BACKGROUND OF THE INVENTION
[0001] The invention relates to a method for optimising the production of a hydrocarbon
production system comprising a cluster of hydrocarbon production wells and an associated
fluid separation assembly.
[0002] Typically, fluid streams produced by individual wells of a well cluster are commingled
into multiphase streams in one or more production manifold (header) conduits and routed
via a fluid separation assembly (comprising one or more bulk separators and/or production
separators) into fluid outlet conduits for transportation and sales of at least nominally
separated streams of liquids, gas and/or other fluids.
[0003] A problem associated with management of fluid flow at the outlets of the bulk or
production separator is that this fluid flow stems from the commingled flux from all
the wells of the cluster and does not provide information about the composition and
flux of fluids produced by the individual wells. Consequently, the individual flux
of fluids produced by the individual wells cannot customarily be tracked accurately
in real time or instantaneously. The inability to track the individual well productions,
together.with the variability of well production and properties over time, leads immediately
to the inability to fully characterize the wells for the purposes of predicting flows
if various well adjustments are made. Further, the production from the wells often
interact due to limited capacity in the manifold and the separator to handle the full
potential productions from the wells. As an example, over-production of gas in one
well may reduce the total oil production in the cluster of wells.
[0004] A further problem with monitoring and controlling the production of a hydrocarbon
production well is that such a well may produce a mixture of crude oil, gas, water
and condensates and that the production may contain irregular slugs of crude oil,
water, solids and/or condensates. Multiphase flowmeters are often too expensive, have
too restricted an operating envelop and are too complex to install on individual well
flowlines to allow individual oil, water and gas components of the well production
to be measured continuously in real time, particularly as the well multiphase flow
characteristic changes significantly over the life of the well. These multiphase flowmeters
also require calibration at start up and/or from time to time thereafter. Consequently,
in the vast plurality of cases, the production of fluids by the individual wells is
not customarily measured directly accurately continuously, or in real time.
[0005] International patent application
WO03/046485 discloses a production metering and well testing system, wherein the accumulated
production of wells of an entire field is measured downstream of a bulk separator
in which the produced fractions of crude oil, water, natural gas, solids and/or condensates
are separated and the flux and composition of the produced crude oil and/or other
fractions can be accurately monitored. This accurate measurement of the accumulated
production of wells of an entire field is made simultaneously, and compared, with
less accurate measurements upstream multiphase flow measurements that are taken simultaneously
at each individual well.
[0006] Applicant's International patent application
PCT/EP2005/055680, filed on 1 November 2005, "Method and system for determining the contributions of individual wells to the
production of a cluster of wells" discloses a method and system named and hereafter
referred to as "Production Universe Real Time Monitoring" (PU RTM). The PU RTM method
allows accurate real time estimation of the contributions of individual wells to the
total commingled production of a cluster of crude oil, gas and/or other fluid production
wells, based on well models derived from well test data and updated regularly using
commingled production dynamic data. The PU RTM method also does not require the deployment
of multiphase meters at each monitored well. SPE 83978 discloses the concept of real-time
optimization in general terms.
[0007] An object of the present invention is to provide a method and system to optimise
production of a cluster of wells on the basis of an estimation of the contributions
of individual wells to the production of the cluster of wells, tailored to the particular
constraints and requirements of the oil and gas production environment. The wells
in the cluster may differ in terms of nature and flux of its effluents, and/or mode
of operation, stimulation and/or manipulation. The wells may also produce from multiple
subsurface zones or branches. The wellheads of the wells in the cluster may be located
on land or offshore, above the surface of the sea or on the seabed. The method according
to the invention may be used to generate one or more optimisation models, taking into
account only significantly relevant well and production system characteristics and
effects.
SUMMARY OF THE INVENTION
[0008] In accordance with the invention there is provided a method for optimising production
of a cluster of wells of which well effluent streams are commingled and separated
in a fluid separation assembly into at least partly separated streams of crude oil,
gas and/or other fluids, the method comprising:
- a) performing a well test on each of the wells during which production from the tested
well is varied and one or more individual well production variables are monitored;
- b) deriving from data obtained by the well tests an estimation model for each well
relating to the variation of the flow pattern of effluents produced by the tested
well and of the monitored well production variables;
- c) putting the wells in normal commingled oil and/or gas production;
- d) monitoring during step c) a dynamic fluid flow pattern of the at least partly separated
streams of crude oil, gas and/or other fluids by means of flow meters arranged in
the at least partly separated streams of crude oil, gas and/or other fluids downstream
of the fluid separation assembly;
- e) monitoring during step c) one or more well production variables relating to characteristics
of the multiphase flow streams produced by the individual wells;
- f) repeatedly estimating a dynamic commingled fluid flow pattern of the cluster of
wells on the basis of the estimation models according to step b) and production variables
monitored in.accordance with step e);
- g) performing a dynamic reconciliation process, wherein during a selected reconciliation
period:
- it is assumed that the estimated dynamic commingled fluid flow pattern according to
step f) is an accumulation of said individual well production estimation models that
are multiplied by unknown weight coefficients;
- the unknown weight coefficients are estimated by iteratively varying each weight coefficient
until the estimated dynamic commingled fluid flow pattern substantially matches with
the monitored dynamic fluid flow pattern; and
- best estimates of production flow are provided for the selected reconciliation period,
and using the individual well reconciliation factors with the estimation models to
estimate production from each well for a next reconciliation period;
- h) defining an operational optimisation target consisting of a target to be optimised
regarding production of one or more wells and/or the cluster of wells;
- i) adjusting production of well effluents of the well cluster such that the optimisation
target is approached; and
- j) steps g and i are repeated from time to time. Optionally, the method according
to the invention may further comprise the steps of:
- identifying for at least one of the wells in the cluster one or more numerical manipulated
variables that can be manipulated directly to vary the production of the well, and
thereafter deriving from data, obtained by the well tests and/or during normal commingled
production, and/or the estimation model, a prediction model relating the well manipulated
variables to the variation of the flux or the flow pattern and/or other characteristics
of the produced well effluents. Wells without identified manipulated variables will
have prediction models that are constant numbers equal to the nominal estimated productions
of wells;
- summing the prediction models of all wells of the well cluster to provide an overall
commingled production prediction model;
- adjusting production of well effluents by means of the well manipulated variables
as guided by the individual well prediction models and the overall commingled production
prediction model to achieve the said optimisation target. Optionally, the method according
to the invention may yet further comprise the steps of:
- measuring an interaction pressure(s), such as a pressure(s) within one or more production
manifolds in the flowlines that are connected to the wellheads of the wells of the
cluster of wells, in which manifolds which the flux from a plurality of well flowlines
is commingled, the variation of which, as total well productions vary, indicates and
links interactions between effluent streams from various wells;
- obtaining dynamic data relating the variations of interaction pressure(s) to the measured
variables of the wells, from normal commingled production and / or during periods
of production upsets and / or by performing a series of well interaction tests during
which the interaction pressure is varied;
- obtaining from dynamic data relating the variations of interaction pressure(s) to
the measured variables of the wells well prediction models relating the variations
of well manipulated variable(s) and interaction pressure(s) to the production of the
wells;
- obtaining dynamic data relating the variations of interaction pressure(s) to the total
commingled production, from periods of normal commingled production and / or during
periods of production upsets and / or by performing a series of tests during which
the interaction pressure is varied, and thereafter one or more manifold interaction
models relating the variation of the interaction pressure(s) with the total commingled
production flows flowing through the manifolds;
- combining the well prediction models to the interaction pressure models to obtain
an overall commingled production prediction model.
[0009] Optionally the method according to the invention may further comprise the step of
periodically repeating the optimisation method by aligning the prediction models with
the current flows so that the aligned prediction models reflect the current flows
as estimated by the dynamic reconciliation process.
[0010] The optimisation target may be a revenue function relating accumulated or averaged
combined and / or individual well production to actual net or gross or incremental
monetary revenue, optionally including associated production costs.
[0011] The optimisation target may be required to be achieved while obeying production constraints,
consisting of bounds on the manipulated variables and / or the individual well productions,
and / or well production quantities, including measurements, and / or that of groups
of wells and / or on the interaction pressure(s), and / or on the commingled total
productions.
[0012] The method according to the invention may further comprise the step of performing
an optimisation using any of a plurality of numerical optimization algorithms over
the manipulated variables based on the operational optimisation target, optionally
with constraints, and well and/or overall commingled production prediction models
to yield a set of optimised manipulated variables that achieve the operational optimisation
target.
[0013] Optionally, the production of well effluents of the wells may be varied by adjusting
the opening of a production choke valve at the wellhead of the wells or in flowlines
connected to the wells, or of a flow control valve in a lift gas injection system
of the wells, or by other means of stimulating or restricting the production of the
wells.
