Background of the Invention
[0001] This invention relates generally to a jigging system for work pieces and, in particular,
to a jigging system for the assembly of wooden trusses for use in building.
[0002] The invention relates to an improvement to that disclosed in our Australian Patent
No. 694642 (U.S. Patent No. 5,854,747)
[0003] Wooden trusses generally comprise a number of wooden components including a bottom
chord, upper chords which are generally arranged in a V-shaped configuration, and
connecting pieces or webs between the chords. The chords and connecting webs are joined
together by metal connector plates which are usually forced into the wooden components
at joints between components on both sides of the truss by a suitable press or the
like. Conventionally, the components from which the truss are to be made are laid
out on a table which has stops (often referred to as pucks) for setting the position
of the chords.
[0004] The above-mentioned Australian patent discloses an automatic method of moving the
stops or pucks to desired locations to set the position of the chords which are to
be joined together to form the truss. The formation of the truss from the chords also
requires the placement of various tools such as a peak or apex tool and clamp tools
in order to define the position of the peak or apex and hold the two chords, which
will be joined together to form the apex, in position. Heel tools are also required
in order to define the points at which the upper chords will intersect with the bottom
chord. The location of these tools is performed manually by locating the tools in
position on the table before or after the stops have been automatically moved to define
the position of the chords.
[0005] The need to manually locate the tools increases the time required in order to set
up the jigging system for formation of a truss and therefore the time required in
order to actually produce a truss.
[0006] The above-mentioned problems have been solved by the provision of a jigging system
for use in arranging components to form an assembly such as a truss, the jigging system
comprising an upper platform having a top surface and spaced apart slots therein,
at least one carriage mounted in one of said slots for sliding movement relative to
the upper platform along said one slot, a component support for supporting the components
in a position above the top surface of the upper platform, the component support being
connected to the carriage and comprising a first portion engaging the carriage and
a second portion spaced above the carriage and having an engaging surface engageable
with one of the components, the second portion's engaging surface being adapted to
resiliently deform upon application of downward force to the component to permit the
component to engage the top surface of the upper platform, and to return to an original
configuration upon release of the downward force.
Brief Description of the Drawings
[0007] A preferred embodiment of the invention will be described, by way of example, with
reference to the accompanying drawings, in which:
Figure 1 is a perspective view of a jigging system according to the preferred embodiment
of the invention;
Figure 2 is a greatly enlarged, fragmentary top plan view of the table showing a puck,
but with the truss shown in Fig. 1 removed for clarity;
Figure 3 is a section taken in the plane including line 3-3 of Fig. 2;
Figure 4 is a section taken in the plane including line 4-4 of Fig. 2;
Figure 5 is a fragmentary plan view similar to Fig. 2, but showing an apex tool;
Figure 6 is section taken in the plane including line 6-6 of Fig. 5;
Figure 7 is a plan view showing a clamp tool;
Figure 8 is a fragmentary plan view of a guide rail of the preferred embodiment of
the invention;
Figure 9 is a section taken as indicated by line 9-9 of Fig. 8;
Figure 10 is a schematic view of a control system for controlling the jigging system
of Figures 1 to 9;
Figure 10A is a diagram illustrating how a carriage is moved along the table according
to one embodiment of the invention;
Figure 11 is a fragmentary plan view of part of the table showing a heel tool according
to a further embodiment of the invention;
Figure 12 is an enlarged top plan view of the heel tool;
Figure 13 is a side view of the heel tool; and
Figure 14 is a section taken in the plane including line 14-14 of the heel tool of
Fig. 12.
Detailed Description of the Preferred Embodiment
[0008] With reference to the drawings, an assembly table 10 is shown. Tables of this type
may typically be up to 30 meters (100 feet) in length and 4.2 meters (15 feet) in
width. The table 10 has an upper platform generally indicated at 12, formed from solid
sheets 12A or sections or the like which are spaced apart to define a plurality of
slots 14 which, in the embodiment of Figure 1, extend across the width of the table.
Rather than extend across the width of the table as shown in Figure 1, the slots 14
could also extend lengthwise or at an angle across the table if desired. The upper
platform 12 constitutes a reaction surface in the preferred embodiment.
