[0001] The present invention relates to a prefabricated construction element comprising
a first concrete slab.
[0002] Prefabricated construction elements of this type are well known in the prior art.
The prefabricated construction elements are used for floors and walls. Such prefabricated
floor elements are concrete slabs which can form a span between two walls by laying
the floor elements on or against a wall or another structure on at least two of their
sides. Vertical placement of the construction elements enables them to be used as
a wall. Structures of this type are used in the construction of houses as well as
offices and commercial properties.
[0003] In order to form a floor, floor elements are laid in such a manner that their edges
abut, following which a covering floor is fitted over the floor elements. The covering
floor is intended for structural strength and finishing of the floor.
[0004] A drawback of a floor structure of this type is that it is no longer possible to
arbitrarily install conduits in the floor after production of the floor elements.
During production, a floor element may be provided with, for example, a central electrical
junction box and cables leading to it can be incorporated in the covering floor later.
In addition, cables with a relatively small height can be arranged in the covering
floor, for, for example, floor connections for computer networks and the like, but
the locations for such connections can only be determined before the covering floor
is fitted. Once the covering floor has been fitted, the connections can no longer
be moved.
[0005] However, in many buildings, there are also conduits with a large cross section, such
as for example sewer conduits and air-conditioning conduits, running through various
rooms. Such conduits are then arranged under the floor and a removable system ceiling
is subsequently fitted under the conduits in order to hide the conduits from view,
while ensuring that they are accessible in case modifications have to be made or malfunctions
have to be rectified. Conduits with a small cross section can likewise be fitted under
the floor, but above the system ceiling, in order to provide flexibility regarding
the position of connections for a computer network or the like.
[0006] The known structure of a floor made from prefabricated floor elements and a lowered
system ceiling requires additional work for attaching conduits to the floor elements
and for attaching the ceiling underneath the latter. In addition, connecting cables
have to be run down for connections, such as computer connections, in vertical cable
ducts, for example. However, for sewer conduits, in many cases holes have to be made
in the floor elements in order to connect, for example, a toilet bowl above the floor
element to a sewer conduit under the floor element. This may cause undesirable noises
on the storey beneath it.
[0007] Conduits are often arranged in walls in order to hide them from view. To this end,
special ducts are accommodated in the design of a building or grooves are provided
in the walls in order to accommodate conduits therein and the grooves are subsequently
concealed again, for example by plastering the wall.
[0008] It is an object of the present invention to provide a construction element in which
the conduits can easily be arranged in a floor or wall and in which, if desired, the
conduits remain accessible in order to modify existing connections, to fit new connections
or to rectify malfunctions.
[0009] The object mentioned above is achieved by means of a prefabricated construction element
which comprises a first concrete slab of a first length and a first width, and which
furthermore comprises a second concrete slab of a second length and a second width,
the first and second concrete slabs being placed at a distance from one another as
well as substantially parallel with respect to one another and being connected by
a load-bearing structure.
[0010] With a prefabricated construction element according to the present invention, which
is used as a floor element, the side of the first concrete slab remote from the second
concrete slab may serve as a ceiling and the side of the second concrete slab remote
from the first concrete slab may serve as a floor. Furthermore, the construction element
may serve as a wall if placed vertically. As the concrete slabs are placed at a distance
from one another, there is a space between the two concrete slabs. This space can
be used to accommodate conduits. The distance between the slabs can be chosen almost
completely arbitrarily during production of the construction elements, for example
depending on the conduits which have to (be able to) be accommodated therein.
[0011] The load-bearing structure has a load-bearing capacity which is such that the space
between the slabs does not have to be filled with any other material in order to attain
sufficient load-bearing capacity, both when used as a floor element and as a wall
element. Therefore, the conduits can be accommodated in the space between the first
and second concrete slab. Conduits can thus be moved, replaced, repaired or added
at any time. It is also possible to fit floor or wall connections in arbitrary locations
to the conduits placed in the floor or wall after the construction elements have been
installed.
[0012] Preferably, the second length is smaller than the first length and/or the second
width is smaller than the first width. If a number of floor elements are placed laterally
next to one another in order to form a ceiling or a floor, with the first concrete
slabs bearing on a wall or other supporting structure and laterally abutting, an opening
remains between the adjacent second concrete slabs. This opening ensures that the
space is easily accessible, even after the floor elements have been placed. Said opening
can be covered in a simple manner with a panel suitable for the purpose, so that an
even floor and/or a continuous ceiling is created.
