[0001] The present invention relates to a method of producing hydrocarbon material from
a layer of oil sand located in an earth formation.
[0002] In the industry of hydrocarbon production from subterranean reservoirs, it is conventional
practice that oil or gas is produced from wellbores by virtue of the high fluid pressures
existing downhole. In case of high viscosity oil, downhole pumps can be applied to
pump the oil to surface, or other methods can be applied to increase the oil production
rate such as steam injection or CO
2 injection into the formation. However, the conventional methods are not adequate
for the production of heavy hydrocarbon material present in rock formations, when
the material is not flowing up a well. Examples are bituminous oil or tar or kerogen
occurring in sands, standstone, or shale based reservoirs in Canada or elsewhere,
e.g. tar sands or Limestone/Dolomite based and calcareous shale based reservoirs such
as found in the Canadian Athabasca or Grosmont regions. Such a reservoir will herein
be referred to as oil sand. Hydrocarbons from oil sand layers can in principle be
recovered by mining. As some oil sands layers occur at relatively shallow depths,
typically between 0 to 200 meters, it is common practice to produce oil from these
layers by surface mining whereby the overburden layer is removed using draglines and/or
shovels and trucks. The produced oil sand is transported to one or more processing
facilities for separation of hydrocarbon fluid from the sand slurries. However, for
oil sands layers at greater depths, removal of the overburden is costly and has a
significant impact on the environment. Therefore alternative methods for producing
oil sands have been proposed.
[0003] One such alternative method is disclosed in a technical paper published in
CIM magazine by the Canadian Institute of Mining & Metallurgy, 2001, Vol. 94, Nr.
1054, pages 63-66, entitled "Hydraulic underground mining of oil sands - the next
big step", by D.D. Tannant et al. This publication discloses a method of producing hydrocarbon fluid from an
oil sands layer located in an earth formation, wherein a first horizontal borehole
is drilled into the oil sands layer and a fluid jetting device is operated through
the borehole to excavate the oil sands layer and thereby form a cavity in the oil
sands layer. A slurry of fluid and oil sands is formed in the cavity as a result of
the fluid jetting operation. Slurry is withdrawn through the borehole, and a stable
cavern is formed containing caved oil sands, water, and possibly injected air. The
cavern is used as a primary fractionator, in which bitumen rises to the top and sand
sinks to the bottom. A second horizontal borehole is provided above the first borehole,
to an upper part of the cavity, to withdraw water and oil. Once the bitumen is removed,
thickened tailings recovered from the portion of the oil sands slurry that was sent
to surface for processing are placed back via the second borehole in the upper part
of the cavern.
[0004] Another method is disclosed in
WO 2008/064305, in which horizontal boreholes extending from a main access tunnel are used to recover
oil sands. Figure 6 of this publication discloses two horizontal boreholes, one above
the other. The lower borehole is a production well, through which a hydraulic mining
bit is operated to create a mined volume that enlarges upwardly, until it reaches
the level of an upper sand injection well, at which point mining is stopped and sand
is injected from the upper well. Initially the sand injection well can also be used
to create a small mined volume at its toe, above and separate from the mined volume
at the toe of the production well. The upper mined volume can then be filled with
sand slurry and pressurized, to assist the hydraulic mining process being applied
from below. In a variant of the known method the lower production and upper sand slurry
injection well can also be operated simultaneously, wherein the sand slurry injection
well sticks out into the cavity and sprays a stream of tailings slurry into the cavity.
[0005] International patent publications No.
WO 2010/000729 and
WO 2010/000736 disclose methods of producing hydrocarbon fluid from a layer of oil sand, wherein
a plurality of vertical injection/refill boreholes and a discharge borehole having
a substantially horizontal borehole section are operated.
[0006] However, there is still a need for an improved method of producing hydrocarbon material
from an oil sands layer combined with reinjection of refill material.
[0007] In accordance with the invention there is provided a method of producing hydrocarbon
material from a layer of oil sand located in an earth formation, the layer of oil
sand having a thickness and extending in an extension direction for more than its
thickness, the method comprising:
- creating a borehole arrangement in the earth formation, including a production borehole
having a production borehole section extending in a production borehole direction,
and a refill borehole having a refill borehole section extending in a refill borehole
direction, wherein both the production and the refill borehole directions are deviating
less than 45 degrees from the extension direction;
- creating a cavity in the layer of oil sand, the cavity being in fluid communication
with the production borehole section;
- extending the cavity by operating fluid jetting means to jet a stream of fluid against
a wall of the cavity, to obtain a slurry comprising fluid, hydrocarbon material, and
sand;
- withdrawing the slurry from the cavity via the production borehole to a processing
facility for processing the slurry; and
- injecting refill material into the cavity via the refill borehole section,
wherein the refill borehole section extends below the production borehole section.
