Technical Field
[0001] The present invention relates to an air conditioner in which an outdoor unit and
a plurality of indoor units are connected through a branch controller, and a supercritical
fluid is used, to thereby establish a single refrigerating cycle.
Background Art
[0002] There has conventionally been known a heat recovery air conditioner for simultaneous
heating and cooling, which uses a supercritical fluid such as CO
2. In such an air conditioner, an outdoor unit and a branch kit are mostly connected
through three pipes of a high-pressure pipe, a low-pressure pipe, and a high-temperature
gas pipe. For the piping from the branch kit to the indoor unit, a two-pipe system
is employed.
[0003] However, the pressure of the supercritical fluid is extremely high in a critical
range, and hence the wall thickness of each connection pipe laid between the units
greatly increases as compared with a conventional case of a refrigerant typified by
chlorofluorocarbon. This fact may easily lead to expectations of increased cost of
materials and enormously increased cost of processes on site, such as pipe bending.
[0004] Therefore, it is conceived that the branch kit for each indoor unit is incorporated
into a single branch controller for the purpose of reduction in number of connection
pipes.
[0005] Meanwhile, the air conditioner using the supercritical fluid has such a characteristic
that the highest performance is obtained with a lower flow rate of the fluid by lowering
temperature of the fluid to be conveyed to an indoor unit in cooling operation and
raising temperature of the fluid to be conveyed to an indoor unit in heating operation.
Accordingly, the efficiency (in this case, coefficient of performance (COP) expressed
by taking performance of an air handling unit (unit: kW) as its numerator and power
consumption (unit: kW) as its denominator) is enhanced as well. Thus, temperature
of an inlet of the indoor unit, that is, temperature of an outlet of a heat-source
side heat exchanger is basically lowered at the time of cooling and raised at the
time of heating.
[0006] However, in the air conditioner that employs a two-pipe system to allow simultaneous
heating and cooling, there is such a trade-off as described below in a case where
the indoor unit in cooling operation and the indoor unit in heating operation simultaneously
exist (are mixed).
[0007] · It is necessary to lower the temperature of the outlet of the heat-source side
heat exchanger so as to supply a low-temperature fluid to the indoor unit in cooling
operation.
· It is necessary to raise the temperature of the outlet of the heat-source side heat
exchanger so as to supply a high-temperature fluid to the indoor unit in heating operation.
[0008] For example, in cooling-dominant operation of the conventional technology (the refrigerating
cycle is a refrigerating cycle of simultaneous heating and cooling operation in a
cooling cycle), both cooling and heating are inevitably controlled at a certain degree
of temperature (for example, approximately 40°C to 50°C under a pressure of 10 MPa
in the supercritical range of the Mollier chart) of the outlet of the heat-source
side heat exchanger. Consequently, there is an insufficiency of an enthalpy difference
to obtain high performance, and hence a flow rate of the fluid is increased (power
consumption of a compressor is increased) for compensation therefor, which results
in a lower COP.
[0009] Further, the efficiency of the air conditioner is conventionally evaluated based
on the above-mentioned coefficient called COP in terms of only the efficiency with
respect to 100% loads. In recent years, however, as to the loads in general offices,
for example, cooling loads have been generated even in a season that necessitates
heating, along with development of OA appliances and improvement in heat insulation
performance of buildings. As a result, the frequency of the simultaneous heating and
cooling operation is becoming higher throughout a year. Therefore, the efficiency
improvement tends more increasingly to be evaluated based not only on the COP with
respect to the 100% loads but also on a COP obtained at the time of the simultaneous
heating and cooling operation.
Disclosure of the Invention
Problem to be solved by the Invention
[0010] As described above, the conventional air conditioner has the problem of decline in
COP caused by the operation for satisfying both cooling and heating.
[0011] The present invention has been made in view of the points described above, and it
is therefore an object of the present invention to provide an air conditioner capable
of improving a COP in simultaneous heating and cooling operation.