[0013] Of course, it is likewise possible to choose the second concrete slab to be larger
than the first, an opening being created between the adjacent first concrete slabs
after the floor element has been placed, so that the space between the concrete slabs
is accessible from underneath. The floor element can then bear with a concrete slab
on a supporting structure or the floor element can bear on the supporting structure
via one or more edges of a concrete slab.
[0014] The load-bearing structure is advantageously made of metal and has an open structure
in the direction of the first and second length and/or in the direction of the first
and second width. A strong open load-bearing structure can easily be produced using
metal. Such an open structure of the load-bearing structure makes it possible to run
conduits through the load-bearing structure. The more openings and the larger the
openings in the load-bearing structure, the easier it is to arrange conduits in the
space between the first and second concrete slabs along an arbitrary path.
[0015] Preferably, the load-bearing structure consists of a number of load-bearing elements,
each load-bearing element comprising a first and a second metal beam and metal bars
fitted in-between the latter, each pair of successive bars forming a triangle with
one of the metal beams, and the first metal beam being disposed, at least partly,
in the first concrete slab and the second metal beam being disposed, at least partly,
in the second concrete slab.
[0016] A load-bearing element of this type is rigid and has a great load-bearing capacity.
The metal is preferably steel and in particular reinforcing steel. Furthermore, the
metal, in particular steel, is preferably tubular, which further increases the strength
of the structure.
[0017] The present invention furthermore relates to a floor and a wall which respectively
comprise at least one floor element and one wall element according to the present
invention.
[0018] Preferably, a concrete layer is arranged on a surface formed by installing a number
of concrete slabs of a number of construction elements as floor elements. The concrete
layer ensures a diaphragm action, as a result of which the structure is strengthened
further, sound insulation and/or thermal insulation.
[0019] If the conduits do not have to be accessible after having been fitted, or if a very
heavy or a very strong floor is desired, the space between the first and second concrete
slabs can at least partially be filled with heavy concrete or cellular concrete.
[0020] In order to further strengthen the floor, a reinforcement may be arranged in the
concrete applied after the construction element has been placed. The reinforcement
ensures an improved diaphragm action.
[0021] With a wall comprising at least one construction element according to the present
invention, the space between the first and the second concrete slab is at least partially
filled with cellular concrete or heavy concrete, thus providing a strong wall. In
addition, it is possible to introduce thermal or sound insulation material in a simple
manner into the space between the first and second concrete slabs.
[0022] Furthermore, the present invention relates to a covering panel which is clearly intended
for covering the openings between the floor elements in a floor according to the present
invention. The dimensions of the covering panels correspond to the dimensions of the
opening between the first and second concrete slabs after the latter have been placed.
In this case, a covering panel may be of a length equal to the opening between the
concrete slabs or a smaller length, so that the entire length of the concrete slabs
can be covered with a number of covering panels.
[0023] If the construction elements are being used as a floor, the covering panels have
to be suitable to support a predetermined minimum weight. A covering panel of this
type may be provided with connecting sockets which are installed during production,
for example for a computer network connection, for air supply and/or discharge or
for an electrical connection.
[0024] The present invention furthermore relates to a method for producing a floor element
according to the present invention, comprising producing a load-bearing element for
a load-bearing structure, producing a first concrete slab in connection with said
load-bearing structure and producing a second concrete slab in connection with said
load-bearing structure, said load-bearing element comprising a first and a second
metal beam and metal bars fitted in-between the latter, each pair of successive bars
forming a triangle with one of the metal beams. The production of the load-bearing
element comprises substantially simultaneously welding a bar to the first beam and
to the second beam, which prevents the bars from becoming warped during welding.
[0025] Preferably, each bar is welded to each beam along two seams in order to provide a
strong connection. Each bar is attached to a beam with its preferably oblique end
side. If only one weld seam is used, a bar may bend or pivot about the weld seam and
may even break away. By using two weld seams, preferably opposite one another viewed
in the direction of the end side of the bar, the weld seams cannot act as a pivot
and, in addition, a stronger connection is achieved. Simultaneous welding of the two
seams prevents the bar from becoming warped during welding.
[0026] Simultaneous welding according to the above method is preferably carried out using
a welding robot, which not only welds simultaneously, but also for an equal period
and over an equal length of every weld seam. In this manner, identical and strong
welded joints are produced which generate as little tension as possible in the bars.
