Pertinent art
[0001] The present invention relates to hydraulic engineering, predominantly, to the technology
of constructing a tunnel for highway traffic or other-purpose tunnel under the river
channel or under the bottom of other shallow water area. Predominantly it can be used
to form a temporary protection for a closed bottom segment in the water area and for
the space above it throughout the depth of water.
Prior art
[0002] A method of forming a new land territory on the bottom of seas and oceans (see
RU Patent No. 2044117, IC E01B 17/00, published on September 20, 1995) is known which includes enclosing
an area of sea or ocean bottom along its perimeter by a main dam higher than the maximum
water level, and further complete removal of water from the space enclosed by the
dam. In parallel with each section of the main dam, a respective section of a protective
single- or multiple-contour dam is set up linked in a pivot manner to one another
with the help of reinforcing cofferdams. In the body of at least one dam and/or between
the dams a system is created to transfer water flows of sea currents to its opposite
side, while the lateral sea-facing surface of the main dam is made with a multiple-control
ribbing positioned in parallel with the bottom in order to stabilize in depth the
water flows going around the dam.
[0003] The known method is very complex to implement and requires considerable material
and labor inputs.
[0004] A sheet-pile wall (see
RU Patent No. 2185476, IC E02D 5/02, published on July 20, 2002) is known which contains piles with sheet-pile
projections rigidly fixed to their outer surfaces, and sheet-pile interlocks, each
made from two profile elements positioned with a clearance between them and connected
to one another with the help of a stiffening rib, which forms a sheet-pile groove
for placing a sheet-pile projection in it. Sheet-pile interlocks are united in pairs
to form closing rod-like elements, each having two longitudinal sheet-pile grooves
and installed in the wall between piles. Each closing rod-like element is made by
welding from two channel bars whose shelves face one another and are positioned so
as to form clearances between them, and from at least one stiffening rib positioned
between channel bars.
[0005] To erect a sheet-pile wall in the form of a closed enclosing structure, it is necessary
to use a high number of constituents, which greatly lengthens the time of completing
construction work.
[0006] A method of building a tunnel in soft grounds (see
RU Application No. 2001134688, IC E02D 29/00, published on August 20, 2003) is known which includes installing
a pile enclosure before the formation of the starting and receiving foundation pits
in the ground within the area of their location, which later protects excavation of
ground in foundation pits.
[0007] To be implemented, the above method requires using a multitude of constituents from
which the closed enclosing structure is made directly on the bottom segment, which
takes a long construction time.
[0008] A sheet-pile wall (see
RU Patent No. 2151236, IC E02D 5/08, published on June 20, 2002) is known consisting of undulating precast
elements, each having shelves positioned on different sides from longitudinal axis
of the wall in parallel with this axis with a displacement relative to each other
and connected with each other by inclined walls positioned at obtuse angle to the
shelves that are parallel with the longitudinal axis.
[0009] Using the known sheet-pile wall to erect a closed enclosing structure requires considerable
labor costs and long time for its erection.
[0010] A method of building a shallow-depth tunnel at the bottom of a water area (see USSR
author's certificate No.
1067142, IC E02D 5/20, published on January 15, 1984) is known which includes creating a
temporary hydraulic enclosure from a set of casings formed from, e.g., metal sheet
pile, each of these casings being element-wise erected, as the depth of the water
area grows, along the perimeter of the closed bottom area selected. The result is
the formation of a closed enclosing zone in the water area. Then water is removed
from the enclosed space and, at the bottom inside it, construction work is carried
out by a dry method to build the tunnel. Upon completion of construction work, the
hydraulic enclosure is element-wise dismounted with possible further use of its elements.
[0011] This known technical solution fixes the task similar to the invention being applied
for and contains the greatest number of common features. However, the major drawback
of the known technical solution is the necessity to use many diversiform constituents
from which a closed enclosing structure is made in the water medium directly on the
bottom segment, which requires a long construction period.