Means for solving the Problem
[0012] An air conditioner according to the present invention is an air conditioning system
in which an outdoor unit and a plurality of indoor units are connected through a branch
controller, and a supercritical fluid is used, to thereby establish a single refrigerating
cycle, the outdoor unit and the branch controller being connected through two pipes
of a high-pressure pipe and a low-pressure pipe, the branch controller and each of
the plurality of indoor units being connected through two pipes of a high-pressure
pipe and a low-pressure pipe, in which the branch controller includes a double-pipe
heat exchanger for heat exchange between a medium-pressure two-phase refrigerant and
a low-pressure two-phase refrigerant, the medium-pressure two-phase refrigerant being
relatively high in temperature and flowing into the double-pipe heat exchanger after
branching a refrigerant flowing from the outdoor unit toward the plurality of indoor
units, and joining together a refrigerant decompressed by a first expansion valve
and a refrigerant flowing from the plurality of indoor units, the low-pressure two-phase
refrigerant being relatively low in temperature and flowing out of the double-pipe
heat exchanger toward the outdoor unit after branching a refrigerant flowing out of
the double-pipe heat exchanger toward the plurality of indoor units, and decompressing
a part of the branched refrigerant by a second expansion valve.
Effect of the Invention
[0013] According to the present invention, significant reduction in number of connection
pipes is realized between the outdoor unit and the branch controller, and between
the branch controller and each of the indoor units. At the same time, a COP in simultaneous
heating and cooling operation is improved because a large enthalpy difference is secured
on the side of the indoor units in cooling operation.
Brief Description of the Drawings
[0014] [FIG 1] A diagram of a refrigerant circuit in cooling-dominant operation of an air
conditioner according to a first embodiment of the present invention.
[FIG. 2] A Mollier chart to be used for description of the air conditioner according
to the first embodiment of the present invention.
[FIG. 3] A diagram of a refrigerant circuit in heating-dominant operation of the air
conditioner according to the first embodiment of the present invention.
[FIG. 4] A control flow chart for a first expansion valve 211 in cooling-dominant
operation of an air conditioner according to a second embodiment of the present invention.
[FIG. 5] A control flow chart for the first expansion valve 211 in full-heating operation
and heating-dominant operation of the air conditioner according to the second embodiment
of the present invention.
[FIG. 6] A control flow chart for a second expansion valve 212 in full-cooling operation
and cooling-dominant operation of an air conditioner according to a third embodiment
of the present invention.
[FIG. 7] A control flow chart for the second expansion valve 212 in heating-dominant
operation of the air conditioner according to the third embodiment of the present
invention.
[FIG. 8] A Mollier chart to be used for description of the air conditioner according
to the third embodiment of the present invention.
Best Mode for carrying out the Invention
First embodiment
[0015] FIG 1 is a diagram of a refrigerant circuit in cooling-dominant operation of an air
conditioner according to a first embodiment of the present invention. In the air conditioner
illustrated in FIG. 1, an outdoor unit 100 and a plurality of indoor units 301 to
303 are connected through a branch controller 200, and a single refrigerating cycle
is established by using a supercritical fluid. The outdoor unit 100 mainly includes
a compressor 110, a four-way valve 120, a heat-source side heat exchanger 130, and
check valves 141 to 147. The indoor units 301 to 303 respectively include use-side
(load-side) heat exchangers 311 to 313, and expansion valves 321 to 323 serving as
restriction devices. Further, the branch controller 200 mainly includes a first expansion
valve 211, a second expansion valve 212, check valves 231 to 233, channel switching
valves 221 to 223, and a double-pipe heat exchanger 240. It should be noted that the
double-pipe heat exchanger 240 may be a plate heat exchanger or a microchannel heat
exchanger.
[0016] Here, two pipes of a high-pressure pipe 400 and a low-pressure pipe 500 connect the
outdoor unit 100 and the branch controller 200, while two pipes of a high-pressure
pipe 700 and a low-pressure pipe 800 similarly connect the branch controller 200 and
each of the indoor units 301 to 303. Cooling-dominant operation mainly involving cooling
operation and partially involving heating operation is herein described. As to heating-dominant
operation, channels are switched by means of the four-way valve 120 and the check
valves 141 to 147.
[0017] It should be noted that, though FIG. 1 illustrates a high-pressure detection means
281, a medium-pressure detection means 282, a first temperature detection means 291,
and a second temperature detection means 292 that are included in the branch controller
200, those components are used in a second embodiment described later but not necessary
in the first embodiment.