[0014] Optionally, the production of well effluents of the wells may be varied by adjusting
the interaction pressure(s) of the production system by means of rerouting well production
through parallel production manifold conduits that are connected between upstream
and downstream manifolds, or by adjusting the pressure of the fluid separation assembly
or assemblies.
[0015] Required adjustments predicted by the method according to the invention to achieve
the optimisation targets may be automatically transmitted to the wells and the production
system, or alternatively, after validation by a human operator.
[0016] One or more of the estimation and/or prediction models may optionally be generated
in part or in full from theoretical and/or empirical physical and/or mechanical and/or
chemical characterization of the wells and/or the production system.
[0017] The optimization target can be adjusted in reaction to and/or in anticipation of
changes to the production requirements and/or costs and/or revenues and/or production
infrastructure and/or state of the wells and/or the state of the production facilities;
and optionally followed up by the conduct of the optimization process, the results
of which are implemented and/or used for analysis and planning and/or recorded for
future action.
[0018] The method and system outlined herein is further applicable to the case where the
optimisation target is achieved by optional means of temporary close in of production
in one or more wells of the well cluster, or the initiation of production of wells
of the well cluster that were initially not in production.
[0019] One or more of the estimation and/or prediction models may optionally be compared
and/or evaluated against theoretical and/or empirical physical and/or mechanical and/or
chemical characterization of the wells and/or the production system; for the purposes
of troubleshooting and/or diagnosis and/or for improving the models and/or for analysis
leading to longer time horizon production management and optimization activities.
[0020] The methods of this invention apply also when one or more of the wells from the cluster
of wells are periodically, or intermittently, operated, or are operated from time
to time, and the production or associated quantities to be optimised, and optionally,
constrained, are evaluated, for example averaged, over fixed periods of time larger
than that characteristic of the periodicity or intermittent operation.
[0021] The methods of this invention apply also when one or more of the wells from the cluster
of wells are periodically, or intermittently, operated, or are operated from time
to time, and the duration of its operation, as a proportion of a fixed period of time,
is taken a manipulated variable for the well.
[0022] The methods of this invention apply additionally to an optimization target defined
on wells in the well cluster with two or more subsurface zones. In this case, "zone
production estimation models" and "zone production prediction models" are generated
in addition to the "well production estimation models" and "well production prediction
models".
[0023] The method according to the invention allows the characterization of the behaviour
of wells individually and within the context of the overall production facility as
a function of variables that can be freely manipulated at the wells and also for the
overall facility. The characterization of the wells and their interactions with the
facility allows directly the accurate real time prediction and optimisation of well
production within the context of the production facility. The method according to
the invention may include consideration of constraints on the production, arising
from both the interactions between wells due to the limitations on the facilities,
as well as externally imposed constraints. The method according to the invention is
also referred to as "Production Universe Real Time Optimisation" (PU RTO).
[0024] The "PU RTO" method according to the invention has several advantages over prior
art methods, for example, as outlined in PU RTM described in International patent
application
PCT/EP2005/055680. In particular, the "PU RTO" method according to the invention may be used to derive
various well and production system characteristics from simple well and production
testing at the well and production facility alone, enabling easier model maintenance
and dispensing with measurements and quantities not continuously measured, but nevertheless
unpredictably variable over periods of time in a production environment, such as piping
surface roughness, reservoir pressure-volume-temperature fluid characteristics and
composition, equipment and well performance curves, and similar. In other words, "PU
RTO" is "data driven". Specifically, the "overall well and production system model"
of the commingled well production system may be constructed without preconceptions
as to its underlying physical nature other than the use basic fundamental topological
and physical relations, and purely from measured data.
[0025] The method according to the present invention may be used to provide characterization
of the combined well and production system that will be of benefit additionally for
offline analysis and planning activities. In other words it is another benefit of
the present invention that it may provide a method and system to link real time current
well production characteristics to the offline analysis and modelling to support wider,
weekly, monthly planning and optimisation of the potential of an integrated production
system comprising of multiple cluster of wells and associated production facilities.
BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The invention will be described by way of example in more detail with reference to
the accompanying drawings in which:
FIG. 1 schematically shows a production system according to the invention in which
a multiphase fluid mixture comprising crude oil, water, natural gas and/or other fluids
is produced by a cluster of multiple wells of which two are represented and transported
via multiphase fluid transport pipelines to a bulk separator;
FIG. 2 schematically shows how the "Aligned Well Production Prediction Models" and
"Aligned Well and Overall Production Prediction Model" is generated from a set of
well and production system testing data; and
FIG. 3 schematically shows how the "Well Operational Production Optimisation" problem
and the "Overall Facility Operational Production Optimisation" problem are formulated
to solve for the "Optimised Setpoints" for the wells selected for individual well
optimisation, and the "Optimised Setpoints" for the other wells and the overall production
facility.
DETAILED DESCRIPTION OF PREFERED EMBODIMENTS OF THE INVENTION
[0027] Reference is made to FIG. 1. FIG. 1 depicts a simple embodiment of a production system
comprising a cluster of wells of which effluents are commingled at a production manifold
and routed to a production separator. Well 1 is shown in detail, and may be taken
as representative of the other wells in the cluster. The other wells in the cluster
may however differ in terms of nature and flux of its effluents, and / or mode of
operation / stimulation / manipulation.
[0028] Well 1 comprises a well casing 3 secured in a borehole in the underground formation
4 and production tubing 5 extending from surface to the underground formation. The
well 1 further includes a wellhead 10 provided with monitoring equipment for making
well measurements, typically for measuring Tubing Head Pressure (THP) 13 and Flowline
Pressure(FLP) 14. Optionally, there may be downhole monitoring equipment for making
subsurface measurements, for example Downhole Tubing Pressure(DHP) 18, and/or subsurface
and/or surface tubing and/or flowline differential pressure meters, for example wet
gas meters (not shown). The wells may also produce from multiple subsurface zones
or branches. The wellheads of the wells in the cluster may be located on land or offshore,
above the surface of the sea or on the seabed.
[0029] The well 1 ,like well 2, and some but not necessarily all of the other wells in the
cluster, will also have some means of adjusting production, such as: a production
control choke 11 or a fixed bean choke (not shown) and/or a lift-gas injection control
system 12 or downhole interval control valves (not shown), which control the production
from one or more inflow regions of the well. Numerical "manipulated variables" are
associated with each of these means of adjusting production.
[0030] The production system further includes a plurality of well production flow lines
20, extending from the wellheads 10 to a production manifold 21, a production pipeline
23 and a means of separating the commingled multiphase flow, in this case a production
separator 25. Production manifold pressure measurement 22 and production separator
pressure measurement 26 will often be available on the production manifold and the
production separator as shown. There will be some means of regulating the level of
the production separator, and optionally its pressure or the pressure difference between
the separator its the single-phase outlets. For simplicity a pressure control loop
27 is show in FIG. 1. Typically, the production manifold pressure measurement 22 (alternatively
the production separator pressure measurement 26) will be used as "interaction pressure",
the variation of which as the well production rates are varied, is an indicator of
the degree of interaction between the wells.
[0031] The production separator 25 is provided with outlets for water, oil and gas 35, 36
and 37 respectively. Each outlet 35, 36 or 37 is provided with flow metering devices,
45, 46 and 47 respectively. Optionally, the water and oil outlets can be combined.
The production separator pressure may optionally be controlled by regulating the gas
flow from 37, thereby affecting the manifold pressure 26 and the flowline pressure
14 and thus the production of the individual wells.
[0032] The well measurements comprising at least data from 13 and optionally from 14, 18,
liftgas injection rate from 12, position of production choke 11, and other measurements
as available, are continuously transmitted to the "Production Data Acquisition and
Control System" 50. Similarly, the commingled production measurements 45, 46, 47 are
continuously transmitted to the "Production Data Acquisition and Control System" 50.
The typical data transmission paths are illustrated as 14a and 45a. The data in 50
is stored and is then subsequently available for non-real time data retrieval for
data analysis and model construction as outlined in this patent. The data in the "Production
Data Acquisition and Control System" is also accessed by "PU RTM" in real time for
use in conjunction with "well production estimation models" for the continuous real
time estimation of individual well productions. Some well production rate controls
will also be adjustable from "Production Data Acquisition and Control System" 50 for
remotely adjusting and optimising the well production, for example, the production
choke opening or the liftgas injection rate, and the signal line for liftgas injection
rate control is shown as 12a.
[0033] An associated well testing facility may optionally and is preferably to be available
for the individual testing and characterization of the wells. In the absence of a
well testing facility, testing for well model construction may be conducted utilizing
measurements 45, 46, 47 from the production separator.
