Backgroud of the Invention
[0001] The invention relates to the reinforcement of an existing armoured concrete console
column with consoles by pre-stressing, which will enable manipulation with heavier
products in old production halls than those for which the hall was originally designed,
and the process of its reinforcement.
State of the Art
[0002] There are numerous production halls dating back to the sixties up to the nineties
that were built as armoured concrete structures. A part of the structure was a crane
runway made on armoured concrete beams with short armoured concrete consoles. The
original crane runways were usually designed for 5-ton bridge cranes. However, recently
the style of the production has notably changed. Demands for engineering production
in particular require manufacturing ever bigger and more complete units that are shipped
to customers as ready-to-use products. Thus the manufacturer has to deal with challenging
requirements for manipulation, usually followed by a requirement for the installation
of a bigger bridge crane with a higher load carrying capacity into the existing production
hall. Current engineering plants thus call for cranes with a higher load carrying
capacity, often requiring a load carrying capacity of 25 tons.
[0003] The problem may be dealt with by installing a new carrying system for a new crane
runway into the existing hall structure. The new structure, which is usually made
of steel, requires, besides heavy expenses, an intervention into the layout of the
hall space itself. A new system of posts and separate footings will be added that
must be embedded beside the existing modular system. The utility value of the hall
space is thus reduced.
[0004] The stress analysis of the structural hall system usually demonstrates, in particular
with terminal, less load carrying columns, where the strain is taken off the roof
structure e.g. due to skylights, or if there is little transversal span between the
columns, the insufficiency of the columns from the viewpoint of the strength limit
state No. 1 (I.LS).
[0005] One commonly used possibility is to reinforce the armoured concrete column by bandaging
it with steel mending plates forming a new external steel carrying system anchored
into the existing columns. A problem arises concerning the divergent behaviour of
steel and concrete, as well as concerning the high labour requirements. This option
may also be complicated by spout pipes and media distribution systems for manufacturing
and heating usually going along the columns.
[0006] These solutions are indeed very costly and require the stoppage of production and
operations in the hall being reconstructed.
[0007] The aim of this invention is to present a solution ensuring enhanced load carrying
capacity of the columns that would allow bridge cranes to be used with high load carrying
capacity, while the manufacture of the invention will not limit operations in the
production hall.
Feature of the Invention
[0008] The above-mentioned disadvantages are considerably eliminated by the use of a reinforced
console column according to the invention, where a hole is bored through the column
section, into which an anchor element is mounted, and the ends of at least two prestressed
guys are anchored to the anchor elements on each side of the column section, the guy
goes through the respective holes in the anchor element and the other end of the prestressed
guy is firmly anchored in the anchor in the foundation and further at least one duct
is made in the console vertically to the column axis going through the console and
the adjacent part of the column strut, the prestressed clamping cable or bar is arranged
in the duct, both ends of which are provided with anchor sockets mounted to the anchor
plates. The fundamentals of the invention can be seen in the attached Graph 1 of the
column load carrying capacity depending on the axial force (kN) and the bending moment
(kN/m). The figures shown are just illustrative, but they in general correspond to
normal conditions.

[0009] By introducing compression into the existing, low loaded but bent column, its load
carrying capacity will be significantly enhanced. In such a case the foundation structure
will not be exposed to an additional load.
[0010] In an advantageous embodiment, the anchor elements are created as anchor tubes and
the prestressed guys are anchored in anchor sockets that fit to the outer surface
of the tube from above and the guys go through them.
[0011] In another advantageous embodiment, the prestressed guy goes angle-wise.
[0012] In still another advantageous embodiment, the hole and the anchor section are arranged
in the upper part of the column section in the area from where the consoles are projecting.
[0013] In another advantageous embodiment, the column is provided with four prestressed
guys with two cables going along each side of the column element whose ends are anchored
in the anchor tube from where the guys go crossways alongside the axis to the anchors
in the foundation.
[0014] Another feature of the invention is the process of manufacture of the reinforced
column where the guy is anchored on both sides of the column section with one end
in the foundation and with the other one in the anchor element which is to be created
in the upper part of the column section, subsequently the guy is prestressed either
parallel with the axis of the column section or angle-wise, and a duct will be made
in the console, vertical to the column axis, going through the console and the adjacent
part of the column strut, afterwards a clamping cable (s) or bar is arranged in the
duct and subsequently ptrestressed and anchored on both ends.
Description of the Drawings
[0015] The invention will be further explained using drawings, in which Fig. 1 is a side
view of the reinforced column subject to the invention according to design no. 1 with
two stay cables, Fig. 2 shows a front view of the same reinforced column, Fig. 3 shows
a side view of the reinforced column subject to the invention according to design
no. 2 with four stay cables, Fig. 4 shows a front view of the same reinforced column,
Fig. 5 shows a schematic cross section of the reinforced console of the armoured concrete
column subject to the invention with console on both sides for the crane runway, Fig.