[0018] First, with reference to FIG. 1, description is given of a flow of the refrigerant
circuit in the cooling-dominant operation. The description is given herein by taking
a case of CO
2 used as the supercritical fluid. A high-pressure and high-temperature fluid that
is compressed by the compressor 110 passes through the four-way valve 120 and is subjected
to heat exchange with the ambient air by the heat-source side heat exchanger 130.
The fluid is cooled down to temperature which does not reach the ambient air temperature,
for example, temperature at which the dryness of a Mollier chart (pressure p-enthalpy
h) illustrated in FIG. 2 becomes approximately 0.5 (point B of FIG. 2). Then, the
fluid of the outlet of the heat-source side heat exchanger 130 enters into a state
of high pressure and medium temperature. The fluid that flows out of the heat-source
side heat exchanger 130 then flows into the branch controller 200 through the high-pressure
pipe 400, and is branched into the indoor units 302 and 303 in cooling operation and
the indoor unit 301 in heating operation by the respective channel switching valves
221 to 223.
[0019] As to the refrigerant for the side of the indoor unit 301 in heating operation, the
high-pressure and medium-temperature fluid that flows into the load-side heat exchanger
311 from a branch port through the channel switching valve 223 is further subjected
to heat exchange with room temperature to become a high-pressure and medium-temperature
fluid, which has temperature substantially equal to the room temperature (point C
of FIG. 2). Then, the fluid is decompressed by the expansion valve 321 (point D of
FIG. 2). The refrigerant that flows out of the indoor unit 301 in heating operation
through the low-pressure pipe 800 passes through the check valve 231 of the branch
controller 200 in the state of medium pressure and medium temperature, and joins another
refrigerant at a point between the first expansion valve 211 and the double-pipe heat
exchanger 240.
[0020] Meanwhile, the refrigerant for the side of the indoor units 302 and 303 in cooling
operation flows from the branch port and is decompressed by the first expansion valve
211 down to medium pressure in the supercritical range, which is slightly lower than
high pressure (point E of FIG. 2). The refrigerant then flows into a medium-temperature
side of the double-pipe heat exchanger 240 in the state of medium pressure and medium
temperature. Further, the medium-pressure and medium-temperature fluid that is decompressed
by the expansion valve 321 of the indoor unit 301 in heating operation joins this
fluid at this point, and then flows into the medium-temperature side of the double-pipe
heat exchanger 240. In this case, a part of the fluid that flows out of the medium-temperature
side of the double-pipe heat exchanger 240 is further branched at a branch port, and
is decompressed by the second expansion valve 212 to become a low-pressure and low-temperature
fluid having two phases of gas and liquid (point I of FIG. 2). Then, the fluid flows
into a low-temperature side of the double-pipe heat exchanger 240.
[0021] The low-pressure and low-temperature fluid on the low-temperature side enters into
a state of low pressure and medium temperature, and a high dryness (point H of FIG.
2) after being subjected to heat exchange with the medium-pressure and medium-temperature
fluid on the medium-temperature side in the double-pipe heat exchanger 240. On the
other hand, the medium-pressure and medium-temperature fluid on the medium-temperature
side is further cooled to become a medium-pressure and medium-temperature fluid in
a state of a low enthalpy (point D of FIG. 2). The medium-pressure and medium-temperature
fluid that is further cooled (point D of FIG. 2) is then further decompressed by the
load-side expansion valves 322 and 323 to become a low-pressure and low-temperature
fluid having two phases of gas and liquid (point G of FIG. 2). Then, the fluid flows
into the load-side heat exchangers 312 and 313 for heat exchange with the room temperature,
to thereby enter into the state of low pressure and medium temperature, and a high
dryness (point H of FIG. 2). Finally, the low-pressure and medium-temperature fluid
that flows out of the low-temperature side of the double-pipe heat exchanger 240 and
the low-pressure and medium-temperature fluid that flows out of the load-side heat
exchangers 312 and 313 join each other, and return to the outdoor unit 100 side through
the low-pressure pipe 500.
[0022] With this configuration, significant reduction in number of connection pipes is realized
between the outdoor unit 100 and the branch controller 200, and between the branch
controller 200 and each of the indoor units 301 to 303. At the same time, a COP in
simultaneous heating and cooling operation is improved because the large enthalpy
difference is secured on the side of the indoor units 302 and 303 in cooling operation.
[0023] Next, FIG. 3 is a diagram of a refrigerant circuit in heating-dominant operation
of the air conditioner according to the first embodiment of the present invention.