[0034] Reference is now made to FIG. 2, which provides one preferred embodiment of the "data
driven" modelling process for this invention. The intent is to generate sustainably
useful models fit for the purpose of the invention, taking into account only significantly
relevant well and production system characteristics and effects. The procedure leading
to the generation of "Aligned Well Production Prediction Models" and "Aligned Well
and Overall Production Prediction Model" for a cluster of
n wells indexed
i = 1,2,..,
n, for which one "manipulated variable" for each well has been identified, and for
which a dedicated well test facility are available, is described as follows:
- a series of well tests are conducted during which production from each well is varied
for well characterization by changing the "manipulated variable" of the well. The
well test data 60 is used to generate a "well production estimation model" 61 in the
form yi=fi(ui,vi), valid for a range of ui,vi within a set Ui×Vi, wherein the vector yi is the oil, water and gas production of well i, ui is the vector of measurements at well i, and vi is the manipulated variable at well i. The procedure for constructing "well production estimation model" using dedicated
well test facilities is as previously outlined in "PU RTM". In "PU RTM" distinction
is not made between the measured variables ui and the manipulated variable vi, (which is also measured) but the distinction is required for this invention;
- a series of "well and production facilities interaction tests" are then conducted
to obtain "well and production facilities interaction test data" 62, or alternatively,
data can also be derived from "production data" 63 which contains a record of dynamic
events during normal production, such as when major gas producing wells are closed
in.
- a "well production manipulation and interaction model" 65 is then constructed relating
the variations of "manipulated variable" of the well and the "interaction pressure"
to the measurements at the well flowline. The relation between the "manipulated variable"
and the measurements at the well flowline may be derived from well test data 60, for
example "DDWTs", or from "production data" 63 by adjusting the manipulated variable
during normal well production, and recording the reactions of the measurements at
the well flowline. Similarly, the relation between "interaction pressure" and the
measurements at the well flowline is established from "well and production facilities
interaction tests" data 62 or from "production data" 63 recording dynamic events during
normal production.
[0035] The "well production manipulation and interaction model" 65 will have the form
ui=
gi(
vi,
w), for each of the wells
i = 1,2,...,
n where
w ∈
W is the common "interaction pressure" ranging.over set
W,
ui is the vector of measurements at well
i, and
vi is the manipulated variable at well
i, as before.
[0036] A "well production prediction model" 66 for each well
i =1,2,...,
n is then generated from the "well production estimation model" 61 and the "well production
manipulation and interaction model" 65 as follows:

so that the function
hi(
vi,
w) relates the vector
yi, the oil, water and gas production of well
i, to the
w, the common "interaction pressure", and
vi, the manipulated variable at well
i.
[0037] Given the characterization of the well 66, it is now required to derive the dependence
of
w, the "interaction pressure" at the production manifold in this embodiment, to the
total commingled production flows routed via the production manifold, and optionally,
of variables,
vw, that are manipulated at a overall facilities level which also affect the "interaction
pressure", for example, the production separator pressure setpoint 27. This is achieved
by using the "well and production facilities interaction test" data 62 to build an
"interaction pressure model" 67,
w=
k(
ŷ,
vw), where
ŷ is defined to be the vector of the sum of the production of the wells routed to the
production manifold, in this case

[0038] There will be instances wherein data from well testing or production is not available
or reliable for a particular well or parts of the overall system, for example when
a well is not yet been brought into production. In such cases, models based on theoretical
and/or empirical physical and/or mechanical and/or chemical characterization of the
wells and/or the production system can be used in place of 65 or 67.
[0039] Once the "well production manipulation and interaction models" 66 and the "interaction
pressure model" 67 are developed, the optimisation process is implemented as per the
online part of the workflow in Fig.2 and then as in Fig.3. The desired production
optimisation formulations are also set out as follows:
- Well Optimisation 78, for selected wells, defined by an index set I which is a proper subset of 1,2,...,n, in the form

subject to constraints ci,j(yi,vi,ui)≥0, j=1,2,...,Ji.
where
Ri(
yi,
vi) is the objective or revenue function 76 for the well
i to be maximized by varying
vi, the manipulated variable at well
i, subject to
Ji constraints on
yi,vi,ui, the well production, the well manipulated variables and the measured variables, respectively,
defined by the constraint inequalities
ci,j(yi,vi,ui)≥0, 77.
- Overall Production Optimisation, 83, for wells i ∉ I (which are wells not already optimised as part of 78), in the form

subject to constraints cj(ŷ,yi,vi,ui,w,vw) ≥0, j=1,2,...,Jw;
where
R(
ŷ,
vi,
ui,
w,
vw) is the objective or revenue function, 81, to be maximized by varying
vi, the manipulated variable at wells
i ∉
I, subject to
Jw constraints, 82,
cj(
ŷ,
yi,
vi,
ui,
w,
vw) ≥ 0 the on
ŷ,
w,
vw, the overall commingled production, the interaction pressure, and the optional vector
of variables that can be manipulated at a overall facilities level, respectively,
and
yi,vi,ui, i =1,2,3,...
n, the individual well productions, well manipulated variables, and well measured variables
for the wells
i=1,2,3,...
n.
[0040] With the wells in normal commingled production, "PU RTM" is run online to produce
continuous real time estimates of production at each individual well 70. The "current"
"PU RTM" estimates of individual well production
ỹi, and the "current" measurements and manipulated variable values
ṽi,
w̃ are used to align the "well production manipulation and interaction models"
yi =
hi(
vi,
w) by defining a constant offset
di=
ỹi-
hi(
ṽi,
w̃) at
ỹi,
ṽi,
w̃. The "Aligned Well Production Prediction Models" 75 then have the form
yi=
hi(
vi,
w)+
di. The alignment process allows the optimisation focus to be on incremental changes
in the production at the well and overall production, so that if Δ
vi=
vi-
ṽi, Δ
w=
w-
w̃ and Δ
yi=
yi-
ỹi, then Δ
yi=0
i if Δ
vi =0 and Δ
w=0. For illustrative purposes, the "Aligned Well Production Prediction Model", 75,
for each well
i, can be cast in the "separated difference" form Δ
yi =
AiΔ
vi+
BiΔ
wi. The symbols
Ai,
Bi can be envisaged as either matrices or functionals operating on Δ
vi and Δ
w. Optionally, cross terms and second and higher order terms on Δ
vi and Δ
w can be inserted without loss of generality.
[0041] For each well
i ∈
I, which are wells for which a well optimization is desired, given its "Aligned well
Production Prediction Model", 75, and the objective or revenue function 76, and associated
optimisation constraints 77, the well optimisation, 78, may then be conducted to solve
for the optimal value of
vi, 79, the manipulated variable at well
i. Note that the well optimisation necessarily assumes the common well interaction
variable
w, which is an variable affected by the collective production of the wells and variables
at the overall production system level, is unchanged by the well optimisation, or
has negligible effect on the optimisation result.
[0042] The "interaction pressure model" 67
w=
k(
ŷ,
vw) be aligned by defining constant
dw=
w̃-
k(
ỹ,
ṽw), where the "current nominal value" of the commingled production measurements
ŷ is denoted by
ỹ. The "aligned interaction pressure model" is then of the form
w=
k(
ŷ,
vw) +
dw. Further, we assume the estimates
ỹi have been fully reconciled by "PU RTM" with the latest nominal overall commingled
production measurements so that

Again, for illustrative purposes, the "aligned interaction pressure model" can also
have the "separated difference" form Δ
w=
KΔ
ŷ + LΔ
vw, where

and Δ
vw=
vw-
ṽw.
[0043] Now

is the estimate of total commingled production from the "Aligned Well Production
Prediction Models" 75. Hence the "Aligned Well + Overall Production Prediction Model"
80 in "Difference" form is then constructed by combining "Aligned Well Production
Prediction Models" 75 with the "aligned interaction pressure model". From

we get

which is an implicit form of the "Aligned Well + Overall Production Prediction Model"
80 relating the variables Δ
ŷ,Δ
vi,Δ
vw, respectively, the total commingled production, the manipulated variables at the
wells, and the manipulated variables at the overall production system level. For given
values of Δ
vi,Δ
vw, depending on the form of the functionals

the implicit form of 80 can be solved Δ
ŷ by a plurality of methods. In the case where the interaction components

are matrices of real numbers, for example, we have

which is solvable for Δ
ŷ given values of
vi,
vw, unless, for example, the operator

is not invertible.
[0044] An estimate of the manipulated variables
vi,
vw required to optimise the production of the overall facility is then obtained by combining
"Aligned Well + Overall Production Prediction Model" 80 with the objective or revenue
function 81, and associated optimisation constraints 82 to form the "Overall Facility
Operational Production Optimisation" 83. The optimisation is then conducted to solve
that for optimal values of the "optimised manipulated variables"
vi,vw, 84.
[0045] Depending on the form of 83, the optimised variables 84 may be directly computed
or an automated numerical iterative optimisation procedure applied. There is a plurality
of automated numerical iterative optimisation approaches that are applicable depending
on the form of 83. Refer for example to the textbook "
Nonlinear Programming - Theory and Algorithms", 2nd Edition, 1993, by M Bazaraa, H.D.
