[0001] Liquid natural gas cooled air separation unit for integrated gasification combined
cycle power plants
FIELD OF INVENTION
[0002] The invention relates to a gas island for an integrated gasification combined cycle
power plant and a method for speeding-up a start-up process for cryogenic separation
of an air feed in an air separation unit.
BACKGROUND OF THE INVENTION
[0003] Integrated gasification combined cycle (IGCC) technology is popular in areas where
natural gas supply is limited, coal is abundant and emission controls are strict.
This is the case, for example, in coastal China.
[0004] Gas turbines used in IGCC power plants typically require a secondary fuel for start-up,
which is often natural gas. When oxygen, nitrogen and synthetic gas (syngas) are ready,
the changeover to syngas combustion is made.
[0005] Where natural gas is not available liquid natural gas (LNG) is delivered to IGCC-power
plants and stored in liquid (cryogenic) form on site. Besides its use for starting
up air-integrated IGCC plants it also is used as secondary fuel in case there is a
problem in the gas island.
[0006] In order to be burnt in the gas turbine, LNG has to be vaporized again. The LNG is
typically warmed and vaporized using large ambient air vaporizers. The liquefaction
of natural gas is energy-intensive and this "cold energy" (the energy invested to
liquefy natural gas) is wasted when the LNG is vaporised using ambient air.
[0007] At the same time, as one of the first stages of the IGCC start-up process, the air
separation unit (ASU), that supplies pure oxygen and nitrogen to the gasifier, must
be cooled to cryogenic temperatures during start-up and kept cool during short outages
(when the secondary fuel is likely to be in use). The ASU is usually cooled through
refrigeration, i.e. compression, cooling, expansion. To cool, product gases are used
(which during start-up are not so cold). This cooling is very energy intensive and
the cooling process for start up from warm can take 36-72 hours. Sometimes the cool-down
period is shortened by use of stored liquid nitrogen (LIN), which is pumped through
the ASU heat exchanger to cool the process fluids. The LIN may have been produced
onsite, or it may have been delivered.
SUMMARY OF THE INVENTION
[0008] An object of the invention is to provide a gas island for an integrated gasification
combined cycle power plant for accelerated start-up processes. Another object of the
invention is to provide a method for speeding-up a start-up process for cryogenic
separation of an air feed for an air separation unit for integrated gasification combined
cycle power plants.
[0009] This object is achieved by the claims. The dependent claims describe advantageous
developments and modifications of the invention.
[0010] An inventive gas island for an integrated gasification combined cycle power plant
comprises an air separation unit, an air duct emptying into the air separation unit
and an LNG duct, wherein a heat exchanger system is arranged on a primary side in
the air duct and on a secondary side in the LNG duct.
[0011] Thereby both, the energy invested to liquefy natural gas is recovered and the start-up
process for the air separation unit is accelerated.
[0012] According to one aspect of the invention the heat exchanger system is a single heat
exchanger. This measure is very cost-efficient.
[0013] According to another aspect of the invention the heat exchanger system comprises
at least a first and a second heat exchanger, wherein a primary side of the first
heat exchanger is arranged in the air duct, a secondary side of the second heat exchanger
is arranged in the LNG duct and the secondary side of the first heat exchanger and
the primary side of the second heat exchanger are interconnected. This solution minimizes
the impact of a leak in the heat exchanger where the LNG flows through.
[0014] It is advantageous when the secondary side of the first heat exchanger and the primary
side of the second heat exchanger are arranged in a closed circuit. This allows operation
of the heat exchanger system even when the heat transfer medium, for example nitrogen
from the ASU, is not available yet.
[0015] Advantageously a pump is arranged in the circuit.
[0016] It is even more advantageous when instead of a simple pump a compressor and an expander
forming a compander are arranged in the circuit to increase the refrigeration efficiency.
[0017] According to an aspect of the invention a multi-port-valve is arranged in a waste
duct interconnecting a distillation column system of the air separation unit and the
secondary side of the first heat exchanger, and where for a switching status of the
multi-port-valve a circuit is interposed, in which the primary side of the second
heat exchanger is arranged, thereby interconnecting the secondary side of the first
heat exchanger and the primary side of the second heat exchanger. This embodiment
makes use of a cooled waste stream as a refrigerant. As an alternative a gaseous nitrogen
(GAN) product stream could be used.
