[0001] Known is a level-crossing that has two or more in one line placed prefabricated,
reinforced concrete slabs (each up to 6 or 9 meter long) with two grooves for the
inclusion of the rails. The slabs are each individually with a crane hoisted in position
in the track, after which the rails are placed in the grooves and fixed and embedded
in casting. To set, each concrete slab is equipped with four adjustable feet, one
at each corner. Each foot includes a below the bottom of the concrete slab projecting
membrane body which during setting is filled with grout or concrete and stably supports
the concrete slab after curing.
[0002] In order to shorten the time of the decommissioning of the railways
NL1030958 (Voestalpine Railpro bv) proposed to produce a level-crossing as a one-piece prefabricated
concrete slab and prior to installing to fit it with the embedded rails. In practice
such product with a monolithic concrete slab proved technically and commercially unfeasible.
[0003] The object of the invention is a technically and commercially viable alternative
to shorten the time of decommissioning of the track.
[0004] Therefore a method is proposed for making a railway from prefabricated concrete slab,
with one or more of the following steps: in a factory two or more concrete slabs with
equal or different length and with equal width and thickness are each separately made
in a mold by placing a reinforcement and casting concrete so that each time a concrete
slab with one or more of the following features is obtained: a in the concrete of
the concrete slab embedded reinforcement of essentially parallel to the rails extending
pretensioned reinforcement elements, such as steel bars or wires, possibly in bundles;
at the top of the concrete slab two parallel grooves for containing the two rails;
near each corner an engagement point for a hoist; two, three, four or more lengthwise
and near the bottom of the concrete slab, preferably mutually at equal level and with
mutual spacing, extending and in its concrete embedded and at both longitudinal sides
debouching hollow channels; at one or both longitudinal sides at a place remote from
top surface and bottom surface, preferably at a distance above the hollow channels,
a surface profiling, preferably of such placement and / or size, that in-use two with
the ends together placed slabs the surface profiling merges, eg the surface profile
formed by one or more recesses and / or protrusions at a distance above and / or next
to each other, such as two or more spaced projections made in the direction of the
length of the rails to protrude over a distance of at least 2 or 5 or 10 cm and at
the other side with said protrusions corresponding recesses shaped corresponding to
the projections, and with a depth such that when two slabs are placed in one line
and the projections of the one concrete slab project to maximum depth in the recess
of the other concrete slab a joint between the concrete slabs with a width preferably
between about 10 or 20 millimeters and 30 millimeters or 50 is left, which protrusions
are preferably of concrete and are integrated in the slab; wherein further during
the process one or more of the following operations are performed: in the mold at
the ends of the concrete slab steel sections are placed widthwise approximately mid-thickness
of the concrete slab with their ends protruding from the side to provide engagement
points; then in succession at least two different grades of concrete are cast in layers
over one another in the mold to obtain a wear-resistant coating; after curing, the
slabs are removed from the molds and turned over and in placed line with each other,
with the possible projections at the end side of the one concrete slab in the recess
at the end side of the other but not to the maximum insertion depth, so a joint is
left between the concrete slabs preferably at least 5 millimeters and 15 millimeters
at the most wider (oversize) than the width of the joint in the finished product,
so that the combination of these concrete slabs has a length equal to the length of
the finished product, apart from the oversizing of the joint, while ensuring that
the grooves for the rails on the one hand and the hollow channels on the other hand
are mutually aligned and through the channels / tubes preferably flexible tension
elements are laced which extend beyond the longitudinal ends of the assembly of slabs
keeping them essentially stress free; shrink free mortar is cast from above into the
joints between the concrete slabs so that the joints, including the possible surface
profiling, is completely filled with mortar; while the mortar is still sufficient
liquid, the tension elements are activated to keep the slabs permanently pressed together
while mortar is pressed from the joint such that the projections at the ends are pushed
deeper into the recesses so that the joint width decreases with mainly the oversize
while the tension elements are brought to their final stress; one allows the mortar
to cure; at the top of the plate the hardened mortar in the joint is covered with
to the concrete and the mortar adhering, permanently flexible , initially form free,
curing material, such as cork rubber, for permanent waterproofing of the joints; in
each groove one places a unitary rail such that at both ends it projects far enough,
eg. at least about 1 or 2 m , eg. about 4 m to facilitate connection with the railway
to further facilitate the rails and be embedded, the assembly which rails are set
and embedded; the prefabricated assembly of in one line positioned slabs containing
the at final pre-load brought tension elements and in both grooves placed, set and
embedded rails is hoisted onto a truck and transported to its destination and hoisted
in the track.