Sherali and C.M. Shetty, or more generally for various rigorous or heuristic "
Global Optimisation" methods, see for example, Computers and Chemical Engineering
28 (2004) 1169-1218, "Part I Retrospective on optimization", and "
Part II. Future Perspective on Optimization", by L.T. Biegler, I.E. Grossmann, and references therein. For a preferred embodiment where the manipulated variables
are continuous variables, and 83 is defined by continuous smooth nonlinear model and
revenue functions and inequality constraints, a sequential quadratic programme (SQP)
with multiple starting points is used for the automated numerical iterative optimisation
to yield the "optimised manipulated variables".
[0046] The set of "optimised manipulated variables" is then available for further action.
Optionally, the "optimised manipulated variables" are reported to the production facility
operators for implementation at the wells and the facility, or alternatively, directly
transmitted to the "Production Data Acquisition & Control System" 50 for automated
implementation.
[0047] The computation and application of the optimised manipulated variables is conducted
from time to time, and is controlled by a "Optimization Initiation System" 90. Preferably,
"Well Operational Production Optimisation" and the "Overall Facility Operational Production
Optimisation" are initiated on a periodic basis, for example once every day, and/or
on demand, in anticipation of changes to the state of the philosophy of management
of the wells or of the production system or of the constraints or of the optimisation
target. In one embodiment, changes in gaslift availability will automatically initiate
an optimisation.
[0048] In a preferred embodiment of the "PU RTO" method according to the invention:
- All models are validated and updated as necessary using current latest and historical
test data.
- The "PU RTM Well Production Estimation Model" is verified and updated periodically
by checking against normal well testing.
- The well manipulated variables are cycled periodically during normal well production
to allow verification and updates of the "Well Manipulation & Interaction Models".
- Production data is captured during normal operations to validate and update as necessary
the "Well Manipulation & Interaction Models", and the "Interaction Pressure Model".
- The "optimised manipulated variables" are transmitted after inspection by a human
operator.
- The computational optimisation step determines the wells that will either be opened
up to resume the individual well production, or closed in to stop the individual well
production, or switched between different production separators, addition to the "optimised
manipulated variables" for the well while in production.
In this case, the manipulated variables vi,vw will include binary values 0 or 1, and various rigorous and heuristic methods are
available for its solution, depending on the structure of the models and optimisation
formulations used.
- The prediction models of the wells and the overall production system, which reflect
the reality of the well and production system, should periodically be compared and
evaluated against theoretical physical and mechanical models of the wells and/or the
production system, if these are available. The evaluation and comparison of the models
derived from the actual well performances as per this invention against theoretical
models will yield information to aid in longer time horizon production management
and optimization activities.
1. A method for optimising production of a cluster of wells of which well effluent streams
are commingled and separated in a fluid separation assembly into at least partly separated
streams of crude oil, gas and/or other fluids, the method comprising:
a) performing a well test on each of the wells during which production from the tested
well is varied and one or more individual well production variables are monitored;
b) deriving from data (60) obtained by the well tests an estimation model (61) for
each well relating to the variation of the flow pattern of effluents produced by the
tested well and of the monitored well production variables;
c) putting the well cluster in normal commingled oil and/or gas production;
d) monitoring during step c) a dynamic fluid flow pattern of the at least partly separated
streams of crude oil, gas and/or other fluids by means of flow meters arranged in
the at least partly separated streams of crude oil, gas and/or other fluids downstream
of the fluid separation assembly;
e) monitoring during step c)one or more well production variables relating to characteristics
of the multiphase flow streams produced by the individual wells;
f) repeatedly estimating a dynamic commingled fluid flow pattern of the cluster of
wells on the basis of the estimation models (61) according to step b) and production
variables monitored in accordance with step e);
g) performing a dynamic reconciliation process, wherein during a selected reconciliation
period:
- it is assumed that the estimated dynamic commingled fluid flow pattern according
to step f) is an accumulation of said individual well production estimation models
that are multiplied by unknown weight coefficients;
- the unknown weight coefficients are estimated by iteratively varying each weight
coefficient until the estimated dynamic commingled fluid flow pattern substantially
matches with the monitored dynamic fluid flow pattern; and
- best estimates of production flow are provided for the selected reconciliation period,
and using the individual well reconciliation factors with the estimation models to
estimate production from each well for a next reconciliation period;
h) defining an operational optimisation target consisting of a target to be optimised
regarding production of one or more wells and/or the cluster of wells;
i) adjusting production of well effluents of the well cluster such that the optimisation
target is approached; and
j) steps g and i are repeated from time to time.
2. The method of claim 1, further comprising the steps of:
- identifying for at least one of the wells in the cluster one or more numerical manipulated
well production variables that can be manipulated directly to vary the production
of the well, and thereafter deriving from data, obtained by the well tests and/or
during normal commingled production, and/or the estimation model, a prediction model
relating the well manipulated variables to the variation of the flux or the flow pattern
and/or other characteristics of the produced well effluents, wherein any wells without
identified manipulated well production variables will have prediction models that
are constant numbers equal to a nominal estimated production of the wells;
- summing the prediction models of all wells of the well cluster to provide an overall
commingled production prediction model;
- adjusting production of well effluents by means of the well manipulated variables
as guided by the individual well prediction models and the overall commingled production
prediction model to achieve the said optimisation target.
3. The method of claim 2, further comprising the steps of:
- measuring one or more interaction pressures, such as a pressure within one or more
production manifolds in well flowlines that are connected to the wellheads of the
wells of the cluster of wells, in which manifolds the flux from a plurality of well
flowlines is commingled, the variation of which interaction pressure, as total well
productions vary, indicates and links interactions between effluent streams from various
wells;
- obtaining dynamic data relating the variations of interaction pressure(s) to the
measured variables of the wells, from normal commingled production and/or during periods
of production upsets and/or by performing a series of well interaction tests during
which the interaction pressure is varied;
- obtaining from dynamic data relating the variations of interaction pressure(s) to
the measured variables of the wells well prediction models relating the variations
of well manipulated variable(s) and interaction pressure(s) to the production of the
wells;
- obtaining dynamic data relating to the variations of one or more interaction pressures
to the total commingled production, from periods of normal commingled production and/or
during periods of production upsets and/or by performing a series of tests during
which the interaction pressure is varied, and thereafter one or more manifold interaction
models relating the variation of one or more interaction pressures with the total
commingled production flows flowing through the manifolds;
- combining the well prediction models to the interaction pressure models to obtain
an overall commingled production prediction model.
4. The method of claims 2 and 3, wherein the method further comprises
periodically repeating the optimisation method by aligning the prediction models with
the current flows so that the aligned prediction models reflect the current flows
as estimated by the dynamic reconciliation process.
5. The method of any one of claims 1-4, wherein the optimisation target is a revenue
function relating accumulated or averaged combined and/or individual well production
to actual net or gross or incremental monetary revenue, optionally including associated
production costs.
6. The method of claim 5, wherein the optimisation target is to be achieved while obeying
production constraints, consisting of bounds on.the manipulated variables, and/or
the individual well productions, and/or well production quantities, including measurements,
and/or that of groups of wells and/or on one or more interaction pressures, and/or
on the commingled total production of the well cluster.
7. The method of claims 5 or 6, further comprising the step of performing an optimisation
using any of a plurality of numerical optimisation algorithms over the manipulated
variables based on the operational optimisation target, optionally with constraints,
and the well and/or overall commingled production prediction models to yield a set
of optimised manipulated variables that achieve the operational optimisation target.
8. The method of any of the claims 1-7, wherein the production of well effluents of the
wells is varied by adjusting the opening of a production choke valve at the wellhead
of the wells or in flowlines connected to the wells, or of a flow control valve in
a lift gas injection system of the wells, or by other means of stimulating or restricting
the production of the wells, such as any means of reversible and controlled closing
in and opening up of a well, a setpoint of a control loop at the well with the production
choke valve as an actuator, a setpoint of a control loop on the well gas-lift injection
rate or pressure, well gas-lift injection off duration, well gas-lift injection on
duration, well gas-lift injection rate, a setpoint of a control loop on the well jet
pump hydraulic fluid injection line, well electrical submersible pump (ESP) speed,
well rod pump motor speed, well rod pump off duration, and/or well downhole interval
control valve opening.
9. The method of any of the claims 1-8, wherein the production of well effluents of the
wells is varied by adjusting one or more interaction pressures of the production system
by means of rerouting well production through parallel production manifold conduits
that are connected between upstream and downstream manifolds, and/or by adjusting
the pressure of the fluid separation assembly and/or by adjusting the valves for the
routing of well effluents to one or more manifolds that commingle production or that
route the commingled production to one or more production separators, and/or by adjusting
speed of a compressor in an outlet conduit of the fluid separation assembly.