[0018] According to anther aspect of the invention the air duct bifurcates into a branch
duct and a main duct, wherein the heat exchanger system and a valve are arranged in
the branch duct. This solution minimizes the interference with the ASU and is very
advantageous in case the standard ASU design shall not be altered.
[0019] According to one aspect of the invention a pump is arranged in the LNG duct in the
direction of flow of LNG upstream of the heat exchanger system. This solution requires
only a simple pump and improves heat exchange efficiency.
[0020] According to another aspect of the invention a compressor is arranged in the LNG
duct in the direction of flow of LNG downstream of the heat exchanger system. Since
the hazard created by hydrocarbons in an ASU or in the inerting nitrogen stream is
significant, this low pressure heat exchanger solution increases heat exchanger safety
in case of a leak. A failure in the wall separating the two media LNG on the one side
and air (or nitrogen) on the other side will lead to a leak of air (or nitrogen) to
the natural gas, having no more serious effect than diluting the fuel. Furthermore,
this solution has no special requirements for the heat exchanger or evaporation cooler
due to LNG pressure.
[0021] Advantageously at least one heat exchanger of the heat exchanger system is an evaporation
cooler.
[0022] Advantageously the gas island is part of an integrated gasification combined cycle
power plant where the LNG duct is connected to a combustion chamber of a gas turbine
and an oxygen duct connects the air separation unit to a gasifier. An inventive method
to speed-up a start-up process for cryogenic separation of an air feed for an air
separation unit for integrated gasification combined cycle power plants comprises
cooling the ASU using LNG evaporation.
[0023] Advantageously the method comprises:
- compressing air with an air compressor connected to a column of an air separation
unit via an air duct,
- cooling air in an expansion stage arranged in the air duct,
- cycling the cooled air via the air duct to the column,
- ramping up the air separation unit to part load,
- supplying LNG to a heat exchanger system arranged in the air duct,
- supplying heated LNG as gas to a combustion chamber of a gas turbine in the combined
cycle power plant,
- firing the gas turbine and beginning operation on natural gas,
- supplying compressed air from a compressor of the gas turbine to the air separation
unit,
- ramping up the air separation unit,
- producing gaseous nitrogen (GAN) and gaseous oxygen (GOX) streams with the air separation
unit.
[0024] In accordance with an aspect of the invention LNG is no longer supplied to ASU for
enhanced cooling, as soon as a gasifier starts up and sufficient syngas is available
and the gas turbine is changed over to syngas operation.
[0025] With this invention energy consumption is reduced by significantly shortening the
cool-down time whilst avoiding storage or delivery of other cryogenics. The cold energy
of the LNG is no longer wasted.
BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The invention will now be further described with reference to the accompanying drawings
in which:
- Figure 1
- is a schematic flow diagram of an integrated combined cycle power plant comprising
a gas island and a power island,
- Figure 2
- represents a basic concept of the inventive gas island with a liquid gas cooled air
separation unit,
- Figure 3
- represents a simple inclined LNG/Air heat exchanger,
- Figure 4
- represents an embodiment with nitrogen refrigerant for enhanced safety,
- Figure 5
- shows a refrigeration cycle with a compander,
- Figure 6
- shows an embodiment with reduced impact on the ASU design, where a slipstream flow
of air is cooled,
- Figure 7
- shows a waste cycle used for additional cooling,
- Figure 8
- represents one aspect of the invention where LNG is used as a main air compressor
aftercooler in a part-integrated air stream.
[0027] In the drawings like references identify like or equivalent parts.
DETAILED DESCRIPTION OF THE INVENTION
[0028] Figure 1 is a schematic flow diagram of an integrated gasification combined cycle
power plant 1 consisting of a gas island 2 and a power island 3. Integrated gasification
combined cycle (IGCC) is a technology that turns coal into gas - synthetic gas (syngas).
For power generation an a combined cycle power plant (CCPP) impurities are removed
from the coal gas before it is combusted.
[0029] In the gas island 2 carbonaceous materials 4, such as coal, petroleum, biofuel, or
biomass is prepared in a fuel preparation 5 and conducted to a gasifier 6 where it
is converted in a gasification process into a gas mixture called synthesis gas or
syngas 7 by reacting the raw material at high temperatures with a controlled amount
of oxygen 8 and/or steam. The resulting gas mixture comprises carbon monoxide and
hydrogen.