[0008] Refilling from below is advantageous for a controlled refill operation. When oil
sand production and refill operations are carried out simultaneously, it will be preferred
to maintain a certain distance between the area of the cavity from which oil sand
is produced, and the area of refill. E.g., the distance along the extension direction
can be 20 m or more, preferably 50 m or more, such as 100 m or more. It is likely
that the cavity at least partially collapses over such distances, so that refill from
above is hampered or impossible. Refilling from above moreover requires a casing/lining
to extend into the cavity for a significant distance, but there is no proper support.
Reference is made in this regard to Figure 8 of
WO 2008/064305, showing such an undesirable operation. Also in the case of discontinuous operation,
wherein refill material is injected after a certain cavity was produced, there is
a risk of (partial) collapse of the cavity. Providing the refill borehole below the
production borehole protects the refill borehole against a potential collapse of the
cavity, and refill can still take place. Refill material can be pumped with excess
pressure in to the cavity in a controlled way from below.
[0009] In one embodiment of the invention, the production borehole can be a combined injection
and discharge borehole. An injection borehole is a borehole through which the fluid
jetting means is operated during normal operation. A discharge borehole is a borehole
through which a slurry comprising oil sand is transported to surface during normal
operation. A combined injection and discharge borehole serves for both functions.
Such a combined borehole is for example disclosed in the above- referenced paper by
Tannant et al., or in WO 2008/064305, both incorporated herein by reference.
[0010] In another embodiment, the production borehole is a discharge borehole, and the borehole
arrangement further includes an injection borehole separate from the discharge borehole.
The injection borehole suitably also has an injection borehole section extending in
an injection borehole direction deviating less than 45 degrees from the extension
direction. Preferably the discharge borehole section extends below the injection borehole
section. In this manner, hydrocarbon-containing slurry that is formed in a lower part
of the cavity by the erosive action of the fluid jetting means and under the influence
of gravity, can be effectively removed via the discharge borehole arranged below the
fluid injection borehole, i.e. in a lower part of the cavity.
[0011] Preferably pressure in the cavity, while the fluid jetting means is operated, is
lower than the bubble point pressure in the pristine oil sands layer before the cavity
is created therein, in particular 50% or less of the pristine pressure, more in particular
20% or less. Oil sands layers can have gas present, e.g. methane. The gas can e.g.
be adsorbed or dissolved. Lowering the pressure below the pressure at which gas can
be released from pores in the sand matrix (which pressure is referred to as bubble
point pressure) can lead to damage to the sand matrix, and to the loss of strength
of the oil sands, at the walls of the cavity. Removal of material by a hydraulic jet
becomes much easier, and the disintegrated oil sand will sink to the bottom of the
cavity.
[0012] In one embodiment, fluid is also injected into the cavity via the discharge borehole.
A particular purpose of this is for stirring or mobilizing the slurry and breaking
of any larger lumps of material in the area of the cavity from which the slurry is
withdrawn via the discharge borehole.
[0013] In one embodiment, no injection or discharge borehole in fluid communication with
the cavity is operated, which borehole is a vertical or near-vertical borehole. Near-vertical
means that the average angle between the vertical and the borehole from surface to
cavity is less than 45 degrees. The present invention allows to excavate a layer of
oil sands using deviated boreholes, with horizontal or near-horizontal borehole sections
in the oil sands layer for extended distances, and thus without the need for a multitude
of vertical or near-vertical wells.
[0014] Suitably the discharge borehole is provided with a liner of a length adapted to be
changed, and the injection borehole is provided with injection tubular of a length
adapted to be changed, and wherein both the lengths of the liner and of the injection
tubular are changed in correspondence with the extension of the cavity. The tubular
can for example be a fluid injection tubular or a liner.
[0015] The length of such a tubular can be changed by a shortening device. For example,
the step of shortening the liner can comprise operating a cutting device to cut the
liner. The liner can also be shortened by the action of a fluid jet, or by any other
means, e.g. by milling, explosives, or a laser. Shortening can be done by removing
coarse discrete pieces of the liner, such as at suitable time intervals, or by producing
small chips of the liner material. To this end the liner is suitably made from a suitable
material for shortening. The liner can be made of metals softer than steel, e.g. aluminium.
Preferably the liner is made of a non-metal material, and in particular the liner
can be made of a plastics material, such as a material comprising 50 wt% or more of
a polymer.
[0016] In one embodiment the discharge borehole is provided with a pump for pumping the
slurry via the discharge borehole to the processing facility, preferably the pump
is sealed relative to an inner surface of the liner. The pump can be axially movable
through the discharge borehole, and moved in correspondence with changing the length
of the liner. The pump can e.g. be driven by electricity, but also by a stream of
fluid pumped through a conduit extending through the discharge borehole. In the latter
case, at least a portion of said stream of fluid is suitably injected into the slurry
of fluid and oil sands present in the cavity, e.g. for stirring.
[0017] The stream of refill material can comprise tailings that are separated in and transported
from the processing facility to the cavity.
[0018] Preferably the refill borehole section is arranged near or at the lower end of the
cavity or just below, e.g. 0-10 m below. There it is nearly unaffected by a (partial)
collapse of the cavity.