[0009] Arranged for movement along the slots 14 in a manner to be described hereinafter
are a plurality of stops or pucks 19. Typically, the shape of a truss 20 is known
and its details are fed into a control system 30, which controls movement of the pucks
19. The pucks 19 are then moved in a manner which will be described hereinafter to
positions needed to locate the truss components for forming the truss 20. In the preferred
embodiment of this invention, some of the slots 14, rather than being provided with
pucks 19 are provided with other jigging tools. Such jigging tools may include apex
tools 19' and clamp tools 19'', described hereinafter. It is to be understood that
"tools" as used herein includes the pucks 19, as well as apex tools 19', clamp tools
19'' or other suitable jigging tools. Such tools are necessarily arranged on the table
10 to define a jig for assembling the truss. Chords 20A, 20B and 20C from which the
truss is to be formed are laid out together with webs 20D, with the chords abutting
the pucks 19. Connector plates C are located in generally opposed relation on top
and bottom of the truss 20 at the joints of the chords 20A, 20B and 20C and the webs
20D, and the connector plates are driven into the truss 20 in a suitable manner such
as by presses or the like (not shown) to form the truss 20. The truss 20 is removed
from the table 10 and new components, such as new chords which are the same as those
referred to above, are located in place to form a new truss. If the shape of the new
truss is different, the jig tools 19, 19', 19'' are first moved under the control
of a control system 30 (Fig. 10) to new positions for locating truss components of
the new truss.
[0010] Figures 2 to 4 are detailed views showing two adjacent table sections 12A separated
by one of the slots 14. A carriage 100 is arranged within the slot 14 and is moved
by a motor M and flexible endless belt 52 (Fig. 10A). The details of the motor M and
belt 52 are fully disclosed in our previously mentioned Australian patent, and will
only be briefly described hereinafter. Suffice it to say that the carriage 100 is
secured to the flexible belt 52 described in the above mentioned patent for movement
along the slots 14 as the belt is driven back and forth by the motor M. There are
preferably two carriages per slot 14.
[0011] The carriage 100 has a top plate 102 which is supported on steps 106 and 108 of a
guide rail 130 by blocks 110 which are attached by welding or the like to the top
plate 102. The top plate 102 supports a puck 19. Alternatively, the carriage 100 can
carry another tool such as an apex tool 19' (Figure 5) for defining the apex of the
truss to be formed or a clamp tool 19'' (Figure 7). The apex tool 19' and clamp tool
19" will be described in more detail with reference to Figures 5 to 7.
[0012] Referring again to Figs. 3 and 4, the carriage 100 further includes a carriage guide
120 located below the top plate 102. The carriage guide is guided in the guide rail
130, in which are defined four channels 131, 132, 133 and 134. The rail 130 is supported
by a frame (not shown) beneath the table sections 12A and has inwardly projecting
flange portions 171 which define the steps 106 and 108 with the sections 12A. The
carriage guide 120 is of generally box construction having side walls 121 and 122,
top wall 124 and bottom wall 123. The top wall 124 has extending flanges 128 and the
bottom wall 123 has extending flanges 129. The flanges 128 and 129 ride in the channels
131 to 134 on plastic strips 141 to facilitate sliding movement of the carriage 100
along the rail 130. The carriage guide 120 is secured to the flexible belt 52 (see
Figure 10A) which is driven by the motor M and drive rollers 46, 46' (as disclosed
in our previously mentioned Australian patent) so that the carriage 100 is driven
along the guide rail 130.
[0013] The top wall 124 of the carriage guide 120 carries a cylindrical sleeve 125 having
an internal annular upper bushing 127 and an internal annular lower bushing 126 which
have a space 144 between them. The puck 19 is provided with a pin 140 which projects
downwardly from the underside of the puck. The pin 140 has a circumferential groove
149 in which is located a split ring retainer or circlip 142 (broadly, "resilient
locking member") when the puck 19 is connected to the carriage 100. Top plate 102
is provided with a hole 161 and the pin 140 passes through the hole and into the sleeve
125 which is aligned with the hole.
[0014] As the pin 140 moves downward past the upper bushing 127 and into the space 144,
the pin engages the inner diameter of the circlip 142. The leading end of the pin
140 is tapered, but the main portion of the pin has a diameter larger than the inner
diameter of the circlip 142 so that the circlip is resiliently deflected outward from
its relaxed position. When the groove 149 of the pin reaches the space 144, the circlip
142 snaps into the groove, attaching the pin 140 to the carriage. Further movement
of the pin 140 axially of the sleeve 125 is resisted by engagement of the circlip
142 with the upper or lower bushings 127, 126 at the boundaries of the space 144.
Thus, the pin 100 snaps into a releasable locking engagement with the carriage 100
upon insertion into the sleeve 125. The pin 140 also couples the top plate 102 to
the carriage guide 120. Thus, when the carriage guide 120 is moved by the flexible
belt 52 along the slot 14, the top plate 102 and puck 19 are moved conjointly with
it. As will be apparent from Figures 2, 3 and 4, the top plate 102 slides on shoulders
106 and 108 via blocks 110 as carriage guide 120 and top plate 102 move.
