[0001] The present invention relates to a method for manufacturing a pile; to a pile obtainable
with this method and to a pile.
[0002] In the prior art the use of piles to support buildings has been known for a long
time. Piles that are currently used can be manufactured in per se efficient manner
by pouring concrete into a mould, this mould giving the pile the desired form. The
use of a mould provides advantages because it is a relatively simple manner of preparing
piles. The drawback of this method of preparing piles is that only solid piles can
be manufactured. These solid piles are relatively heavy and have to be provided with
relatively heavy longitudinal reinforcement. This results in transport costs being
relatively high.
[0003] In addition, not all concrete present in the solid concrete pile is necessary from
a structural viewpoint. In particular a portion of the concrete present around the
core, i.e. the centre of the pile, could from a structural point of view be removed
and replaced by another material, preferably a lighter and/or cheaper material.
[0004] No practical method has however been available heretofore for the manufacture of
such piles. This has the consequence that structurally too much material is used to
prepare a pile, this having an unfavourable effect on the costs of producing and transporting
the pile. It further results in a greater environmental impact.
[0005] The present invention has for its object to provide a solution to the above stated
problems.
[0006] A first aspect of the present invention therefore relates to a method for preparing
a pile, comprising the steps of:
I) arranging in a mould a plastic fill element and at least one positioning means
for positioning the plastic fill element in the mould;
ii) pouring concrete into the mould such that the fill element is substantially enclosed
by the concrete;
iii) at least partially curing the poured concrete.
[0007] An advantage of this method is that a pile with an acceptable structural strength
can be manufactured wherein less concrete need be used than in a conventional solid
pile. This has a favourable effect on the production cost of the pile and on the environmental
impact resulting from the production process.
[0008] It is possible to position the fill element at a desired position by means of the
positioning means. The fill element is preferably positioned such that it is situated
centrally in the pile to be formed.
[0009] It is recommended that the fill element comprises a plastic foam material, such as
for instance a polystyrene foam. An advantage of the use of such materials is that
they are relatively light but can also withstand the pressure of the poured concrete.
This prevents considerable differences occurring in the thickness of the wall of the
pile along its length. The plastic foam is preferably in the form of an already solid
foam which can be brought into a desired shape which it also substantially retains
during pouring of the concrete.
[0010] The positioning means preferably comprise a fixing element extending in longitudinal
direction of the mould, wherein during the performing of step i) the fill element
is arranged on or round the fixing element. Through the use of such a fixing element
it is possible to arrange the fill element in the mould, preferably centrally in the
pile to be formed, in simple and rapid manner. This has a favourable effect on, among
other things, the production cost of the pile.
[0011] It is further recommended that the positioning means comprises at least one spacer,
wherein the fill element is positioned before or during performing of step ii) of
the method according to the invention.
[0012] An advantage of the use of such spacers is that the fill element can be positioned
relatively quickly and easily at the correct location in the pile to be formed. The
fill element can be positioned during pouring of the concrete due to the presence
of the spacers, which are preferably of plastic. Through the pouring of the concrete
the fill element will generally begin to float, at least move toward the top side
of the mould. By arranging spacers in the mould this upward directed movement of the
fill element is stopped, and the fill element is positioned. A plurality of spacers
are preferably used to position the fill element. The spacers can be provided with
a clamping part with which they can be fixed for instance to the reinforcement and/or
mould of the pile.
[0013] It is recommended that the spacer is fixed to the reinforcement of the pile to be
formed. It is particularly recommended here that it is fixed to longitudinal reinforcement
of the pile. It is further also possible for the spacers to be (removably) fixed to
the mould or a mould cover extending over the top side of the mould. Such a mould
cover preferably comprises a metal plate or pin.
[0014] It is further recommended that the spacers are placed partially in the fill element.
It is then recommended that the fill element comprises a plastic foam material, such
as for instance recycled polystyrene or expanded polystyrene. The portion of the spacer
extending into the fill element is then preferably provided with a barbed profile
such that a good connection is obtained between the fill element and the spacer. The
spacer is in this case preferably supported by a mould cover.
[0015] It is further recommended that the positioning means substantially centre the fill
element in the pile to be formed. A pile is hereby obtained which very readily absorbs
the forces during inter alia pile-driving. In addition less concrete is necessary,
this resulting in reduced production cost and less of an environmental impact.