[0019] In a preferred option inserting a stream of refill material into the cavity comprises
providing the refill borehole section with a casing. The casing protects against collapse
of the borehole. After extending the cavity for a selected length, the casing is perforated
within that length, and refill material is pumped through the perforations.
[0020] The invention will be described hereinafter in more detail, and by way of example,
with reference to the accompanying drawings in which:
Fig. 1 schematically shows an example of a production unit for use in an embodiment
of the method of the invention;
Fig. 2 schematically shows a detail of the production unit of Fig. 1;
Fig. 3 schematically shows another example of a production unit for use in an embodiment
of the method of the invention;
Fig. 4 schematically shows a top view at surface of a production field using embodiments
of the present invention; and
Fig. 5 schematically shows another example of a production unit for use in an embodiment
of the method of the invention;.
[0021] In the Figures, like reference numerals relate to like or similar components.
[0022] Referring to Figs. 1 and 2 there is shown an earth formation 1 containing an oil
sands layer 2 located between an overburden layer 4 above the oil sands layer 2 and
an underburden layer, shown as a layer of rock material 6, such as limestone, below
the oil sands layer 2. Earth formation below the oil sands layer is referred to as
underburden. The oil sands layer 2 has respective upper and lower boundaries 20, 22
extending generally horizontally in this example. An overburden can for example be
between 50 and 1000 m thick, in particular between 100 and 800m. The layer of oil
sands extends in an extension direction 21, in particular a non-vertical extension
direction, in this example horizontally between an overburden and an underburden.
The layer of oil sands has a thickness defining a thickness direction 21a, which is
in this example vertical. The extension direction 21 is different from, often perpendicular
to, the thickness direction, and is in this example in the horizontal plane. The layer
extends more in the extension direction than its thickness, typically for more than
twice its thickness, such as for more that 5 or 10 times its thickness, or even more.
It will typically extend for less than 10000 times its thickness.
[0023] The thickness can for example be between 1 m and 500 m, in particular between 5 m
and 200 m, such as between 10 and 100 m, and may vary along the extension direction.
It will be understood that the layer can extend along a flat or curved plane.
[0024] An injection borehole 8 is provided, which in this example is a deviated borehole
extending from an injection station 10 at the earth surface 11 to a cavity 12 formed
in the layer of oil sands 2. The cavity has an upper portion 12a containing gas (e.g.
CO2, methane, air, and/or H2S) and a lower portion 12b containing a mixture (referred
to hereinafter as "slurry") 13 of fluid (preferably water) and oil sands particles
comprising hydrocarbon material and sand, which may partly or fully separate in the
slurry.
[0025] A deviated discharge borehole 14, which is also referred to as production borehole,
extends from a production station 15 at the earth surface to the cavity 12 whereby
the production station 15 is horizontally spaced from the injection station 10 and
debouches into the lower cavity portion 12b at some distance above the bottom of the
cavity.
[0026] The injection borehole 8 and the discharge borehole 14 each have an upper section
16, 16a extending downwardly, such as substantially vertically from surface, and a
non-vertical lower section 18, 18a. The expression lower borehole section is used
for a borehole section that is further away from surface along the borehole trajectory
than an upper borehole section. The lower borehole section 18 of the discharge borehole
extends in a discharge borehole direction, below the injection borehole section 18a
of the injection borehole 8, extending in an injection borehole direction. Each of
the injection and discharge borehole directions is a selected direction within the
layer 2, in this example an azimuthal direction from the cavity 12. The intersection
between the lower borehole section 18a of the injection borehole 8 and the cavity
12 defines a front surface 23 of the cavity 12.
[0027] Each of these selected directions suitably is a direction within the layer. The lower
sections of the injection and discharge boreholes each deviate less than 45 degrees
from the extension direction 21, wherein the angle is preferably counted in a vertical
plane through the extension direction. These borehole sections preferably extend substantially
parallel to the upper boundary 20 and/or lower boundary 22 of the oil sands layer
2. Suitably the selected direction substantially coincides with the extension direction,
so that the cavity is extended within the layer, substantially parallel with its upper
and/or lower boundary, for more than the layer thickness, such as for between 2 and
5000 times the layer thickness. The expression "substantially parallel" herein accounts
for the precision with which deviated boreholes can be drilled in an underground layer.
In the present example the lower sections 18, 18a extend substantially horizontally.
The expression "direction" is used herein to refer to a direction without specifying
the sense of direction, unless otherwise indicated. The extension direction may deviate
somewhat from the horizontal plane due to geological circumstances, as can the directions
of the lower sections 18, 18a in the practice of directional drilling. It is desired
to arrange the lower sections such that they extend for a substantial length within
the oil sands layer, such as for between 50 and 5000 m, in particular between 100
and 2000 m. The injection and discharge borehole sections preferably deviate less
than 30 degrees from the extension direction, more preferably less than 15 degrees.
