[0001] The invention relates to an offshore installation for offshore energy resources exploitation.
[0002] Such offshore installations are widely known and used for the exploitation of offshore
energy resources. Offshore energy resources exploitation may be understood to comprise
the exploitation of oil and/or gas fields, the exploitation of wind energy using offshore
wind turbines, the exploitation of wave energy and/or the exploitation of solar energy
offshore. The exploitation of wind energy, wave energy and/or solar energy usually
comprises the generation of electricity to be transported to a further, usually onshore,
location. The exploitation of an oil and/or gas field, usually comprises the winning
of oil and/or gas which may have to be transported to a further, usually onshore,
location.
[0003] Advantageously a movable self-installing platform may be used for the exploitation
of the energy resources offshore. After expiration of the life time of e.g. the exploitation
of a wind mill park or an oil and/or gas field, the platform can be removed from the
offshore location and can be relocated to a further offshore location.
[0004] Such a platform is known for example known from the Dutch patent
NL 1005463. Also several of such platforms are being operated in the North Sea, some known as
Mobile Offshore Application Barge (MOAB) and others as Multi Purpose Platform (MPP).
These platforms comprise a floating pontoon and four retractable legs, which can be
lowered and lifted with respect to the pontoon. The lower end of each leg may be fitted
with suction cans, which can penetrate the sea bottom and provide a fixed connection
to the bottom. If the legs are lowered in relatively shallow water, at some stage
the legs may reach the seabed and the suction cans may penetrate in the sea bottom.
As the legs are moved further by force, the pontoon will be elevated out of the water.
The purpose of lifting the pontoon out of the water is to obtain a relatively stable
fixed structure, which is not subjected to wave loads and which can therefore safely
stay in place offshore, also during storm conditions. The pontoon may provide a stable
deck on which for example sheltered areas can be provided e.g. for oil and/or gas
production facilities and/or for systems of an electrical power network for wind turbines.
These pontoons with retractable legs are usually referred to as "Self Installing Platform",
which may be abbreviated as "SIP".
[0005] For the installation of an offshore installation of the above mentioned type usually
various peripheral equipment needs to be provided. Peripheral equipment such as cabling,
e.g. electrical cabling and/or piping may be provided. Cabling, in particular electrical
cabling may be important for installations where electricity may be generated, such
as electricity generation by wind energy and/or wave energy and/or solar energy. Piping
may be provided for installations where oil and/or gas may be exploited. Of course,
also for an oil and/or gas installation cabling may be required and/or for an electricity
generating installation piping may be required. The cabling and/or piping is usually
provided on the sea bottom.
[0006] A drawback of the cabling and/or piping is that the cabling and/or piping is rather
vulnerable and thus may increase installation time of the offshore installation. When
first installing the platform and thereafter installing the cabling and/or piping,
this is relatively costly due to the time the platform is already on the offshore
location but cannot be used yet. The relatively vulnerable cabling and/or piping can
however be connected directly to the platform. Alternatively, when first installing
the cabling and/or piping and thereafter installing the platform, the cabling and/or
piping needs to be stored during a certain period of time on the sea bottom making
it vulnerable to damage. In addition, after connection of the cabling and/or piping,
the relatively vulnerable equipment may be exposed to environmental influences, and
therefore may be prone to damage.
[0007] Publication
EP 0 518 709 discloses a method for installing a marine structure having a hollow base which is
to be flooded with water, a topside deck and a plurality of hollow telescopic caissons
connecting the base to the deck. A J-tube may be casted in one of the caissons for
providing horizontal access to the caisson.
[0008] The objective of the invention is to provide an offshore installation of the above
mentioned type that obviates at least one of the above mentioned drawbacks.