10. The method of any of the claims 1-9, wherein required adjustments predicted to achieve
the optimisation targets are automatically transmitted to the wells and the production
system, optionally, after validation by a human operator.
11. The method of any of the claims 1-10, wherein one or more of the estimation and/or
prediction models may optionally be generated in part or in full from theoretical
and/or empirical physical and/or mechanical and/or chemical characterization of the
wells and/or the production system.
12. The method of any of the claims 1-11, wherein the optimisation target is adjusted
in reaction to and/or in anticipation of changes to the production requirements and/or
costs and/or revenues and/or production infrastructure and/or state of the wells and/or
the state of the production facilities; and optionally followed up by the conduct
of the optimisation process, the results of which are implemented and/or used for
analysis and planning and/or recorded for future action.
13. The method of any of the claims 1-12, wherein the optimisation target is achieved
by optional means of temporary close in of production in one or more wells of the
well cluster, or the initiation of production of wells of the well cluster that were
initially not in production.
14. The methods of claims 2 and 3, whereby one or more of the estimation and/or prediction
models may optionally be compared and/or evaluated against theoretical and/or empirical
physical and/or mechanical and/or chemical characterization of the wells and/or the
production system; for the purposes of troubleshooting and/or diagnosis and/or for
improving the models and/or for analysis leading to longer time horizon production
management and optimisation activities.
15. The methods of the claims 1-13, wherein one or more of the wells from the cluster
of wells are periodically, or intermittently, operated, or are operated from time
to time, and the production or associated quantities to be optimised and optionally
constrained are evaluated, for example averaged, over fixed periods of time larger
than that characteristic of the periodicity or intermittent operation.
16. The method of claim 15, wherein one or more of the wells from the cluster of wells
are periodically, or intermittently, operated, or are operated from time to time,
and the duration of its operation, as a proportion of a fixed period of time, is taken
a manipulated variable for the well.
17. The method of any one of claims 1-13, wherein of the method is applied additionally
to an optimisation target defined on wells in the well cluster with two or more subsurface
inflow zones, in which case, "zone production estimation models" and "zone production
prediction models" are generated in addition to the "well production estimation models"
and "well production prediction models".
18. The method of Claim 1, whereby the well production variables, such as pressure and/or
other fluid flow characteristics of the individual well effluent streams include one
or more of the following variables: well tubing head pressure, well flowline pressure,
well tubing head temperature, well flowline temperature, differential pressures across
well production choke valve, differential pressures across any differential pressure
producer,including a wet gas venturi, on the well flowline, flow meters,nominally
suitable only for single phase flow, which are suitable to be used to provide an input
to the well estimation models even if the well has multiphase flow, well production
choke valve opening state or position, opening state or position of any means of reversible
and controlled closing in and opening up of the well, well lift-gas injection rate,
well jet pump hydraulic fluid injection rate, well production casing pressure, well
electrical submersible pump (ESP) speed, well ESP pump intake pressure, well ESP down
hole pump discharge pressure, well ESP down hole venturi differential pressure, well
ESP power consumption, well ESP motor phase current, well rod pump motor power input,
well rod pump motor speed, well rod pump stroke displacement, well rod pump load cell,
beam pump gear box shaft position, well rod pump differential speed / motor/gear box
slip, well downhole tubing pressure, well downhole annulus pressure, well downhole
tubing or annulus temperature ,or various derivations thereof monitored by distributed
temperature sensors, well downhole interval control valve opening, amplitude of a
selection of sound frequencies from one or more sound sensors mounted on well flowline,
propagation delay of correlated sound patterns at a selection of frequencies from
two or more sound sensors mounted in an upstream-downstream direction on a well flowline.
1. Verfahren zum Optimieren der Förderung aus einem Cluster von Schächten, deren Schachtaustragströme
vermischt sind und in einer Fluidtrennanordnung in zumindest teilweise getrennte Ströme
aus Rohöl, Gas und/oder anderen Fluiden getrennt werden, wobei das Verfahren umfaßt:
a) Ausführen eines Schachttests an jedem der Schächte, während die Förderung aus dem
getesteten Schacht variiert wird und eine oder mehrere einzelne Schachtfördervariablen
überwacht werden;
b) Erzeugen eines Schätzmodells (61) für jeden Schacht aus den durch die Schachttests
gewonnenen Daten (60), das sich auf die Variation der Strömungsmuster der Austragströme,
die von dem getesteten Schacht gefördert werden, und der überwachten Schachtfördervaria-blen
bezieht;
c) Einführen des Schachtclusters in normal vermischte Öl- und/oder Gasförderung;
d) Überwachen während des Schrittes c) eines dynami-schen Fluidströmungsmusters der
zumindest teilweise getrennten Strömen aus Rohöl, Gas und/oder anderen Fluiden mittels
Durchflußmessern, die in den zumindest teilweise getrennten Strömen aus Rohöl, Gas
und/ oder anderen Fluiden stromabwärts der Fluidtrennanordnung angeordnet sind;
e) Überwachen während des Schrittes c) einer oder mehrerer Schachtfördervariablen,
die sich auf die Merkmale der Mehrphasenströme beziehen, die von den einzelnen Schächten
gefördert werden;
f) wiederholtes Schätzen eines dynamisch vermischten Fluidströmungsmusters des Clusters
von Schächten auf der Basis des Schätzmodells (61) gemäß Schritt b) und der Fördervariablen,
die gemäß dem Schritt e) überwacht werden;
g) Durchführen eines dynamischen Verträglichkeitsverfahrens während einer ausgewählten
Verträglichkeitspe-riode:
- es wird angenommen, daß das geschätzte dyna- mische vermischte Fluidströmungsmuster
gemäß Schritt f) eine Ansammlung von einzelnen Schachtförder-Schätzmodellen ist, die
durch unbekannte Gewichtskoeffizienten multipliziert werden;
- die unbekannten Gewichtskoeffizienten werden durch iteratives Variieren jedes Gewichtskoeffizienten
geschätzt, bis das geschätzte dynamische vermischte Fluidströmungsmuster im wesentlichen
dem überwachten dynamischen Fluidströmungsmuster entspricht; und
- die besten Schätzungen des Förderstromes werden für die ausgewählte Verträglichkeitsperiode
bereitgestellt, wobei die einzelnen Schachtverträglichkeitsfaktoren mit den Schätzmodellen
verwendet werden, um die Förderung aus jedem Schacht für eine nächste Verträglichkeitsperiode
zu schätzen;
h) ein betriebliches Optimierungsziel wird definiert, das aus einem zu optimierenden
Ziel hinsichtlich der Förderung aus einem oder mehreren Schächten und/oder des Clusters
von Schächten definiert wird;
i) Einstellen der Förderung der Schachtausträge des Schachtclusters derart, daß das
Optimierungsziel angenähert wird; und
j) die Schritte g) und i) werden von Zeit zu Zeit wiederholt.
2. Verfahren nach Anspruch 1, das ferner die Schritte aufweist:
- Identifizieren für zumindest einen der Schächte in dem Cluster einer oder mehrerer
numerischer manipulierter Schachtfördervariablen, die direkt manipuliert werden können,
um die Förderung des Schachtes zu variieren, und danach Ableiten aus den Daten, die
aus den Schachttests und/oder während der normalen vermischten Förderung erhalten
wurden, und/oder dem Schätzmodell, ein Vorhersagemodell, das sich auf die manipulierten
Schachtvariablen zur Variation des Flusses und/oder Strömungsmusters und/oder anderer
Merkmale der geförderten Schachtausträge bezieht, wobei irgendwelche Schächte ohne
identifizierte manipulierte Schachtfördervariablen Vorhersagemodelle aufweisen, die
konstante Zahlen gleich einer geschätzten Nennförderung der Schächte sind;
- Summieren der Vorhersagemodelle aller Schächte des Schachtclusters zur Schaffung
eines Gesamtvermischtförderungs-Vorhersagemodells;
- Einstellen der Förderung der Schachtausträge mittels der manipulierten Schachtvariablen,
geführt von den einzelnen Schachtvorhersagemodellen und des Gesamtvermischtförderungs-Vorhersagemodells
zur Erzielung des Optimierungszieles.