It can alternatively be said that the injection and discharge borehole sections preferably
are substantially horizontal borehole sections. A substantially horizontal borehole
section deviates 30 degrees or less from the horizontal plane, more preferably 15
degrees or less. The selected direction can be at least 45 degrees away from the thickness
direction, in particular at least 45 degrees away from the vertical. All angles specified
herein are to be understood as absolute (positive) values, unless otherwise specified.
It will be understood that when the cavity is extended along the injection and/or
discharge borehole directions that deviate by a certain angle from the extension direction,
the cavity is at the same time extended in the extension direction.
[0028] The expression "extending below" in relation to two borehole sections is used to
refer to the situation that one borehole section extends at a greater vertical depth
than the other. Preferably the two borehole sections extend substantially along the
same trajectory in a vertical projection onto the earth's surface, which can for example
mean that the horizontal deviation in such projection is 50 m or less, preferably
10 m or less, more preferably 5 m or less, such as 2 m or less.
[0029] The vertical distance between the discharge borehole section and the injection borehole
section thereabove is suitably in the range of 1-100 m, preferably between 2 and 50
m, such as between 5 and 30 m.
[0030] The upper borehole sections 16, 16a are each provided with a conventional casing
(or liner) 24, 24a, whereas the lower borehole sections 18, 18a are each provided
with a liner 26,26a, e.g. of plastics material, for example glass fibre reinforced
plastic. The liner 26 extends a minimal distance into the cavity 12. Furthermore in
this example, a jet pump 28 is positioned in the liner 26 in a manner that the jet
pump 28 is sealed relative to the inner surface of the liner 26 and is axially movable
through liner 26. A fluid conduit 30 for driving the jet pump 28 extends from the
production station 15 through the casing 24 and the liner 26 to the jet pump 28. When
driven by fluid, such as water, pumped through the fluid conduit 30, the jet pump
28 is arranged to pump the slurry 13 of fluid and particles from the lower cavity
portion 12b, via the annular space 27 between the fluid conduit 30 on one hand and
the liner 26 and casing 24 on the other hand, to the production station 15. The jet
pump 28 is thereto provided with one or more flow channels 32 (Fig. 2) allowing the
slurry to flow in axial direction through the jet pump 28. The fluid conduit 30 extends
further from the jet pump 28 through liner 26 to the cavity 12. A lower end part 34
of the fluid conduit 30 is provided with a shortening device, in this embodiment cutter
36, for shortening the liner 26, one or more nozzles 38 for initially forming the
cavity 12 and/or for stirring the slurry present in the cavity 12, and a bit or mill
39 for crushing lumps of rock material that may be present in the cavity 12. Conduit
30 can be rotatable.
[0031] Alternatively, the discharge borehole can also be set up for operation in 'reverse
circulation', where driving fluid for the jet pump is pumped from surface via the
annulus, and slurry is pumped via an inner tubular like reference numeral 30. Liner
26 and jet-pump 28 are suitably designed to withstand the pressure of driving fluid,
e.g. a plastic liner of sufficient strength can be used. An advantage of this reverse
circulation operation is that there is no wear of the slurry in the annulus. Also
the slurry travelling inside a slowly rotating production pipe will not be able to
settle down.
[0032] An injection string 40 for injecting fluid into the cavity 12 extends from the injection
station 10 via the injection borehole 8 into the cavity 12, the injection string 40
having a lower end provided with fluid jetting means in the form of fluid jetting
head 41 comprising jetting nozzles 42, the fluid jetting head being located in the
upper portion 12a of cavity 12. An annular seal 43 (e.g. such as used in a rotating
head) is arranged in an upper part of the first injection borehole 8 to seal the annular
space formed between the injection string 40 and the wall or casing of the first injection
borehole 8. The injection string 40 can also be provided with a shortening device
(not shown) for shortening the liner 26a extending into the cavity 12, which can be
similar to the shortening device 36 of the conduit 30. Injection string 40 can be
rotatable.
[0033] In accordance with the invention there is further provided a refill borehole 108
which in this example is also a deviated borehole extending from a refill station
110 at the earth's surface 11 to the lower end of the cavity 12. The refill borehole
108 has an upper section 116 extending downwardly, such as substantially vertically,
and a lower section 118. The lower borehole section 118 extends below lower non-vertical
section 116 of the discharge borehole 14, such as between 1 and 20 m below the lower
section in particular between 2 and 10 m, preferably substantially parallel therewith.
The lower borehole section preferably extends substantially along the lower boundary
22, such as within 5 meters from the boundary, preferably within 1 m from the boundary.
The refill borehole 108 on this embodiment is provided with casing 124, preferably
a steel casing, and with an injection string 148 for refill material, which can be
rotatable. The injection string is optional; the injection borehole could alternatively
be arranged without such string, so that the injection slurry is passed through the
casing. The refill borehole section preferably deviates less than 30 degrees from
the extension direction, more preferably less than 15 degrees. It can alternatively
be said that the refill borehole section preferably is a substantially horizontal
borehole section.