[0009] Thereto, the invention provides for an offshore installation for offshore energy
resources exploitation comprising a movable self-installing platform wherein the platform
comprises a floatable pontoon with at least one leg that is adjustable between a transport
position in which the leg is elevated with respect to the pontoon and an installation
position in which the leg is lowered with respect to the pontoon, wherein the platform
is arranged for connection of cabling and/or piping from the sea bottom to the pontoon,
further comprising a protection pipe arranged to enclose the cabling and/or piping
between the sea bottom and the pontoon.
[0010] By providing a protection pipe between the sea bottom and the pontoon, the relatively
vulnerable cabling and/or piping can be protected from e.g. the relatively harsh environmental
conditions. This may increase the life time of the cabling and/or piping and may reduce
maintenance and/or repair costs. The protection pipe may support and guide the cables
and/or pipelines, and also may protect them from impact loads, e.g. collision with
a vessel, and/or environmental loads. The protection pipe provides for a relatively
cost-effective protection structure for the cabling and/or piping. Of course, the
platform may also be provided with two or more protection pipes.
[0011] In particular for the development and exploitation of offshore wind mill parks, the
platform may function as a substation comprising electrical equipment such as transformers.
The electrical cabling to and from the platform may be extensive and complex. The
installation of the electrical cabling may therefore be time consuming. The electrical
cabling is also rather vulnerable, mainly due to the relatively small diameters of
the electrical cabling. A protection structure as a relatively larger diameter protection
pipe that can guide and protect the electrical cabling may provide a reliable and
cost effective protection which may increase the life time of the electrical cabling.
[0012] The protection pipe fully encloses the cabling and/or piping between the sea bottom
and the pontoon in order to provide optimal protection for the vulnerable cabling
and/or piping. The protection pipe comprises a relatively large diameter pipe that
can fully enclose the cabling and/or piping and which is usually installed upwardly
at a side of the pontoon. The protection pipe may comprise coupling elements for coupling
to the platform and/or the pontoon. The coupling elements may comprise brackets or
welding or other connection means.
[0013] The platform comprises a floatable pontoon with at least one leg. The leg is adjustable
between a transport position and an installation position. In the transport position
is the leg elevated with respect to the pontoon, the leg substantially extends above
the pontoon, such that during transport, when the pontoon is floating in the water,
the draft of the floating platform can remain relatively limited. In the installation
position, the leg is lowered with respect to the pontoon, preferably until the leg
can be installed with respect to the sea bottom.
[0014] By providing a tie-in tube at a lower end of the protection pipe, the cabling and/or
piping can be relatively smoothly tied in from the sea bottom into the protection
pipe. Preferably, the tie-in tube is of a tube of the J-type such that the cabling
and/or piping can relatively easily be pulled through the J-tube into the protection
pipe. Alternatively, the cabling and/or piping may be arranged in the protection pipe
and may be pulled through the tie-in tube towards the sea bottom for further installation
on the sea bottom. Preferably, the tie-in tube is provided at a lower end of the protection
pipe, such that when the protection pipe is installed on the sea bottom, the tie-in
tube is located near the sea bottom to accommodate a relatively smooth transition
of the cabling and/or piping between the sea bottom and the protection pipe. An alternative
connection for, in particular pipelines, can be a flange connection to pre-installed
piping inside the protection pipe. Preferably, the protection pipe extends over approximately
the whole height of the platform, from a lower side where the piping and/or cabling
is entering the protection pipe to an upper side where the piping and/or cabling is
connecting to the pontoon and/or to the platform. The lower side may be at, near or
in the sea bottom.
[0015] By providing the protection pipe with a suction anchor at a lower end, the protection
pipe can be independently anchored to the sea bottom. The protection pipe can thus
be installed independently of the platform. The protection pipe can be connected to
the sea bed e.g. by one ore more suction cans which are fitted to the protection pipe.
