Technical Field
[0001] The present invention relates to a hoisting machine unit for installing an elevator,
which is mounted with a hoisting machine for raising/lowering a car and a counterweight,
and to a method of looping a main rope for the elevator.
Background Art
[0002] In a conventional elevator, with a view to looping a main rope around a driving sheave
of a hoisting machine within a housing, there is proposed a method in which a flat
band-shaped leader strip made of an elastic material is coupled to the main rope,
thrust into the housing from an entrance hole thereof, moved along an inner surface
of the housing, and then pulled out from an exit hole of the housing to loop the main
rope around the driving sheave. In the conventional elevator, the main rope is looped
around the driving sheave after the hoisting machine has been installed in a hoistway
(see Patent Document 1).
Disclosure of the Invention
Problem to be solved by the Invention
[0004] However, in the case where the hoisting machine is installed at a certain spot, components
provided, for example, on an inner wall surface of the hoistway or within the hoistway
may cause obstruction to an extent of making the operation of passing the leader strip
into a casing difficult. Accordingly, the operation of looping the main rope around
the driving sheave requires a great deal of time and effort.
[0005] The present invention has been made to solve the above-mentioned problem, and it
is therefore an obj ect of the present invention to obtain a hoistingmachine unit
for installing an elevator and a method of looping a main rope for an elevator which
make it possible to loop the main rope around a sheave with ease.
Means for solving the Problem
[0006] A hoisting machine unit for installing an elevator according to the present invention
includes: an attachment frame; a hoisting machine having a driving sheave and provided
on the attachment frame; a leader strip, which is looped around the driving sheave,
for pulling and moving a main rope for suspending a car to loop the main rope around
the driving sheave; and a holding device for holding both ends of the leader strip
with respect to the attachment frame.
Brief Description of the Drawings
[0007]
Fig. 1 is a plan view showing a hoisting machine unit for installing an elevator according
to Embodiment 1 of the present invention.
Fig. 2 is a partial lateral view showing a state in which the hoisting machine unit
for installing the elevator shown in Fig. 1 is installed in the upper portion within
the hoistway.
Fig. 3 is an enlarged view showing the connection portion of Fig. 2.
Fig. 4 is an enlarged view showing another example of a portion for connecting a first
leader strip and a first main rope of Fig. 3 to each other.
Fig. 5 is an enlarged view showing another example of a portion for connecting a first
leader strip and a first main rope of Fig. 3 to each other.
Fig. 6 is a partial lateral view showing a hoisting machine unit for installing an
elevator according to Embodiment 2 of the present invention.
Fig. 7 is a partial lateral view showing a state in which the hoisting machine unit
1 for installing an elevator according to Embodiment 3 of the present invention is
installed in the upper portion within the hoistway.
Fig. 8 is a plan view showing the guide device of Fig. 7.
Best Modes for carrying out the Invention
[0008] Preferred embodiments of the present invention will be described hereinafter with
reference to the drawings.
Embodiment 1
[0009] Fig. 1 is a plan view showing a hoisting machine unit for installing an elevator
according to Embodiment 1 of the present invention. Referring to Fig. 1, a hoisting
machine unit 1 for installing an elevator is installed in an upper portion within
a hoistway in setting up the elevator. A car (not shown) and a counterweight (not
shown) are suspended within the hoistway by means of a plurality of first main ropes
and a plurality of second main ropes after the hoisting machine unit 1 for installing
the elevator has been installed in the upper portion within the hoistway.
[0010] The hoisting machine unit 1 for installing the elevator has an attachment frame 2,
a unit-mounted component 3 provided on the attachment frame 2, a plurality of first
leader strips 4 for conducting the respective first main ropes to the unit-mounted
component 3, and a plurality of second leader strips 5 for conducting the respective
second main ropes to the unit-mounted component 3.