The air conditioner illustrated in FIG. 3 has the same configuration as the configuration
of the first embodiment illustrated in FIG. 1.
[0024] With reference to FIG. 3, description is given of a flow of the refrigerant circuit
in the heating-dominant operation. A high-pressure and high-temperature fluid that
is compressed by the compressor 110 flows into the branch controller 200 through the
four-way valve 120, the check valve 145, and the high-pressure pipe 400. Then, the
high-pressure and high-temperature fluid is branched into the indoor unit 303 in cooling
operation and the indoor units 301 and 302 in heating operation at the respective
channel switching valves 221 to 223 of the branch controller 200. Further, the first
expansion valve 211 is fully closed to block the flow.
[0025] The refrigerant for the side of the indoor units 301 and 302 in heating operation
flows into the load-side heat exchangers 311 and 312 from the branch port of the branch
controller 200 through the channel switching valves 222 and 223 and the high-pressure
pipes 700, and the high-pressure and medium-temperature fluid is further subjected
to heat exchange with the room temperature to become a high-pressure and medium-temperature
fluid, which has temperature substantially equal to the room temperature (point C
of FIG. 2). Then, the fluid is decompressed by the expansion valves 321 and 322 to
become a medium-pressure and medium-temperature fluid (point D of FIG. 2). The refrigerant
that is decompressed by the expansion valves 321 and 322 then flows into the branch
controller 200 through the low-pressure pipes 800, and passes through the check valves
231 and 232 in the state of medium pressure and medium temperature to join another
refrigerant at the point between the first expansion valve 211 and the double-pipe
heat exchanger 240.
[0026] Meanwhile, the refrigerant for the side of the indoor unit 303 in cooling operation
flows into the load-side expansion valve 323 through the following path. The fluid
that flows into the medium-pressure and medium-temperature side of the double-pipe
heat exchanger 240 from the indoor units 301 and 302 in heating operation through
the low-pressure pipes 800 and the check valves 231 and 232 is further branched at
the branch port, and a part of the fluid is further decompressed by the second expansion
valve 212 to become a low-pressure and low-temperature fluid (point I of FIG. 2).
The fluid then flows into the low-temperature side of the double-pipe heat exchanger
240. Then, the fluid is subjected to heat exchange with the medium-pressure and medium-temperature
fluid on the medium-temperature side by the double-pipe heat exchanger 240. As a result,
the low-pressure and low-temperature fluid on the low-temperature side enters into
the state of low pressure and medium temperature, and a high dryness (point H of FIG.
2), while the medium-pressure and medium-temperature fluid on the medium-temperature
side is further cooled to become a medium-pressure and medium-temperature fluid in
a state of a low enthalpy (point D of FIG. 2).
[0027] The medium-pressure and medium-temperature fluid that is further cooled (point D
of FIG. 2) is then further decompressed by the load-side expansion valve 323 to become
a low-pressure and low-temperature fluid. Then, the fluid flows into the load-side
heat exchanger 313 for heat exchange with the room temperature, to thereby enter into
the state of low pressure and medium temperature, and a high dryness (point H of FIG.
2). Finally, the low-pressure and medium-temperature fluid that flows out of the low-temperature
side of the double-pipe heat exchanger 240 and the low-pressure and medium-temperature
fluid that flows out of the load-side heat exchanger 313 join each other, and return
to the outdoor unit 100 side through the low-pressure pipe 500, the heat-source side
heat exchanger 130, and the four-way valve 120.
[0028] As described above, according to the first embodiment, the single outdoor unit 100
and the single branch controller 200 are connected through two pipes, and the branch
controller 200 and each of the plurality of indoor units 301 to 303 are connected
through two pipes. Accordingly, significant reduction in number of connection pipes
is realized between the branch controller 200 and each of the indoor units 301 to
303, and at the same time, the COP in simultaneous heating and cooling operation is
improved because the large enthalpy difference is secured on the side of the indoor
units 302 and 303 in cooling operation. In addition, power-save operation is realized
also in the cooling-dominant operation mainly involving cooling and partially involving
heating operation.