[0016] Providing the protection pipe with one ore more suction anchors leaves the opportunity
to install the protection pipe before the installation of the platform. This offers
the option that pipeline and/or cables are also installed before the platform is installed,
such that the connections to the platform can be made faster and operation can start
earlier. This may reduce installation time and thus costs. Also, by pre-installing
the protection pipe the cabling and/or piping installed on the sea bottom may be stored
dry, i.e. in the protection pipe, until the platform arrives for connection to the
platform. For example, for an offshore wind mill park with its complex and expensive,
mainly electrical, cabling, this offers the opportunity to pre-install approximately
all electrical cabling, which may be advantageous due to the relatively long installation
time involved. By pre-installing the protection pipe, the already installed electrical
cabling can be stored dry in or at a dry end of the protection pipe, which may give
a significant cost advantage. Also, the platform can be installed later and connecting
the electrical cabling to the platform may become relatively easy due to the dry storage
of the electrical cabling, thus reducing the installation and/or hook-up time for
the platform.
[0017] When pre-installing the protection pipe, the pontoon may be provided with an adapted
corner element for receiving the pre-installed protection pipe as leg of the pontoon.
Instead of a guide element arranged in the corner for guiding the leg, the corner
may be provided as an open corner to relatively easily receive the already installed
protection pipe. The corner may then be closed to connect the protection pipe to the
pontoon, e.g. by using a clamping element. Also, the pontoon may be provided with
two or more open corners allowing installation of the normal legs outside a dry dock,
e.g. when the pontoon is floating in a harbour. With the clamping elements, the legs
can be connected to the pontoon. The open corner elements with the clamping elements
may also provide a guide through which the leg can be lowered and/or the pontoon can
be lifted for installation at the offshore location. The clamping element can be removed
from the pontoon e.g. by the use of removable fastening means such as bolts. Providing
an open corner with a clamping element allows installation of the legs to the platform
without the use of a dry dock or an additional barge. The pontoon can be kept floating
in the water, e.g. in a harbour and a crane on the shore, can hang the leg in the
open corner and can lower the leg a bit in the open corner. Then the leg can be positioned
in the open corner and the clamping element may close the open corner and fasten the
leg for transport. Also, by providing an open corner, the suction may be assembled
to the leg onshore and the leg with suction can may be installed at once in the open
corner to the pontoon of the platform.
[0018] Alternatively, the protection pipe can also be installed after the platform is installed.
In this case the advantage is that the protection pipe can be transported to location
on the platform and the installation can also be done from the platform. This may
avoid for example hiring of equipment e.g. a crane vessel for separately installing
the protection pipe, since the protection pipe can then be installed from the platform.
[0019] Advantageously, the protection pipe is provided as a leg of the platform, thus reducing
installation and/or manufacturing costs. A platform is usually fitted with four legs
at corners of the pontoon. By providing one leg as the protection pipe, the other
legs may remain conventional legs.
[0020] By providing at least two strand jacks working in opposite directions on the same
pre-tensioned strand bundle to the legs and/or the protection pipe, a relatively cost-effective
and re-usable system may be obtained to move the legs with respect to the pontoon.
A double set of strand jacks working in opposite directions is used to move the legs
up or down, such that forces can be generated both upward, to lift the pontoon upward
and downward, to lower the legs. The two or more strand jacks for lifting and lowering
work in line on a single wire bundle. The advantage of this arrangement is that the
wire bundles can be pre-tensioned by a separate system such that no slack wire occurs
during lifting or lowering of the legs. A relatively simple control of the wire tension
may thus be possible.
[0021] By providing a base frame that can be installed on the sea bed, the platform may
be installed in larger water depths. A movable self-installing platform can usually
be installed up to water depths of around 30 m. It is known in the art to provide
a base frame when installing a movable self-installing platform in larger water depths,
e.g. in water depths of 80 m up to 100 m. In publication
NL 1003439 is the use of such a base frame described. The base frame may also provide extra
strength. The base frame can be installed on the sea bed and the legs of the platform
are lowered in the corner legs on top of the base frame. The base frame can be pre-installed
on the sea bed prior the installation of the platform.