[0034] Figure 1 shows the invention with several of the components at a stage of normal
operation after some time of operation. The cavity 12 is being extended by operating
the fluid jetting means using nozzles 42 via the injection borehole to jet a stream
of fluid against a wall of the cavity, in particular the front surface 23, starting
from an initial cavity 12' in an azimuthal direction, along the parallel lower borehole
sections 18 and 18a. The initial cavity 12' that was created in the layer of oil sands
2 is indicated with a dashed line. Suitably the jetting fluid is a low solids fluid,
i.e. it contains substantially no solids, such as less than 10 wt% or less than 1
wt% of solids. Water is a suitable jetting fluid. The water can contain one or more
additives such as a surfactant, but this is not required. Reference to water herein
is to a fluid that contains at least 80 wt%, preferably at least 90 wt% of pure water.
The temperature of the jetting fluid (water) can be selected or modified such as by
heating. For example, water at a temperature of 25 °C or above, or 40 °C or above,
can be used.
[0035] Thus the front surface 23 of the cavity has been moving in the extension direction,
with the sense of direction generally uphole, defined by the injection borehole's
sense of direction towards surface. As a result, the lower borehole sections 18, 18a
have become shorter compared to an initial length indicated at 18' and 18a'. The liners
26 and 26a have been shortened at the side of the cavity 12 in correspondence with
shortening of the lower borehole sections 18,18a. The fluid conduit 30 with the jet
pump 28 connected thereto has been pulled upward through discharge borehole 14 over
a distance about equal to the reduction in length of liner 26, and likewise the injection
string 40 has been retracted, so that the nozzles stay in sufficient proximity to
the front wall 23 so that the fluid jetting is effective to extend the cavity. Suitably,
the nozzles are at a distance of between 0.5 m and 15 m from the wall against which
the fluid jet is exerted.
[0036] During normal operation of the system of Figs. 1-2, the injection borehole 8 and
the discharge borehole 14, and the refill borehole are drilled into the oil sands
layer 2 using one or more conventional drilling rigs, and completed as needed, such
as with the casings 24, 24a and liners 26,26a. The injection station 10 and the production
station 15 are installed at their respective positions as indicated in Fig. 1. In
a next step, the initial cavity is created. The fluid conduit 30 with the jet pump
28 connected thereto is lowered through the discharge borehole 14 until end part 34
of the fluid conduit 30 extends just beyond the far end of the liner 26. Water at
high pressure is then pumped from the production station 15 into the fluid conduit
30 so that the pumped water is jetted through the nozzles 38 to impact the formation
at the end of the liner 26 with great force. Alternatively, the discharge borehole
is operated in reverse circulation as discussed above. If desired, the fluid conduit
30 is simultaneously rotated about its longitudinal axis to induce the bit or mill
39 to crush the rock formation. As a result the oil sands layer 2 is gradually excavated
so that the cavity 12' and the slurry 13 of water and oil sand particles are initially
formed. Furthermore, by virtue of pumping of water through fluid conduit 30, the jet
pump 28 is operated to pump the slurry 13 from the cavity 12' via the flow channels
32 of the jet pump 28 and via the annular space 27 between the fluid conduit 30 and
the liner 26/casing 24, to the production station 15.
[0037] Alternatively or in addition, the initial cavity 12' is created by fluid jetting
via the injection borehole, optionally using equipment and operation similar to what
was described above for the discharge borehole.
[0038] In an alternative embodiment, the cavity 12' is initiated by underreaming, via injection
borehole 8 or discharge borehole 14, or even from a separate borehole (not shown)
such as from a vertical borehole above the cavity.
[0039] Once the cavity 12 is sufficiently large so that fluid communication between the
cavity 12 and the injection borehole 8 is established, in particular so that both
boreholes 8,14 are intersecting the cavity 12, the injection string 40 is operated
via the first injection borehole 8. Fluid, preferably water, is pumped at high pressure,
such as between 10 and 500 bar, in particular between 100 and 200 bar from the injection
station 10 into the injection string 40. The pumped water is jetted through the jetting
nozzles 42 and impacts the wall of the cavity 12 with great force. As a result, the
oil sands layer 2 is further excavated and the slurry 13 of water and oil sand particles
is continuously formed in the cavity 12. The size of the cavity increases as jetting
of water through the nozzles 42 continues. Water is pumped at a suitable pressure
from production station 15 into the fluid conduit 30 to operate the jet pump 28. Thereby,
the jet pump 28 withdraws the slurry of fluid and particles from the lower cavity
portion 12b, via the annular space between the fluid conduit 30 and the liner 26 or
casing 24, and the flow channels 32 of the jet pump 28, to the production station
15. Arrows 115 (Fig. 2) indicate the direction of flow of water pumped through fluid
conduit 30, and arrows 116 indicate the direction of flow of the slurry of water and
oil sand through said annular space and channels 32. Note that in case of reverse
circulation, below the pump arrows 115 and 116 have the same direction as circulating
conventional. Above the pump the direction of the arrows reverses. Injection of fluid
via the injection well and withdrawal of slurry via the discharge well occurs simultaneously.