6 shows a schematic cross section of the reinforced console of the armoured concrete
column subject to the invention with a console for the crane runway on one side only,
and Fig. 7 shows a partial cross section of an alternative design of the reinforced
console.
Preferred Embodiments of the Invention
[0016] Figs. 1 and 2 show that the reinforced column
1 consists of an armoured concrete column section
2 equipped with a console
3, on which beams
4 of the crane runway are mounted. The column section
2 is embedded in the foundation
5. A hole is bored through the column section
2, into which an anchor element
6 is embedded. In an advantageous embodiment, it is made as an anchor tube
7. The ends of the prestressed guys
8 are anchored into the anchor elements
6 by pulling the guy through the respective holes in the anchoring tube
7, and in the downward direction the ends of the guys
8 are firmly fixed in the anchor sockets
9 that fit to the anchor tube
7. In this case the bearing surface of the anchor sockets
9 has such a shape to allow it to fit to the tube
7 perimeter shape-wise.
[0017] The other end of the prestressed guy
8 is firmly anchored in the anchor
10 in the foundation
5. In the embodiment shown, the prestressed guy
8 is arranged angle-wise, but this is not conditional. It may also be arranged vertically.
The reason of the arrangement of the guys
8 on the column element
2 is the reinforcement of column
1 in the direction of its axis.
[0018] The hole with the anchor tube
7 is made in the upper part of the column section
2 taking advantage of the spot where the consoles
3 project from the section.
[0019] Figs. 3 and 4 show the embodiment of the reinforced column
1 provided with four prestressed guys
8. Afterwards the ends of both guys
8 are arranged in the anchor tube
7 on each side of the column section
2 ;from there the guys
8 go crossways to the anchors
10 in the foundation
5.
[0020] As it is evident in Figs. 1 and 3, two guys are used for columns with one console,
while four guys
8 are used for columns with consoles on both sides. These columns are subject to greater
stress and it is thus necessary to reinforce column
1 more.
[0021] Fig. 5 shows that consoles
3 for crane runways are projecting from the armoured concrete column
1 on both sides, on which beams
4 for bridge crane tracks will be mounted. Both consoles
3 are interconnected by pre-bored ducts
12, vertical to the column
1 axis. The prestressed clamping cables
13, or rather bars, go through these pre-bored ducts
12. They are anchored on each side in the anchor sockets
15 with nuts. There is an anchor plate
14 under the anchor sockets.
[0022] The upper prestressed clamping cable(s)
13 is led in the upper part of the consoles
3 where the lateral surface is vertical to the pre-bored duct
12. Thus the anchor plate
14 will easily fit to the side of the console
4. The lower prestressed clamping cable
13 is led in the bottom part where the bottom wall of the console
3 joins the strut angle-wise: A recess
11 is made around the duct
12 with its front parallel to the axis of the column
1. The anchor plate
14 will then easily lean against this front.
[0023] Fig. 6 shows the reinforced (e.g. terminal) console column
1 also consisting of a strut from which, however, a console
3 for beam
4 projects, on which the tracks for the bridge crane are mounted on one side only.
The console
3 and the adjacent part of the strut are interconnected by pre-bored ducts
12, vertically to the axis of the column
1. Prestressed clamping cables
13 or rather bars are led through these pre-bored ducts
12. They are anchored on each side in the anchor sockets
15 with nuts. Under the anchor sockets there is the anchor plate
14. In the area of the lower prestressed clamping cable
13, a recess
11 is made in the oblique wall of the console
3.
[0024] Fig. 7 shows details of a solution in which the recess
11 referred to in the previous designs is not used for the lower post-tensioning cable,
but a spacer
16 is inserted in between the anchor plate
14, which is oblique and lies on the unmodified oblique lateral wall of the console
3, and the socket
15 with a nut. The spacer corresponds on one side to the inclination of the oblique
lateral wall of the console
3 and has a bearing surface for the anchor socket
14 on the other side parallel to the column axis. The concept of a reinforced console
of a column is based on a surprising discovery that, in contrast to the theories acknowledged
so far, it is not necessary to apply counter pressure in the same direction against
the direction of the stress. The point is that the console
3 is subject to downward stress and that the anticipated deforming fracture would go
from the lower footing of the console crossways to the upper surface where the beam
for crane tracks is mounted. So far theory would induce to anchor the cable on the
oblique side of the console and to anchor its other end somewhere higher to the column
so that the cable goes vertically to the fracture, i.e. against the direction of stress.
It is obvious that such anchorage would be very demanding as far as the anchoring
element on the column is concerned; it would require double boring of the column for
ducts
12 in the bilateral console.
[0025] There is lateral force applied against the direction of stress in the reinforced
console column subject to the invention.
The Process of Reinforcement of Short consoles of Armoured Concrete Columns by Prestressing
[0026] The use of a non-typical steel device mounted to the armoured concrete column allows
for boring with a standard drill, even in the oblique part of the column console.
