DESCRIPTION OF THE INVENTION
[0001] The invention relates to the field of the construction, in particular to ways and
methods of the erection and construction of cast-frame houses with a different number
of floors and multilayer walls, which do not require the heat insulation, additional
treatment and finish of internal and external surfaces.
[0002] There is the method of multilayer wall production, including the formation of a rigid
spatial frame with constructional grids for the attachment of concrete layers and
connecting elements, the installation of the heat insulation material slab in this
frame. Also this method includes subsequent fixation of the frame on the foundation
and the infliction of inner and outer concrete layers by the guniting. Herewith the
formation of the frame is carried out in a horizontal position with a size of the
floor, taking into account the thickness of the wall with a simultaneous placement
of the heat insulation material inside the frame. And in the case of the frame formation
the heat insulation material slab is amplified by connecting, as those used reinforcing
bars, rigid spatial bracings, bar bracings, technological bars. Herewith reinforcing
bars and rigid spatial bracings are placed in pre-made holes in the heat insulation
material slab, bar bracings are passed through the heat insulation material at the
angle of 45° to its plane and technological bars are installed and fixed on the surface
of the heat insulation material with the formation of the thermoreinforcing package,
used as a permanent formwork (see the invention patent
RU Nº 2095526, K

. E 04 B 2/86, published in 1997). This fairly widespread method of wall erection
contains a large number of sequential labor-intensive operations, leading to a rise
in the cost of a construction and waste of time for the erection of a building. Also
it has a narrow range of applications and is not intended for the erection of buildings
in earthquake zones.
[0003] Also there is the method of the manufacturing of multilayer construction product.
This method includes operations of alternate layer stacking in the framework, and
the concrete mixture is leveled in a horizontal plane flush with the first bead of
the permanent formwork after the stacking of the first fine concrete layer in the
permanent formwork. Then longitudinal reinforcement of the first layer is laid on
the first bead, and the heat-insulated layer of the light-weight concrete is laid.
This layer is located in a parallel plane with respect to the first layer. After the
concrete mixture is leveled in a horizontal plane flush with the second bead of the
permanent formwork, and the longitudinal reinforcement of the second layer is laid
on the second bead, the second layer of the fine concrete is laid. Finally the concrete
mixture is leveled in a horizontal plane flush with the shear of the permanent formwork,
simultaneous vibroforming is produced for all layers, and everything is retained until
mixture setting. Herewith the permanent formwork is enclosed in the hard jig (see
the invention patent
RU Nº 2307903, K

. E 04 C 1/40, published in 2007). This method allows to improve heat insulation properties,
increase the durability and reliability of construction panels, wall and buildings,
which are made of them. However, this method is not suitable for monolithic housing
and makes it impossible to erect buildings with high strength and aseismic stability.
[0004] Besides that there is the method of the erection of the precast-monolithic framework
of a multistory building, which includes floor-by-floor alignment axes installation
of unconsoled reinforced concrete columns, placement of assembly bridges, mounted
on supporting posts, in the spans between columns for the installation of prefabricated
carrier bearing elements of precast-monolithic cross frame beams of the girth of unconsoled
columns and the formwork for the formation of reinforced concrete monolithic spacer
longitudinal linking frame beams of the girth. Also this method includes laying on
carrier bearing parts of precast-monolithic cross frame beams in a design position
for the formation of the discs of per floor ceiling of multihollow reinforced concrete
slabs, installation of frame beam reinforcement, simultaneous laying of the high-strength
concrete around the interfloor ceiling with the formation of longitudinal spacer frame
beams and carrier precast-monolithic cross frame beams and dwelling units of floor-by-floor
ceiling. These units forms discs and are rendered monolithic with frame beams into
a coherent whole through concrete longitudinal joints. Dwelling units are adjacent
and based on every carrier precast-monolithic cross frame beam of adjacent multihollow
reinforced concrete slabs. With regard to the method, it also contains the exposure
of laid high-strength concrete, stripping of floor-by-floor ceiling after the concrete
will reach the design strength, and permutation of assemble bridges on the finished
stripping floor-by-floor ceiling for their subsequent use in the erection of next
floor-by-floor ceiling. Herewith the formation of every carrier precast-monolithic
cross fame beam proceeds in two stages, the first of them is the setting of supporting
elements in a design position with the bearing on posts of assembly bridges. As the
supporting elements are used the prestressed vibropressed reinforce concrete girder
with lateral stepped ledges, which are symmetrical to the longitudinal axis of the
girder. This girder is prefabricated and overlaps the cross bay between adjacent unconsoled
columns. And also the girder forms permanent formwork bottom of upper monolithic part
of this cross frame beam. The second stage involves the implementation of vertical
walls formation of mentioned permanent formwork and also the formation of concrete
longitudinal seams and depressions for cross reinforced key slots of upper monolithic
part of the cross frame beam of the girth. These seams and depressions have a common
working cavity of the box with the permanent formwork. So mentioned seams and depressions
are formed by means of the usage of this permanent formwork. This happens after the
installation of one of interfloor ceiling discs of adjacent prestressed vibropressed
multihollow reinforced concrete slabs in a design position on lateral stepped ledges
of prestressed vibropressed reinforced concrete girder of generators. These slabs
are in contact with each other and form the box of concrete longitudinal seams with
symmetrical longitudinal shelves with upper profiled surfaces, which are situated
in lower parts of their lateral surfaces. Slabs have longitudinal depressions on the
upper surface of the permanent formwork ends of multihollow reinforced concrete slabs
for the formation of cross reinforced key slots of the upper cast part of the mentioned
cross frame beam during the concreting (see the invention patent
RU Nº 2318099, K