[0016] In a recommended embodiment the positioning means comprise a fixing element extending
in longitudinal direction as well as spacers. A good fixation of the fill element
in the mould is thus obtained.
[0017] The fill element is preferably manufactured from material with a lower specific mass
than cured concrete. An advantage hereof is that the pile is relatively light, which
has a favourable effect on the cost of transporting the pile.
[0018] It is recommended that the fill element extends substantially along the whole length
of the mould. An advantage hereof is that even less concrete need be used. This has
a favourable effect on production cost and on environmental impact.
[0019] It is a further recommended that the fill element is of elongate form.
[0020] It is also recommended that the fill element comprises separate parts. The advantage
hereof is that people involved in the manufacture of the pile can relatively easily
arrange the fill element, at least the separate parts thereof, on the fixing element
(or spacers). In addition, the fill element is then relatively easy to transport.
This is particularly recommended when the pile is relatively long.
[0021] In a further preferred embodiment the fill element is constructed from a number of
fill element parts placed successively with intermediate spacing. The intermediate
spaces are herein filled with concrete during pouring. The structural stiffness of
the pile can be adjusted as required by variation of the number, the positions and/or
the dimensions of the intermediate spaces. In a further embodiment the spacers extend
through the intermediate spaces so that the spacers can rest on the fixing element
instead of on the fill element.
[0022] It is possible by means of the fixing element to position the fill element in the
mould such that the fill element is centred in the pile to be formed.
[0023] The fixing element preferably comprises a soft steel rod, a prestressed steel wire,
a prestressed steel strand or a prestressed plastic wire.
[0024] The fill element is preferably arranged at a distance from a first outer end and/or
a second outer end of the mould such that at least one solid end of the pile is formed
when the concrete is poured. The advantage hereof is that a solid head and/or foot
of the pile is obtained in this manner which can withstand relatively great loads
during pile-driving. An additional advantage is that no earth can enter the pile during
pile-driving.
[0025] It is further recommended that the fill element is rod-like and is provided with
a slot extending in the longitudinal direction for arranging the fill element on or
round the fixing element. The fill element can be arranged very quickly by means of
such a slot.
[0026] It is also recommended that the slot width of the fill element is greater than the
transverse dimension of the fixing element. The fill element can hereby be arranged
quickly and easily on or round the fixing element, and can also be displaced.
[0027] It is further recommended that the slot extends beyond the centre of gravity of the
fill element.
[0028] It is also recommended that the slot of the fill element is pushed over the fixing
element such that the fill element is substantially centred in the pile to be formed,
and wherein the fill element is rotated before or during pouring of the concrete such
that the fill element is fixed on the fixing element during the pouring. Fixing is
here understood to mean, among other things, that the fill element cannot float upward
during the pouring.
[0029] It is further recommended that longitudinal reinforcement is arranged in the mould
prior to the performing of step ii) of the method according to the invention such
that the longitudinal reinforcement is incorporated in the concrete. Such longitudinal
reinforcement results in a reduced chance of the pile breaking during transport and
pile-driving.
[0030] In a recommended embodiment spiral reinforcement is arranged at least at one end
of the mould. Through the arranging of such spiral reinforcement the end of the pile
is better able to withstand the relatively great loads during pile-driving.
[0031] It is also recommended that a reinforcing band extending along the inner periphery
of the mould is arranged at least at one end of the mould. Such a reinforcing band
is preferably of metal. An advantage of such a band is that it can be placed relatively
easily in the mould. An additional advantage is that the band can also be arranged
after curing of the pile. A further advantage of such a band is that a head or a foot
is obtained which can withstand the relatively great loads during pile-driving.
[0032] The fill element preferably comprises a tube. The advantage of such a fill element
is that it is relatively strong, whereby a relatively large amount of concrete can
be poured onto it without it being compressed. In addition, relatively little material
is required to manufacture a fill element of a relatively large size.
[0033] In a recommended embodiment the fill element is a tube, wherein at least a portion
of the inner side of the tube is provided with a securing element extending over the
inner periphery of the tube. It is recommended here that the securing element comprises
a plastic foam material such as polystyrene foam. The securing element can then be
arranged on or round the fixing element such that the tube is positioned. It is recommended
here that the securing element is a plastic cylinder, the wall of which is in clamping
contact with the inner wall of the tube.