[0011] The unit-mounted component 3 has a hoisting machine 6, a first car-side return sheave
9, a second car-side return sheave 10, a first counterweight-side return sheave 11,
a second counterweight-side return sheave 12, and a turning sheave 13. The hoisting
machine 6 has a hoisting machine body 7 including a motor, and a driving sheave 8
that is rotated by the hoisting machine body 7. The hoisting machine 6 is designed
as a low-profile hoisting machine having a structure in which the driving sheave 8
is larger in radial dimension than in axial dimension. The first car-side return sheave
9, the second car-side return sheave 10, the first counterweight-side return sheave
11, the second counterweight-side return sheave 12, and the turning sheave 13 are
designed as driven sheaves that are rotated as the driving sheave 8 rotates when the
first main ropes and the second main ropes are attached to the unit-mounted component
3.
[0012] Respective rotational shafts of the first car-side return sheave 9, the second car-side
return sheave 10, the first counterweight-side return sheave 11, and the second counterweight-side
return sheave 12 are disposed perpendicularly to a rotational shaft of the driving
sheave 8.
[0013] A plurality of groove portions are provided in an outer peripheral portion of each
of the sheaves 8 to 13 along a rotational direction thereof. Main rope latches 14
to 19, which face the outer peripheral portions of the sheaves 8 to 13, respectively,
are attached to the sheaves 8 to 13, respectively.
[0014] The respective first leader strips 4 and the respective second leader strips 5 are
selectively looped around the respective sheaves 8 to 13 to be attached to the unit-mounted
component 3. The respective first leader strips 4 are continuously looped around the
first counterweight-side return sheave 11, the driving sheave 8, and the first car-side
return sheave 9 in the stated order. The respective second leader strips 5 are continuously
looped around the second counterweight-side return sheave 12, the driving sheave 8,
the turning sheave 13, and the second car-side return sheave 10 in the stated order.
The respective first leader strips 4 and the respective second leader strips 5 are
lower in bending rigidity than the respective main ropes for suspending the car and
the counterweight.
[0015] Fig. 2 is a partial lateral view showing a state in which the hoisting machine unit
1 for installing the elevator shown in Fig. 1 is installed in the upper portion within
the hoistway. Referring to Fig. 2, the attachment frame 2 is fixed to an inner wall
surface of a hoistway 20. The hoisting machine 6 is disposed horizontally so that
the rotational shaft of the driving sheave 8 extends vertically. Also, the hoisting
machine 6 is disposed such that the driving sheave 8 is located at a position higher
than the hoisting machine body 7. Thus, the driving sheave 8 faces a ceiling surface
within the hoistway 20.
[0016] To conduct each of first main ropes 21 placed at a landing 31 to the unit-mounted
component 3, an end of the first main rope 21 is connected to one end of a corresponding
one of the first leader strips 4 via a connection portion 22. The first leader strip
4 is moved by being pulled in such a direction as to conduct the first main rope 21
to the unit-mounted component 3. That is, the first leader strip 4 is moved while
the other end thereof is pulled. Thus, the first leader strip 4 tows the first main
rope 21 in such a manner as to conduct the first main rope 21 to the unit-mounted
component 3. The first main rope 21 is moved together with the first leader strip
4 to be continuously looped around the first counterweight-side return sheave 11,
the driving sheave 8, and the first car-side return sheave 9 in the stated order.
[0017] To conduct each of the second main ropes to the unit-mounted component 3, an end
of the second main rope is connected to one end of a corresponding one of the second
leader strips 5 via a connection portion. The second leader strip 5 is moved by being
pulled in such a direction as to conduct the second main rope to the unit-mounted
component 3, so the second main rope is continuously looped around the second counterweight-side
return sheave 12, the driving sheave 8, the turning sheave 13, and the second car-side
return sheave 10 in the stated order.
[0018] Fig. 3 is an enlarged view showing the connection portion 22 of Fig. 2. Referring
to Fig. 3, the first leader strip 4 has a bendable core cable (e.g., a wire or the
like) 23, and a covering material (e.g., rubber or the like) 24 for covering the core
cable 23. The core cable 23 is exposed from the covering material 24 at one end of
the first leader strip 4. The exposed portion of the core cable 23 is annularly bent
and swaged by a swaging member 25 to be made into a leader strip-side annular portion
26.