[0040] If desired, pumping of the slurry of fluid and particles from the cavity 12 to the
production station 15 can be enhanced by maintaining a suitable elevated pressure
in the cavity 12. The pressure can be adjusted by influx and/or outflux of gas, taking
into account gas that is released from the matrix below the bubble point. Preferably
however the pressure in cavity 12 is kept lower than the pressure in the pristine
oil sands layer 2 before the cavity 12, 12' is created therein, such as at or below
90%, or at or below 80%, of the hydrostatic pressure in the pristine oil sand layer.
The pressure can be 5 bar below the bubble point pressure, or lower. At lower pressure,
the gas contained in the oil sands layer can be released, and the sands matrix loses
strength and is jetted away into a slurry relatively easily.
[0041] Furthermore, a portion of the water pumped through fluid conduit 30 is injected/jetted
into the lower cavity portion 12b through nozzles 38 in order to achieve some stirring
of the slurry 13 in the cavity 12, simultaneously with fluid jetting via the injection
borehole.
[0042] Jetting of water through nozzles 42 is continued so as to extend the cavity 12 in
the azimuthal direction of the lower borehole section 18 whereby the front surface
23 of the cavity moves in said azimuthal direction. As a result, a portion 117 of
the liner 26 (Fig. 2) gradually becomes protruding into the cavity 12. In order to
reduce the length of, or completely remove, the protruding liner portion 117, the
cutter 36 is operated to cut the protruding liner portion 117 at time intervals selected
in accordance with the speed of movement of the front surface 23 in the azimuthal
direction. The fluid conduit 30 is moved upwardly in correspondence with shortening
of the liner 26 whereby the jet pump 28 slides along the inner surface of the liner
26. If desired, the fluid conduit 30 is rotated to induce bit 39 to crush rock particles
that may be present in the cavity 12. Likewise, the portion of the liner 26a of the
injection borehole section 18a protruding into the cavity can be shortened using a
cutter (not shown). Alternatively, the liner 26 and/or 26 a can be shortened in another
way, such as by using a fluid jet.
[0043] The amount of fluid flowing through the injection nozzles 42 can typically be in
the range of 50-5000 1/min, in particular between 100 and 1000 1/min, such as between
200 and 800 1/min. The amount of fluid flowing through the nozzles 38 can be in the
same range as the amount of water injection through the injection borehole. An aqueous
slurry that is formed and produced during operation can have a density of between
1100 and 1600 kg/m3. The pristine oil sand may for example contain between 1 and 50
wt% of hydrocarbons, based on total oil sand including hydrocarbons, in particular
between 2 and 30 wt%, such as between 5 and 20 wt%. The width of the cavity in the
horizontal plane perpendicular to the direction of the injection borehole 8 depends
on the precise orientation and operation of the nozzles, and is typically in the range
of 1-50 m, such as between 10 and 40 m. The jetting nozzles can be arranged to jet
in a fixed direction against a front, side, rear, upper, and/or lower wall of the
cavity, or can be movable such as rotatable. The growth of the cavity in the extension
direction can for example be in the range of between 10 cm/day to 10 m/day, so for
example the liners need to be shortened by approximately 1 m/day.
[0044] In this way, the hydrocarbon material from the oil sand layer can be produced in
a continuous process, by simultaneous operation of the injection and discharge borehole
sections, and over an extended length, such as for 20 m or more, 50 m or more, 100
m or more, even 500 m or more, and for extended periods of time, such as for a day
or more, a week or more, a month or more, even a year or more.
[0045] It will be understood that for very thick layers of oil sands, more than one injection
borehole can be arranged at various heights. Each additional injection borehole can
be substantially similar to injection borehole 8 as described above, with a non-vertical
lower section extending substantially above the non-vertical lower section 18a, the
injection borehole 8 thus extending below additional injection boreholes. This may
be useful when the vertical thickness of the oil sands layer 2 is 30 m or more, or
50 m or more.
[0046] If the operation is conducted as described hereinbefore, the earth's surface may
subside above the cavity as a result. On the other hand, tailings are produced to
surface, which are separated from hydrocarbon material and water, and it is typically
desired to reinject tailings for disposal, and to avoid or reduce subsidence.
[0047] To this end the refill borehole is provided. In a preferred operation, the slurry
13 of water and oil sand is transported from the production station 15 to a separation
plant (not shown) for separating hydrocarbon material and tailings from the slurry.
The hydrocarbon material is recovered as product and optionally subject to further
transport, purification, separation, treatment and/or processing to further products.
