[0001] The invention relates to a load bearing structure for railways comprising ballast
and a coagulant for binding the ballast to form a cohesive mass.
[0002] As is generally well known, rail systems typically comprise a track supported on
a ballast bed together with various trackside equipment such as signals, location
boxes, trackside buildings and the like. Typically various communication cables will
run buried underground adjacent to the tracks. As such communication cables are vital
to running the railway, before any digging can be carried out a CAT scan is required
to see if there is a cable present which might be damaged. The industry standard requires
that a fresh CAT scan be made every 15cm of depth, so that several separate scans
are required at each location.
[0003] The most commonly used system for installing signals and other trackside equipment
involves building solid foundations using pre-cast concrete, which is sectionalised
and assembled on site and then pouring concrete prepared on site onto this pre-cast
concrete. Whilst this approach has proved satisfactory over many decades, it is slow
as it requires a great deal of manpower and expensive as it can also cause disruption
to railway operations. A return visit must be made to complete the installation once
the concrete has cured after 7 to 14 days.
[0004] Various alternative proposals have been made involving the use of special preformed
substructures but these are impractical for most existing rail systems on cost grounds
alone and only really suitable for new routes.
[0005] The present invention seeks to provide a load bearing structure and a method for
making this, which is quicker and cheaper to install than the presently used methods.
[0006] According to the invention there is provided a load bearing structure for railways
comprising ballast and a coagulant adapted to bind the ballast, wherein the coagulant
is an elastomeric dispersion, which dispersion is added to the ballast in situ, such
that the ballast and coagulant form a cohesive mass.
[0007] In a preferred embodiment, the coagulant is added to ballast adjacent to a railway
track. In an alternative embodiment, the coagulant is added to the ballast in the
region of a set of points. The cohesive mass preferably has a load bearing capacity
of 0.5 tons per square foot or more. Preferably the coagulant is a polyurethane foam.
[0008] The invention provides the advantage over the known solutions that it is quick and
easy to install as the coagulant can cure typically in less than 30 minutes. As the
ballast can be poured over the existing trackside, if it is not already present, the
need to dig foundations and hence carry out CAT scans is obviated. By overcoming the
requirement to dig conventional foundations, it also becomes possible to install new
signals in places where previously land owners permission would have been required.
[0009] Exemplary embodiments of the invention will now be described in greater detail with
reference to the drawings in which:
Figure 1 shows a typical layout for trackside equipment;
Figure 2a shows a schematic longitudinal cross-section through a part of a railway
track bed for jointed track;
Figure 2b shows a schematic longitudinal cross-section through a part of a railway
track bed for a continuous rail track;
Figure 3 shows a schematic plan view of a part of railway track;
Figure 4 shows a schematic plan view of a set of points;
[0010] Figure 1 shows a pair of rails 1,2 supported on a sleeper 2 on a ballast bed 3. Adjacent
to the track at a typical distance of 2 m are a plurality of handrails separating
the trackside equipment from the rails. Adjacent to the rails on the side remote from
the track is shown by way of example some cable routing 4, location case 5 on a firm
standage 6 and a signal 7. In general the standage will be made from a combination
of pre-cast concrete and site poured concrete as outlined above.
[0011] Figure 2a and 2b show a schematic longitudinal cross-section through a track bed
for a jointed rail and a continuous rail respective. The standard ballast 10 arrangement
for each type of bed is shown in solid profile. According to an aspect of the invention,
additional ballast 11 is the spread adjacent to the conventional ballast 10, which
is protected by shutters 12 and 13. In figure 2a this is shown as having a level which
is substantially parallel to the conventional track bed, whereas in figure 2b, it
is slightly below the raised edge of the ballast. The amount of additional ballast
used is dependent on the requirements of the trackside equipment to be supported but
in general no excavations will be necessary.
[0012] A coagulant, such as polyurethane foam, is then poured over the additional ballast
11 in the area to form the load bearing structure. In an exemplary embodiment, about
25kg of polyurethane is poured over an area of 4 square feet, to a depth of 2 feet
such as would used to support a signal. The polyurethane has a curing time of about
one hour, so that the signal can be installed shortly after the load bearing structure
has been prepared and formed. Although polyurethane has shown to be suitable, any
coagulating foam, which when combined with the ballast achieves a load bearing capacity
of in the region of ½ ton per square foot would be suitable. Once the load bearing
structure has cured the shutters 12 and 13 can be removed for re-use if necessary.
[0013] Although it is possible to have the load bearing structure separate from the conventional
ballast 10, it is preferable to have the structure linked to the original ballast
track 10. In its simplest form this can be achieved simply by pouring the coagulant
foam over the original ballast 10 as well as the additional ballast 11.
[0014] Figure 3 shows a particularly preferred embodiment of the load bearing structure
for supporting a signal in which first and second cantilevers 20, 21 are fixed to
sleepers 22,23. The first and second cantilevers 20, 21 meet a point remote from the
original track bed. The space between and around the cantilevers is covered with additional
ballast and then coagulant is poured over the additional ballast to form the load
bearing structure. The signal is then installed at the point where the cantilevers
meet. In an alternative embodiment, a single cantilever extending parallel from a
sleeper could be used. This particular embodiment has the additional advantage that
the track will be stabilised by the load bearing structure.
[0015] Figure 4 shows a schematic plan view of a set of points 30 on a bed of ballast. A
particular problem with points on curved section of track is that the momentum of
the train will tend to try to bend the track straight leading to slight warping of
the rails. Over time this leads to a points failure as the points are gradually shifted
out of position with respect to the other rails. Coagulant foam is poured over the
ballast in the region of points and allowed to cure. Due to the elasticity provided
by the elastomeric polyurethane coagulant, the track will be stabilised and the load
bearing structure will provide a damping effect on vibrations and any rail movements.
To minimise the drainage problems that the coagulant will cause, a small channel can
be left in the centre of the ballast bed so that water can drain away.
[0016] Suitable polyurethane foams include foams formed from a mixture of polyether polyols
and polyether/polyester polyols using amine catalysts, such as those sold under the
Eviromould and Envirofoam trade marks. Other possible foams include diphenylmethane
diisocyanate based foams.
[0017] Although the structure has been described as suitable for providing support for railway
trackside equipment, it is envisaged that the structure could also be used for certain
conventional building foundations. In a further application the structure can act
as a vibration dampener for certain bridge and gantry foundation systems, in particular
for metal beam type structures.
1. A load bearing structure for railways comprising ballast and a coagulant adapted to
bind the ballast, wherein the coagulant is an elastomeric dispersion, which dispersion
is added to the ballast in situ, such that the ballast and coagulant form a cohesive
mass.
2. A load bearing structure according to Claim 1, wherein the coagulant is added to ballast
adjacent to a railway track.
3. A load bearing structure according to Claim 1, wherein the coagulant is added to the
ballast in the region of a set of points.
4. A load bearing structure according to any one of Claims 1 to 3, wherein the cohesive
mass has a load bearing capacity of 0.5 tons per square foot or more.
5. A load bearing structure according to any one of Claims 1 to 4, wherein the coagulant
is a polyurethane foam.