[0019] The first main rope 21 is manufactured by twisting a plurality of strands 27. The
respective strands 27 are loosened at the end of the first main rope 21. That one
of the respective strands 27 which is located at a central portion of the first main
rope 21 is passed through the leader strip-side annular portion 26. The portion of
the strand 27 passed through the leader strip-side annular portion 26 is annularly
bent and swaged by a swaging member 28 to be made into a main rope-side annular portion
29. In this manner, the first leader strip 4 and the first main rope 21 are connected
to each other. The connection portion 22 has the leader strip-side annular portion
26 and the main rope-side annular portion 29.
[0020] In conducting the second main rope to the unit-mounted component 3 as well, the same
connection portion as described above is constructed to connect the second leader
strip 5 and the second main rope to each other.
[0021] Next, a procedure followed in setting up the elevator will be described. In a plant,
the hoisting machine unit 1 for installing the elevator has been assembled in advance.
The hoisting machine unit 1 for installing the elevator is assembled by attaching
the hoisting machine 6, the first car-side return sheave 9, the first counterweight-side
return sheave 10, the second car-side return sheave 11, the second counterweight-side
return sheave 12, and the turning sheave 13 to the attachment frame 2 at predetermined
positions thereof, respectively, looping the plurality of the first leader strips
4 around the first counterweight-side return sheave 11, the driving sheave 8, and
the first car-side return sheave 9 in succession, and then looping the plurality of
the second leader strips 5 around the second counterweight-side return sheave 12,
the driving sheave 8, the turning sheave 13, and the second car-side return sheave
10 in succession (in a unit assembling process).
[0022] After that, the hoisting machine unit 1 for installing the elevator is conveyed to
a place where the elevator is to be set up, and is then installed in the upper portion
within the hoistway 20. In this case, the attachment frame 2 is fixed within the hoistway
20 such that the driving sheave 8 faces the ceiling surface within the hoistway 20
(in a unit installing process).
[0023] After that, the plurality of the first main ropes 21 and the plurality of the second
main ropes are prepared at the landing 31 of the uppermost floor. Then, the end of
each of the first main ropes 21 is connected to one end of a corresponding one of
the first leader strips 4, and the end of each of the second main ropes is connected
to one end of a corresponding one of the second leader strips 5. In this case, the
connection portion 22 between each of the first leader strips 4 and the corresponding
one of the first main ropes 21 is formed by passing the strand 27 at the end of the
first main rope 21 through the leader strip-side annular portion 26, which is provided
in advance at one end of the first leader strip 4, to form the main rope-side annular
portion 29. The same connection portion as described above is also formed between
each of the second leader strips 5 and the corresponding one of the second main ropes
(in a connection process).
[0024] After that, while the driving sheave 8 is rotated at a low speed through the driving
of the hoisting machine body 7, the other end side of each of the first leader strips
4 and the other end side of each of the second leader strips 5 are pulled simultaneously.
Thus, the respective first leader strips 4 and the respective second leader strips
5 are moved, so the first main ropes 21 and the second main ropes are moved by being
towed by the first leader strips 4 and the second leader strips 5, respectively. After
that, the respective first leader strips 4 and the respective second leader strips
5 are pulled out from the unit-mounted component 3 to replace the first leader strips
4 with the first main ropes 21, respectively, and replace the second leader strips
5 with the second main ropes, respectively. Thus, the respective first main ropes
21 are successively looped around the first counterweight-side return sheave 11, the
driving sheave 8, and the first car-side return sheave 9 in the stated order, and
the respective second main ropes are successively looped around the second counterweight-side
return sheave 12, the driving sheave 8, the turning sheave 13, and the second car-side
return sheave 10 in the stated order. In this manner, the respective first main ropes
21 and the respective second main ropes are attached to the unit-mounted component
3 (in a main rope looping process).
[0025] In the main rope looping process of this example, the operation of looping the respective
first main ropes 21 and the operation of looping the respective second main ropes
are performed simultaneously. However,itisalso appropriate to firstloop either the
respective first main ropes 21 or the respective second main ropes and then loop the
other main ropes.
[0026] After that, both the ends of each of the first main ropes 21 and both the ends of
each of the second main ropes are brought down, and the car and the counterweight
within the hoistway 20 are suspended by means of the respective first main ropes 21
and the respective second main ropes.