[0034] It is further recommended that the fixing element is removed after or during performing
of step iii).
[0035] In an embodiment according to the invention the concrete in step ii) comprises broken
concrete granulate, this resulting in a relatively small environmental impact since
broken concrete granulate can be reused.
[0036] In another embodiment of the present method a metal band extending along the periphery
of the pile is arranged after performing step iii). It is particularly recommended
here that the pile is substantially cured.
[0037] A second aspect of the present invention relates to a pile obtainable with the above
described method.
[0038] A third aspect of the present invention relates to a pile comprising a casing of
cured concrete and a core extending in longitudinal direction of the pile, which core
comprises a plastic fill element.
[0039] The advantage of such a pile is that it comprises relatively little concrete. The
cost price of such a pile is hereby relatively low. Such a pile further has less of
an environmental impact since it comprises less concrete than a solid pile.
[0040] It is recommended here that the fill element comprises a plastic foam material such
as polystyrene foam. Such material is relatively light and well able to withstand
compression, whereby a pile is obtained with a diameter of the core which is substantially
the same everywhere.
[0041] It is recommended that the fill element has a substantially round, polygonal such
as octagonal or rectangular form.
[0042] It is further recommended that the fill element is rod-like.
[0043] In a recommended embodiment the fill element is provided with a slot which extends
in longitudinal direction of the fill element and which is used to arrange the fill
element on the fixing element. The slot preferably extends as far as or beyond the
centre of gravity of the fill element. If the fixing element is removed after preparation
of the pile, this slot can be used for different purposes, such as for instance concrete
core activating purposes. Particularly when a plastic foam material is used, the core
can then serve as insulating/protective material for a conduit arranged through the
slot.
[0044] It is recommended here that the slot width is smaller than the transverse dimension
of the fixing element. The advantage hereof is that the fill element can be arranged
relatively easily on the fixing element and, if necessary, can be rotated more easily.
Close to the end of the slot the slot width is preferably greater than the transverse
dimension of the fixing element. The fill element can hereby be arranged even more
easily on the fixing element and held at the desired position.
[0045] It is recommended that at least one end of the pile is provided with a concrete closure.
The advantage of such a closure is that a head and/or foot of the pile is obtained
which can withstand relatively great loads during pile-driving. An additional advantage
is that no earth can penetrate into the pile during pile-driving.
[0046] It is also recommended that the core is provided with a fixing element extending
in longitudinal direction of the pile. The advantage of such a fixing element is that
it can also be used as prestressed reinforcement for purposes of strength, but also
as earthing rod/earthing wire, for instance for an electrical system.
[0047] Mentioned and other features of the method for manufacturing a pile and the pile
according to the invention will be further elucidated hereinbelow on the basis of
a number of exemplary embodiments, which are given only by way of example without
the invention thereby being deemed limited thereto. Reference is herein made to the
accompanying drawings, in which:
Figure 1 shows a view of a mould for preparing a pile according to the invention;
Figure 2 shows a view of the mould of Figure 1, wherein a fill element is arranged
for the preparation of a pile according to the invention;
Figure 3 shows a view of the pouring of concrete into the mould of Figure 2;
Figure 4 shows a view of a pile according to the invention;
Figure 5 shows a cross-section along the line IV-IV of the pile of Figure 4;
Figure 6 shows a cross-section of a pile according to an embodiment of the invention;
Figure 7 shows a view of a pile according to the invention;
Figure 8 shows a cross-section along the line VIII-VIII of the pile of Figure 7;
Figure 9 shows a cross-section of a further embodiment of the pile;
Figure 10 shows a view of a pile according to an embodiment of the invention;
Figure 11 shows a cross-section of the pile of Figure 10;
Figure 12 shows a view of a pile according to an embodiment of the invention;
Figure 13 shows a cross-section of the pile of Figure 12;
Figure 14 shows a top view of a mould for preparing a pile according to the invention;
Figure 15 shows a cross-section of a further preferred embodiment of a pile according
to the invention;
Figure 16 shows yet another embodiment of the pile according to the invention;
Figure 17 shows yet another embodiment of the pile according to the invention.
[0048] Figure 1 shows a view of a mould 1 for preparing a pile according to the invention.
