[0001] Scaffolding has long been used in industry for gaining access to high and awkward
locations. Whilst scaffolding provides a safe environment for operatives to work this
is not always the case for the persons erecting and dismantling scaffolding structures.
Various systems exist for providing temporary safety rails guard rails in advance
of the erection of the scaffolding tower but they are often difficult to install and
adjust.
[0002] This invention relates to a releasable attachment system whereby the guardrail system
may be easily adjusted within the scaffolding tower.
[0003] The guard rail system is independent from the scaffolding structure and is arranged
such that the scaffolding can be erected and dismantled whilst within the perimeter
of the guard rail system.
[0004] Once in place on the scaffold at ground level, the guard rail system may be progressively
relocated to higher levels in the scaffold tower providing a safe place of work for
the scaffolder to erect further equipment and to erect the permanent guardrail system.
During dismantling the safety rail system may be progressively relocated to lower
levels within the scaffold tower to provide a safe working environment for the operatives.
[0005] When the scaffold tower is erected to the required height, it is not necessary to
remove the upper guardrail system which may be left in place as a permanent safety
system until such time as dismantling of the scaffolding is performed.
[0006] The invention will now be described with reference to the following drawings in which:-
Fig.1 shows a front elevation, side elevation and plan view of a typical scaffolding
tower together with the guardrail system.
Fig.2, & Fig.3, show side elevations of the guardrail system used in the vertical
mode incorporating the locking and release mechanism.
Fig.4 shows a side elevation of the guardrail system used in the angled mode incorporating
the locking and release mechanism.
[0007] The Invention comprises of scaffolding frames 1-4 which incorporate vertical frame
members 5 and 6 and multiple, equally pitched, horizontal frame members 7 forming
a ladder like structure. These frames together with tie members 8 and bracing members
9 and 10 are coupled together using releasable hook members to form a scaffolding
structure. Platform units 11 may be positioned on any rung position to provide a level
working platform. The platform must be provided with a safely guarded area for the
scaffolding erector to work. This is achieved by attaching a guard rail system comprising
of end frames 20 & 21 and telescopic guard rails 22 & 23 which are pivotally and releasably
attached to the end frames. This 'guard rail assembly' may be attached to the scaffolding
rungs by remotely releasable hook devices.
[0008] The guard rail end frames 20 & 21 comprise upright members 30 & 31 together with
upper and intermediate horizontal members 32 & 33 together with a spacing member 34
which connect the upright members together. Releasable couplings 35 are incorporated
near to the upper and intermediate rail positions for the releasable attachment of
the telescopic guard rails. Each end frame upright member incorporates a lower hook
assembly 36 incorporating twin downward facing receiving apertures 37 & 38 which are
dimensioned such that they are a close fit around the scaffolding frame rung members.
[0009] Additionally third and fourth receiving members 39 incorporating horizontally facing
receiving apertures 40 are attached to the end frame members at such a position as
to present the apertures at a position relating to the position of a frame horizontal
member. Hook member 51 are attached to each of the third and fourth receiving members
and incorporates an abutment portion 52 and a limiting portion 53 and is pivotally
attached to the second receiving member such that the end of the hook member 55 partially
blocks the receiving aperture. The end frame upright members each incorporate a sliding
member 61 which is located around the upright frame member and incorporates blocking
pieces 62 and pairs of operating hand grips 63 and 64 similarly located around the
vertical member which are connected to the sliding member by a linking member 65 such
that when either the upper or lower hand grips are raised or lowered the sliding member
incorporating the blocking piece is raised in unison.
[0010] Raising of the blocking piece releases the rotating hook such that the hook is free
to rotate allowing the restriction in the horizontal receiving aperture to be removed,
lowering the blocking device causes the blocking piece to push onto the surface 62
causing the hook to rotate into the blocking position thus preventing the release
of the frame from the scaffolding.
[0011] To adjust the position of the guardrail system within the tower structure, the scaffolder
positions himself in a position within the permanent guarding on the tower and with
two hands grips either the upper or lower hand grips whichever is most convenient.
Raising both mechanisms simultaneously causes both hook blocking piece to be raised
(arrow 'A'), by then drawing the end frame towards himself rotationally (arrow 'C')
the hook members are caused to rotate (arrow 'B') opening the jaws of the horizontal
receiving aperture. The end frame and attached handrails may be lifted from the tower
and may be repositioned at a higher or lower position within the scaffold.
[0012] The action of holding the handgrips upwards maintains the disengagement of the blocking
piece and causes the complete end frame assembly to be carried by the mechanism. To
relocate the frame at a new position the lower hook jaws 37 are reengaged over the
required rung position and the frame is pushed away from the operator causing the
horizontal apertures to re-engage around the frame rung member.
[0013] Lowering the handgrips causes the blocking piece to cause the rotating hook to rotate
to the locking position thus securing the end frame at a new position.
[0014] In some circumstances it is necessary to install the guardrail end frames at an inclination
to the scaffolding tower frames such that further frame members may be installed or
removed. This is achieved by locating the alternative lower hook jaws 38 around the
scaffolding rung member such that when the end frame is relocated and locked onto
the scaffolding frame an angle is formed between the scaffolding frame 4a and the
guardrail end frame member.
1. A guard rail protection system for use on scaffolding characterised in that the system comprises at least one lockably releasable hook means, a blocking portion
and slidable means with at least one grip so operable that when the grip means is
raised or lowered the hook means is rotationally released or locked allowing the restriction
in the upper receiving aperture to be applied or released.
2. A guard rail system for use on scaffolding as claimed in, claim 1, characterised in that end frames and pivotally connected telescopic guard rails with each guard rail end
frame upright member incorporating a lower hook assembly incorporating at least one
downward facing receiving aperture and incorporating at least one horizontally facing
receiving aperture at such a position as to present the apertures at a position relating
to the position of a frame horizontal member.
3. A guard rail system as claimed in any one of the preceding claims, characterised in that the end frame member may be attached in an angularly situated position in relation
to the scaffolding.
4. A guard rail system as claimed in any one of the preceding claims, characterised in that the sliding handgrip may be used to carry the weight of the guardrail assembly such
that the assembly may be relocated on the scalding without having to release hold
of the handgrip and such that on lowering the guardrail frame assembly into the desired
final position the locking device may be re-applied in one movement sequence only
releasing the handgrip when the final locked state is achieved. When the scaffold
tower is erected to the required height, it is not necessary to remove the upper guardrail
system which may be left in place as a permanent safety system until such time as
dismantling of the scaffolding is performed.
5. A guard rail system as claimed in any one of the preceding claims, characterised in that when the scaffold tower is erected to the required height, the upper guardrail system
may be left in place as a permanent safety system until such time as dismantling of
the scaffolding.