[0030] The oxygen 8 is provided by an air separation unit 9, where air 10 is separated into
its primary elements typically nitrogen, oxygen and argon. There are various technologies
that are used for the separation process; the most common is via cryogenic distillation
consisting of the following three stages compression, purification and distillation.
During the compression stage atmospheric air is pre-filtered, compressed and then
subsequently cooled to remove large size particles and moisture. In the purification
stage the process air is passed through a molecular sieve, which removes any remaining
water vapour, carbon dioxide and hydrocarbons in alternating absorption units. In
the distillation stage process air is passed through a heat exchanger and cooled.
The process air enters into a distillation column were it is separated into pure nitrogen,
pure oxygen and residual gas. The nitrogen 11 can either be used for flushing of the
fuel system or for mixing with the synthesis gas. The oxygen 8 is delivered to the
gasifier 6.
[0031] A means of mitigating the contribution of fossil fuel emissions to global warming
is carbon capture and storage (CCS) based on capturing carbon dioxide (CO
2) and storing it away from atmosphere. For this purpose, after the gasification process
the obtained raw gas containing large amounts of carbon monoxide undergoes the water-gas
shift reaction in a shift reactor 12, a chemical reaction in which carbon monoxide
reacts with water vapor to form carbon dioxide and hydrogen:
CO + H
2O → CO
2 + H
2
[0032] After sulphur removal 13 and removal of carbon dioxide 14 the syngas contains mainly
hydrocarbon, which after further conditioning steps is sent to the gas turbine 15
of the power island 3 to be burnt.
[0033] For start-up as well as for other cases where syngas or a natural gas pipeline are
not available an LNG tank 16 is arranged on the gas island 2 for storing liquid (cryogenic)
natural gas (LNG) 17 on site. In case of need, the gas turbine 15 of the power island
3 is supplied with LNG 17. For this purpose LNG 17 has to be vaporized again. The
LNG 17 is typically warmed and vaporized using large ambient air vaporizers 18.
[0034] Figure 2 shows the basic concept of the inventive gas island with a liquid gas cooled
air separation unit for integrated gasification combined cycle power plants.
[0035] Air 10 is compressed in main air compressor 19, cooled in heat exchanger 20 and cleaned
and dried in molecular sieve 21, then supplied via air duct 35 to a heat exchanger
system 37 which could be a single heat exchanger 22. During start-ups and outages,
LNG 17, until then stored in LNG tank 16, is supplied to the main heat exchanger 22
via LNG duct 36 to be evaporated against the compressed air 10. The recovered natural
gas 44 is then supplied via compressor 45 to the combustion chamber 23 of the gas
turbine 15 and the cooled and compressed air 10 is transferred to the high pressure
(HP) column of a distillation column system 24 of the ASU 9 for distillation.
[0036] ASUs 9 are often built with an expander cycle (not shown), to provide the necessary
refrigeration. It is anticipated that this process will still be needed, as the LNG
will only offer cooling during start-up.
[0037] The IGCC start-up procedure is as follows:
- 1. ASU 9 begins compression with its main air compressor 19 (MAC). It cycles air to
a distillation column system 24 (including an expansion stage) and begins to cool.
A partially air-integrated ASU 9 will ramp up to 50% load with its MAC 19. LNG is
supplied to the ASU heat exchanger 22 or MAC aftercooler 20. The cooling process is
enhanced.
- 2. The LNG boils and is supplied as gas to CCPP combustion chamber 23.
- 3. The gas turbine 15 fires and begins operation on natural gas. Oxygen and Nitrogen
products are not yet required.
- 4. The gas turbine compressor supplies compressed air to the ASU 9.
- 5. The ASU 9 ramps up.
- 6. As the ASU 9 cools, it begins to produce gaseous nitrogen (GAN) and gaseous oxygen
(GOX) streams.
- 7. When GAN and GOX streams reach desired purity, the gasifier starts up. Syngas is
initially supplied to the flare (if necessary).
- 8. When sufficient syngas is available, gas turbine changes over to syngas operation.
No more natural gas is required.
- 9. LNG is no longer supplied to ASU 9 for enhanced cooling. Some NG may be flared.