[0022] In an advantageous embodiment is the protection pipe part of the base frame. The
protection pipe can be mounted on a side of the base frame or the protection pipe
can replace a leg of the base frame. When the protection pipe is provided at a side
of the base frame, the protection pipe can be fitted with or without a suction can
for anchoring the protection pipe to the sea bottom. When connecting the protection
pipe to the base frame, anchoring of the protection pipe to the sea bottom may be
left away. The protection pipe may then be sufficiently anchored to the base frame.
[0023] Preferably, the legs of the base frame are fitted with suction anchors for easy and
reliable anchoring of the base frame to the sea bed. In case the protection pipe replaces
a leg of the base frame, the protection pipe may also be fitted with a suction anchor
for anchoring the protection pipe to the sea bottom. The legs of the base frame are
usually approximately as high as the base frame itself. The protection pipe however
extends from approximately the sea bottom to approximately the height of the pontoon
in installed position and thus extends above the base frame. If the platform, and
therefore the base frame, has four corners each arranged to fit with a leg, than three
'normal' legs remain while the fourth leg may be replaced by the protection pipe.
[0024] By pre-installing the base frame with the protection pipe, the platform can be completed,
equipped and commissioned onshore and can then be town to the offshore location where
the base frame is already waiting. The completed platform can then be installed on
the base frame relatively fast and easy, without expensive crane vessels etc. Also,
the piping and/or cabling that is, preferably, pre-installed through the protection
pipe, can be easily connected to the platform. After connection of the piping and/or
cabling, the platform can become operational. Thus, in a relatively efficient and
cost effective way, a self-installing platform can be installed in larger water depths
using pre-installed facilities, such as a base frame and a protection pipe. Such a
platform can for example be used as a base station or a transformer station for offshore
energy parks, comprising electrical equipment. The electrical equipment may then be
fully tested and commissioned onshore, while being connected offshore to the piping
and/or cabling. The self-installing platform may also be a satellite platform for
an oil and/or gas well, for example comprising processing equipment that may be tested
and commissioned onshore and connected to the well and/or pipeline offshore. The piping
and/or cabling may advantageously be pre-installed through the protection pipe.
[0025] The invention further relates to a method for connecting cabling and/or piping to
an offshore installation comprising a movable self-installing platform wherein the
platform comprises a floatable pontoon with at least one leg that is adjustable between
a transport position in which the leg is elevated with respect to the pontoon and
an installation position in which the leg is lowered with respect to the pontoon,
comprising installing the cabling and/or piping on the sea bottom to the platform
location, providing a protection pipe for enclosing the cabling and/or piping between
the sea bottom and the pontoon, installing the protection pipe on the sea bottom,
tying in the cabling and/or piping in the protection pipe.
[0026] By installing the protection pipe prior to installation of the platform, tying-in
the cabling and/or piping into the installed protection pipe prior to installation
of the platform, a further reduction in installation time and costs can be achieved.
A platform can then be completed, equipped and commissioned onshore, while once at
the offshore location, can be installed and connected to the pre-installed cabling
and/or piping. After connection to the cabling and/or piping, the platform can become
operational.
[0027] Further advantageous embodiments are represented in the subclaims.
[0028] Further, the invention relates to the following aspects. According to an aspect of
the invention, the legs and/or the protection pipe are fitted with at least two strand
jacks working in opposite directions on the same pre-tensioned strand bundle for lifting
and/or lowering the legs with respect to the pontoon.
[0029] According to an aspect of the invention, the offshore installation further comprises
a base frame comprising interconnected legs at corners of the base frame, wherein
the base frame is arranged for installation on the sea bottom and wherein the base
frame legs are arranged to receive the legs of the platform.
[0030] According to an aspect of the invention, the base frame is pre-installed on the sea
bottom prior to installation of the platform.
[0031] According to an aspect of the invention, the protection pipe is part of the base
frame.
[0032] According to an aspect of the invention, the protection pipe is provided as a leg
of the base frame.