[0015] A resilient truss component support 150 connected by the pin 140 to the carriage
100 holds a chord (such as the chord 20B shown in Fig. 3) above a top surface of the
upper platform 12 of the table 10. The support 150 comprises a metal spring plate
152 which has a hole 154 through which the pin 140 passes so that the plate 152 is
secured to the carriage 100 on the top plate 102 by the pin 140. The spring plate
152 extends substantially the length of the top plate 102 and rests at its ends on
the top plate 102. A raised central ("second") portion 155 is higher than the level
of the table sections 12A. Many or all of the carriages 100 carrying a puck 19 have
the support 150 so that the supports collectively hold the chords 20A-20C and webs
20D off the upper platform 12. Thus, the truss chords 20A-20C are supported above
the level of the assembly table sections 12A so that tooth connector plates C can
be positioned on the sections 12A beneath the chords 20A-20C. The left heel of the
truss 20 is broken away in Fig. 1 to reveal a connector plate C located on the bottom
side of the truss. Bottom side connector plates (not shown) are similarly located
at the other joints of the truss 20.
[0016] The support plate 152 is formed from a resilient spring metal and has an end flange
153 which extends over the end of top plate 102 and into slot 14 so that the spring
plate 152 cannot be inadvertently rotated relative to the top plate 102, and the spring
plate 152 can be maintained in the operative position shown in Figures 2, 3 and 4
for supporting a chord 20B. Any tendency for the plate 152 to rotate in the directions
indicated by double headed arrow A in Figure 2 will be prevented by the sides of the
flange 153 contacting side walls 12B of the sections 12A.
[0017] The spring metal plate 152 holds the chords 20A-20C in a position slightly above
the top of the upper platform 12. Thus, connector plates can be slid, teeth up, under
the chords 20A-20C and webs 20D at joint locations, or put in these locations prior
to placement of the chords and webs on the upper platform 12. Connector plates are
also placed on top of the chords and webs at the joints. To attach the connector plates
to the chords 20A-20C and webs 20D, a suitable press (not shown) applies a downward
force to the chords, webs and connector plates. The force of the press overcomes the
spring force of the metal spring plates 152, deflecting the central portion 155 and
pushing it down so that the top surface of the sections 12A of the upper platform
12 can provide a rigid reaction surface opposing the action of the press. The teeth
of the connector plates are driven by the press into chords 20A-20C and webs 20D as
a result of the reaction force provided by the upper platform 12. The spring plates
152 resume their prior configuration as soon as the press force is released. In this
way, the carriage 100 is protected from experiencing the high loads from the press
while permitting placement of connector plates under the chords and webs.
[0018] Figure 5 shows a plan view similar to Figure 2 except that an apex tool 19' for positively
locating the apex of truss 20 is shown. The apex tool 19' has a base plate 250 (closely
similar to top plate 102) which is provided with a hole 252. The base plate 250 has
a block 110' (Fig. 6) at each end which ride on steps 106 and 108 of the guide rail
130 in the same manner as the blocks 110 attached to the top plate 102 of the carriage
100 described with reference to Figure 4. An apex tool cross-member 251 is attached
as by welding to the base plate 250 so the base plate (with the blocks 110') and cross-member
are a single unit. The cross-member 251 carries a retractable locating finger 253
which has a side edge 254. The side edge 254 positions an angled end 255 of chord
20B of the truss 20 (shown in phantom) so that the chord can be correctly located
in place at the apex of the truss. The apex tool 19' is moved to the desired position
by carriage 100 (as describe above for puck 19) so as to locate the locating finger
253 and therefore the edge 254 in the required position. When the chord 20B is positioned,
the locating finger 253 can be withdrawn (as indicated in hidden lines in Fig. 5)
so that the other upper chord 20C can abut against the end of the chord 20B to thereby
position the chord 20C. The structure and mode of operation of the member 251 is conventional
and therefore the apex tool 19' will not be shown or described in any further detail.
[0019] As best shown in Figure 6, the blocks 110' of the apex tool 19' ride on the steps
106 and 108 which are formed at the ends of the portions 171 of the guide rail 130.
In this embodiment, the upper plate 102 (with its attached blocks 110) of the carriage
100 is removed by simply removing the pin 140 which attaches the top plate 102 to
the carriage guide 120 and lifting the top plate 102 out of the slot 14. The base
plate 250 is then placed in the slot 14 on the steps 106 and 108 and the hole 251
aligned with sleeve 125 of the carriage guide 120. A pin 257 is then pushed through
the aligned hole 251 and the sleeve 125 so that the pin 257 secures the apex tool
19' to the carriage guide 120 in exactly the same manner as the pin 140 secures the
puck 19 to the carriage guide 120 described with reference to Figure 4. In Figure
5, a pin 140 can be provided by one of the pucks 19 previously described. However,
in the embodiment shown the pin 257 is a separate pin which is similar to the pin
140 except that the head 259 is substantially flat since the pin 257 need not form
the function of the puck 19.
[0020] Figure 7 shows an embodiment in which a clamp tool 19'' is automatically moved by
the carriage 100. In this embodiment, the top plate 102 is located in position in
the same manner as described with reference to Figures 3 and 4. The clamp tool 19''
is secured to the top plate 102 by the same type of pin 257 described with reference
to Figures 5 and 6 and which passes through a hole 261 formed in the clamp tool 19''.