[0027] The invention will be described in more detail below with reference to a non-limiting
exemplary embodiment which is shown in the attached drawing and in which:
Fig. 1 shows a cross section of a construction element according to the present invention,
Fig. 2 shows a view of a load-bearing element of a load-bearing structure for a construction
element according to the present invention,
Fig. 3 shows a cross section of a floor according to the present invention,
Fig. 4 shows a cross section of a wall and a floor supported by said wall, both comprising
a construction element according to the present invention,
Fig. 5 shows a cross section of an embodiment of a floor element fitted to a wall
element, and
Fig. 6 shows a floor according to the present invention, the space between the concrete
slabs of the floor element being accessible from below.
[0028] Fig. 1 shows a construction element 2 which is constructed from a first concrete
slab 4 and a second concrete slab 6. With the illustrated construction element 2,
the second concrete slab 6 is of a smaller width than the first concrete slab 4. The
length of the first concrete slab 4 and the length of the second concrete slab 6 may
be equal or one of the two lengths may be smaller, depending on the use and the chosen
design.
[0029] A steel load-bearing structure is disposed between the first and second concrete
slabs 4, 6. The load-bearing structure comprises a first load-bearing element 8a and
a second load-bearing element 8b. The two load-bearing elements 8a and 8b are at an
angle with respect to one another for structural rigidity and strength.
[0030] A construction element 2 may also comprise more than two load-bearing elements, depending
on the desired width of the construction element 2, a minimum weight to be supported,
a span to be bridged and possible other aspects which depend on the individual case.
Each construction element 2 can be designed for an individual case, based on a span
to be bridged, a minimum weight to be supported and other criteria, such as conduits
to be installed.
[0031] Fig. 2 shows a load-bearing element 8 with two beams 10a and 10b and bars 12 fitted
in-between the latter. Each pair of successive bars 12 forms a triangle together with
one of the beams 10a, 10b. The geometry of the triangle may be chosen on the basis
of the desired height of the construction element and the desired strength. The beams
10a and 10b are disposed in the concrete slabs 4, 6.
[0032] Fig. 2 shows a construction element which has been installed as a floor element and
rests on a wall 14. The load-bearing element 8 according to the present invention
is incorporated into the concrete slab 6 which has been placed on a supporting body,
such as the load-bearing wall 14. This concrete slab is further supported in at least
one other location of the floor element. Preferably, the floor element is supported
at locations where one or two bars 12 are connected to the beam 10b, as is shown in
Fig. 2. In Fig. 2, the floor element is in fact supported at one end by the wall 14
and at the supporting location, a bar 12a is connected to the beam 10b. This prevents
the beam 10b from bending under the load to be borne at the supporting location.
[0033] The configuration of the beams 10a, 10b and the bars 12 in the form of adjoining
triangles shown in Fig. 2 has been chosen for structural strength and rigidity which
are inherent to such triangular configurations, as is known in the field. However,
other configurations are also possible, as long as the strength of the structure remains
sufficient.
[0034] With the load-bearing element 8 shown in Fig. 2, the bars 12 have been welded to
the beams 10. For a strong construction, each bar 12 has been welded to each beam
at two spots or along two seams. When a bar 12 is welded in one spot or along one
seam, the bar 12 may deform and thus make welding along the second seam or to the
second beam difficult or impossible, and if it is still possible, undesirable stresses
will occur in the load-bearing element 8. In order to prevent this problem, the bars
are preferably welded simultaneously to the beam at the two spots or along the two
seams. In this case it is advantageous if the welding is carried out by an automatic
welding device, as such a device produces two (or more) substantially identical welds,
as a result of which stresses in the respective materials are reduced further. Deformations
of the bars 12 are further reduced by producing the total of four welds on the two
beams simultaneously, preferably using an automatic welding device. By means of this
method, it is possible to produce straight and strong load-bearing elements, which
enables the production of floor elements according to the present invention.
[0035] Fig. 3 shows an embodiment of a floor made up of construction elements 2 according
to the present invention, in which use is made of a load-bearing construction comprising
three load-bearing elements 20a, 20b, 20c. The use of three load-bearing elements
can result in a greater load-bearing capacity and/or greater rigidity of the construction
element. As a result, it is possible to construct and use wider and/or longer concrete
slabs 4, 6. It is also possible to use a load-bearing structure of this type in order
to enable a floor to bear a greater load.
[0036] Fig. 3 shows a number of construction elements 2 according to the invention. The
construction elements 2 are placed next to one another and form a continuous surface
on the side of the concrete slabs 6. This continuous surface may, as illustrated,
be located at the bottom and act as a ceiling, but may also be located on any other
side, depending on the use.
