[0001] A concrete manufacturing plant and a method for manufacturing concrete
[0002] The present invention relates to a concrete manufacturing plant and a method for
manufacturing concrete.
[0003] Polish patent specification
183166 entitled "The concrete mix manufacturing plant" discloses a plant featuring an aggregate
tank to which the central part is permanently fixed in a manner constituting a whole
with the tank. Also, the concrete manufacturing plant comprises a conveyor which transports
aggregate to the aggregate mixing compartment, while the said aggregate mixing compartment
contains equipment for mixing with devices designed for dosing and weighing. The concrete
mix manufacturing plant features a connecting unit, connected to the connection located
at the bottom of the mixing compartment and to the connection located at the front
upper side of the said central part. The combined frame is connected to the upper
connection located at the top of mixing compartment and to the bottom connection at
the top back of the central part, thus ensuring the possibility of lifting the mixing
compartment from the transportation position to the mixing position and lowering it
to the transportation position, while leaving all cable connections unaffected.
[0004] Polish patent specification
38365 entitled "A method for manufacturing dry concretes" discloses a method for manufacturing
concretes, wherein cement is mixed with aggregate with no addition of water, and water
in a suitable quantity each time specified in the recipe is added on the construction
site, and wherein concrete of a desired class is packed into bags in a dry state,
marking every bag with the designation of concrete class and the recipe for a required
quantity of water according to the proper cement-water ratio.
[0005] Polish patent specification
103005 entitled "A method for manufacturing cementless concrete" discloses a method for
manufacturing cementless concrete from aggregate composition, micro-filler, binder
in the form of artificial resin and initiators of polymerization, and possibly with
addition of polymerization inhibitors and accelerants, by using a concrete mixer employing
the forced mixing method, wherein the manufacturing procedure starts from resin being
mixed with additives specified in the recipe. The essence of the invention is that
the micro-filler in quantity defined by the ratio required by the recipe is added
to the resin previously mixed with additives, and mixed until a fully uniform mixture
is obtained, next the aggregate composition is added and the resulting mixture is
still mixed in the same concrete mixer.
[0006] Also, Polish patent
149755 entitled "A method for manufacturing bituminous-mineral mixtures of the bitumen concrete
type" discloses a method for manufacturing bituminous-mineral mixtures of the bitumen
concrete type, wherein a filler in the form of lime dust is added to the heated mineral
aggregate containing 24-45 wt % of 6.3/12.8 chippings, 10-30 wt % of 4.0/6.3 chippings,
20-48 wt % of 0/4.0 fine granulated aggregate, and 14-23 wt % of sand, and then the
heated paving grade bitumen in the amount of 6.0-8.0 wt % is added to the prepared
mineral aggregate.
[0007] The essence of the invention is that a straight run bitumen or oxidised bitumen with
penetration index of 70 - 200 10" mm or petroleum vacuum distillation residue bottoms
are used, all previously treated with the modifying agent manufactured from the by-product
obtained during the coke-oven or town gas purification using a dry method, or products
of purification of such gases using a dry and wet method, i.e. gas pitch and colloidal
sulphur, brought to the air-dry state. The gas pitch is crushed to the grain size
below 0.3 mm with the fraction of grain size below 0.075 mm amounting to at least
90%.
[0008] The modification process is run at the temperature of 383-433 K for 1-6 hours, and
one mass part of the modifying agent is used for 1 to 5 mass parts of bitumen.
[0009] Mineral aggregate heated up to the temperature of 433-443 K can preferably be introduced
to the process, and modified bitumen heated up to the temperature of 398-433 K can
preferably be added to the mineral aggregate. The quantity of lime dust with the mineral
substance contained in modified bitumen preferably amounts to 9-15% of mineral aggregate.
[0010] The concrete manufacturing plant according to the present invention is equipped with
devices designed for mixing and with devices designed for dosing and weighing. Moreover,
the plant features the following detachable equipment, arranged as a sequence: hoist
winch container, silo container, mixer container, and the cement silo located at the
side of the plant.
[0011] The plant is also equipped with the ash silo located at the side of the plant.
[0012] The cement silo, mixer container, silo container and hoist winch container are all
equipped with lifting devices.
[0013] Also, the plant has a mobile mixer with two feeding chambers.