- 10. ASU 9 continues to cool via normal design.
[0038] With reference to Figure 3, a simple inclined LNG/Air heat exchanger 22 is shown.
There is a danger of mixing natural gas into the process air 10 of the ASU 9. The
hazard created by hydrocarbons in an ASU 9, or in the inerting nitrogen stream (see
alternative embodiment in Figure 7) is significant. Some advantage may be taken from
the pressure difference. If the LNG 17 is to be evaporated at ambient pressure before
compression for combustion, then the pressure difference is optimal for a safe heat-exchanger
as shown in Figure 3. A failure in the wall 25 separating the two media will lead
to a leak of air 10 (or nitrogen, see Figures 4 and 7) to the natural gas 25, having
no more serious effect than diluting the fuel. A significant leak would be detected
if heating value / Wobbe index measurements are made before combustion or air flow
in the ASU 9 is measured.
[0039] If the LNG 17 is to be pumped while still liquid and evaporated at pressure, there
is a greater risk of natural gas leaking into the air or the refrigerant. Pumped LNG
will require a (e.g.) 30 bar ambient vaporiser, requiring much thicker walls and thus
a significant capital increase.
[0040] This is a key reason to avoid the integration in the main heat exchanger 22 (Figure
2) but instead to use a separate heat exchanger 26 as shown in Figure 4.
[0041] Figure 4 suggests a setup that uses gaseous nitrogen (GAN) as the refrigerant, thereby
minimising the impact of a leak. However as pure nitrogen will not be available at
the start of cool-down, this option is only possible with a closed loop cooling system.
A pump 27 circulates the GAN. In this embodiment the compressor 45 of Figure 2 arranged
downstream of the heat exchanger system 37 can be replaced by a pump 46 arranged upstream
of the heat exchanger system 37.
[0042] Figure 5 represents another refrigeration cycle using nitrogen as the refrigerant.
But instead of a simple positive displacement machine 16 to circulate the GAN as in
Figure 4, a complete refrigeration cycle could be installed with a compander 28. Also
by raising the pressure of the nitrogen the (higher boiling point) LNG should provide
sufficient refrigeration to liquefy.
[0043] Where ASU suppliers are unwilling to alter their standard design, or the engineering
required removes the cost benefit, the process could be removed from the ASU. Figure
6 shows an embodiment where a second heat exchanger 26 is installed that cools an
air stream 29 at the ASU boundary, thereby minimising interference with the ASU 9.
The LNG cools part of the feed air stream 10, which in turn cools the distillation
column system 24.
[0044] In an alternative arrangement shown in Figure 7 a waste stream 30 of the ASU 9 is
used as refrigerant for the compressed air stream 10. A further possibility would
be to use the GAN product stream as refrigerant (cf. Figure 5, where nitrogen is used
as refrigerant in a closed loop in contrast to Figure 7 with an open loop).
[0045] By cooling a waste cycle, a cooled waste stream could be diverted to a heat exchanger
26 and used as the refrigerant. For this purpose a multi-port-valve 31 arranged in
a waste duct 38 interposes a circuit 32 in which the primary side of the second heat
exchanger 26 is arranged, thereby interconnecting the secondary side of the first
heat exchanger 22 and the primary side of the second heat exchanger 26. During normal
operation the circuit 32 is bypassed.
[0046] Figure 8 shows an ASU design where an additional refrigeration unit 33 is installed
downstream of the main air compressor (MAC) 19. This allows more water to be condensed
out 40 and thus reduces the size of the adsorbers 21. Where the additional cooling
is only available at start-up, the adsorber size must remain the same. However, the
existence of this design might further reduce necessary re-engineering.
[0047] Figure 8 further shows a part-integrated embodiment where part of the air from the
compressor 34 of the gas turbine 15 is used to feed the ASU 9. This part stream can
either be added to the air stream 10 of the MAC 19 before (dashed line) or after (solid
line) the additional refrigeration unit 33.
[0048] With this invention a start-up time saving of 20-30 hours could be possible. This
results in much less use of secondary fuel and less power demand from the ASU 9. Since
this invention removes the need for an LNG vaporiser there may be a further availability
benefit or a reduction in maintenance activities achieved as ambient vaporisers tend
to ice up and can become ineffective if not regularly thawed.