[0037] After the construction elements 2 have been placed next to one another, a concrete
layer 22 is disposed between the two concrete slabs 4, 6 on the concrete slabs 6.
A reinforcement 24 is arranged in the concrete layer 22 above a joint between adjacent
construction elements 2. The concrete layer 22 ensures a diaphragm action, as a result
of which the entire structure is reinforced. Incidentally, depending on the use, the
entire space between the concrete slabs 4, 6 may be filled with concrete, cellular
concrete or another material, for example a sound- or vibration-dampening material
and/or thermal insulation material.
[0038] Openings between the concrete slabs 4 are covered with a covering panel 26. The covering
panel 26 can be made from any material, depending on the desired strength and use.
The covering panels 26 and the concrete slabs 4 together form a surface, the covering
panels, if desired, being removable in order to access the space between the concrete
layer 22 and the concrete slabs 4.
[0039] There is a space between the concrete layer 22 on one side and the concrete slabs
4 and the covering panels 26 on the other side for installing electrical cables 29
and other conduits 30. If the covering panels 26 have been fitted so as to be removable
and replaceable, the cables/conduits 29, 30 are easily accessible in case of malfunctions
or new conduits and/or pipes can easily be installed in the gap. In Fig. 3, the electrical
cables 29 are connected to an electrical junction box, which is arranged in a concrete
slab 6.
[0040] Depending on the choice of the load-bearing structure, i.e. the configuration thereof,
the materials used and the form of the section of the bars 12 and the beams 10, etc.,
the construction elements 2 can bridge spans of up to 20 metres at least.
[0041] Fig. 4 illustrates a floor element 2 and a wall element 42 according to the present
invention. The floor element 2 comprises a first concrete slab 4 and a second concrete
slab 6, the first concrete slab 4 being wider than the second concrete slab 6. As
a result of the first concrete slab 4 protruding relative to the second concrete slab
6, the floor element 2 can easily be placed on a load-bearing structure.
[0042] In the embodiment shown in Fig. 4, the first concrete slab 4 rests on a first concrete
slab 44 of a wall element 42 according to the present invention. The second concrete
slab 46 is higher than the first concrete slab 44, namely such that the end side of
the second concrete slab 46 is level with the top of the first concrete slab 4 of
the floor element 2.
[0043] It can clearly be seen from Fig. 4 that the space between the first and the second
concrete slab 4, 6 in the floor element 2 is greater than that of the wall element
42. Furthermore, the concrete slabs 4, 6 of the floor element 2 are thicker than those
of the wall element 42. Such a difference in dimensions is not required and only depends
on the desired strength. All dimensions of the construction elements may be selected
to be different, depending on function and desired strength and space and other parameters.
[0044] In addition to the beams 10, bars 12, concrete layer 22 and conduits 30 already shown
in the previous figures, Fig. 4 shows a reinforcement 24 which also provides a connection
between the concrete layer 22 and the first concrete slab 44 of the wall element 42.
This results in a strong connection between the floor element 2 and the wall element
42. The conduits 30, which are arranged between the concrete slabs 4, 6 of the floor
element 2, are connected to the conduits 30 in the wall element 42 by means of a coupling
piece 31. However, a coupling piece 31 is not essential, but does simplify installation
of the conduits 30.
[0045] The space between the concrete slabs 44, 46 of the wall element 42 may remain empty
(except for the conduits 30 installed therein) or this space can be filled with any
material, for example sound insulation, thermal insulation material, sand or concrete,
depending on the desired properties of the wall.
[0046] Fig. 5 shows another embodiment of a connection between a wall and a floor element
42, 2 according to the present invention. In this embodiment, a first, relatively
large concrete slab 6 rests on a wall element 42A, while a second, relatively small
concrete slab 4 above it forms a floor. A filling material 22, for example concrete,
is disposed in the first wall element 42A.
[0047] A second wall element 42B is placed in the first wall element 42A. The wall element
42B comprises two concrete slabs 44, 46, which in the position shown are vertically
level. The second wall element 42B is likewise filled with a material 48. Preferably,
this material 48 is the same as the filling material 22 with which the first wall
element 42A is filled and the material 48 provides a connection to the filling material
22. Although this has not been shown, a reinforcement material may be arranged in
the filling material 22, 48 in order to further reinforce the connection.