[0027] In the method of looping the main rope for the elevator as described above, the first
leader strips 4 and the second leader strips 5 are looped in advance around the driving
sheave 8 of the hoisting machine 6 provided on the attachment frame 2, the first main
ropes 21 and the second main ropes are connected to the first leader strips 4 and
the second leader strips 5, respectively, after the hoisting machine unit 1 for installing
the elevator has been installed within the hoistway 1, and the first leader strips
4 and the second leader strips 5 are pulled to be moved, so the first main ropes 21
and the second main ropes are looped around the driving sheave 8. It is therefore
possible to perform the operation of looping the first leader strips 4 and the second
leader strips 5 around the driving sheave 8 outside the hoistway 20. Accordingly,
the components and the like on the inner wall surface of the hoistway 20 and within
the hoistway 20 do not cause obstruction in looping the first leader strips 4 and
the second leader strips 5 around the driving sheave 8, so it is possible to perform
the operation of looping the first leader strips 4 and the second leader strips 5
with ease.
[0028] The first main ropes 21 and the second main ropes are conducted to the outer peripheral
portion of the driving sheave 8 by the first leader strips 4 and the second leader
strips 5, respectively, even after the hoisting machine unit 1 for installing the
elevator has been installed within the hoistway 20, so it is possible to loop the
first main ropes 21 and the second main ropes around the driving sheave 8 with ease
without removing the main rope latch 14, which faces the outer peripheral portion
of the driving sheave 8, from the driving sheave 8. Thus, there is no need to readjust
the dimension of the gap between the outer peripheral portion of the driving sheave
8 and the main rope latch 14, so it is possible to further facilitate the operation
of looping the first main ropes 21 and the second main ropes.
[0029] The attachment frame 2 is provided with the first car-side return sheave 9, the first
counterweight-side return sheave 10, the second car-side return sheave 11, the second
counterweight-side return sheave 12, and the turning sheave 13 in addition to the
hoisting machine 6, and the first leader strips 4 and the second leader strips 5 are
looped around the respective sheaves 8 to 13 selectively and successively. Therefore,
even in the case where the attachment frame 2 is provided with a plurality of sheaves,
it is possible to perform the operation of successively looping the first main ropes
21 and the second main ropes around the respective sheaves with ease.
[0030] In the foregoing example, each of the first leader strips 4 and the second leader
strips 5 is made by covering the core cable 23 with the covering member 24. However,
the construction of the first leader strips 4 and the second leader strips 5 is not
limited thereto as long as the first leader strips 4 and the second leader strips
5 are lower in bending rigidity than the first main ropes 21 and the second main ropes,
respectively. For example, as shown in Fig. 4, the first leader strip and the second
leader strip may each be manufactured by twisting a plurality of strands 32.
[0031] In this case, the first leader strip 4 and the first main rope 21 are connected to
each other by twisting the strands 27 of the first leader strip 4 and the strands
32 of the first main rope 21 together. That is, at the end of the first main rope
21, two of the plurality of the strands 27 are removed to form strand grooves 33.
At one end of the first leader strip 4, only two of the plurality of the strands 32
are left while the other of the strands 32 are cut off. The two remaining strands
32 are fitted along the strand grooves 33 formed at the end of the first main rope
21, respectively. Thus, the strands 32 are twisted together with the strands 27, so
the first leader strip 4 and the first main rope 21 are connected to each other (Fig.
4). The second leader strip 5 and the second main rope are also connected to each
other in the same manner.
[0032] In the foregoing example, the strand 27 at the end of the first main rope 21 is passed
through the leader strip-side annular portion 26 provided at one end of the first
leader strip 4, and the strand 27 thus passed therethrough is annularly bent to form
the main rope-side annular portion 29, so the first leader strip 4 and the first main
rope 21 are connected to each other. However, as shown in Fig. 5, the first leader
strip 4 and the first main rope 21 may be connected to each other via a universal
joint 34.