Alternatively the production station 15 and the separation plant can be integrated
in a single unit. The production station and optionally the separation plant form
part of a production facility. Suitably, at least part of the tailings is used to
refill the cavity 12. The tailings can comprise solids like sand and/or clay. It can
be desired to re-use part or all of the sand produced to surface for other purposes
than reinjection, and to reinject only or predominantly other tailings like for example
clay. For refilling, tailings are pumped into the rear portion of cavity 12 (such
as beginning at the initial cavity 12') via the injection string 148. Suitably, first
a cement plug 150 is provided, and then perforations 154 are created in the casing
at the desired locations, through which tailings are pumped into the cavity. In this
manner, the rear portion of cavity 12 is gradually filled with the body of tailings
149. In the context of the present description, any reference to "the cavity" is meant
to include the upper cavity portion 12a, the lower cavity portion 12b, the initial
cavity 12', and the rear portion filled with refill material such as tailings or tailings.
[0048] Reference is now made to Figure 3, showing schematically an alternative example of
operating the present invention. In this example, the operation is started as described
above with reference to Figures 1 and 2. The extension of a cavity in the extension
direction 21 is stopped at a certain moment, such as when a certain horizontal length
of the cavity is reached, or when the constitution of the oil sands layer changes.
The tubulars 30,40 are retracted a certain distance in the injection and discharge
(production) boreholes, such as by 1 to 100 m, preferably 5-50 m, e.g. 20 m, before
a further cavity is created. The liners 26,26a can e.g. be cut off and abandoned.
Cement plugs are suitably set in between cavities along the pathway of the injection
and discharge boreholes. In this way pillars 170 are created between cavities to prevent
or minimize subsidence, and/or to avoid producing areas that do not contain sufficient
hydrocarbons or are otherwise not interesting to produce. Figure 3 shows a first cavity
12a that is fully produced and refilled with tailings 149; a second cavity 12b created
and produced after the first cavity 12a, and being refilled with tailings 149; and
a third cavity 12c in production, substantially as described with reference to Figures
1 and 2.
[0049] Figure 5 shows schematically an embodiment in which a production borehole in the
form of a combined injection and discharge borehole 514 is arranged above a refill
borehole 108. The lower section 518 of the combined injection and discharge borehole
514 extends substantially horizontally above the lower section 118 of the refill borehole
108. During operation, fluid driving the jetting head 41 is pumped through tubing
530, and oil sand slurry that is obtained in the cavity 12 is produced via the annulus
527 between the liner/casing 526 and the tubing 530, as indicated by the arrows. Refill
material is injected via perforations 154 substantially as discussed with reference
to Figure 1. Parts having the same reference number as parts in Figure 1 are substantially
similar in form and operation. Other parts shown in Figure 1 can be installed as well,
e.g. a jet pump in the production well, and have not been shown for clarity.
[0050] In the context of the present description, an assembly comprising a cooperating production
borehole and refill borehole, injection, production, refill station and one or more
cavities created along these boreholes is referred to as a production unit. A production
field comprises one or more production units. An injection, production and/ or refill
station can include a drilling rig.
[0051] Referring to Figure 4, there is schematically shown a top view at surface of a layout
of a production field 201 for recovering hydrocarbons from an underground oil sands
layer. The Figure shows a plurality of production units 210, 212, 214, 216, 218, 220,
222, 224, 226, 228, 230, 232, 234, 236, 238, 240, 242, 244, 246, 248 in four field
sections 251,252,253,254 on either side of a backbone 260. Each production unit can
be substantially similar to and operated as described hereinbefore with reference
to Figs. 1-3, and has an injection borehole above a discharge borehole above a refill
borehole, overlapping in the top view.
[0052] The production units are in different stages of operation. The solid lines, e.g.
270, indicate a section of a production unit that is producing hydrocarbons (slurry)
to a separation plant 275, whereas the dashed lines, e.g. 280, indicate an area that
has already been produced and is abandoned, or refilled. Units 218, 228, 230 and 240
were the first units to produce and have already stopped production. Units 210,220,238
and 246 just started production. Remaining units are in an intermediate stage. At
282, boreholes for a future production unit are being drilled. The area 285 that is
generally defined by the dashed lines can be referred to as reclaimed area of the
production field, and the area 288 generally defined by solid lines can be referred
to as producing area of the production field 201. It shall be clear that only one,
two or three of the field sections 251-254 may be arranged, or may be developed at
different periods in time, and that more or less production units than shown can be
provided in a field section.
[0053] The backbone provides for transport of fluids (slurry, tailings) between the production
units and the separation plant 275 via suitable pipelines/conduits. It concentrates
the surface equipment in a relatively narrow surface area or streak, for easy accessibility
and minimum surface impact. This area is moreover typically not or only modestly affected
by subsidence.
[0054] The backbone can be between 0.1 and 50 km long, preferably between 0.5 and 20 km,
and may grow in the lifetime of a field, which is suitably developed starting with
production units close to the separation plant 275. The lateral spacing between production
units can be between 10 m and 500 m, preferably between 20 m and 100 m. They can in
particular be arranged such that the cavities along adjacent production units join
or overlap, or remain separate. Each production unit may have a length of between
50 and 5000 m, in particular between 100 and 2000 m. Areas where it is not desired
or possible to produce oil sand can be avoided in the layout.