[0048] Fig. 6 shows a further embodiment of a construction element according to the present
invention which acts as a floor element. The floor element comprises a first concrete
slab 6 which forms a continuous floor surface with the adjacent floor elements. The
floor element furthermore comprises two concrete slabs 4A and 4B which are each connected
separately by means of a load-bearing structure with load-bearing elements 20 according
to the present invention to the first concrete slab 4. The concrete slabs 4A and 4B
form a ceiling for a storey running beneath the floor elements, covering panels 26
closing the ceiling surface. The covering panels 26 are removable so that conduits
30 are easily accessible. Connections for the conduits 30 can easily be installed
in the covering panels 26, as well as for example an electrical junction box 28.
[0049] In order to provide a strong structure by forming a diaphragm which ensures diaphragm
action, a cover layer 32 may be provided on the top of the floor element. In addition,
a reinforcement may be arranged in the cover layer 32.
[0050] The construction elements according to the present invention are particularly suitable
for use in commercial properties which require many cables/conduits, such as for example
hospitals, where many electrical devices are often moved around and furthermore conduits
for air treatment, oxygen and the like have to be accessible near each bed. Likewise,
office environments where electrical appliances are being used in increasing numbers
at each work station and more and more air treatment is being applied, space in the
floors and/or the walls offers possibilities. A floor and/or wall according to the
present invention, for example, make the well-known cable ducts on the walls of offices
redundant.
1. Prefabricated construction element (2, 42) which comprises a first concrete slab (4,
44) of a first length and a first width characterized in that the construction element comprises a second concrete slab (6, 46) of a second length
and a second width, in which the first and second concrete slabs (4, 6, 44, 46) are
placed at a distance from one another as well as substantially parallel with respect
to one another and are connected by a load-bearing structure.
2. Prefabricated construction element according to claim 1, in which said second length
is smaller than said first length.
3. Prefabricated construction element according to claim 1 or 2, in which said second
width is smaller than said first width.
4. Prefabricated construction element according to one of the preceding claims, in which
the load-bearing structure (8) has an open structure in the direction of the first
and second length and/or in the direction of the first and second width.
5. Prefabricated construction element according to claim 4, in which the load-bearing
structure comprises a number of load-bearing elements (8, 20), each load-bearing element
(8) comprising a first and a second metal beam (10) and metal bars (12) fitted in-between
the latter, each pair of successive bars (12) forming a triangle with one of the metal
beams (10), and the first metal beam (10) being disposed, at least partly, in the
first concrete slab (4) and the second metal beam (10) being disposed, at least partly,
in the second concrete slab (6).
6. Prefabricated construction element according to one of the preceding claims, in which
the load-bearing is produced of steel and in particular reinforcing steel.
7. Floor comprising at least one construction element according to one of the preceding
claims.
8. Floor according to claim 7, in which a concrete layer (22, 32) is arranged on a surface
formed by installing a number of concrete slabs (4, 6, 44, 46) of a number of construction
elements (2, 42) as floor elements.
9. Floor according to claim 7 or 8, in which the space between the first and second concrete
slabs (4, 6, 44, 46) is at least partially filled with cellular concrete, heavy concrete,
thermal insulation material or sound insulation material.
10. Floor according to claim 8 or 9, in which a reinforcement (24) is arranged in concrete
applied after a construction element (2) has been installed.
11. Wall comprising a prefabricated construction element (42) according to one of the
claims 1-6.
12. Wall according to claim 11, in which the space between the first and second concrete
slabs (44, 46) is at least partially filled with cellular concrete, heavy concrete,
thermal insulation material or sound insulation material.
13. Wall according to claim 12, in which a reinforcement (24) is arranged in concrete
(48) applied after a construction element (42) has been installed.
14. Covering panel clearly intended for covering openings between construction elements
(2, 42) in a floor according to one of claims 7 - 10 or a wall according to one of
claims 11 - 13.
15. Method for producing a construction element according to one of the claims 1 - 6,
the method comprising:
producing a load-bearing element (8) for a load-bearing structure,
producing a first concrete slab (4, 44) in connection with said load-bearing structure,
and
producing a second concrete slab (6, 46) in connection with said load-bearing structure,
said load-bearing element (8) comprising a first and a second metal beam (10) and
metal bars (12) fitted in-between the latter, each pair of successive bars (12) forming
a triangle with one of the metal beams (10) and production of the load-bearing element
(8) comprising substantially simultaneously welding a bar (12) to the first beam (10)
and to the second beam (10).
16. Method according to claim 15, in which the welding of a bar (12) to a beam (10) comprises
welding simultaneously along two seams.