The minimum diameter of the borehole for one cable is 24 mm, being 40 mm for a cluster
of cables. For a cluster of cables the borehole is widened to a minimum diameter of
80 mm at its end with a depth of 170 mm. The recess will allow for distributing the
cables into the anchoring elements with permissible curvature. The directioning itself
of the prestressed clamping cables
13 is achieved by beveling the bearing surface for the anchors on the anchor bearing
plate and directioning the cable entry.
[0027] Prestressing of each separate cable is carried out in 6 steps, starting at 0 kN and
reaching the final value of 220 kN. The prestressing procedure is checked during each
step in accordance with the stress-strain diagram of the prestressing jack where the
value of the operating pressure of the jack corresponds to the prestress force introduced.
The pressure is monitored with a pressure gauge. Individual steps of the whole prestressing
procedure are entered into a control record where the value of elongation in mm is
entered with the particular value of the operating pressure of the prestressing jack
in MPa. After achieving the maximum value of the jacking force of 220 kN, the cable
is re-tensioned twice with a 15-minute delay as a minimum. This shall eliminate the
losses of prestress force due to relaxation of the prestressed reinforcement. The
overall elongation of the cable, the anchorage of the opposite anchor and cable rectification
may vary from 35 to 55 mm with commonly used consoles. Subsequently the cable is carefully
anchored at the side where tensioning takes place.
[0028] Concrete compression from 50 µm/m to 90 µm/m is achieved by the above-mentioned method
for standard types of consoles using three cables prestressed at 220 kN, depending
on the particular value of the stress modulus of the column console concrete.
[0029] When using a cluster of cables, the widened area of the borehole is injected with
a constant-volume sealing compound. A grout hole is made in the anchor plate for this
purpose.
[0030] An analogical procedure will be used with other types of prestressing reinforcement
taking into account its particular stress-strain diagram, the maximum value of prestress
and the manner of anchorage.
1. Reinforced console column consisting of a column section and a console, characterized in that a hole is bored through the column section (2), into which an anchor element (6)
is mounted, and the ends of at least two prestressed guys (8) are anchored to the
anchor elements (6) on each side of the column section, the guy (8) goes through the
respective holes in the anchor element (6) and the other end of the prestressed guy
(8) is firmly anchored in the anchor (10) in the foundation (5) and further at least
one duct (12) is made in the console (3) vertically to the column axis (1) going through
the console (3) and the adjacent part of the column strut, the prestressed clamping
cable (13) or bar is arranged in the duct, both ends of which are provided with anchor
sockets (15) mounted to the anchor plates (14).
2. Reinforced console column according to claim 1 characterized in that the anchor elements (6) are created as anchor tubes (7) and the prestressed guys
(8) are anchored in anchor sockets (9) that fit to the outer surface of the tube (7)
from above and the guys (8) go through them.
3. Reinforced console column according to claim 1 characterized in that at least one cable (13) is arranged under the upper surface of the console (3) in
the manner that the anchorage is made on the flat part of the lateral wall parallel
to the column axis, and the other cable is arranged in the lower part of the console
(3) and the anchorage is made on the oblique part of the lateral wall.
4. Reinforced console column according to claim 7 characterized in that the anchor plates (14) of the lower prestressed clamping cable (13) are placed on
the oblique part of the lateral wall of the console (3), and a spacer (16) is inserted
between the anchor plate (14) and the anchor socket, whose bearing surface towards
the anchor plate (14) has an inclination corresponding to the inclination of the oblique
part of the lateral wall of the console (3).
5. Reinforced console column according to claim 1 characterized in that a recess (17) is made in the console (3) under the anchor plate (14) for the distribution
of the cluster of cables and subsequent constant-volume mortar injection.
6. The process of manufacture of the reinforced console column according to claims 1
to 9 characterized in that the guy is anchored on both sides of the column section with one end in the foundation
and with the other one in the anchor element which is to be created in the upper part
of the column section, subsequently the guy is prestressed either parallel with the
axis of the column section or angle-wise, and a duct will be made in the console,
vertical to the column axis, going through the console and the adjacent part of the
column strut, afterwards a clamping cable (s) or bar is arranged in the duct and subsequently
prestressed and anchored on both ends.
7. The process according to claim 6 characterized in that two guys are anchored on each side of the column section and both of them are anchored
in the anchor element and are led to the anchors in the base angle-wise.
8. The process of manufacture of the console column according to claim 7 characterized in that one the prestressed clamping cable is arranged under the upper surface of the console
and the other cable in the lower part of the console on the oblique part of its lateral
wall.
9. The process of manufacture of the console column according to claim 8 characterized in that a recess is made in the oblique part of the lateral wall of the console.
10. The process of manufacture of the console column according to claim 6 characterized in that the duct is widened at its periphery into a recess which, is filled with grout after
prestressing of the clamping cable.