein:
said upper case 60 is arcuate;
said lower case 62 is arcuate and adjoins said upper case at a gap 64 therebetween
to collectively define a segmented tubular enclosure around said loadcell; and
said conductor 46 is flexible and disposed circumferentially between said upper and
lower cases across said gap.
9. A stub according to claim 4 wherein said primary loadpath comprises:
a mounting plate 68 disposed atop said lower hanger 42, and pivotally joined to said
loadcell;
a plurality of springs 70 disposed atop said mounting plate; and
a plurality of mounting bolts 72 extending through respective ones of said springs
and said mounting plate, and fixedly joined to said lower hanger 42 for clamping said
mounting plate in abutment atop said lower hanger.
10. A stub according to claim 9 wherein said secondary loadpath comprises:
a plurality of secondary bolts 80 extending through said upper hanger 40 and fixedly
joined to said lower hanger; and
each of said secondary bolts includes a head spaced vertically atop a corresponding
seat in said upper hanger to define said backlash.
11. A stub according to claim 10 further comprising a sleeve 82 surrounding each of said
secondary bolts 80 between said upper and lower hangers.
12. A stub according to claim 10 further comprising a mounting block 66 fixedly joined
atop said lower hanger 42, and said mounting plate 68 is clamped thereatop.
13. A stub according to claim 12 further comprising an electrical insulating pad 78 disposed
between said mounting plate 68 and said mounting block 66.
14. A stub according to claim 10 further comprising means 84 for channeling a coolant
inside said upper and lower cases 60,62 for cooling said loadcell.