[0005] Further, preferably one or more of the following apply: the hollow channel debouches
at the one side at a level above the bottom of the plate at least 1, 2 or 3 cm higher
than the level at which the hollow channels at the opposite side debouche, preferably
the side with the higher level of the hollow channels is intended to be turned away
from the other concrete slab in the assembly; the hollow channels follow a path through
the concrete slab that is horizontal, is continuously rising or consists of alternating
horizontal and continuously rising parts; the hollow channels are across the entire
length filled with shrinkfree cast mortar so the tension elements in the hollow channels
throughout their length are embedded in mortar; the surface profiling at the end side
consists only in the flat surface made recesses; the surface profiling includes one
or more grooves running parallel to each other; the in the grooves located rails placed
project hardly above the top of the plate wherein the top of the plate may be formed
by a coating that is subsequently affixed to the top of the plate to provide the riding
surface for cars and the like.
[0006] Preferably one or more of the following apply: provision for making adjustable feet
below the concrete slabs, as an example one at every corner of a concrete slab; sufficient
attention during manufacturing in the mold to ensure the required minimum galvanic
resistance between the rails; in the track, the product is placed on a temporary foundation
for, based on that foundation, through the pipes integral in the concrete slabs fill
the support feet with grout; the rails are connected to the rails on either side of
the level-crossing ; using a concrete slab or mold of a first length, eg. 6 meter
and a concrete slab or mold of a second length, eg. 9 meter; exclusive use of one
or more concrete slabs respectively mold of a first length and one or more concrete
slabs respectively mold of a second length; use of two or three slabs at the most
for making a prefabricated assembly.
[0007] Thus it has been possible for a level-crossing to prefabricate it in modular manner.
Key to this showed that the tension cables preferably obtain their final tension before
the filling of the joint cures or until the filling is in the early stage of curing
and is not set yet. Also shown essential is that preferably the joint is first completely
filled with sealing compound and then, before the sealing compound cures or sets,
the joint is squeezed permanently, for example at least 5 mm and possibly up to 15
mm so that part of the stuffing is pressed out of the joint It was learned that it
may suffice to only have tension cables at the bottom of product. To undergrout is
not necessary, allowing a significant time savings during installation.
[0008] By applying through the ducts running tension cables the level-crossing can be lifted
in its entirety at a limited number of engagement points and there is no risk that
after installation the level-crossing will have a concave or convex shape
[0009] A non-limiting example is as follows: Two concrete slabs with a length of 6 resp.
9 meter are made in the factory in a shed by placing in a 6 or. 9 meter long moldreinforcement
and casting concrete. During curing vibrators are used to compact the concrete. The
mostly flat bottom of the mold is equipped with profiles that provide the grooves
for the rails in the concrete surface. In the mold at least two grades of concrete
are cast in layers; first concrete is cast, which provides a highly wear resistant
surface. Also before or during the making of the concrete slab devices are placed
in the mold for the integration of the supporting legs and the connected grout pipes
in the concrete slab. Also in the mold steel profiles, eg. rail pieces, are placed
with a length greater than the width of the concrete slab. These profiles project
approximately half the thickness of the concrete slab with their ends aside from the
concrete slab and provide lifting points. And hollow tubes in the longitudinal direction
of the mold are placed nearby, for example 25 cm, below the fill level of the mold.
[0010] One ensures that at the one longitudinal side of the concrete slabs two integral,
identical protrusions, are made, which in side view of the concrete slab have a truncated
cone-shape, with the truncated top facing away from the concrete slab while in that
same view they are behind each other. In top view of the concrete slab each projection
extends 1/3 of the width of the slab, while keeping a distance to the side edge of
the concrete slab and keeping a larger distance to the other projection. On the other
side, each concrete slab has a recess which closely fits the projection, while maintaining
a joint between the sides facing each other. To maximum depth in the recess of the
one slab projecting protrusion of the other slab, the concrete slabs are supported
only through the projection respectively recess and the joint width is 20 mm.