[0049] Another benefit is the enhanced molecular-sieve operation during start-up since it
is possible that the reduced air temperature will increase the effectiveness of the
molecular sieve.
1. A gas island (2) for an integrated gasification combined cycle power plant (1), comprising:
an air separation unit (9),
an air duct (35) emptying into the air separation unit (9) and
a liquid natural gas duct (36),
characterized in that a heat exchanger system (37) is arranged on a primary side in the air duct (35) and
on a secondary side in the liquid natural gas duct (36).
2. The gas island (2) as claimed in claim 1, wherein the heat exchanger system (37) is
a single heat exchanger (22,33).
3. The gas island (2) as claimed in claim 1, wherein the heat exchanger system (37) comprises
at least a first (22) and a second heat exchanger (26), wherein a primary side of
the first heat exchanger (22) is arranged in the air duct (35), a secondary side of
the second heat exchanger (26) is arranged in the liquid natural gas duct (36) and
the secondary side of the first heat exchanger (22) and the primary side of the second
heat exchanger (26) are interconnected.
4. The gas island (2) as claimed in claim 3, wherein the secondary side of the first
heat exchanger (22) and the primary side of the second heat exchanger (26) are arranged
in a closed circuit.
5. The gas island (2) as claimed in claims 3 or 4, wherein a pump (27) is arranged in
the circuit.
6. The gas island (2) as claimed in claims 3 or 4, wherein a compander (28) is arranged
in the circuit.
7. The gas island (2) as claimed in claim 3, wherein a multi-port-valve (31) is arranged
in a waste duct (38) interconnecting a distillation column system (24) of the air
separation unit (9) and the secondary side of the first heat exchanger (22), and where
for a switching status of the multi-port-valve (31) a circuit (32) is interposed in
which the primary side of the second heat exchanger (26) is arranged, thereby interconnecting
the secondary side of the first heat exchanger (22) and the primary side of the second
heat exchanger (26).
8. The gas island (2) as claimed in any of the preceding claims, wherein the air duct
(35) bifurcates into a branch duct (41) and a main duct (42), wherein the heat exchanger
system (37) and a valve (43) are arranged in the branch duct (41).
9. The gas island (2) as claimed in any of the preceding claims, wherein a pump (46)
is arranged in the liquid natural gas duct (36) in the direction of flow of liquid
natural gas upstream of the heat exchanger system (37).
10. The gas island (2) as claimed in any of claims 1 to 8, wherein a compressor (45) is
arranged in the liquid natural gas duct (36) in the direction of flow of liquid natural
gas downstream of the heat exchanger system (37).
11. The gas island (2) as claimed in any of the preceding claims, wherein at least one
heat exchanger (26) of the heat exchanger system (37) is an evaporation cooler.
12. An integrated gasification combined cycle power plant (1) with a gas island (2) as
claimed in any of the preceding claims, wherein the liquid natural gas duct (36) is
connected to a combustion chamber (23) of a gas turbine (15) and an oxygen duct (8)
connects the air separation unit (9) to a gasifier (6).
13. A method for speeding-up a start-up process for cryogenic separation of an air feed
for an air separation unit (9) for integrated gasification combined cycle power plants
(1), comprising: cooling air to be fed to the air separation unit (9) using liquid
natural gas expansion.
14. The method as claimed in claim 13, comprising:
- compressing air with an air compressor connected to a column of an air separation
unit via an air duct,
- cooling air in an expansion stage arranged in the air duct,
- cycling the cooled air via the air duct to the column,
- ramping up the air separation unit to part load,
- supplying liquid natural gas to a heat exchanger system arranged in the air duct,
- supplying heated liquid natural gas as gas to a combustion chamber of a gas turbine
in the combined cycle power plant,
- firing the gas turbine and beginning operation on natural gas,
- supplying compressed air from a compressor of the gas turbine to the air separation
unit,
- ramping up the air separation unit,
- producing gaseous nitrogen (GAN) and gaseous oxygen (GOX) streams with the air separation
unit.
15. The method as claimed in claims 13 or 14, wherein LIQUID NATURAL GAS is no longer
supplied to the ASU (9) for enhanced cooling, as soon as a gasifier (6) starts up
and sufficient syngas is available and the gas turbine (15) is changed over to syngas
operation.