3. Verfahren nach Anspruch 2, das ferner die Schritte aufweist:
- Messen eines oder mehrerer Interaktionsdrücke, wie eines Druckes innerhalb eines
oder mehrerer Förderverteiler in den Schachtströmungsleitungen, die mit den Schachtköpfen
der Schächte des Clusters von Schächten verbunden sind, wobei in diesen Verteilern
der Fluß aus einer Vielzahl von Schachtströmungsleitungen vermischt wird, wobei die
Variation des Interaktionsdruckes, wenn die Gesamtschachtförderungen variieren, angezeigt
und die Interaktionen zwischen den Austragströmen von verschiedenen Schächten verlinkt
werden;
- Erzeugen aus dynamischen Daten, welche die Varia- tionen der Interaktionsdrücke
auf die gemessenen Variablen der Schächte beziehen, aus der normalen Vermischtförderung
und/oder während Perioden der Förderungsstörung und/oder des Durchführens einer Reihe
von Schachtinteraktionstests, während welchen der Interaktionsdruck variiert wird;
- Erzeugen aus den dynamischen Daten, die sich auf die Variationen des Interaktionsdruckes
bzw. der Interaktionsdrücke zu den gemessenen Variablen der Schächte beziehen, von
Schachtvorhersagemodellen, die sich auf die Variationen der manipulierten Schachtvariable(n)
und des Interaktionsdruckes bzw. der Interaktionsdrücke zur Förderung der Schächte
beziehen;
- Erzeugen dynamischer Daten, die sich auf die Variationen eines oder mehrerer Interaktionsdrücke
zur Gesamtvermischtförderung beziehen, aus Zeitspannen normaler Vermischtförderung
und/oder während Zeitspannen der Förderungsstörung und/oder des Durchführens einer
Reihe von Tests, während denen der Interaktionsdruck variiert wird, und danach eines
oder mehrerer Verteilerinteraktionsmodelle, die sich auf die Variation eines oder
mehrerer Interaktionsdrücke zu den Gesamtvermischtförderströmen beziehen, die durch
die Verteiler strömen;
- Kombinieren der Schachtvorhersagemodelle mit den Interaktionsdruckmodellen zur Erzielung
eines Gesamtvermischtförderungs-Vorhersagemodells.
4. Verfahren nach den Ansprüchen 2 und 3, wobei das Verfahren ferner umfaßt
periodisches Wiederholen der Optimierungsmethode durch Ausrichten der Vorhersagemodelle
mit den vorhandenen Strömungen derart, daß die ausgerichteten Vorhersagemodelle die
vorhandenen Strömungen als durch das dynamische Verträglichkeitsverfahren geschätzt
reflektieren.
5. Verfahren nach einem der Ansprüche 1-4, bei welchem das Optimierungsziel eine Gewinnfunktion
ist, welche einen Bezug der angesammelten oder durchschnittlich kombinierten und/oder
einzelnen Schachtförderung zu dem tatsächlichen Netto- oder Gesamt- oder Teilgeldgewinn
herstellt, gegebenenfalls einschließlich assoziierter Förderkosten.
6. Verfahren nach Anspruch 5, bei welchem das Optimierungsziel erreicht werden soll,
während Förderungszwänge beachtet werden, die aus den Grenzen der manipulierten Varia-blen
und/oder der einzelnen Schachtförderungen und/oder Schachtfördermengen, einschließlich
Messungen, und/oder der Gruppen von Schächten und/oder einem oder mehreren Interaktionsdrücken
und/oder der vermischten Gesamtförderung des Schachtclusters bestehen.
7. Verfahren nach Anspruch 5 oder 6, das ferner den Schritt des Durchführens einer Optimierung
unter Verwendung jedes einer Vielzahl von numerischen Optimierungsalgorithmen gegenüber
den manipulierten Variablen umfaßt, basierend auf dem Betriebsoptimierungsziel, gegebenenfalls
mit Zwängen, und den Schacht- und/oder Gesamtvermischtförderungs-Vorhersagemodellen,
um einen Satz von optimierten manipulierten Variablen zu erzeugen, welche das Betriebsoptimierungsziel
erreichen.
8. Verfahren nach einem der Ansprüche 1-7, bei welchem die Förderung der Schachtausträge
der Schächte durch Einstellen der Öffnung des Förderdrosselventils am Schachtkopf
der Schächte oder in Strömungsleitungen, die mit den Schächten verbunden sind, oder
eines Durchflußsteuerungsventils in einem Liftgaseinspritzsystem der Schächte, oder
durch andere Mittel der Stimulierung oder Beschränkung der Förderung der Schächte
variiert wird, wie irgendwelche Mittel des reversiblen und gesteuerten Schließens
und Öffnens eines Schachtes, eines Einstellpunktes einer Steuerschleife des Schachtes
mit dem Förderdrosselventil als Betätiger, eines Einstellpunktes einer Steuerschleife
an dem Schachtgaslift-Einspritzdurchsatz oder -druck, der Dauer des Abschaltens des
Gaslifteinspritzens, der Dauer des Anschaltens der Gaslifteinspritzung, des Schachtgaslift-Einspritzungsdurchsatzes,
eines Setzpunktes einer Steuerschleife an der Schachtdüsenpumpen-Einspritzleitung
für hydraulisches Fluid, der Geschwindigkeit einer elektrischen Schachttauchpumpe
(ESP), der Schachtstangenpumpen-Motorgeschwindigkeit, der Dauer des Abschaltens der
Schachtstabpumpe und/oder der Öffnung des Bohrlochintervall-Steuerventils.
9. Verfahren nach einem der Ansprüche 1-8, bei welchem die Förderung von Schachtausträgen
der Schächte variiert wird, indem ein oder mehrere Interaktionsdrücke des Fördersystems
dadurch eingestellt werden, daß die Schachtförderung durch parallele Förderverteilleitungen
umgeleitet wird, die zwischen dem stromaufwärtigen und dem stromabwärtigen Verteiler
eingeschaltet sind, und/oder durch Einstellen des Druckes der Fluidtrennanordnung
und/oder durch Einstellen der Ventile zum Umleiten der Schachtausträge zu einem oder
mehreren Verteilern, welche die Förderung vermischen oder die vermischte Förderung
zu einem oder mehrerer Fördertrenneinrichtungen leiten, und/oder durch Einstellen
der Geschwindigkeit eines Kompressors in einer Auslaßleitung der Fluidtrennanordnung.
10. Verfahren nach einem der Ansprüche 1-9, bei welchem die erforderlichen Einstellungen,
die vorhergesagt sind, um Optimierungsziele zu erreichen, automatisch an die Schächte
und das Fördersystem, gegebenenfalls nach der Validierung durch einen menschlichen
Betreiber, übertragen werden.
11. Verfahren nach einem der Ansprüche 1-10, bei welchem eine oder mehrere der Schätzungs-
und/oder Vorhersagemodelle gegebenenfalls teilweise oder zur Gänze aus theoretischen
und/oder empirisch physikalischen und/oder mechanischen und/oder chemischen Merkmalen
der Schächte und/oder des Fördersystems erzeugt werden können.
12. Verfahren nach einem der Ansprüche 1-11, bei welchem das Optimierungsziel in Reaktion
auf und/oder in Erwartung der Änderungen der Förderanforderungen und/oder Kosten und/oder
Erträge und/oder Produktionsinfrastruktur und/oder des Status der Schächte und/oder
des Status der Förderanlagen eingestellt wird; und gegebenenfalls gefolgt von der
Durchführung des Optimierungsverfahrens, dessen Ergebnisse implementiert und/oder
zur Analyse und zur Planung und/ oder Aufzeichnung weiterer Aktionen verwendet werden.
13. Verfahren nach einem der Ansprüche 1-12, bei welchem das Optimierungsziel durch allfällige
Mittel zum temporären Stillsetzen der Förderung in einem oder mehreren Schächten des
Schachtclusters oder durch Initiierung der Förderung von Schächten des Schachtclusters,
die ursprünglich nicht in Förderung waren, erreicht wird.
14. Verfahren nach den Ansprüchen 2 und 3, bei welchen eines oder mehrere der Schätz-
und/oder Vorhersagemodelle gegebenenfalls mit theoretischen und/oder empirischen physikalischen
und/oder mechanischen und/oder chemischen Merkmalen der Schächte und/oder des Fördersystems
verglichen und/oder ausgewertet werden; zum Zwecke der Überprüfung und/oder Diagnose
und/oder Verbesserung der Modelle und/oder zur Analyse, die zu längerem Zeithorizontfördermanagement
und Optimierungsaktivitäten führen.
15. Verfahren nach den Ansprüchen 1-13, bei welchen einer oder mehrere der Schächte aus
dem Cluster von Schächten periodisch oder intermittierend betrieben wird, oder von
Zeit zu Zeit betrieben wird, und die Förderung oder assoziierte Mengen, die optimiert
werden sollen und gegebenenfalls beschränkt sind, ausgewertet werden, beispielsweise
als Durchschnitt ausgewertet werden, über feststehende Zeitspannen, die größer als
dieses Merkmal des periodischen oder intermittierenden Betriebes sind.
16. Verfahren nach Anspruch 15, bei welchem einer oder mehrere der Schächte aus dem Cluster
von Schächten periodisch oder intermittierend betrieben wird, oder von Zeit zu Zeit
betrieben wird, und die Betriebsdauer als Teil einer feststehenden Zeitspanne als
manipulierte Variable für den Schacht genommen wird.