Second embodiment
[0029] A configuration of the second embodiment is the same as the configurations of the
first embodiment illustrated in FIGS. 1 and 3. Further, in FIGS. 1 and 3, the high-pressure
detection means 281, the medium-pressure detection means 282, the first temperature
detection means 291, and the second temperature detection means 292 are provided to
the branch controller 200, which are unnecessary in the first embodiment.
[0030] The flow of the refrigerant of the second embodiment is the same as that of the first
embodiment. Hereinbelow, a control method for the first expansion valve 211 is described.
First, Table 1 shows overviews of control in each control mode (full cooling, cooling
dominant, full heating, or heating dominant).
[Table 1]
[0031] List of overviews of expansion valve control
| Control mode |
First expansion valve 211 |
Second expansion valve 212 |
| Full cooling |
Fully opened |
After initial degree of opening, control according to temperature difference ΔT |
| Cooling dominant |
After initial degree of opening, control according to pressure difference ΔP |
↑ |
| Full heating |
Fully closed |
Fully opened |
| Heating dominant |
After initial degree of opening, control according to pressure difference ΔP |
After fully closed for initial degree of opening, control according to ΔP |
[0032] In the case of the full-cooling operation (hereinafter, abbreviated as "full cooling")
in which all the indoor units 301 to 303 perform cooling operation, the first expansion
valve 211 is fully opened and the flow rate is controlled based on loads only by the
expansion valves 321 to 323 of the indoor units 301 to 303.
[0033] In FIG. 1, there are provided temperature sensors 311a, 312a, and 313a for detecting
temperatures on the upper side of the load-side heat exchangers 311 to 313, respectively.
There are also provided temperature sensors 311b, 312b, and 313b for detecting temperatures
and pressure sensors 311c, 312c, and 313c for detecting pressures between the load-side
heat exchangers 311 to 313 and the load-side expansion valves 321 to 323, respectively.
[0034] In the case of the full-cooling operation, temperature differences between the temperature
sensors 311a, 312a, and 313a, and the temperature sensors 311b, 312b, and 313b are
calculated, respectively, and calculation results thereof are each set as a degree
of superheat. The degree of opening of each of the load-side expansion valves 321,
322, and 323 is adjusted so that the degree of superheat becomes a predetermined value,
for example, approximately 2°C.
[0035] In the case of the "cooling-dominant" operation in which the simultaneous heating
and cooling operation is performed in the state of the cooling cycle, pressure difference
control, which is described later, is performed by using a pressure difference between
the high-pressure detection means 281 and the medium-pressure detection means 282.
Also in the cooling-dominant operation, when the load-side heat exchangers operate
as evaporators, the above-mentioned degree of superheat is detected and the degree
of opening of each of the load-side expansion valves is adjusted so that the degree
of superheat becomes a predetermined value.
[0036] Further, in the case of the full-heating operation (hereinafter, abbreviated as "full
heating") in which all the indoor units 301 to 303 perform heating operation, the
first expansion valve 211 is fully closed basically and the flow rate is controlled
based on loads only by the expansion valves 321 to 323 of the indoor units. Further,
the pressure difference control, which is described later, is performed by using the
pressure difference between the high-pressure detection means 281 and the medium-pressure
detection means 282.
[0037] The temperature sensors 311b, 312b, and 313b for detecting temperatures and the pressure
sensors 311c, 312c, and 313c for detecting pressures are provided between the load-side
heat exchangers 311 to 313 and the load-side expansion valves 321 to 323, respectively.
[0038] In the case of the full-heating operation, pressure values obtained through detection
by the pressure sensors 311c, 312c, and 313c are used for calculating a saturation
temperature T
sc. The calculated saturation temperature is set as a condensation temperature T
c. A relational expression between the saturation temperature T
sc and a pressure P as in Expression (1) needs to be prepared in advance:

[0039] It should be noted that, as illustrated in FIG. 8 which is referenced later, in a
case where carbon dioxide is used as a refrigerant, the high-pressure side operates
above the critical point, and hence there is no phase change. In other words, there
exists no saturation temperature T
sc. In view of the above, an experiment for the refrigerating cycle, or the like is
conducted to set a virtual saturation temperature based on balanced pressure and intake
air temperature. For example, it is assumed that, when the pressure is 100 kgf/cm
2, the saturation temperature is 45°C. Expression (1) according to this embodiment
is an arithmetic expression by which the virtual saturation temperature T
sc is calculated.