[0014] A method for manufacturing concrete according to the present invention consists in
the following procedure: the loading tank is filled using the loading machine and
aggregate is transported cyclically to each aggregate silo equipped with dosing flaps
until the given silo is full. Simultaneously, the cement balance is filled with cement,
water balance with water, water tank with water and plasticizer balance with plasticizers.
Subsequently, sand is fed, under control of a control system, from the aggregate silos
through the dosing flaps onto the weighing conveyor, and, after weighing a suitable
required amount of sand, it is transported by the weighing conveyor to one of the
buffering chambers previously filled with the weighed amount of cement. Simultaneously,
aggregates are dosed, under control of a control system and through the dosing flaps
of aggregate silos, onto the weighing conveyor, while, after weighing a suitable amount
of aggregate, it is transported to the second buffering chamber. Then the mobile mixer
comprising two feeding chambers is driven under the buffering chamber, while in the
first feeding chamber, after filling it with mixture of sand and aggregate from one
of the buffering chambers, the mixture is mixed for several, preferably from 1 to
15, seconds. Then plasticizers are added from the plasticizer balance and the content
is mixed again for several, preferably from 1 to 15, seconds. Finally water is added
from the water balance and the content is mixed once again for several, preferably
from 1 to 15, seconds. Simultaneously, aggregate is fed to the second chamber of the
mobile mixer, which next, while continuously stirring its content, is driven up to
the top of the plant, where the stationary mixer is filled with the mixed content
of the first chamber, i.e. with the mixture of sand, cement, plasticizers and water,
and the content of the second chamber, i.e. aggregate. Finally, all substances are
mixed together in the said stationary mixer and the finished product is discharged
from the mixer to the concrete delivery truck.
[0015] The concrete manufacturing plant according to the invention is easy to assemble and
disassemble, therefore can be quickly moved to another location. Also, preparation
of the site for the plant is not very much work-consuming. These advantageous features
of the plant make it particularly useful for manufacturing concrete for the needs
of highway engineering, where the construction site moves forward along with the progress
of road construction.
[0016] Using the method for manufacturing concrete according to the present invention, it
is possible to manufacture concrete and deliver it in required amounts much faster
than in solutions known hitherto and in close vicinity of the construction site.
[0017] An embodiment of the concrete manufacturing plant according to the invention is shown
on the figure, where Fig. 1 shows the side view of the concrete manufacturing plant,
Fig. 2 shows the top view of the concrete manufacturing plant, Fig. 3 shows the axonometric
view of the concrete manufacturing plant, Figure 4 shows the side view of the hoist
winch container, Fig. 5 shows the side view of the silo container, Fig. 6 shows the
side view of the mixer container, and Fig. 7 shows the side view of the cement silo.
[0018] The concrete manufacturing plant is designed in such a way that it features the following
detachable equipment, arranged as a sequence: hoist winch container 5, silo container
4, mixer container 3, and the cement silo 2 located at the side of the plant. The
plant is also equipped with ash silo 1 with ash conveyor 1.1 located at the side of
the plant.
[0019] The hoist winch container 5 is equipped with mobile aggregate silo loading tank 5.1,
upper sections 5.2 of aggregate silos, and lifting device 5.3.
[0020] The silo container 4 comprises buffer 5.1, aggregate silo 4.2 with dosing flaps,
weighing conveyor 4.3, plasticizer balance 4.4, cement balance 4.5, water balance
4.6, rope hoist 4.8, and lifting device 4.9.
[0021] The mixer container 3 features stationary mixer 3.1, mobile mixer 3.2, and lifting
device 3.3.
[0022] The cement silo 2 is equipped with worm conveyor 2.1 for cement transporting and
lifting device 2.2.
[0023] Due to own hydraulic or power lifting devices 2.2, 3.3, 4.9, 5.3 the unit can be
lifted above the semi-trailer after arriving at the site, and then the semitrailer
can be driven away from under particular units. Then the units are lowered onto the
ground which should be previously hardened on the whole area under the unit or just
in points where the unit rests on the ground.
[0024] At the first stage the hoist winch unit 5 is hydraulically lifted by means of the
lifting device 5.3, thus allowing the semitrailer to drive away from under the hoist
container 5. Then the hoist winch container 5 is lowered down to the ground, the front
part of the hoist container 5 is unlocked and lifted at a specified angle.