[0033] In this case, the universal joint 34 has a base shaft 35, and a pair of ring members
36 and 37 provided through the base shaft 35 to be rotatable about an axial direction
of the base shaft 35. The core cable 23 is passed through the ring member 36, the
strand 27 is passed through the ring member 37, and the passed portions of the core
cable 23 and the strand 27 are each tied with a wire or the like so as to assume an
annular shape. In this manner, the first main rope 21 is rotated with respect to the
second leader strip 4. It is therefore possible to prevent the first main rope 21
from being wrenched with respect to the first leader strip 4 even when the first main
rope 21 is looped around a plurality of sheaves continuously. As a result, it is possible
to prevent the connection portion between the first leader strip 4 and the first main
rope 21 from being wrenched to a rupture.
Embodiment 2
[0034] Fig. 6 is a partial lateral view showing a hoisting machine unit for installing an
elevator according to Embodiment 2 of the present invention. Referring to Fig. 6,
the attachment frame 2 is provided with a plurality of holding devices 41 for holding
both ends of each of the first leader strips 4 and both ends of each of the second
leader strips 5 with respect to the attachment frame 2, respectively. In this example,
the respective holding devices 41 are disposed within an outside dimension of the
attachment frame 2 (within the attachment frame 2). By being held by the respective
holding devices 41, both the ends of each of the first leader strips 4 and both the
ends of each of the second leader strips 5 are also disposed within the outside dimension
of the attachment frame 2 (within the attachment frame 2). Mentionable as the holding
devices 41 are, for example, adhesive tapes for sticking both the ends of each of
the first leader strips 4 and both the ends of each of the second leader strips 5
to the attachment frame 2, respectively, hold-down plates for holding down both the
ends of each of the first leader strips 4 and both the ends of each of the second
leader strips 5 onto the attachment frame 2, respectively, and the like.
[0035] Each of the holding devices 41 holds both the ends of a corresponding one of the
first leader strips 4 and both the ends of a corresponding one of the second strips
5, so a predetermined tensile force is applied to each of the first leader strips
4 and the second leader strips 5. Even when the hoisting machine unit 1 for installing
the elevator is tentatively placed on a floor surface 42, the first leader strips
4 and the second leader strips 5 are held by the hoisting machine unit 1 for installing
the elevator while remaining apart from the floor surface 42. Embodiment 2 of the
present invention is identical to Embodiment 1 of the present invention in other constructional
details.
[0036] In the hoisting machine unit 1 for installing the elevator constructed as described
above, the attachment frame 2 is provided with the holding devices 41 for holding
both the ends of each of the first leader strips 4 and both the ends of each of the
second leader strips 5 with respect to the attachment frame 2, respectively, so the
predetermined tensile force can be applied to each of the first leader strips 4 and
the second strips 5. Thus, it is possible to prevent the first leader strips 4 and
the second leader strips 5 from slacking to come off from the sheaves. Accordingly,
it is possible to allow the hoisting machine unit 1 for installing the elevator to
be conveyed and installed within the hoistway 20 more reliably.
[0037] By being held by the holding devices 41, both the ends of each of the first leader
strips 4 and both the ends of each of the second leader strips 5 are disposed within
the outside dimension of the attachment frame 2. It is therefore possible to prevent
the first leader strips 4 and the second leader strips 5 from being wedged between
the attachment frame 2 and the floor surface 42 to be indented when the hoisting machine
unit 1 for installing the elevator is tentatively placed on the floor surface 42.
Accordingly, it is possible to prevent the first leader strips 4 and the second leader
strips 5 from decreasing in tensile strength. As a result, it is possible to prevent
the first leader strips 4 and the second leader strips 5 from being ruptured.
Embodiment 3
[0038] Fig. 7 is a partial lateral view showing a state in which the hoisting machine unit
1 for installing an elevator according to Embodiment 3 of the present invention is
installed in the upper portion within the hoistway 20. Referring to Fig. 7, the attachment
frame 2 is provided with a guide device 51 for guiding the first leader strips 4 and
the first main ropes 21 such that the first leader strips 4 and the first main ropes
21 are moved along the outer peripheral portion of the first counterweight-side return
sheave 11, and a guide device 52 for guiding the first leader strips 4 and the first
main ropes 21 such that the first leader strips 4 and the first main ropes 21 are
moved along the outer peripheral portion of the first car-side return sheave 9.