However, once again, a puck 19 having the 5 pin 140 could be used instead of the pin
257. The clamp tool 19'' is pivotal about the pin 257 to arrange the tool at right
angles with respect to a chord 20C so that a clamp head 260 can engage the.chord 20C
to push the chords 20A-20C and webs 20D together. Since the clamp tool 19'' is at
right angles to the chord 20C, load applied by the chords against the clamp head 260
is in the direction of ram arm 262 and therefore does not tend to rotate the clamp
19'' on pin 257. The clamp tool 19'' is of known design except of the inclusion of
a hole through which the pin 257 can pass to secure the clamp tool 19'' to the top
plate 102 of the carriage 100.
[0021] It should be understood that in some embodiments of the invention, the carriage 100
is made up of the carriage guide 120 and the top plate 102. In other embodiments,
the top plate 102 is effectively incorporated into the tool (such as the plate 250
which forms part of the apex tool 19') and therefore the carriage is effectively comprised
of the carriage guide 120 and the tool defines the top plate (such as plate 250) and
blocks (such as blocks 110') connected to the plate 250 which slide on the steps 106
and 108 on the guide rail.
[0022] Figures 8 and 9 illustrate in more detail the configuration of the guide rail 130.
As best shown in Figures 8 and 9, the guide rail 130 is formed from two inverted L-shaped
rail members 301 which are arranged in face to face or mirror image relationship with
respect to one another. The rail members 301 have the inwardly projecting flange portions
171 which, together with the sections 12A define the steps 106 and 108 upon which
the top plate 102 or the base plate 250 of the apex tool 19' ride. The flange portions
171 are supported by side walls 302. The side walls 302 are coupled together by a
plurality of lower plates 135 which are welded to lower edges of the side walls at
locations spaced along the length of the guide rail 130. The flanges 171 also each
have spaced apart holes 307 which facilitate bolting of the sections 12A of the platform
5 12 to the flanges.
[0023] Elongate bars 305 are welded to the inner surfaces of the side walls 302 of the guide
rail 130 so as to define the channels 131, 132, 133 and 134. Some of the plates 135
carry sleeves 311 so that jacks or other suitable supporting structure (not shown)
can be engaged with the sleeves to support the guide rails 130 above ground level.
I-beams (not shown) may be provided between adjacent guide rails 130 for supporting
mid portions of the sections 12A. The I-beams are attached to a conventional frame
of the table 10. Thus, the sections 12A of the upper platform 12 are supported by
the guide rails 130 as well as additional frame members formed at least partly by
the I-beams (not shown).
[0024] A jig tool 19, 19' or 19'' may be secured to the top plate 102 and carriage 120 which
covers substantially the entire plate 102. If the support of the chord 20B at that
particular top plate 102 is not required, the spring plate 152 can simply be lifted
up slightly so as to raise the flange 153 above the top surface of the sections 12A
and then the plate 152 can be rotated about the pin 140 into a position 180° from
that shown in Figures 2 and 3 to move the spring plate 152 into a non-operative position
and out of any interference with the tool to be supported on the top plate 102. For
example, the spring plate 152 could be moved into the non-operative position as shown
in phantom in Figure 7 so that the central portion 155 does not interfere with correct
positioning of the clamp tool 19'' relative to the top plate 102 and the chord 20C.
This enables the spring plate 152 to be moved out of the way while retaining the spring
plate on the apparatus for convenient repositioning should the respective carriage
102 again be required to support one of the chords 20A-20C above the platform 12.
Retention of the spring plate 152 on the carriage 100 also prevents misplacement of
the spring plates or accidental loss of the spring plates when they are not in use.
[0025] Figures 10 and 10A schematically illustrate the control system 30 for controlling
the jig. The control system 30 includes a portable computer PC which is coupled to
a controller 80. The controller 80 is then in turn coupled to motor M, encoder 68
and also controls solenoid 70 and disc brakes 66. One controller 80 can be used to
control, for example, six pucks 19, six other jig tools (e.g., 19', 19''), or some
combination of pucks and other tools. In the instance where the table 10 has forty-two
tools (including pucks 19), seven controllers 80 connected to the PC for controlling
the jig are used. The controller 80 which controls each set of six tools (19, 19'
or 19'') will also control the associated motor M, encoder 68, brakes 66 and solenoid
70 associated with those tools.
[0026] Each of the controllers 80 therefore is controlling six of the tools (19, 19' or
19''). The controller 80 obtains information identifying the position of each of the
tools which it is to control. The information is fed to the controller 80 from the
encoder 68 on the pulleys 46. It should also be noted that all of the tools could
be under the control of a single controller 80 rather than a number of controllers
and all driven simultaneously to their desired positions under the command of the
controller 80. Conceivably, a greater number of controllers could be employed.