[0025] During the next stage the silo container 4 is driven to the site and, when unloaded
in the similar way as the previous container, placed directly in front of the lifted
hoist winch container 5. Then the front part of the silo container 4 is unlocked and
lifted by means of the lifting device 4.9. Upon completion of this operation, the
buffer 4.1 located on the silo container 4 is lowered down using the rope hoist 4.8
and placed in the working position. Next operations include lowering of the front
part of hoist winch container 5, hooking the rope hoist 4.8 to the hoist winch container
5, pulling the hoist container 5 up onto the silo container 4 and placing the latter
in the working position.
[0026] Next, the mixer container 3 is attached to the previously arranged units 5, 4. It
is placed in front of the lifted front part of the silo container 4 and fastened to
the previously arranged container units 5, 4. In the same way as it was done with
the other two units 5, 4, the front part of the mixer container 3 is lifted by means
of the lifting device 3.3. Then, a track for the mobile mixer 3.2 is placed on the
mixer container 3, and the stationary mixer 3.1 is placed in the working position.
[0027] Subsequently, the cement silo 2 is driven to the site and placed next to the previously
arranged container units 5, 4, 3. The cement silo is lifted using hand crank jacks.
The truck drives away from the cement silo 2 and the worm feeder unit 2.2 is drawn
from the container and connected to the cement balance 4.5 located on the silo container
4. Procedure of plant disassembly is the reversal of the assembly procedure described
above.
1. A concrete manufacturing plant equipped with devices designed for mixing and devices
designed for dosing and weighing, characterized in that it features the following detachable equipment, arranged as a sequence: hoist winch
container (5), silo container (4), mixer container (3), and the cement silo (2) located
at the side of the plant.
2. A concrete manufacturing plant according to claim 1, characterized in that it features the ash silo (1) located at the side of the plant.
3. A concrete manufacturing plant according to claim 1, characterized in that the cement silo (2) is equipped with the lifting device (2.2).
4. A concrete manufacturing plant according to claim 1, characterized in that the mixer container (3) is equipped with the lifting device (3.3).
5. A concrete manufacturing plant according to claim 1, characterized in that the silo container (4) is equipped with the lifting device (4.9).
6. A concrete manufacturing plant according to claim 1, characterized in that the hoist winch container (5) is equipped with the lifting device (5.3).
7. A concrete manufacturing plant according to claim 1, characterized in that it features the mobile mixer (3.2) comprising two feeding chambers.
8. A method for manufacturing concrete from cement, sand, water, plasticizers and aggregates,
characterized in that the loading tank (5.1) is filled using the loading machine and aggregate is transported
cyclically to each aggregate silo (4.2) equipped with dosing flaps until the given
silo is full, and, simultaneously, the cement balance (4.5) is filled with cement,
water balance (4.6) with water, water tank (4.7) with water and plasticizer balance
(4.4) with plasticizers, and, subsequently, sand is fed, under control of a control
system, from the aggregate silos (4.2) through the dosing flaps onto the weighing
conveyor (4.3), and, after weighing a suitable required amount of sand, it is transported
by the weighing conveyor (4.3) to one of the buffering chambers (4.1) previously filled
with the weighed amount of cement, while, simultaneously, aggregates are dosed, under
control of a control system and through the dosing flaps of aggregate silos (4.2),
onto the weighing conveyor (4.3), while, after weighing a suitable amount of aggregate,
it is transported to the second buffering chamber (4.1), and, subsequently, the mobile
mixer (3.2) featuring two feeding chambers is driven under the buffering chamber (4.1),
while in the first feeding chamber, after filling it with mixture of sand and aggregate
from one of the buffering chambers (4.1), the mixture is mixed for several, preferably
from 1 to 15, seconds, and, subsequently, plasticizers are added from the plasticizer
balance (4.4) and the content is mixed again for several, preferably from 1 to 15,
seconds, and finally water is added from the water balance (1.6) and the content is
mixed once again for several, preferably from 1 to 15, seconds, and, simultaneously,
aggregate is fed to the second chamber of the mobile mixer (3.2), which next, while
continuously stirring its content, is driven up to the top of the plant, where the
stationary mixer (3.1) is filled with the mixed content of the first chamber, i.e.
with the mixture of sand, cement, plasticizers and water, and the content of the second
chamber, i.e. aggregate, and, finally, all substances are mixed together in the said
stationary mixer and the finished product is discharged from the mixer (3.1) to the
concrete delivery truck.