[0039] The guide device 51 is disposed below the first counterweight-side return sheave
11. The guide device 52 is disposed below the first car-side return sheave 9. That
is, the guide device 51 is disposed on the side where the first main ropes 21 are
led into the unit-mounted component 3, and the guide device 52 is disposed on the
side where the first main ropes 21 are led out from the unit-mounted component 3.
The guide devices 51 and 52 are attached to the attachment frame 2 via attachment
members 53 and 54, respectively. The attachment members 53 and 54 are removable from
the attachment frame 2.
[0040] Provided at the landing 31 of the uppermost floor are a main rope hold-down device
55 for holding down the first main ropes 21 or the second main ropes that are pulled
up from the landing 31 to be led into the unit-mounted component 3, and a turning
device 56 for changing the direction of the first leader strips 4 or the second leader
strips 5, which are led out from the unit-mounted component 3 to be pulled down, into
an upward direction.
[0041] The main rope hold-down device 55 has a guide roller 57 that is rotated as the first
main ropes 21 or the second main ropes are moved. The turning device 56 has a guide
roller 58 that is rotated as the first leader strips 4 or the second leader strips
5 are moved.
[0042] A plurality of rotary tables 59 for placing the first main ropes 21 and the second
main ropes thereon respectively are provided at the landing 31 of the uppermost floor.
In leading the first main ropes 21 and the second main ropes into the unit-mounted
component 3, the first main ropes 21 and the second main ropes are reeled out while
the respective rotary tables 59 are rotated.
[0043] The attachment frame 2 is also provided with guide devices (not shown) for guiding
the second main ropes and the second leader strips 5 such that the second main ropes
and the second leader strips 5 are moved along the outer peripheral portions of the
second car-side return sheave 10 and the second counterweight-side return sheave 12.
[0044] That is, in attaching the respective first main ropes 21 and the respective second
main ropes to the unit-mounted component 3, the first main ropes 21 and the second
main ropes are placed on the rotary tables 59. The first main ropes 21 are passed
through the main rope hold-down device 55 and the guide device 51 in the stated order
and are then connected to the first leader strips 4, respectively. The second main
ropes are passed through the main rope hold-down device 55 and the guide device (not
shown) in the stated order and then connected to the second leader strips 5 respectively.
The first leader strips 4 led out from the unit-mounted component 3 are passed through
the guide device 52 and the turning device 56 in the stated order and are then pulled
up at the other end sides thereof, respectively. The second leader strips 5 led out
from the unit-mounted component 3 are passed through the guide device (not shown)
and the turning device 56 in the stated order and then pulled up at the other end
sides thereof, respectively.
[0045] Fig. 8 is a plan view showing the guide device 51 of Fig. 7. The guide device 51
has an annular body 60 through which the first main ropes 21 are passed, a support
portion 61 fixed to the attachment member 53 to support the annular body 60, and a
plurality of rollers 62 provided rotatably on the annular body 60. The respective
rollers 62 are disposed in the circumferential direction of the annular body 60. The
guide device 52 is also constructed in the same manner. Embodiment 3 of the present
invention is identical to Embodiment 1 of the present invention in other constructional
details.
[0046] Next, a procedure followed in setting up the elevator will be described. After the
guide devices 51 and 52 have been attached to the attachment frame 2, the hoisting
machine unit 1 for installing the elevator is installed in the upper portion within
the hoistway 20.
[0047] After the hoisting machine unit 1 for installing the elevator has been installed
within the hoistway 20, the respective first main ropes 21 are passed through the
main rope hold-down device 55 and the guide device 51 in the stated order, and the
end of each of the first main ropes 21 is connected to one end of a corresponding
one of the first leader strips 4. The respective second main ropes are passed through
the main rope hold-down device 55 and the guide device (not shown) in the stated order,
and the end of each of the second main ropes is connected to one end of a corresponding
one of the second leader strips 5. In this case, the other end of the first leader
strip 4 is passed through the guide device 52 and the turning device 56 in the stated
order, and the other end of the second leader strip 5 is passed through the guide
device (not shown) and the turning device 56 in the stated order.