[0027] In the preferred embodiment, information relating to a truss layout is fed into the
PC and that information is then provided to the controller 80. Initially, the tools
19, 19', 19'' are moved to a zero position by the controller 80. The controller 80
selects one of the tools, e.g., one of the pucks 19, and knowing the position of the
puck 19, it will compare the required position to the actual position of the puck.
A command is issued from the controller 80 to the brake 66 associated with the relevant
puck 19 so that the brake is released. An output is supplied to solenoid 70 to ensure
that the shaft 60 is moved axially into the position so that the spline 62 or 64 engages
the appropriate pulley 46 and a voltage is supplied to the motor M to drive the shaft
60 at high speed. The shaft 60 rotates the pulley 46 to drive the appropriate belt
52 about the pulleys 46 and 48 to move the carriage 100 to the desired position to
correctly position the puck 19.
[0028] When the puck 19 comes to within a specified distance from its required position
(which may be indicated by a number of counts issued from encoder 68) the motor speed
is switched to low speed by the controller 80. Typically this will occur after one
or two seconds of running. Again, when the puck 19 is within the specific number of
counts of the actual position required, the controller 80 issues a signal to disc
brake 66 to apply the brake to stop the pulley 46 so that the tool 19 comes to rest
at the required position. The motor M is then switched off. The specific number of
counts at which the motor is reduced to low speed and at which the brake is applied
can be determined by the system response time and could be adjustable and preset in
the controller 80. The controller then selects another tool (19, 19' or 19'') so that
the next tool can be moved. The solenoid 79 is operated to disengage splines 62 of
the shaft 60 from the pulley 46 and to engage the other spline 64 with its pulley
46'. The same procedure as outlined above is then repeated to position the other tools.
[0029] For any truss configuration only some of the tools 19, 19', 19'' which may be provided
may be used. Those tools which need not be used for a particular truss configuration
can be controlled so that they are moved to the edge of the table so that they are
completely out of the way of the truss 20 which is to be manufactured.
[0030] In the preferred embodiment of the invention, the pucks 19 are coupled to top plates
102 and carriages 120 by a pin 140 so that the pucks 19 can be released from any of
the respective carriages in a similar fashion to the tools 19', 19''. The tools 19,
19', 19'' are released from their carriage guides 120 by simply prying the pin 140
upward from the sleeve 125 by means of a screwdriver or any other suitable tool. The
upward motion of the pin 140 overcomes the spring force of the circlip 142 and drives
the circlip out of the groove 149 and into the space 144 so the pin can be withdrawn
from the sleeve 125. The easy removal and replacement of the jig tools 19, 19' or
19" enables a particular jig tool to be associated with any one of the carriages 100
associated with any one of the slots 14.
[0031] The processor PC will determine at which of the slots 14 the apex 21 of the truss
is to be located and will show this either graphically, numerically or otherwise on
a display screen. If an apex tool 19' is not already associated with the slot 14,
the apex tool associated with one of the other slots 14 can be removed by releasing
the pin 140 as described above and the apex tool snapped into connection with the
carriage 100 associated with the appropriate slot 14. Similarly, other tools such
as clamp tool 19'' and pucks 19 can be released from particular carriages 100 and
connected to other carriages 100 under the direction of the PC. The PC then controls
the carriages 100 as described above to position the tools 19, 19' and 19" in the
required position for enabling the chords 20A-20C (and web 20D in the embodiment shown
in Figure 1) to be located and fastened together by the connector plates previously
described.
[0032] Figures 11 to 14 show a further embodiment in which a heel tool for locating the
heel position of a truss is shown. The heel tool 400 is not movable along the channels
14 as is the case with the tools 19, 19', 19'' previously described but is fixed in
position to the table 10 by pairs of holes 401 and 402 which are provided on some
or all of the sections 12A of the upper platform 12. In the embodiment shown in Figure
11, two rows (labeled C and D) of holes 401 and 402 are shown. The heel tool 400 is
fixed to one of the hole pairs 401 and 402 in row C on the section 12A' shown in Figure
11. The holes 401, 402 are covered by the tool 400 in Figure 11.
[0033] The tool 400 has a base section 403 and a heel point section 405 which is moveable
relative to the base section 403. As best shown in Figure 12 which shows the tool
more enlarged (and in a more retracted position than in Figure 11) the base 403 has
a recess 431 in which is located a head 409 arranged on a pin 407, which pin is located
in the hole 401 shown in Figure 11. The base 403 also carries an elongate hole 415
which carries a floating pin 419 for location in the hole 402 in the section 12A'
shown in Figure 11. The pins 407 and 419, as well as the holes 401 and 402 are preferably
configured similar to the pin 140 and sleeve 125 previously described for secure releasable
connection. The floating pin 419 in the elongated groove 415 provides some degree
of movement of the pins 407 and 419 relative to one another to ensure that they can
properly locate in the precision drilled holes 401 and 402. The ability to locate
the tool 400 on the assembly table 20 and then simply move the heel point section
a short distance to define the heel point location enables quick and accurate determination
of the heel point location and positioning the tool 400.