17. Verfahren nach einem der Ansprüche 1-13, bei welchem das Verfahren zusätzlich zu einem
Optimierungsziel angewendet wird, das an den Schächten des Schachtclusters mit zwei
oder mehr unterirdischen Einströmzonen definiert ist, in welchem Fall die "Zonenförderung-Schätzmodelle"
und die Zonenförderungs-Vorhersagemodelle" zusätzlich zu den "Schachtförderungs-Schätzmodellen"
und "Schachtförderungs-Vorhersagemodellen" erzeugt werden.
18. Verfahren nach Anspruch 1, bei welchem die Schachtfördervariablen, wie Druck und/oder
Fluiddurchflußmerkmale der einzelnen Schachtaustragströme, eine oder mehrere der folgenden
Variablen umfassen: den Schachtrohrkopfdruck, den Schachtströmungsleitungsdruck, die
Schachtrohrkopftemperatur, die Schachtströmungsleitungstemperatur, Differentialdrücke
über das Schachtförderungs-Drosselventil, Differentialdrücke über Differentialerzeuger,
einschließlich eines Nassgas-Venturi, an der Schachtströmungsleitung, Durchflußmesser,
die für eine Einphasenströmung nominal geeignet sind, aber die geeignet sind, um einen
Input für die Schachtschätzmodelle zu liefern, selbst wenn der Schacht ein Mehrphasen-Strömungsschacht
ist, die Öffnungs- oder Schließposition des Schachtdrosselventils, den Öffnungsstatus
oder die Position irgendwelcher Mittel zum rever-siblen und kontrollierten Schließen
und Öffnen des Schachtes, die Schachtliftgas-Einspritzrate, die Schachtdüsenpumpen-Hydraulikfluid-Einspritzrate,
den Schachtförderauskleidungsdruck, die elektrische Schachttauchpumpengeschwindigkeit,
den Schachttauchpumpen-Eingangsdruck, den Schachtbohrloch-Ausgangsdruck, den Schachttauchpumpen-Bohrloch-Venturi-Differentialdruck,
den Schachtbohrlochpumpen-Energieverbrauch, den Schachttauchpumpenmotor-Phasenstrom,
den Schachtpumpenmotor-Energieeintrag, die Schachtpumpenmotorgeschwindigkeit, den
Schachtpumpenmotorhub, die Schachtpumpenmotor-Ladezelle, die Position des Pumpengetriebeschaftes,
die Schachtpumpenstangen-Differentialgeschwindigkeit / den Motor/Getriebekastenschlupf,
den Schachtbohrlochdruck, den Schachtbohrloch-Ringdruck, die Schachtbohrloch- oder
Ringdrucktemperatur, oder verschiedene Ableitungen derselben, die von verteilten Temperatursensoren
gemessen werden, das Schachtbohrloch-Steuerventil-Öffnungsintervall, die Amplitude
einer Auswahl von Tonfrequenzen aus einem oder mehreren Tonsensoren, die in der Schachtströmungsleitung
montiert sind, die Fortpflanzungsverzögerung der zugehörigen Tonmuster bei einer Auswahl
von Frequenzen aus zwei oder mehr Sensoren, die in stromaufwärtiger oder stromabwärtiger
Richtung an einer Schachtströmungsleitung montiert sind.
1. Procédé d'optimisation de la production d'un ensemble de puits, dont des courants
effluents sont mêlés et séparés dans un ensemble de séparation de fluides en courants
au moins partiellement séparés de pétrole brut, de gaz et/ou d'autres fluides, le
procédé comprenant les étapes consistant à :
a) effectuer un test sur chacun des puits, au cours duquel la production du puits
testé est modifiée et une ou plusieurs variables de production de puits individuels
est ou sont contrôlées ;
b) tirer de données (60) obtenues par les tests sur les puits un modèle d'évaluation
(61) pour chaque puits se référant à la variation du motif d'écoulement d'effluents
produits par le puits testé et des variables de production de puits contrôlées ;
c) amener l'ensemble de puits en production mixte normale d'huile et/ou de gaz ;
d) contrôler au cours de l'étape c) un motif d'écoulement de fluides dynamiques des
courants au moins partiellement séparés de pétrole brut, de gaz et/ou d'autres fluides
au moyen de débitmètres aménagés dans les courants au moins partiellement séparés
de pétrole brut, de gaz et/ou d'autres fluides en aval de l'ensemble de séparation
de fluides ;
e) contrôler au cours de l'étape c) une ou plusieurs variables de production de puits
se rapportant à des caractéristiques des courants d'écoulement multiphase produits
par les puits individuels ;
f) évaluer de manière répétée un motif d'écoulement de fluides dynamiques mixtes de
l'ensemble de puits sur la base des modèles d'évaluation (61) selon l'étape b) et
des variables de production contrôlées selon l'étape e) ;
g) effectuer un processus de réconciliation dynamique, dans lequel, au cours d'une
période de réconciliation choisie :
- on suppose que le motif d'écoulement de fluides dynamiques mixtes évalué selon l'étape
f) est une accumulation desdits modèles d'évaluation de production des puits individuels
qui sont multipliés par des coefficients pondéraux inconnus ;
- les coefficients pondéraux inconnus sont évalués en faisant varier de manière itérative
chaque coefficient pondéral jusqu'à ce que le motif d'écoulement de fluides dynamiques
mixtes évalué corresponde sensiblement au motif d'écoulement de fluides dynamiques
contrôlé ; et
- de meilleures évaluations de l'écoulement de production sont fournies pour la période
de réconciliation choisie et l'usage de facteurs de réconciliation de puits individuels
avec les modèles d'évaluation pour évaluer la production de chaque puits pendant une
période de réconciliation suivante ;
h) définir une cible d'optimisation opérationnelle constituée d'une cible à optimiser
concernant la production d'un ou plusieurs puits et/ou de l'ensemble des puits ;
i) ajuster la production d'effluents de l'ensemble de puits de sorte que la cible
d'optimisation soit approchée ; et
j) les étapes g et i sont répétées de temps à autre.
2. Procédé selon la revendication 1, comprenant par ailleurs les étapes consistant à
:
- identifier pour au moins un des puits de l'ensemble une ou plusieurs variables numériques
de production de puits manipulées qui peuvent être manipulées directement pour faire
varier la production du puits et, ensuite, tirer de données obtenues par les tests
des puits et/au cours d'une production mixte normale, et/ou du modèle d'évaluation,
un modèle de prédiction rapportant les variables manipulées des puits à la variation
de l'écoulement ou du motif d'écoulement et/ou d'autres caractéristiques des effluents
produits dans les puits, dans lequel les puits éventuels sans variables de production
de puits manipulées identifiées auront des modèles de prédiction qui sont des nombres
constants égaux à une production théorique évaluée des puits ;
- sommer les modèles de prédiction de tous les puits de l'ensemble de puits pour fournir
un modèle de prédiction de production mixte global ;
- ajuster la production des effluents de puits au moyen des variables manipulées des
puits, telles qu'elles sont guidées par les modèles de prédiction de puits individuels
et le modèle de prédiction de production mixte globale pour obtenir ladite cible d'optimisation.
3. Procédé selon la revendication 2, comprenant par ailleurs les étapes consistant à
:
- mesurer une ou plusieurs pressions d'interaction, telles qu'une pression dans un
ou plusieurs collecteurs de production dans des conduites d'écoulement de puits qui
sont raccordées aux têtes des puits de l'ensemble de puits, dans lesquels collecteurs
l'écoulement provenant d'une pluralité de conduites d'écoulement de puits est mélangé,
la variation de la pression d'interaction, lorsque les productions totales des puits
varient, indiquant et liant les interactions entre courants d'effluents des divers
puits ;
- obtenir des données dynamiques rapportant les variations de la ou des pressions
d'interaction aux variables mesurées des puits, à partir d'une production mixte normale
et/ou au cours de périodes de dérèglement de la production et/ou en effectuant une
série de tests d'interaction de puits, au cours desquels la pression d'interaction
est modifiée ;
- obtenir à partir de données dynamiques rapportant les variations de la ou des pressions
d'interaction aux variables mesurées, des modèles de prédiction de puits rapportant
les variations de variable(s) manipulée(s) des puits et la ou les pressions d'interaction
à la production des puits ;
- obtenir des données dynamiques rapportant les variations d'une ou plusieurs pressions
d'interaction à la production mixte totale, à partir de périodes de production mixte
normale et/ou au cours de périodes de dérèglement de production et/ou en effectuant
une série de tests au cours desquels la pression d'interaction est modifiée, et ensuite,
un ou plusieurs modèles d'interaction de collecteurs rapportant la variation d'une
ou plusieurs pressions d'interaction aux écoulements de production totale mixte s'écoulant
à travers les collecteurs ;
- combiner les modèles de prédiction des puits avec les modèles de pression d'interaction
pour obtenir un modèle de prédiction de production mixte global.