On the inner side of mould 1 a fixing element 2 is arranged in longitudinal direction
for the purpose of fixing a fill element 4 (not shown). Mould 1 is further provided
with longitudinal reinforcement 3 extending in lengthwise direction of mould 1. This
longitudinal reinforcement 3 ensures that the chance of the pile breaking during transport
and pile-driving is reduced.
[0049] Figure 2 shows the mould of Figure 1, wherein a fill element 4, preferably of polystyrene
foam, is arranged round fixing element 2. Fill element 4 is provided along the whole
length with a slot 5. It is possible to slide fill element 4 over the fixing element
through this slot 5. Slot 5 extends inward at least to a position beyond the centre
of gravity 6 of the fill element. In order to ensure that fill element 4 does not
detach from fixing element 2 during pouring of the concrete 7 (not shown), the fill
element is rotated such that opening 8 of slot 5 is directed toward the upper side
of mould 1.
[0050] Figure 3 shows pouring of concrete 7 in mould 1. The pile is given the desired form
by means of walls 9 and 10 and bottom 11 of the mould. Possible shapes are, among
others, square, pentagonal, hexagonal, octagonal or round. The longitudinal reinforcement
3 and fill element 4 are wholly enclosed by the concrete 7 during the pouring. Fixing
element 2 here ensures that fill element 4 does not displace to the top side of the
mould, or only does so to a limited extent. Pouring of concrete 7 continues until
the upper edge of walls 9 and 10 is reached. The whole is then allowed to cure for
some time. The mould is optionally provided with a mould cover (not shown) extending
along the top side of the mould.
[0051] Figure 4 shows a pile 12 according to the invention. Pile 12 is provided with a fill
element 13 extending in longitudinal direction of the pile, wherein the fill element
is enclosed by a casing 14 of cured concrete. Fill element 13 consists of a number
of separate parts 13a and 13b, whereby the fill element can be arranged relatively
easily during preparation of pile 12. The fixing element 15 is visible that has served
to hold fill element 13 in its position. It is however possible to remove this fixing
element 15 during or after curing of pile 12. Pile 12 is further provided with longitudinal
reinforcement 16 in order to ensure a reduced chance of pile 12 breaking during transport
and pile-driving.
[0052] Figure 5 shows a cross-section of pile 12 of Figure 4. Here the fill element 13 is
enclosed by a concrete casing 14. Longitudinal reinforcement 16 is incorporated in
this concrete casing. Fill element 13 is provided with a slot 17 extending up to the
centre of gravity 18 of the fill element. Fill element 13 lies against fixing element
15. Fixing element 15 and fill element 13 are positioned during preparation of pile
12 such that fill element 13 is situated centrally in pile 12. Further indicated are
optional spacers 19 remaining on the outer surface of fill element 13 which further
contribute toward the fill element 13 being held at the desired position during preparation
of pile 12. The use of only a fixing element 15 is however also possible.
[0053] Figure 6 shows an embodiment of the invention wherein spacers 20 and 21 are used
to position fill element 22 during preparation of pile 23. Spacers 20 are connected
to longitudinal reinforcement 24 extending in lengthwise direction of pile 23. During
manufacture of pile 23 the spacer 21 was connected to a mould cover arranged on the
top side of mould 25 (not shown). Spacers 20 can optionally be used separately or
spacer(s) 21 can be used separately. It is however recommended to use them together.
[0054] Figure 7 shows another preferred embodiment of a pile 26 according to the invention.
Pile 26 is provided with a fill element 27 situated in the core of pile 26. This fill
element 27 is here enclosed by a concrete casing 28. This fill element 27 consists
of a tube 29, preferably of plastic, which is provided at one end with a securing
element 31 extending along inner wall 30 of the tube. This securing element 31 is
preferably manufactured from metal or plastic. Securing element 31 herein lies close-fittingly
against inner wall 30 of tube 29. By making use of such an arrangement it is possible
to position tube 29 centrally in pile 26 because the tube is arranged around fixing
element 32. Pile 26 is further provided with longitudinal reinforcement 33 extending
in the concrete casing 28. Spacers 34 and/or 35 are optionally arranged in order to
further ensure that tube 29 is held centrally in the pile 26 to be formed during preparation
of the pile. Spacers 34 are attached to longitudinal reinforcement 33 of pile 26,
spacer 35 having been connected to the mould and/or mould cover (not shown) during
preparation of the pile. During preparation of pile 26 the tube 29 comes to lie against
these spacers 34 and/or 35, whereby tube 29 can be positioned precisely.