[0040] A virtual condensation temperature T
c is calculated by using Expression (1) based on the pressure values obtained by the
pressure sensors 311c, 312c, and 313c. A difference between a temperature T
L obtained by each of the temperature sensors 311b, 312b, and 313b and the virtual
condensation temperature T
c (Tc-T
L) is obtained, and this value is set as a degree of subcooling SC. The degree of opening
of each of the load-side expansion valves 321, 322, and 323 is adjusted so that the
degree of subcooling SC becomes a predetermined value, for example, approximately
5°C.
[0041] Further, similarly to the case of the full heating, in the case of the "heating-dominant"
operation in which the simultaneous heating and cooling operation is performed in
the state of the heating cycle, the first expansion valve 211 is fully closed basically,
and the pressure difference control, which is described later, is performed by using
the pressure difference between the high-pressure detection means 281 and the medium-pressure
detection means 282.
[0042] Next, with reference to control flow charts illustrated in FIGS. 4 and 5, the control
method is described in detail. First, in the "full-cooling" operation, the first expansion
valve 211 is fully opened constantly and the flow rate is controlled based on loads
only by the expansion valves 321 to 323 of the indoor units.
[0043] In the "cooling-dominant" operation, as illustrated in FIG. 4, start up of the compressor
110, or the like triggers the first expansion valve 211 to start with an initial degree
of opening L0 that is set in advance (Step S41). When a predetermined period U has
elapsed from the start (Step S42), the degree of opening of the first expansion valve
211 is controlled according to comparison between the pressure difference ΔP obtained
based on detection values of the high-pressure detection means 281 and the medium-pressure
detection means 282, and set values P1 and P2 (P1<P2) that are set in advance.
[0044] For example, in a case where ΔP>P2, the degree of opening of the first expansion
valve 211 is increased by a predetermined degree of opening that is set in advance
(Steps S43→S44). In a case where P1≤ΔP≤P2, the degree of opening of the first expansion
valve 211 is maintained at the current degree of opening (Steps S43→S45→S46). In a
case where ΔP<P1, the degree of opening of the first expansion valve 211 is decreased
by a predetermined degree of opening that is set in advance (Steps S43→S45→S47→S48).
[0045] Through the control described above, it is possible to secure the pressure difference
necessary to cause the refrigerant to flow at a flow rate according to the load on
the side of the indoor unit in heating operation, and to decrease the pressure into
low pressure due to an excess pressure difference, which results in suppression of
decline in COP.
[0046] Further, in the "full-heating" operation, the first expansion valve 211 is fully
closed constantly and the flow rate is controlled based on loads only by the expansion
valves 321 to 323 of the indoor units.
[0047] In the "heating-dominant" operation, as illustrated in FIG. 5, start up of the compressor
110, or the like triggers the first expansion valve 211 to start with the fully closed
state (Step S51). When the predetermined period U has elapsed from the start (Step
S52), the degree of opening of the first expansion valve 211 is controlled according
to comparison between the pressure difference ΔP obtained based on detection values
of the high-pressure detection means 281 and the medium-pressure detection means 282,
and the set values P1 and P2 (P1<P2) that are set in advance.
[0048] For example, in a case where ΔP>P2, the degree of opening of the first expansion
valve 211 is increased by a predetermined degree of opening that is set in advance
(Steps S53→S54). In a case where P1≤ΔP≤P2, the degree of opening of the first expansion
valve 211 is maintained at the current degree of opening (Steps S53→S55→S56). In a
case where ΔP<P1, the degree of opening of the first expansion valve 211 is decreased
by a predetermined degree of opening that is set in advance (Steps S53→S55→S57→S58).
[0049] Through the control described above, it is possible to secure the pressure difference
necessary to cause the refrigerant to flow at a flow rate according to the load on
the side of the indoor unit in heating operation, and to secure the pressure difference
necessary to cause the refrigerant to flow at a flow rate according to the load on
the side of the indoor unit in cooling operation by approximating the pressure of
the inlet of the indoor unit in cooling operation to the low pressure due to an excess
pressure difference, which results in suppression of decline in COP. In addition,
the change in pressure may be suppressed, and hence the refrigerant may stably be
conveyed to the indoor unit, to thereby realize power-save operation and comfort.