4. Procédé selon les revendications 2 et 3, dans lequel le procédé comprend par ailleurs
la répétition périodique du procédé d'optimisation en alignant les modèles de prédiction
avec les écoulements courants de sorte que les modèles de prédiction alignés reflètent
les écoulements courants tels qu'ils sont évalués par le procédé de réconciliation
dynamique.
5. Procédé selon l'une quelconque des revendications 1 à 4, dans lequel la cible d'optimisation
est une fonction de revenu rapportant la production de puits accumulée ou moyenne
combinée et/ou individuelle au revenu monétaire réel net ou brut ou incrémental, incluant
éventuellement des coûts de production associés.
6. Procédé selon la revendication 5, dans lequel la cible d'optimisation doit être réalisée
tout en répondant à des contraintes de production, qui sont constituées de limites
sur les variables manipulées, et/ou à des productions de puits individuels et/ou à
des quantités de production de puits, notamment des mesures, et/ou à celles de groupes
de puits et/ou sur une ou plusieurs pressions d'interaction et/ou sur la production
totale mixte de l'ensemble de puits.
7. Procédé selon la revendication 5 ou 6, comprenant par ailleurs l'étape de réalisation
d'une optimisation en utilisant l'un quelconque d'une pluralité d'algorithmes d'optimisation
numériques sur les variables manipulées sur la base de la cible d'optimisation opérationnelle,
éventuellement avec des contraintes, et des modèles de prédiction de production mixte
et/ou globale des puits pour donner un ensemble de variables optimisées manipulées
qui assure la cible d'optimisation opérationnelle.
8. Procédé selon l'une quelconque des revendications 1 à 7, dans lequel la production
d'effluents des puits est modifiée en ajustant l'ouverture d'une soupape d'étranglement
de production sur la tête des puits ou dans les conduites d'écoulement raccordées
aux puits, ou d'une soupape de commande d'écoulement dans un système d'injection de
gaz sustentateur des puits ou par d'autres moyens de stimulation ou de restriction
de la production des puits, notamment tout moyen réversible et contrôlée de fermeture
et d'ouverture d'un puits, un point de consigne d'une boucle de commande dans le puits
avec la soupape d'étranglement de production comme moyen d'actionnement, un point
de consigne d'une boucle de commande sur le taux d'injection ou la pression de gaz
sustentateur, une durée d'arrêt d'injection de gaz sustentateur des puits, une injection
de gaz sustentateur des puits sur la durée, un taux d'injection de gaz sustentateur
de puits, un point de consigne d'une boucle de commande sur la conduite d'injection
de fluide hydraulique dans les pompes d'injection de puits, une vitesse de la pompe
submersible électrique des puits (ESP), une vitesse de moteur de pompes à tiges de
puits, une durée d'arrêt de pompes à tiges de puits et/ou une ouverture de la soupape
de commande d'intervalle de forages de puits.
9. Procédé selon l'une quelconque des revendications 1 à 8, dans lequel la production
des effluents des puits est modifiée en ajustant une ou plusieurs pressions d'interaction
du système de production au moyen d'un ré-acheminement de la production de puits via
des conduites de collecteurs de production parallèles qui sont raccordées entre collecteurs
amont et aval et/ou en ajustant la pression de l'ensemble de séparation de fluides
et/ou en ajustant les soupapes pour l'acheminement des effluents de puits à un ou
plusieurs collecteurs qui mélangent la production ou qui acheminent la production
mixte à un ou plusieurs séparateurs de production, et/ou en ajustant la vitesse d'un
compresseur dans une conduite de sortie de l'ensemble de séparation de fluides.
10. Procédé selon les revendications 1 à 9, dans lequel les ajustements requis prédits
pour obtenir les cibles d'optimisation sont automatiquement transmis aux puits et
au système de production, éventuellement, après validation par un opérateur humain.
11. Procédé selon l'une quelconque des revendications 1 à 10, dans lequel un ou plusieurs
des modèles d'évaluation et/ou de prédiction peut ou peuvent éventuellement être générés
en partie ou en totalité à partir d'une caractérisation physique et/ou mécanique et/ou
chimique théorique et/ou empirique des puits et/ou du système de production.
12. Procédé selon l'une quelconque des revendications 1 à 11, dans lequel la cible d'optimisation
est ajustée en réaction et/ou en anticipation de variations des exigences de production
et/ou des coûts et/ou des revenus et/ou de l'infrastructure de production et/ou de
l'état des puits et/ou de l'état des installations de production ; le tout étant éventuellement
suivi par la réalisation du processus d'optimisation, dont les résultats sont mis
en oeuvre et/ou utilisés pour l'analyse et la planification et/ou enregistrés pour
une action future.
13. Procédé selon l'une quelconque des revendications 1 à 12, dans lequel la cible d'optimisation
est obtenue par des moyens facultatifs de fermeture temporaire de la production dans
un ou plusieurs puits de l'ensemble de puits, ou par l'initiation de la production
de puits de l'ensemble de puits qui n'étaient initialement pas en production.
14. Procédé selon les revendications 2 et 3, dans lequel un ou plusieurs des modèles d'évaluation
et/ou de prédiction peut ou peuvent éventuellement être comparés et/ou évalués vis-à-vis
de la caractérisation physique et/ou mécanique et/ou chimique théorique et/ou empirique
des puits et/ou du système de production ; aux fins de dépanner et/ou de diagnostiquer
et/ou d'améliorer les modèles et/ou pour l'analyse menant à des activités de gestion
de production et d'optimisation à plus long terme.
15. Procédé selon les revendications 1 à 13, dans lequel un ou plusieurs des puits de
l'ensemble de puits est ou sont exploités de manière périodique ou intermittente ou
sont exploités de temps à autre, et la production de quantités associées à optimiser
et éventuellement contraintes est évaluée, par exemple mises en moyenne, sur des périodes
de temps fixes plus grandes que la caractéristique de l'exploitation périodique ou
intermittente.
16. Procédé selon la revendication 15, dans lequel un ou plusieurs des puits de l'ensemble
de puits est ou sont exploités périodiquement ou de manière intermittente ou sont
exploités de temps à autre et la durée de leur exploitation, en proportion d'une période
de temps fixe, est prise comme variable manipulée pour le puits.
17. Procédé selon l'une quelconque des revendication 1 à 13, dans lequel le procédé est
appliqué en outre à une cible d'optimisation définie sur les puits de l'ensemble de
puits avec deux zones d'influx de sous-surfaces ou plus, auquel cas des « modèles
d'évaluation de production de zones » et des « modèles de prédiction de production
de zones » sont générés en plus des « modèles d'évaluation de production de puits
» et des « modèles de prédiction de production de puits ».
18. Procédé selon la revendication 1, dans lequel les variables de production de puits,
telles que la pression et/ou d'autres caractéristiques d'écoulement de fluides des
courants d'effluents de puits individuels comprennent une ou plusieurs des variables
suivantes : pression de tête des canalisations de puits, pression de canalisation
de puits, température de tête des canalisations de puits, température de canalisations
de puits, pressions différentielles aux bornes de la soupape d'étranglement de production
de puits, pressions différentielles aux bornes du producteur de pression différentielle
éventuel, notamment un venturi à gaz humide, sur la conduite d'écoulement de puits,
des débitmètres, convenant théoriquement uniquement à un écoulement en phase unique,
qui conviennent pour être utilisés afin de fournir une entrée aux modèles d'évaluation
de puits, même si le puits a un écoulement multiphase, un état ou une position d'ouverture
de la soupape d'étranglement de production, un état ou une position d'ouverture d'un
moyen quelconque de fermeture et d'ouverture réversible et contrôlée de puits, taux
d'injection de gaz sustentateur de puits, taux d'injection de fluide hydraulique de
pompe à jet de puits, pression de cuvelage de production de puits, vitesse de pompe
submersible électrique (ESP) de puits, pression d'admission de pompe ESP de puits,
pression de décharge de pompe de forage ESP de puits, pression différentielle venturi
de forages ESP de puits, consommation d'énergie ESP de puits, courant de phase motrice
ESP de puits, entrée d'énergie de moteur de pompe à tige de puits, vitesse de moteur
de pompe de tige de puits, déplacement de course de pompe à tige de puits, cellule
de charge de pompe à tige de puits, position de l'arbre de la boîte de vitesse du
mât de charge, vitesse différentielle de pompe à tige de puits/moteur/glissement de
la boîte de vitesse, pression de cuvelage de forages de puits, pression d'anneau de
forages de puits, température de cuvelage ou d'anneau de forages de puits ou leurs
diverses dérivations contrôlées par des capteurs de température distribués, ouverture
de soupape de commande à intervalles de forages de puits, amplitude d'une sélection
de fréquences sonores provenant d'un ou plusieurs capteurs sonores montés sur une
canalisation de puits, retard de propagation de motifs sonores corrélés pour une sélection
de fréquence provenant de deux ou plusieurs capteurs de son montés dans la direction
amont-aval sur une canalisation de puits.