[0011] After sufficient curing, the concrete slab is removed from the mold and reversed
so that the in the mold to the bottom facing side with the two grooves is turned upward.
[0012] The two slabs are placed against each other so that the grooves and the hollow tubes
are in line. In the hollow tubes tensioning cables are inserted whose ends extend
outside the concrete slabs. On the ends one screws threaded turnbuckles, without tensioning
the ropes. Along the bottom and at both sides of the seam between the concrete slabs
a formwork is made after which from the top the joint is filled with mortar as liquid
as water. Immediately afterwards one turns the clamping screws, which directly or
indirectly press against the sides of the concrete slabs while tensioning the tension
cables. Thus the concrete slabs are pressed to each other so that the joint width
decreases, mortar is squeezed from the joint and eventually the concrete slabs bear
mutually through the in the recesses projecting projections. Once the desired tension
is built up in the tension cables the clamping nuts are secured after which the mortar
in the joint is allowed to cure. After the mortar has hardened, the joint at the top
of the product is to any depth then scratched open and the vacant space is filled
with an adhesive, curing, flexible remaining kit or pasta so that the joint is permanently
watertight from above.
[0013] The rails are then placed in the grooves and then the remaining space in the groove
is filled with an initially formfree embedding and bonding material. The rails are
eight meters longer than the two slabs together and project at both sides for approximately
the same distance beyond the end of the two concrete slabs. After sufficient curing
of said embedding material the product is placed on a truck and transported to its
destination.
[0014] At the place of destination, the product is at its four corners and elsewhere along
its length by the sideways projecting rails attached to the lifting hook of a crane
and lifted to its final destination. Bearing on a temporary foundation, the product
is set, after which the supporting legs are filled with grout.
[0015] After sufficient curing of the grout, the temporary supports are removed and the
set concrete product bears on its feet.
[0016] In one alternative, the level-crossing is directly from the transport vehicle placed
on a levelled sand bed as its final destination, and use of a temporary foundation,
setting the product and filling of the supporting feet is superfluous
[0017] The attached drawing shows in Fig 1 a perspective view of a portion of a concrete
slab according to an implementation of the invention and fig. 2 shows a side view
in section along the line II-II in fig. 1 of a portion of two in line positioned slabs
of fig. 1 to create a level-crossing according to the invention.
[0018] Illustrated are the slabs 1, the grooves 2 for the rails 3, the lifting points 4,
the surface profiling 5 in the ends, the hollow tubes 6 and the joint 7.
[0019] In fig. 1 the rails 3 are missing and in both figures the wires in the tubes 6 are
missing. The tubes 6 debouch below the profiling 5 are aside each other and run from
the joint 7 inclined upward to the opposite side (this applies to both the plate 1
to the one or the other side of the joint 7) . The profile 5 consists of three horizontal
grooves running over each other. The rails 3 project outside the concrete slabs (Fig.
2).
[0020] Other versions belong to the invention. E.g. where the projections and possibly also
the matching notches on the end side of each plate are missing, or each side of each
plate contains both slots and matching protrusions, or each side of each slab only
contains notches. The slabs could also on their sides at two or more levels be fitted
with protrusions and/or matching recesses. It should be clear that the intention is
that protrusions on the end side of one plate fit into notches on the end side of
an adjacent plate.
[0021] The product can, apart from the rails, have a length created by the assembly of one,
two or more pieces of 6 or 9 meter, so that one creates a length of 6 meter plus or
a multiple of 3 meter, for example 18 or 27 meter.