Third embodiment
[0050] As in the second embodiment described above, a configuration of a third embodiment
is the same as the configurations of the first embodiment illustrated in FIGS. 1 and
3. Further, in FIGS. 1 and 3, the high-pressure detection means 281, the medium-pressure
detection means 282, the first temperature detection means 291, and the second temperature
detection means 292 are provided to the branch controller 200, which are unnecessary
in the first embodiment.
[0051] The flow of the refrigerant of the third embodiment is the same as that of the first
embodiment. Hereinbelow, a control method for the second expansion valve 212 is described.
First, Table 1 shows overviews of control in each control mode (full cooling, cooling
dominant, full heating, or heating dominant).
[0052] In the case of the "full-cooling" operation in which all the indoor units 301 to
303 perform cooling operation, for the second expansion valve 212, temperature difference
(superheat) control, which is described later, is performed by using the first temperature
detection means 291 and the second temperature detection means 292, and the flow rate
is controlled based on loads by the expansion valves 321 to 323 on the side of the
indoor units 301 to 303. The same control as in the case of the "full cooling" applies
to the case of the "cooling-dominant" operation in which the simultaneous heating
and cooling operation is performed in the state of the cooling cycle.
[0053] Further, in the case of the "full-heating" operation in which all the indoor units
301 to 303 perform heating operation, the second expansion valve 212 is fully opened
and the flow rate is controlled based on loads by the expansion valves 321 to 323
of the indoor units. Then, the refrigerant subjected to heat exchange with the load
side flows into the low-pressure line of the outdoor unit through the second expansion
valve 212.
[0054] In the case of the "heating-dominant" operation in which the simultaneous heating
and cooling operation is performed in the state of the heating cycle, the second expansion
valve 212 is fully closed basically, and the pressure difference control, which is
described later, is performed by using the pressure difference between the high-pressure
detection means 281 and the medium-pressure detection means 282.
[0055] Next, with reference to control flow charts illustrated in FIGS. 6 and 7, the control
method is described in detail. First, in the "full-cooling" operation, as illustrated
in FIG. 6, start up of the compressor 110, or the like triggers the second expansion
valve 212 to start with the initial degree of opening L0 that is set in advance (Step
S61). When the predetermined period U has elapsed from the start (Step S62), a temperature
difference ΔT (degree of superheat) is calculated based on detection values of the
first temperature detection means 291 and the second temperature detection means 292,
and the degree of opening of the second expansion valve 212 is controlled according
to comparison between the temperature difference ΔT and values T1 and T2 (T1<T2) that
are set in advance.
[0056] For example, in a case where ΔT>T2, the degree of opening of the second expansion
valve 212 is increased by a predetermined degree of opening that is set in advance
(Steps S63→S64). In a case where T1≤ΔT≤T2, the degree of opening of the second expansion
valve 212 is maintained at the current degree of opening (Steps S63→S65→S66). In a
case where ΔT<T1, the degree of opening of the second expansion valve 212 is decreased
by a predetermined degree of opening that is set in advance (Steps S63→S65→S67→S68).
[0057] Through the control described above, it is possible to secure the enthalpy difference
necessary to lower the temperature of the refrigerant in the inlet on the side of
the indoor unit in cooling operation, to thereby obtain satisfactory performance,
which results in suppression of decline in COP. In addition, also in the cooling-dominant
operation mainly involving cooling and partially involving heating operation, a lower-temperature
refrigerant may be conveyed to the indoor unit in cooling operation, and power-save
operation can accordingly be realized.
[0058] Further, in the "full-heating" operation, the second expansion valve 212 is fully
opened constantly and the flow rate is controlled based on loads by the expansion
valves 321 to 323 of the indoor units. Then, the refrigerant subjected to heat exchange
with the load side flows into the low-pressure line of the outdoor unit through the
second expansion valve 212.
[0059] In the "heating-dominant" operation, as illustrated in FIG. 7, start up of the compressor
110, or the like triggers the second expansion valve 212 to start with the fully closed
state (Step S71). When the predetermined period U has elapsed from the start (Step
S72), the degree of opening of the second expansion valve 212 is controlled according
to comparison between the pressure difference ΔP obtained based on detection values
of the high-pressure detection means 281 and the medium-pressure detection means 282,
and the set values P1 and P2 (P1<P2) that are set in advance.