[0055] Figure 8 shows a cross-section of pile 26 of Figure 7. Tube 29 is situated centrally
in pile 26. In order to hold tube 29 in position during manufacture a securing element
31 is arranged in tube 29. This securing element 31 is arranged round fixing element
32. Tube 29 is enclosed by a casing 28 of cured concrete. Longitudinal reinforcement
33 is arranged in this casing 28 for additional strength during transport. Spacers
34 and/or 35 are further received in concrete casing 28. These spacers 34 and/or 35
are used during manufacture to position tube 29 centrally in pile 26.
[0056] Figure 9 shows a pile 36 according to a further embodiment of the present invention.
The fill element herein comprises a tube 37, preferably of plastic. Tube 37 is enclosed
by a concrete casing 38. Longitudinal reinforcement 39 is received in this concrete
casing 38. This longitudinal reinforcement 39 extends in the lengthwise direction
of pile 36 and reduces the chance of pile 36 breaking during transport and pile-driving.
Spacers 40 and 41 are further provided. These spacers 40 and/or 41 are used during
manufacture of pile 36 to position tube 37 centrally in pile 36.
[0057] Figure 10 shows a pile 42 according to the invention. This pile 42 is open on the
top side such that fill element 43, which is situated centrally in pile 42, can be
seen. This fill element 43 is enclosed by a concrete casing 44. In order to impart
extra strength to the head and/or the foot of the pile, the upper end and/or the lower
end of the pile is provided with a reinforcing band 45 extending in peripheral direction
of pile 42.
[0058] Figure 11 shows a cross-section of pile 42 of Figure 10. Pile 42 herein comprises
a fill element 43 extending along a fixing element 46. Fill element 43 is enclosed
by a concrete casing 44 incorporating longitudinal reinforcement 47. The head of the
pile is however open, at least fill element 43 is visible from outside. A reinforcing
band 45 extending along the periphery of the pile is arranged in the head, close to
the end of the pile.
[0059] Figure 12 shows a recommended embodiment of the present invention. Pile 48 herein
comprises a concrete closure 49 (not shown) which ensures that a solid head 50 and/or
foot is formed. The pile is further provided with a concrete casing 51.
[0060] Figure 13 shows pile 48 of Figure 12 in cross-section. Pile 48 is provided with a
solid head 50 and a concrete casing 51 provided with longitudinal reinforcement 52.
A fill element 53 also extends in longitudinal direction of pile 48. The concrete
closure 54 is preferably integrated with the concrete casing 51 of pile 48. Owing
to this solid head 50 pile 48 is better able to withstand the relatively great forces
during pile-driving. Pile 48 is preferably further provided in head 50 and/or the
foot with so-called spiral reinforcement 54. This spiral reinforcement 54 makes head
50 still better able to withstand the great forces during pile-driving.
[0061] Figure 14 shows a long mould 55 wherein the mould is divided into a number of sub-moulds
56. Sub-moulds 56 are separated from each other by means of end surface partitions
57. A plurality of concrete piles can be prepared in a batch by making use of such
a long mould 55. Longitudinal reinforcement 58 and fill elements 59 are arranged in
sub-moulds 56. These fill elements are positioned using a fixing element 60 (not shown).
[0062] Figure 15 shows a further preferred embodiment of the invention. This embodiment
greatly resembles the embodiment shown in figure 5 and a detailed description thereof
will not therefore be given. The embodiment of figure 15 shows a fill element with
an octagonal cross-section which is enclosed by a concrete casing 64 which incorporates
longitudinal reinforcement 66. Fill element 63 is provided with a slot 17 so that
the fill element can be pushed over fixing element 15. In contrast to the embodiment
shown in figure 5, spacers 69 do not rest on the outer surface of fill element 63
but are extended to a position against the central fixing element 15. Spacers 69 are
herein arranged at the position of the intermediate spaces between the separate parts
of fill element 63. Because spacers 69 rest on fixing element 15, less stringent structural
requirements need be made of the material of fill element 63. In the embodiment shown
in figure 5 the material of fill element 13 must after all have a strength such that
the underside of the respective spacers 19 do not cause any damage to the outer surface
of fill element 13. In addition, five spacers 69 are arranged in the embodiment shown
in figure 15. In other embodiments (not shown) this number can however be smaller,
as discussed above with reference to other embodiments of the invention.