[0012] A technical solution is known called "A system for temporary drainage of a bottom
segment" (see USSR author's certificate
No. 1067142, IC E02D 5/20, published on January 15, 1984). It realizes the aforementioned known
method of building a low-depth tunnel at the bottom of a water area and presents a
temporary closed hydraulic enclosure submerged to the bottom of the water area. This
enclosure consists of a set of diversiform casings formed, e.g., from sheet piles
and having elliptic, circular or parabolic outline in plan.
[0013] The known system consists of a set of isolate elements different both in form and
making, which requires a long construction period to assemble them into a single structure
in water, as well as high precision of assemblage thereof in complex hydrological
conditions and, consequently, greater labor costs. This temporary hydraulic enclosure
cannot be used as a vertically loaded structure in order to ensure the process of
building the tunnel inside the enclosure.
Disclosure of the invention
[0014] The task of the technical solution being applied for is to create such a
method for building a shallow-depth tunnel at the bottom of a water area and realizing
its systems, which would be simpler and more reliable and enable to build a shallow-depth
tunnel for a short period of time, while the system could perform additional functions
during the driving of the tunnel.
[0015] In what concerns the method, the task set is solved by using the method for building
a shallow-depth tunnel at the bottom of a water area, which includes the fabrication
of a single bottomless hydraulic enclosure with controlled buoyancy. The enclosure
is further transported and placed in the tunnel's route, submerged to the bottom through
decreasing its buoyancy and fixed at the bottom with the help of retainers and a system
of anchors, thus forming a temporary hydraulic enclosure along the perimeter of the
closed bottomsegment. The upper part of the hydraulic enclosure positioned above water
level is horizontally flattened. Crane equipment and platforms for temporary storage
of construction materials are placed thereon; then sheet-pile walls are erected within
the enclosed space; after which the water is removed from the enclosed space; sea
soil is excavated by way of digging a foundation pit followed by the creation of the
tunnel's bearing pile field, on which a foundation mat is erected with precast or
monolith ferroconcrete sections of the tunnel placed on it. After work is over within
the enclosed space, the hydraulic enclosure is returned its initial buoyancy, separated
from the bottom and transported to another tunnel construction site.
[0016] A bottomless floating dock can be used as a hydraulic enclosure.
[0017] The task set to find a system realizing the method is solved by making the temporary
hydraulic enclosure as a single bottomless structure with controlled buoyancy and
movable retainers in the form of knives along vertical walls.
[0018] A temporary hydraulic enclosure can be made as a bottomless floating dock.
[0019] Such technical solution enables to create a new method for building a shallow-depth
tunnel within the water area, which, compared with similar-purpose known methods,
has the following advantage, namely, a single shop-mounted reusable hydraulic enclosure.
It is essential that said hydraulic enclosure has a feature absent in the prototype,
namely, it can be a bearing structure, on which, e.g., crane equipment and platforms
for temporary storage of construction materials can be placed.
[0020] In comparison with the known solution, the system applied for has essential distinctions
consisting, first and foremost, in that a single shop-mounted structure is used as
a temporary enclosure for the closed bottom segment.
[0021] From the state of the art, systems for temporary enclosure are known that are created
in water medium at the bottom segment of a water area from a serially mounted set
of diversiform elements. In our case, a hydraulic enclosure is shop-mounted as, e.g.,
a dock, to which the function of a temporary hydraulic enclosure is added.
Brief description of the drawings
[0022] The essence of the inventions is illustrated by the drawings, where:
- Fig. 1 shows the cross-section of a temporary hydraulic enclosure at the stage of
tunnel construction;
- Fig. 2 shows the general view of the hydraulic enclosure in its transit position;
- Fig. 3 shows the general view of the hydraulic enclosure in axonometry at the stage
of submergence to the bottom of the water area.
[0023] Practical application of the inventions being applied for is explained by the description
below.