[0048] After that, the other end of each of the first leader strips 4 and the other end
of each of the second leader strips 5 are simultaneously pulled up while the driving
sheave 8 is rotated at a low speed through the driving of the hoisting machine body
7. Thus, the first leader strips 4 and the second leader strips 5 are moved together
with the first main ropes 21 and the second main ropes, respectively. At this time,
the movement of the first main ropes 21 causes the corresponding ones of the rotary
tables 59 to rotate, so the first main ropes 21 are reeled out from spots on those
rotary tables 59, respectively. The movement of the second main ropes causes the corresponding
ones of the rotary tables 59 to rotate, so the second main ropes are reeled out from
spots on those rotary tables 59, respectively.
[0049] Thus, the first main ropes 21 replace the first leader strips 4, respectively, and
are successively looped around the first counterweight-side return sheave 12, the
driving sheave 8, and the first car-side return sheave 9 in the stated order. The
second main ropes replace the second leader strips 5, respectively, and are successively
looped around the second counterweight-side return sheave 12, the driving sheave 8,
and the second car-side return sheave 10 in the stated order.
[0050] After that, the guide devices 51 and 52 as well as the attachment members 53 and
54 are removed from the attachment frame 2, and the first leader strips 4 are disconnected
from the first main ropes 21, respectively. The guide devices (not shown) are also
removed from the attachment frame 2, and the second leader strips 5 are also disconnected
from the second main ropes, respectively. The subsequent procedure is the same as
in Embodiment 1 of the present invention.
[0051] In this example, the operation of looping the respective first main ropes 21 and
the operation of looping the respective second main ropes are performed simultaneously.
However, the operation of looping the respective first main ropes 21 and the operation
of looping the respective second main ropes may also be performed separately.
[0052] In the hoisting machine unit 1 for installing the elevator constructed as described
above, the attachment frame 2 is provided with the guide devices 51 and 52 for guiding
either the first leader strips 4 or the first main ropes 21 such that the first leader
strips 4 or the first main ropes 21 are moved along the outer peripheral portions
of the first car-side return sheave 9 and the first counterweight-side return sheave
11, respectively. It is therefore possible to prevent the first leader strips 4 and
the first main ropes 21 from being inclined with respect to the first car-side return
sheave 9 and the first counterweight-side return sheave 11. Thus, it is possible to
prevent the first leader strips 4 or the first main ropes 21 from being wedged between
the main rope latch 15 and the first car-side return sheave 9 or between the main
rope latch 17 and the first counterweight-side return sheave 11. As a result, it is
possible to prevent the occurrence of an inconvenience such as ruptures of the first
leader strips 4 or the first main ropes 21.
[0053] The attachment frame 2 is provided with the guide devices for guiding either the
second leader strips 5 or the second main ropes such that the second leader strips
5 or the second main ropes are moved along the outer peripheral portions of the second
car-side return sheave 10 and the second counterweight-side return sheave 12, respectively.
It is therefore possible, in the same manner as described above, to prevent the second
leader strips 5 or the second main ropes from being wedged between the main rope latch
16 and the second car-side return sheave 10 or between the main rope latch 18 and
the second counterweight-side return sheave 12. As a result, it is possible to prevent
the occurrence of an inconvenience such as ruptures of the second leader strips 5
or the second main ropes.
[0054] In leading the first main ropes 21 or the second main ropes into the unit-mounted
component 3 (in the main rope looping process), each of the main ropes to be lead
into the unit-mounted component 3 is placed on the corresponding one of the rotary
tables 59 provided at the landing 31 of the uppermost floor, and then reeled out while
the rotary table 59 is rotated. It is therefore possible to prevent the main ropes
from becoming tangled. As a result, it is possible to achieve an improvement in operation
efficiency.
[0055] The turning device 56 for changing the direction of the first leader strips 4 or
the second leader strips 5 that have been led out from the unit-mounted component
3 is provided at the landing 31 of the uppermost floor. It is therefore possible to
change the direction of the first leader strips 4 or the second leader strips 5 into
such a direction that makes it easy for an operator to pull the first leader strips
4 or the second leader strips 5 at the landing 31. As a result, it is possible to
achieve a further improvement in operation efficiency.