[0033] The invention will further be elucidated on the basis of exemplary embodiments which
are represented in a drawing. The exemplary embodiments are given by way of non-limitative
illustration of the invention.
[0034] In the drawing:
Fig. 1 shows a schematic view of a platform with protection pipe;
Fig. 2 shows a schematic view of a platform with a base frame and a protection pipe;
Fig. 3 shows a schematic view tie-in tube for a protection pipe;
Fig. 4 shows a schematic perspective view of protection pipe with tie-in tubes;
Fig. 5 shows a schematic view of a strand jack arrangement;
Fig. 6 shows a schematic view of an installation of a leg of a platform with an open
corner piece;
Fig. 7 shows the embodiment of Fig. 6 with a clamping element; and
Fig. 8 shows a platform in floating position.
[0035] It is noted that the figures are only schematic representations of embodiments of
the invention that are given by way of non-limiting example. In the figures, the same
or corresponding parts are designated with the same reference numerals.
[0036] Fig. 1 shows an offshore installation 1 comprising a platform 2. The platform 2 is
a movable self-installing platform comprising a floatable pontoon 3 and legs 4. The
pontoon 3 may comprise one or more decks.
[0037] The platform 2 is adjustable between a transport position, as shown for example in
Fig. 8 and an installed position, as shown in Fig. 1. In the transport position, the
pontoon 3 is floating on the water and the legs are in elevated with respect to the
pontoon 3. The legs 4 extend substantially above the pontoon 3. In the installed position,
the legs 4 are lowered with respect to the pontoon 3. The legs 4 extend substantially
below the pontoon 3. In a final installed position is the pontoon 3 elevated with
respect to the water level at the offshore location. The platform 2 is considered
to be a self-installing platform since the platform can be installed at the offshore
location without the requirement of a crane vessel for example. Also, the platform
can be transported to the offshore location without the use of a barge, since the
pontoon is self floating. The legs can move upward and downward with respect to the
pontoon along the longitudinal guides 7.
[0038] In this embodiment, the legs 4 are provided with suction anchors 5 for anchoring
to the sea bottom 6. The suction anchors usually are provided as suction cans 5. Upon
installing a platform 2, the leg 4 is lowered to the sea bottom 6, whereby the suction
cans 5 penetrate the sea bottom 6. The leg 4 is moved further down by which the pontoon
3 is lifted out of the water. Finally, the legs 4 and the pontoon 3 are connected
to each other such that the platform 2 becomes a stable platform. When de-connecting
the legs 4 and the pontoon 3 and removing the suction cans 5 from the sea bottom 6,
the platform 2 can be removed from the offshore location and can be moved further,
for example to another offshore location or to a harbour. The platform 2 is thus movable.
[0039] The platform 2 usually is arranged for the connection of cabling and/or piping 8
from the sea bottom 6 to the pontoon 3. In particular when the platform 2 serves as
an offshore substation for a wind mill park, extensive cabling may go to and from
the platform. This cabling 8, mainly electric cabling, is laid on the sea bottom and
may connect for example wind mills with the substation, or may connect for example
the substation with an onshore location. The cabling 8 may be connected to the pontoon
3 of the platform 2 from the sea bottom 6. The pontoon 3 may comprise internal closed
compartments that can be utilized for the installation of equipment, such as transformers.
In case of equipment which is sensitive to temperature, moisture and/or saltiness
of the environment, such as electrical and/or electronic equipment, the closed compartments
can be fitted with an air conditioning system. Access of large components of the equipment
into and out of the compartments can be created by hatches in the main deck of the
pontoon.
[0040] The cabling 8 is relatively vulnerable for example for impact damage or environmental
loads. Thereto, a protection pipe 9 is provided at the side of the platform 2. The
protection pipe 9 is a relatively large diameter pipe, e.g. a diameter between approximately
2 m and approximately 6 m, that fully encloses the cabling 8 between the sea bottom
6 and the pontoon 3. As the cables or pipelines 8 are inside the protection pipe 9,
they are protected against external loads. By protecting the cabling 8 the life time
of the cabling may be increased and/or installation and/or connection of the cabling
may be facilitated, thus reducing costs such as installation and/or maintenance costs.