1. Method for making a prefabricated railway level-crossing with a minimum length of
ten meters from two or more prefabricated concrete slabs, each with a minimum length
of five meters, with in a factory the two or more slabs of equal width and thickness
and together with a length essentially equal to the level-crossing are manufactured
by in a mold for each placing reinforcement and at least two parallel hollow tubes
(6) and pour concrete so that concrete slabs in each mold are manufactured upside
down which by curing in the mold obtain the following properties: near the bottom
in use run the hollow tubes (6) next to each other and at mutually equal level lengthwise
of the level-crossing and at the top two parallel grooves (2) run to therein house
the rails ( 3), while
after demolding the two or more cured concrete slabs (1) are in the plant arranged
in one line so that the grooves (2) and duct (6) are mutually aligned in maintaining
a joint (7) between the two connecting concrete slabs and in each tube (6) one or
more tension elements are arranged so that each tension element coverings essentially
the entire length of the level-crossing , and
the one or more joints (7) are filled with an initially formfree filler and the tension
elements are brought to the desired final tension and the rails are placed, set and
fixated in the grooves (2) ,
such that after the curing of the filler the slabs are permanently fixed to each other
and the thus prefabricated level-crossing with to the final tension brought pretension
elements and in the two grooves, placed, set and embedded rails is from the factory
transported to its final destination and the rails (3) thereof are connected to the
rails of the railway on either side of the level-crossing .
2. Method according to claim 1, whereby the tension elements are brought to the desired
final tension while the filler is not cured yet, so that while tensioning the tension
elements the slabs are moved toward each other in reducing the width of the joint,
preferably over at least about 5 millimeters, and a part of the filler is pressed
from the joint (7).
3. Method according to claim 1 or 2, ensuring that the concrete slabs during forming
in the mold obtain at one or both ends at a place remote from the top surface and
bottom surface, preferably at a distance above the hollow channels, a surface profiling
(5), preferably consisting exclusively of recesses made in the flat surface, such
as one or more grooves running parallel to each other, which profiling (5) is of such
placement and size that of two slabs placed in the in-use condition with the ends
together have the surface profiling merging, and which surface profiling is part of
the joint (7) and when with filler filling the joint is also completely filled with
filler.
4. Method according to one of the claims 1-3, ensuring for the concrete slabs that when
forming in the mold the ducts (6) at the one end debouch at a level above the bottom
of the plate at least 1, 2 or 3 cm higher than the level at which the tubes debouch
at the opposite end, preferably while following a path that is continuously rising
or alternately horizontally and constantly rising, and possibly wherein the end with
the higher level of the tubes is placed facing away from the other slab in the assembly
which shares the joint (7)
5. Method according to one of the claims 1-4, which during the from the slabs composing
of the level-crossing the ducts (6) over the full length are filled with initially
formfree material so that the tension elements in the tubes over their entire length
are embedded in hardened filler.
6. Prefabricated level-crossing with a minimum length of ten meters, which is composed
of two or more prefabricated concrete slabs, each with a minimum length of five meters
and of equal width and thickness, and together with a length essentially equal to
the level-crossing and at least two parallel in the length of the level-crossing concurrent
hollow tubes (6) near the in use bottom at mutual equal level and with at the top
two parallel grooves (2) containing embedded rails (3) protruding at both ends beyond
the assembly of concrete slabs, and in each duct (6) one or more tension elements
at final pretension so that each tension element extends substantially the complete
length of the level-crossing through all slabs, and with a joint between the slabs
(7) which is filled with an initially formfree filler with which the slabs are permanently
fixed together,
so that the thus prefabricated level-crossing with the at the final pretension brought
pretension elements and in both grooves located, set and embedded rails can be transported
from the factory to its final destination and its rails (3) can be connected to the
rails of the track at both sides of the level-crossing .
7. Railroad level-crossing according to claim 6, where the joint (7) on both sides is
bounded by a mutually overlapping surface profiling (5) in the sides of the concrete
slabs at a distance from the top surface and bottom surface and above the hollow tubes
(6) , preferably consisting exclusively of recesses made in the flat surface, such
as one or more grooves running parallel to each other, completely filled with filler.
8. Railroad level-crossing according to claim 6 or 7, the ducts (6) on the one side debouch
at a level above the bottom of the plate at least 1, 2 or 3 cm higher than the level
at which the tubes on the other side debouch, while following a path that is continuously
raising or alternately horizontally and continuously raising, and where the side with
the higher level of tubes placed facing away from the slab of the assembly sharing
the joint (7)
9. Railroad level-crossing according to claim 6, 7 or 8, where the ducts (6) over the
full length are filled with initially formfree filler material so that the tension
elements in the tubes are over their entire length embedded in hardened filler.