[0063] Figure 16 shows a further preferred embodiment which largely corresponds with the
embodiment shown in figure 6. In the further embodiment no fixing element 15 is arranged
in fill element 73 of octagonal cross-section 9. In this embodiment fill element 73
is held in position by spacers 74 resting on one side on the outer surface 72 of fill
element 73 and/or attached on the other side to longitudinal reinforcement 39. In
this embodiment five spacers 74 are once again shown. An application with the small
number of spacers does however fall wholly within the reach of the skilled person.
[0064] Figure 17 shows a further preferred embodiment of the present invention. In this
embodiment no fixing element is arranged in fill element 79. Fill element 79 is held
in position in this embodiment by a spacer 75 extending in fill element 79, wherein
spacer 75 is provided at the end extending in fill element 75 (preferably of recycled
polystyrene foam) with a barbed profile 80 such that it is firmly connected to fill
element 75. The other end 81 of spacer 75 supports against a so-called mould cover
(not shown), such as for instance a pin which extends transversely of the longitudinal
direction of the mould and which is connected to the top side of the longitudinal
walls of the mould. This prevents fill element 79 floating upward during pouring of
the concrete. In addition, spacers 77 can also be used which are attached to longitudinal
reinforcement 76. An even better fixation of fill element 79 in the mould is thus
obtained.
[0065] The present invention is not limited to the preferred embodiments thereof described
herein. The rights sought are rather defined by the following claims, within the scope
of which many modifications can be envisaged.
1. Method for preparing a pile, the method comprising the steps of:
I) arranging in a mould a plastic fill element and at least one positioning means
for positioning the plastic fill element in the mould;
ii) pouring concrete into the mould such that the fill element is substantially enclosed
by the concrete;
iii) at least partially curing the poured concrete.
2. Method as claimed in claim 1, wherein the fill element comprises a plastic foam material,
preferably a polystyrene foam.
3. Method as claimed in claim 1 or 2, wherein the positioning means comprise a fixing
element extending in longitudinal direction of the mould, and wherein during performing
of step i) the fill element is arranged on or round the fixing element.
4. Method as claimed in claim 3, wherein the fixing element extends substantially centrally
in the pile to be formed.
5. Method as claimed in any of the claims 1-4, wherein the positioning means comprises
at least one spacer, wherein the fill element is positioned before or during performing
of step ii).
6. Method as claimed in claim 5, wherein a first end of the spacer is arranged in the
fill element and wherein a second end is supported against a mould cover.
7. Method as claimed in any of the claims 1-6, wherein the positioning means comprises
at least a first and second positioning means, and wherein the first positioning means
comprises a fixing element extending in longitudinal direction of the mould, and wherein
the second positioning means comprises at least one spacer.
8. Method as claimed in any of the claims 1-7, wherein the spacer is fixed to reinforcement
of the pile to be formed.
9. Method as claimed in any of the claims 1-8, wherein the spacer is fixed to the mould
cover and/or wall of the mould.
10. Method as claimed in any of the claims 1-9, wherein the positioning means substantially
centre the fill element in the pile to be formed.
11. Method as claimed in any of the claims 1-10, wherein the fill element has a lower
specific mass than cured concrete.
12. Method as claimed in any of the claims 1-11, wherein the fill element extends substantially
along the whole length of the mould.
13. Method as claimed in any of the claims 1-12, wherein the fill element defines an elongate
form.
14. Method as claimed in any of the claims 1-13, wherein the fill element comprises separate
parts.
15. Method as claimed in claim 14, wherein the fill element is constructed from a number
of fill element parts placed successively with intermediate spacing.
16. Method as claimed in any of the claims 1-15, wherein the fill element is arranged
at a distance from a first outer end and/or a second outer end of the mould such that
at least one solid end of the pile is formed when the concrete is poured.
17. Method as claimed in any of the claims 1-16, wherein the fill element is rod-like
and is provided with a slot extending in the longitudinal direction for arranging
the fill element on the fixing element.
18. Method as claimed in claim 17, wherein the slot width is greater than the transverse
dimension of the fixing element.
19. Method as claimed in claim 17 or 18, wherein the slot extends beyond the centre of
gravity of the fill element.