Best embodiment of the invention
[0024] The method proposed to build a shallow-depth tunnel at the bottom of a water area
is implemented as follows:
First, single temporary hydraulic enclosure 1 with controlled buoyancy is fabricated
at a plant, in particular, as a dock with no bottom part (see figs. 1, 2, 3). It can
have, e.g., the following geometrical dimensions: 30 m wide (for navigating through
draw spans of existing brides), 60 m long and 15 m high. Side towers 2 of enclosure
1 are made with the closed perimeter, each of the towers being, e.g., 3 m wide. Buoyancy
cisterns 3 placed inside them ensure the transportation of enclosure 1 and its positioning
on bottom 4 of the water area (see fig. 3). When such hydraulic enclosure is made
at a plant, it is towed (fig. 2) through draw spans of bridges (not shown in the figure),
placed in the tunnel's route, submerged to bottom 4 by decreasing its buoyancy, fixed
with the help of sliding knives 5, and reliably fastened to the ground by a system
of anchors. The upper part of enclosure 1 is horizontally flattened, which enables
to place crane equipment and platforms for temporary storage of construction materials
on this enclosure. The upper part of 1 can be flattened by way of planning bottom
4 of the water area and moving knives 5 out (see fig. 1). The upper part of enclosure
1 in this case rises above water level 7. To excavate seabed soil inside enclosure
1, sheet-pile walls 8 are erected along the perimeter of the future foundation pit.
Water is then removed from the enclosed space and tunnel construction work is carried
out using a dry cut-and-cover method. Such hydraulic enclosure 1 can serve as a place
to moor floating cranes (not shown in the figure). Upon completion of construction
work, hydraulic enclosure 1 is returned its initial buoyancy, separated from the bottom
and transported to the next tunnel construction site (see fig. 2).
[0025] The proposed system for temporary drainage of the bottom segment used to realize
the aforementioned method consists of a closed temporary hydraulic structure 1. This
structure is made as a single bottomless structure with controlled buoyancy, e.g.,
in the form of a dock. Movable retainers, e.g., in the form of knives 5 are positioned
on its internal walls (see fig. 1). Such system is used as described above. After
the enclosed space has been drained, a foundation pit is dug out at the bottom of
the water area; the tunnel's bearing pile field 9 is created on which foundation mat
10 is erected; and precast or monolith ferroconcrete sections of tunnel 11 are placed
with their reliable joining and flashing ensured. Then a near-bottom protective cushion
is dumped over tunnel 11 cover and move the system to a new tunnel 11 construction
site.
1. A method of building a shallow-depth tunnel at the bottom of a water area, including
the formation of a temporary hydraulic enclosure along the perimeter of a closed bottom
segment and removal of water from the enclosed space; performance of construction
work inside it using a dry method with further dismounting of the hydraulic enclosure,
differing in that a single bottomless hydraulic enclosure with controlled buoyancy
is produced, then transported and placed in the tunnel's route, submerged to the bottom
through reducing its buoyancy and fixed at the bottom with the help of retainers and
a system of anchors, the upper part of the hydraulic enclosure rising above water
level is horizontally flattened; and crane equipment and platforms for temporary storage
of construction materials are put on it; then sheet-pile walls are erected inside
the enclosed space; after which water is removed from the enclosed space; seabed soil
is excavated by digging out a foundation pit; and then the tunnel's bearing pile field
is created, on which a foundation mat is installed with the tunnel's precast or monolith
ferroconcrete sections placed on it; upon completion of construction work the hydraulic
enclosure is returned its initial buoyancy, separated from the bottom and transported
to the next tunnel construction site.
2. A method according to p. 1, wherein a bottomless floating dock is used as a hydraulic
enclosure.
3. A system for temporary drainage of the bottom segment used to exercise the method
according to p.1, wherein the temporary hydraulic enclosure is made as a single bottomless
structure with controlled buoyancy and with movable retainers in the form of knives
on vertical walls.
4. A system according to p. 3, wherein a bottomless floating dock is used as a temporary
hydraulic enclosure.