[0034] When the truss 20 is being formed, the PC will identify the heel point location for
the truss 20 which is to be formed and will then display the holes 401 and 402 to
which the heel tool 400 should be attached. The PC will then indicate the amount of
movement of the heel point section 405 relative to the base 403 which is required
in order to position a heel point locating tab 412 on the tool 400 at the desired
point to identify the heel location of the truss 20. The section 405 carries a scale
411, and the base 403 a pointer 447. Thus, the computer can indicate a value on the
scale 411 which should be aligned with the pointer 447 to locate the heel point section
405 in the desired position relative to the base 403 for positioning the heel point
locating tab 412 at the required place on the assembly table 400.
[0035] As is best shown in the cross-sectional view of Figure 14, the heel point section
405 is formed from a generally C-shaped channel having bottom wall 405A, end wall
405C and top wall 405B. A pair of inwardly directing flanges 455 and 456 define a
narrow slot 471 in the heel point section 405. The base 403 is formed of a generally
C-shaped channel having a bottom wall 403A, a top wall 403B and end wall 403C. The
walls 403A and 403B have free ends 472 which face and generally abut the flanges 455
and 456. The walls 403A and 403B define an open space 460 therebetween and the walls
405A and 405B define a cavity 470 therebetween.
[0036] A locking bar 449 is accommodated in the cavity 470 of the heel point section 405
and has an enlarged head 450 and a stem 456 which projects through the channel 471
between the flanges 472. A bar 451 is coupled to the stem 456 and projects into the
space 460. Pin 407 carries an integral eccentric 453. A sleeve 452 is provided about
the eccentric so that the pin and eccentric can rotate about the axis L of the pin
relative to the sleeve. The bar 451 is welded to the sleeve 452 which holds the sleeve
against rotation with the eccentric 453.
[0037] In order to lock the heel point section 405 to the base 403 so that the heel point
section cannot move relative to the base 403, a handle 410 mounted on top of the pin
407 is rotated in the direction of arrow F (Fig. 12) so the pin rotates about its
longitudinal axis L (Fig. 14) in hole 401. This rotation causes the eccentric 453
to rotate with the pin 407 and the rotation of the eccentric 453 causes the sleeve
452 to move in the direction of arrow G in Figure 14 within the space 460 to pull
the bar 451 and also the head 450 in the same direction so that the head securely
clamps the flanges 455 against the free ends 472 of the walls 403A and 403B. Thus,
the heel point section 405 is securely clamped against the base 403 so it cannot move.
In order to release the heel point section 405 for movement relative to the base 403
in either direction of double headed arrow D in Figure 12, the handle 410 is rotated
in the opposite direction to arrow F (back, for example, to the position shown in
Figure 12) so as to rotate the eccentric 453 to move the sleeve 452 in a direction
opposite arrow G in Figure 14. This causes the clamping pressure supplied by the head
450 which pushes the flanges 455 hard against the free ends 472 to be released. The
heel point section 405 can then slide in the direction of arrow D relative to both
the locking bar 449 and also the base 403 with the flanges 455 sliding on the free
ends 472 of the walls 403A and 403B. To prevent rotation of the heel point section
405 about bar 451, relative to the base 403 into and out of the plane of the paper
of Figure 12, which may be allowed by any tolerance provided for the sleeve 452 and
eccentric 453 within the space 460, a tongue 481 is provided on the heel point section
405 which projects into the space 460 between the walls 403A and 403B.
[0038] According to the preferred embodiment of the invention, the jig system can be automatically
set up to receive components of a truss and the truss can be easily manipulated to
enable connector plates to be inserted in place for formation of the truss. Thus,
not only is set up of the jig quickly effected, but formation of the truss is also
more easily and quickly performed.
[0039] Since modifications within the scope of the invention as defined in claim 1 may readily
be effected by persons of ordinary skill in the art, it is to be understood that this
invention is not limited to the particular embodiment described by way of example
hereinabove.
1. A jigging system for use in arranging components (20A, 20B, 20C, 20D) to form an assembly
such as a truss (20), the jigging system comprising:
an upper platform (12) having a top surface and spaced apart slots (14) therein;
at least one carriage (100) mounted in one of said slots (14) for sliding movement
relative to the upper platform (12) along said one slot (14); and
a component support (150) for supporting the components (20A, 20B, 20C, 20D) in a
position above the top surface of the upper platform (12), the component support (150)
being connected to the carriage (100) and comprising a first portion (140) engaging
the carriage (100) and a second portion (155) spaced above the carriage (100) and
having an engaging surface engageable with one of the components (20A, 20B, 20C, 20D);
characterised in that the second portion's engaging surface being adapted to resiliently deform upon application
of downward force to the component (20A, 20B, 20C, 20D) to permit the component (20A,
20B, 20C, 20D) to engage the top surface of the upper platform (12), and to return
to an original configuration upon release of the downward force.