[0041] The protection pipe 9 is here further provided with J-tubes 10 for accommodating
tying in of the cabling 8 to the protection pipe. Fig. 3 and Fig. 4 give a more detailed
overview of the J-tube 10 at the lower end of the protection pipe 9. The J-tube 10
is a tie-in tube arranged at the lower end of the protection pipe 9 such that, when
the protection pipe 9 is installed the J-tube 10 is positioned near the sea bottom
6.
[0042] In this embodiment, the protection pipe 9 is provided with a suction can 5 at its
lower end for anchoring to the sea bottom 6. By providing the suction can 5, the protection
pipe 9 can be installed independently of the platform 2, such that the protection
pipe 9 may be installed prior to the installation of the platform 2 or after the installation
of the platform 2.
[0043] In Fig. 2, the installation 1 is provided with a base frame 11 which can be pre-installed,
e.g. by a crane vessel, and connected to the sea bottom 6, e.g. by suction cans 5
or by piles driven vertically in the soil. The base frame may be used as a stable
support for the platform 2 and may enable the installation of the platform 2 in deeper
water, e.g. above x meter water depth.
[0044] As can be seen in Fig. 2 comprises the base frame interconnected legs 12. The legs
12 are here interconnected by a truss-structure. In this embodiment is one leg 12
replaced by the protection pipe 9, also provided with a J-tube 10. The protection
pipe 9 reaches from the sea bottom 6 to the pontoon 3, whereas the legs 12 of the
bas frame 11 are approximately as high as the base frame itself. The legs 12 are arranged
to couple with the legs 4 of the platform 2. This coupling may be for example a stabbing
connection. Of course, other connections, such as welding, bolting, etc. are also
possible.
[0045] The protection pipe 9 as part of the base frame 11 is installed together with the
base frame 11 prior to the installation of the platform. If the platform 2 is arranged
for receiving four legs at the corners, then the protection pipe serves as one leg.
The platform 2 comprising the pontoon 3 and three legs 4 is then transported to the
offshore location where the base frame 11 is installed. One corner of the pontoon
3 is arranged for receiving the already installed protection pipe 9. For example,
the corner can be provided as an open corner in which the protection pipe 9 can be
accommodated. To connect the protection pipe 9 to the pontoon 3 the corner can be
closed with a closing piece 13. The closing piece 13 can for example be a clamping
element for removable clamping the protection pipe 9 to the pontoon.
[0046] Also, the pontoon 3 can be fitted with an open corner for facilitating installation
of the legs to the pontoon without the requirement of a relative expensive dry dock.
The legs 4 can then be installed when the pontoon 3 is floating, e.g. in a harbour
as illustrated in Fig. 6 and Fig. 7. Fig. 6 shows that a leg 4 is positioned into
the open corner using a crane 14. In this way, the dry dock or a second barge are
not required as the connections which are to be made between the leg 4 and the pontoon
3 and the closing piece 13 are above the water. The leg 4 is positioned and kept in
place at the mounting location e.g. by slings or temporary hooks. As a next step in
the assembly procedure of assembling the leg 4 to the pontoon 3, the closing piece
13 is aligned and connected to the pontoon 3, e.g. by bolts or by welding. The weight
of the closing piece 13 is relatively small, which makes it relatively easy to handle.