[0060] For example, in a case where ΔP>P2, the degree of opening of the second expansion
valve 212 is decreased by a predetermined degree of opening that is set in advance
(Steps S73→S74). In a case where P1≤ΔP≤P2, the degree of opening of the second expansion
valve 212 is maintained at the current degree of opening (Steps S73→S75→S76). In a
case where ΔP<P1, the degree of opening of the second expansion valve 212 is increased
by a predetermined degree of opening that is set in advance (Steps S73→S75→S77→S78).
[0061] Through the control described above, it is possible to secure the pressure difference
necessary to cause the refrigerant to flow at a flow rate according to the load on
the side of the indoor unit in heating operation, and to approximate the pressure
of the inlet of the indoor unit in cooling operation to the low pressure due to an
excess pressure difference (approximation of medium pressure to low pressure), which
results in suppression of decline in COP caused by the fact that the pressure difference
necessary to cause the refrigerant to flow at a flow rate according to the load on
the side of the indoor unit in cooling operation cannot be secured.
[0062] At the time of the cooling-dominant operation, the heat-source side heat exchanger
130 operates as a condenser (radiator). In the cooling-dominant operation, the cooling
load exceeds the heating load, and hence a part of the heat radiation capability needs
to be supplemented by the heat-source side heat exchanger 130. Therefore, the heat
exchanger capacity needs to be increased and decreased by adjusting the fan speed
and dividing the heat-source side heat exchanger 130.
[0063] According to the present invention, description is given of a method of adjusting
the heat radiation capability without dividing the heat-source side heat exchanger
130. In the embodiments of the present invention, carbon dioxide is used as the refrigerant.
The high-pressure side operates above the critical point of this refrigerant as illustrated
in FIGS. 2 and 8. With this characteristic, the heat radiation capacity can be adjusted
with ease.
[0064] As illustrated in FIG. 3, there are provided a pressure sensor 900 and a temperature
sensor 901 between the heat-source side heat exchanger 130 and the check valve 141,
and a temperature sensor 902 to the inlet of the heat-source side heat exchanger 130.
In the supercritical state, when the temperature and the pressure are determined,
the enthalpy is uniquely determined.
[0065] In FIG 8, "a" represents an enthalpy H
1 of the inlet of the heat-source side heat exchanger 130; "b", an enthalpy H
2 of the outlet of the heat-source side heat exchanger 130 (inlet of the load-side
heat exchanger in heating operation); and "c", an enthalpy H
3 of the inlet of the heat-source side heat exchanger 130.
[0066] The load on the heating side may be grasped from the number of indoor units in heating
operation and the capacity of each of the connected indoor units. This heating load
is denoted by Q
c. Further, a refrigerant flow rate G
r may be obtained based on discharge pressure and suction pressure of the compressor.
An enthalpy difference ΔH necessary to cover the heating load may be obtained from
Expression (2):

[0067] Further; the enthalpy H
3 of the outlet of the load-side heat exchanger (heating) may be determined by using
the pressure sensor 311c. and the temperature sensor 311b provided to the outlet of
the load-side heat exchanger. Expression (2) is converted into Expression (3):

[0068] In other words, the enthalpy H
2 of the outlet of the heat-source side heat exchanger is determined. The enthalpy
of the outlet of the heat-source side heat exchanger may be obtained by using the
pressure sensor 900 and the temperature sensor 901. The enthalpy obtained from Expression
(3) is set as a target enthalpy H
2m.
[0069] Further, the enthalpy measured by the pressure sensor 900 and the temperature sensor
901 is denoted by H
2s. A difference between the target enthalpy H
2m and the measured enthalpy H
2s (H
2m-H
2s) is calculated, and H
2m-H
2s=ΔH
s holds.
[0070] Then, a control means increases and decreases the rotation of the heat-source side
fan (blower) so that -epsH
2<ΔH
s<epsH
2 (it should be noted that -epsH
2 and epsH
2 denote a lower limit value and an upper limit value in an error range, respectively)
becomes a predetermined value. Control is performed so that, in a case where -epsH
2>ΔH
s, the number of rotations of the fan is increased, while in a case where ΔH
s>epsH
2, the number of rotations of the fan is decreased.
[0071] It should be noted that, in order to obtain an enthalpy H, a physical property expression
as in Expression (4) needs to be prepared in advance:

where P denotes pressure and T denotes temperature.