20. Method as claimed in any of the claims 17-19, wherein the slot of the fill element
is pushed over the fixing element such that the fill element is substantially centred
in the pile to be formed, and wherein the fill element is rotated before or during
pouring of the concrete such that the fill element is fixed on the fixing element
during the pouring.
21. Method as claimed in any of the claims 1-20, wherein longitudinal reinforcement is
arranged in the mould prior to performing of step ii).
22. Method as claimed in any of the claims 1-21, wherein spiral reinforcement is arranged
at least at one end of the mould.
23. Method as claimed in any of the claims 1-22, wherein a reinforcing band extending
along the inner periphery of the mould is arranged at least at one end of the mould.
24. Method as claimed in any of the claims 1-23, wherein the fixing element comprises
a soft steel rod, a prestressed steel wire, a prestressed steel strand or a prestressed
plastic wire.
25. Method as claimed in any of the claims 1-24, wherein the fill element comprises a
tube.
26. Method as claimed in any of the claims 1-25, wherein the fill element is a tube, and
wherein at least a portion of the inner side of the tube is provided with a securing
element.
27. Method as claimed in claim 26, wherein the securing element comprises a cylinder of
plastic foam material, wherein substantially the whole wall of the cylinder is in
clamping contact with the inner wall of the tube, whereby the cylinder is fixed in
the tube.
28. Method as claimed in any of the claims 1-27, wherein the fixing element is removed
from the pile after or during performing of step iii).
29. Method as claimed in any of the claims 1-28, wherein the concrete in step ii) comprises
broken concrete granulate.
30. Method as claimed in any of the claims 1-29, wherein a metal band extending along
the periphery of the pile is arranged after performing step iii).
31. Pile comprising a casing of cured concrete and a core extending in longitudinal direction
of the pile, which core comprises a plastic fill element.
32. Pile as claimed in claim 31, wherein the fill element comprises a plastic foam material,
preferably a polystyrene foam, such as recycled polystyrene foam.
33. Pile as claimed in claim 31 or 32, wherein the fill element has a substantially circular
or polygonal cross-section.
34. Pile as claimed in any of the claims 31-33, wherein the fill element is rod-like and
provided with a slot extending in longitudinal direction for arranging the fill element
on the fixing element.
35. Pile as claimed in claim 34, wherein the slot width is greater than the transverse
dimension of the fixing element.
36. Pile as claimed in claim 34 or 35, wherein the slot extends beyond the centre of gravity
of the fill element.
37. Pile as claimed in any of the claims 30-36, wherein the fill element has a lower specific
mass than cured concrete.
38. Pile as claimed in any of the claims 30-37, wherein the fill element comprises a tube.
39. Pile as claimed in any of the claims 30-38, wherein the fill element is a tube, wherein
at least a portion of the inner side of the tube is provided with a securing element.
40. Pile as claimed in claim 39, wherein the securing element comprises a cylinder of
plastic foam material, wherein substantially the whole wall of the cylinder is in
clamping contact with the inner wall of the tube, whereby the cylinder is fixed in
the tube.
41. Pile as claimed in any of the claims 31-40, wherein the fill element extends substantially
along the whole length of the pile.
42. Pile as claimed in any of the claims 31-41, wherein the fill element defines an elongate
form.
43. Pile as claimed in any of the claims 31-42, wherein the fill element is centred in
the pile.
44. Pile as claimed in any of the claims 31-43, wherein the fill element comprises separate
parts.
45. Pile as claimed in any of the claims 31-44, wherein the fill element is constructed
from fill element parts placed successively with intermediate spacing.
46. Pile as claimed in any of the claims 31-45, wherein at least one end of the pile is
provided with a concrete closure.
47. Pile as claimed in any of the claims 31-46, wherein the concrete casing is provided
with longitudinal reinforcement.
48. Pile as claimed in any of the claims 31-47, wherein at least one end of the concrete
casing is provided with spiral reinforcement.
49. Pile as claimed in any of the claims 31-48, wherein a reinforcing band extending along
the inner periphery of the mould is arranged at least at one end of the mould.
50. Pile as claimed in any of the claims 31-49, wherein the core is provided with a fixing
element extending in longitudinal direction of the pile.
51. Pile as claimed in any of the claims 31-50, wherein the fixing element comprises a
soft steel rod, a prestressed steel wire or a prestressed plastic wire.
52. Pile obtainable according to the method of any of the claims 1-30.