[0055] With the method described above it is achieved that hydrocarbon fluid is produced
from the oil sands layer without removing the overburden layer. Moreover, by refilling
the cavities with tailings it is achieved that any subsidence of the overburden layer
is reduced to a minimum. In a preferred embodiment, the cavities are refilled with
tailings from the produced slurries of water and oil tailings after cleaning at the
separation plant. Suitably a binding material like cement is mixed into the tailings.
[0056] In the examples described above, the discharge borehole is provided with a single
pump (jet pump 28) for pumping the slurry of fluid and oil sand particles via the
discharge borehole to the production station at surface. However, depending on the
depth of the cavity and/or other operational parameters, a single pump may not suffice
to pump the slurry to surface at an efficient flow rate. In that case, one or more
additional pumps can be applied in the discharge borehole. For example, the upper
section of the discharge borehole can be provided with a single-stage or multi-stage
centrifugal pump driven by a hydraulic or electric motor, to pump the slurry to surface.
Such additional pump can be positioned, for example, in the lower end part of the
casing provided in the discharge borehole, just above the liner. Alternatively or
in addition, an additional jet pump or gas lift can be applied.
[0057] In the examples described above, various boreholes extend from surface locations
mutually spaced in horizontal direction. In an alternative arrangement, the boreholes
can extend as deviated boreholes from a fewer or a single surface location, or as
branch boreholes of a multilateral borehole. Such arrangement can be attractive in
applications whereby the surface area is difficult accessible, for example if the
oil sands layer is located below a body of water or a swamp area.
1. A method of producing hydrocarbon material from a layer of oil sand located in an
earth formation, the layer of oil sand having a thickness and extending in an extension
direction for more than its thickness, the method comprising:
- creating a borehole arrangement in the earth formation, including a production borehole
having a production borehole section extending in a production borehole direction,
and a refill borehole having a refill borehole section extending in a refill borehole
direction, wherein both the production and the refill borehole directions are deviating
less than 45 degrees from the extension direction;
- creating a cavity in the layer of oil sand, the cavity being in fluid communication
with the production borehole section;
- extending the cavity by operating fluid jetting means to jet a stream of fluid against
a wall of the cavity, to obtain a slurry comprising fluid, hydrocarbon material, and
sand;
- withdrawing the slurry from the cavity via the production borehole to a processing
facility for processing the slurry; and
- injecting refill material into the cavity via the refill borehole section,
wherein the refill borehole section extends below the production borehole section.
2. The method of claim 1, wherein the production borehole is a combined injection and
discharge borehole.
3. The method of claim 1 or 2, wherein the production borehole is a discharge borehole,
and wherein the borehole arrangement further includes an injection borehole having
an injection borehole section extending in an injection borehole direction deviating
less than 45 degrees from the extension direction, preferably wherein the discharge
borehole section extends below the injection borehole section.
4. The method according to any one of claims 1-3, wherein the pressure in the cavity,
while the fluid jetting means is operated, is lower than the pressure in the pristine
oil sand layer before creating the cavity therein, preferably lower than the bubble
point pressure.
5. The method according to any one of claims 1-4, wherein fluid is also injected into
the cavity via the discharge borehole.
6. The method of any one of claims 1-5, wherein no borehole in fluid communication with
the cavity is arranged, which borehole is a vertical or near-vertical borehole.
7. The method of any one of claims 1-6, wherein the production borehole is provided with
a tubular of a length adapted to be changed, and wherein the length of the tubular
is changed in correspondence with the extension of the cavity in the extension direction.
8. The method of any one of claims 1-7, wherein the production borehole is provided with
a pump for pumping the slurry via the discharge borehole to the processing facility,
preferably wherein the pump is sealed relative to an inner surface of the liner.
9. The method of claim 8, wherein the pump is axially movable through the production
borehole, and wherein the method further comprises axially moving the pump through
the production borehole in correspondence with changing the length of the liner.
10. The method of any one of claims 8-9, wherein the pump is driven by a stream of fluid
pumped through a conduit extending through the production borehole, preferably
wherein at least a portion of said stream of fluid is injected into the slurry of
fluid and oil sand present in the cavity.
11. The method of any one of claims 1-10, wherein at least one of the production borehole
section and the refill borehole section extends substantially horizontal, preferably
wherein both extend substantially horizontal.
12. The method of any one of claims 1-11, wherein the refill material comprises tailings.
13. The method of claim 12, wherein the refill material is transported from the processing
facility to the cavity.
14. The method according to any one of claims 1-13, wherein operating the fluid jetting
means and inserting refill material are carried out simultaneously.
15. The method of any one of claims 11-12, wherein inserting refill material into the
cavity comprises, after extending the cavity for a selected length, perforating the
casing within that length, and pumping refill material from the refill well through
the perforations.