2. A jigging system according to claim 1, wherein the component support (150) includes
a third portion (153) disposed on an opposite end of the component support (150) from
the first portion (140), the third portion (153) engaging the carriage (100).
3. A jigging system according to claim 2, wherein the second portion (155) of the component
support (150) has a generally inverted channel shape.
4. A jigging system according to claim 3, wherein the first portion (140) of the component
support (150) is attached to the carriage (100) and the second and third portions
(155, 153) are free of connection to the carriage (100).
5. A jigging system as set forth in claim 4 further comprising a tool (19, 19', 19")
for locating at least one of the components (20A, 20B, 20C, 20D) on the upper platform
(12), the tool (19, 19', 19") mounting itself and the component support (150) on the
carriage (100).
6. A jigging system according to claim 5 wherein the tool (19, 19', 19") and carriage
(100) are adapted for releasable snap locking interengagement.
7. A jigging system according to any one of claims 1 to 6, further comprising a drive
(M, 52) for driving movement of said one carriage (100) in the slot (14).
8. A jigging system according to any one of claims 1 to 7, further comprising a heel
locating device (400) including a first section (403) adapted for connection to the
upper platform (12), a second section (405) slidably mounted on the first section
(403) for extension and retraction relative to the first section (403), the second
section (405) having an end (412) constructed for locating a heel of a truss (20),
a locking device (449) for locking the first and second sections (403, 405) in a fixed
position relative to each other, and a scale (411) associated with one of the first
and second sections (403, 405) for locating the second section (405) relative to the
first section (403).
1. Setzsystem zum Gebrauch beim Anordnen von Komponenten (20A, 20B, 20C, 20D) zum Bilden
einer Baugruppe wie zum Beispiel eines Fachwerks (20), wobei das Setzsystem aufweist:
eine obere Plattform (12) mit einer oberen Oberfläche und darin vorgesehenen, beabstandeten
Schlitzen (14),
mindestens einen Wagen (100), der in einem der genannten Schlitze (14) für Verschiebebewegung
in bezug zur oberen Plattform (12) entlang des genannten einen Schlitzes (14) angebracht
ist; und
einen Komponentenhalter (150) zum Halten der Komponenten (20A, 20B, 20C, 20D) in einer
Position über der oberen Oberfläche der oberen Plattform (12), wobei der Komponentenhalter
(150) mit dem Wagen (100) verbunden ist und einen ersten Teil (140), der den Wagen
(100) ergreift, und einen zweiten Teil (155) aufweist, der über dem Wagen (100) beabstandet
ist und eine Eingriffsfläche aufweist, die mit einer der Komponenten (20A, 20B, 20C,
20D) in Eingriff gebracht werden kann; dadurch gekennzeichnet dass die Eingriffsfläche des zweiten Teils ausgelegt ist, um elastisch bei Anlegung einer
nach unten gerichteten Kraft auf die Komponente (20A, 20B, 20C, 20D) verformt zu werden,
um zuzulassen, dass die Komponente (20A, 20B, 20C, 20D) die obere Oberfläche der oberen
Plattform (12) ergreift, und zu einer Ausgangskonfiguration bei Aufhebung der nach
unten gerichteten Kraft zurückzukehren.
2. Setzsystem nach Anspruch 1, bei dem der Komponentenhalter (150) einen dritten Teil
(153) einschließt, der auf einem entgegengesetzten Ende des Komponentenhalters (150)
von dem ersten Teil (140) angeordnet ist, wobei der dritte Teil (153) den Wagen (100)
ergreift.
3. Setzsystem nach Anspruch 2, bei dem der zweite Teil (155) des Komponentenhalters (150)
eine allgemein umgekehrte Kanalform aufweist.
4. Setzsystem nach Anspruch 3, bei dem der erste Teil (140) des Komponentenhalters (150)
an dem Wagen (100) befestigt ist und der zweite und dritte Teil (155, 153) keine Verbindung
zum Wagen (100) aufweisen.
5. Setzsystem nach Anspruch 4, das ferner ein Werkzeug (19, 19', 19") zum Anordnen mindestens
einer der Komponenten (20A, 20B, 20C, 20D) auf der oberen Plattform (12) aufweist,
wobei das Werkzeug (19, 19', 19") sich selbst und den Komponentenhalter (150) an dem
Wagen (100) anbringt.
6. Setzsystem nach Anspruch 5, bei dem das Werkzeug (19, 19', 19") und der Wagen (100)
für lösbares Schnappverschluss-Ineinandergreifen ausgelegt sind.