[0047] Fig. 2 further shows a strand jack arrangement 15 for lowering and lifting the legs
with respect to the pontoon. Fig. 5 shows two strand-jacks 16a, 16b acting in line
in opposite directions on a single strand bundle 17. The strand jack 16a is mounted
such that it is capable of pulling a bundle of strands 17 upward, indicated by arrow
A. The strand-jack 16b is mounted such that it is capable of pulling the same bundle
of strands 17 downward, indicated by arrow B. The bundle of strands 17 is pre-tensioned
by a pulling device 18 between the top and bottom of the leg 4 in order to prevent
the strands to become slack if a vertical load is acting on the support 19 which is
rigidly connected to the pontoon 3. Slack strands are to be avoided for proper functioning
of the strands and also to avoid impact loads when the slack strands are tensioned
after reversal of the load. Here, an upward force at the pontoon 3 is achieved by
the action of strand jack 16a, while the strand jack 16b is not active. A downward
force of the pontoon is achieved by the action of strand jack 16b, while the strand
jack 16a is not active. Therefore, only one strand jack 16a, 16b has to be controlled
at the time, depending on the direction of the load acting on the pontoon 3, thereby
allowing less complex control mechanisms.
[0048] Suction cans 5 fitted to the underside of the legs 4 can be placed centred, as shown
in the previous embodiments, but can also be placed eccentrically, as shown in Fig.
8. In order to reduce the draft of the platform 2 in transport position, when the
pontoon 3 is floating and the legs 4 are elevated, leg guides 20 for guiding the legs
during lowering and/or lifting, can be moved upward and sideward of the pontoon. In
the embodiment of Fig. 1 for example, is a corner of the pontoon 3 provided with a
passage for the leg 4, thereby functioning as leg guide embodied in the pontoon 3.
An advantage of the arrangement of Fig. 8 is that the suction can 5 can be lifted
higher, such that the draft of the floating platform may be smaller. The leg guide
20 can be closed with a closing piece 13 for relatively easy assembly of the leg 4
to the pontoon 3.
[0049] Many variants will be apparent to the person skilled in the art. For example, a platform
may be provided with more than one protection pipe and/or one or more legs of the
platform may be arranged as protection pipe. All variants are understood to be comprised
within the scope of the invention as defined in the following claims.
1. Offshore installation for offshore energy resources exploitation comprising a movable
self-installing platform wherein the platform comprises a floatable pontoon with at
least one leg that is adjustable between a transport position in which the leg is
elevated with respect to the pontoon and an installation position in which the leg
is lowered with respect to the pontoon, wherein the platform is arranged for connection
of cabling and/or piping from the sea bottom to the pontoon, further comprising a
protection pipe arranged to enclose the cabling and/or piping between the sea bottom
and the pontoon.
2. Offshore installation according to claim 1, wherein the protection pipe comprises
a tie-in tube at a lower end for tying in the cabling and/or piping from the sea bottom
into the protection pipe.
3. Offshore installation according to claim 2, wherein the tie-in tube is a J-type tube.
4. Offshore installation according to any one of the preceding claims, wherein the protection
pipe comprises a suction anchor at a lower end for anchoring in the sea bottom.
5. Offshore installation according to claim 4, wherein the protection pipe is pre-installed
before installation of the platform.
6. Offshore installation according to claim 4, wherein the protection pipe is installed
after installation of the platform.
7. Offshore installation according to any one of the preceding claims, wherein the protection
pipe is provided as a leg of the platform.
8. Offshore installation according to any one of the preceding claims, wherein the floatable
pontoon comprises at least one deck.
9. Method for connecting cabling and/or piping to an offshore installation comprising
a movable self-installing platform wherein the platform comprises a floatable pontoon
with at least one leg that is adjustable between a transport position in which the
leg is elevated with respect to the pontoon and an installation position in which
the leg is lowered with respect to the pontoon, comprising installing the cabling
and/or piping on the sea bottom to the platform location, providing a protection pipe
for enclosing the cabling and/or piping between the sea bottom and the pontoon, installing
the protection pipe on the sea bottom, tying in the cabling and/or piping in the protection
pipe.
10. Method according to claim 9, further comprising installing the protection pipe prior
to installation of the platform, tying-in the cabling and/or piping into the installed
protection pipe prior to installation of the platform.