7. Setzsystem nach einem der Ansprüche 1 bis 6, das ferner einen Antrieb (M, 52) für
Antriebsbewegung des genannten einen Wagens (100) in dem Schlitz (14) aufweist.
8. Setzsystem nach einem der Ansprüche 1 bis 7, das ferner eine Fersenlokalisiereinrichtung
(400) aufweist, welche einen ersten Abschnitt (403), der für Verbindung mit der oberen
Plattform (12) ausgelegt ist, und einen zweiten Abschnitt (405) einschließt, der verschiebbar
an dem ersten Abschnitt (403) für Ausstreckung und Einziehung in bezug zum ersten
Abschnitt (403) angebracht ist, wobei der zweite Abschnitt (405) ein Ende (412) aufweist,
das zum Lokalisieren einer Ferse eines Fachwerks (20) aufgebaut ist, eine Verriegelungseinrichtung
(449) zum Verriegeln des ersten und zweiten Abschnitts (403, 405) in einer feststehenden
Position in bezug zueinander, und eine Skala (411) aufweist, die mit einem des ersten
und zweiten Abschnitts (403, 405) verknüpft ist, um den zweiten Abschnitt (405) in
bezug zum ersten Abschnitt (403) zu lokalisieren.
1. Système d'assemblage à utiliser pour disposer des éléments (20A, 20B, 20C, 20D) afin
de former un ensemble comme une ferme (20), ce système d'assemblage comprenant :
une plate-forme supérieure (12) ayant une surface supérieure et des rainures écartées
(14) dans cette surface ;
au moins un chariot (100) monté dans une desdites rainures (14) pour fournir un mouvement
de coulissement par rapport à la plate-forme supérieure (12) le long de ladite rainure
unique (14); et
un support d'éléments (150) pour supporter les éléments (20A, 20B, 20C, 20D) dans
une position au-dessus de la surface supérieure de la plate-forme supérieure (12),
ce support d'éléments (150) étant relié au chariot (100) et comprenant une première
portion (140) s'engageant avec le chariot (100) et une deuxième portion (155) écartée
au-dessus du chariot (100) et ayant une surface d'engagement pouvant être engagée
avec un des éléments (20A, 20B, 20C, 20D); caractérisé en ce que la surface d'engagement de la deuxième portion est adaptée de façon à se déformer
de manière élastique lors de l'application d'une force vers le bas sur l'élément (20A,
20B, 20C, 20D) afin de permettre à l'élément (20A, 20B, 20C, 20D) de s'engager avec
la surface supérieure de la plate-forme supérieure (12), et de retourner à une configuration
d'origine lors du relâchement de la force vers le bas.
2. Système d'assemblage selon la revendication 1, dans lequel le support d'éléments (150)
comprend une troisième portion (153) disposée sur un côté opposé du support d'éléments
(150) par rapport à la première portion (140), cette troisième portion (153) s'engageant
avec le chariot (100).
3. Système d'assemblage selon la revendication 2, dans lequel la deuxième portion (155)
du support d'éléments (150) a une forme généralement en U inversé.
4. Système d'assemblage selon la revendication 3, dans lequel la première portion (140)
du support d'éléments (150) est attachée au chariot (100) et la deuxième et la troisième
portions (155, 153) ne sont pas reliées au chariot (100).
5. Système d'assemblage tel que décrit dans la revendication 4, comprenant également
un outil (19, 19', 19") pour positionner au moins un des éléments (20A, 20B, 20C,
20D) sur la plate-forme supérieure (12), cet outil (19, 19', 19") se montant lui-même
ainsi que le support d'éléments (150) sur le chariot (100).
6. Système d'assemblage selon la revendication 5 dans lequel l'outil (19, 19', 19") et
le chariot (100) sont adaptés pour un inter-engagement à blocage par déclic pouvant
être dégagé.
7. Système d'assemblage selon l'une quelconque des revendications 1 à 6, comprenant également
un entraînement (M, 52) pour le mouvement d'entraînement dudit un chariot (100) dans
la rainure (14).
8. Système d'assemblage selon l'une quelconque des revendications 1 à 7, comprenant également
un dispositif de positionnement de pied de chevron (400) comprenant une première section
(403) adaptée pour être reliée à la plate-forme supérieure (12), une deuxième section
(405) montée de façon à pouvoir coulisser sur la première section (403) afin de permettre
une extension et un retrait par rapport à la première section (403), la deuxième section
(405) ayant une extrémité (412) construite pour positionner un pied de chevron d'une
ferme (20), un dispositif de blocage (449) pour bloquer la première et la deuxième
section (403, 405) dans une position fixe l'une par rapport à l'autre, et une échelle
(411) associée à une des première et deuxième sections (403, 405) afin de positionner
la deuxième section (405) par rapport à la première section (403).