. E 04 B 1/20, published in 2008). So the well-known method of the monolithic housing
involves the erection of monolithic building framework, consisting of posts and ceilings.
The area between them is filled with blocks or bricks, or panels (they are not made
monolithic with the frame work).
[0005] There is the method of multilayer wall formation, including the formation with the
usage of the formwork of three vertical layers of monolithic reinforced concrete.
These three layers are alternated by thermal insulation layers and sealed with each
other by rigid jumpers, which are not located coaxially (see the invention patent
RU Nº 2335604, K

. E 04 B 2/84, published in 2008). This method allows the erection of monolithic walls
of different thickness at a sufficiently high strength. But the method does not solve
the problem of building durability. Walls require additional finishing and subsequent
regular repair in the case of the erection, with the usage of this technology.
[0006] The most efficient technical solution is the method of building erection, involving
framework erection from reinforced concrete rendered monolithic precast elements.
Part of these elements are made on the technological line, which contains the equipment
for the concreting, systems for the feeding and installation of the reinforcement,
formwork with the strand longitudinal molding cavity under the appropriate designs,
produced at the same time, including molding surfaces and the pallet, which is installed
on discrete bearings with the rigid fixation in the central part of the length. Also
there is the possibility of directional slippage in both directions and the adjustment
of pallet altitudinal position on bearings for the rest of the length. And the pallet
is provided with mounting joints of the central board, which are placed along the
longitudinal axis of the pallet. The board forms formwork molding surface. Also the
pallet is provided with fixation joints, which are situated along longitudinal edges
of the pallet, and opening joints of longitudinal exterior folding boards, forming
other molding surfaces. Herewith the formwork is provided with cross molding cutting
removable terminal membranes (see the invention patent
RU Nº 2293822, K

. E 04 B 1/18, published in 2007). This method of building erection is technically
complex and requires a lot of additional operations and funds for the construction.
[0007] The present invention is directed to solve the technical problem of labor content
reducing and terms of building erection, improving of design flexibility of building
framework with monolithic walls, which do not require additional finishing and repair
of internal and external surfaces, improving of building operating characteristic,
simplifying of concrete pouring process during the erection of building walls, increasing
of the reliability, durability and aseismic stability of the construction.
[0008] The solution of this technical problem lies in the fact that this method of the erection
of the cast-frame building with decorative external finish involves foundation pouring,
reinforcing construction tying of the first floor, wall pouring of the first floor,
installation of frame beam reinforcement and pouring of ceilings and frame beams.
Also this method includes reinforcing construction tying of the second floor and subsequent
floors with the wall pouring, installation of frame beam reinforcement and pouring
of ceilings and frame beams of subsequent floors and roof erection. Herewith reinforcing
tabs, which are set vertically, and mounting lugs for formworks of walls are laid
preliminary in the foundation during foundation pouring. Reinforcing tabs are tied
to the reinforcement of lower floor walls, mounting lugs are set for the formwork
of walls during ceiling pouring. Reinforcing construction of walls is tied to reinforcing
tabs, leaving vertical apertures for windows and doors. Then wall formwork is put
down vertically on the reinforcement, and wall formworks are used, consisting of a
hollow cap and pallet. There is a wall blank in the pallet. This blank is made at
the factory and contains at least one decorative and one heat insulating layers, related
to each other by reinforcement elements, located with the decorative layer outside.
Reinforcement of wall supporting layer is situated in the hollow cap of wall formwork.
Then wall formworks are fixed in mounting lugs of the foundation by fixing extensions,
and voids around the reinforcement are filled with concrete inside hollow caps of
wall formworks, forming supporting concrete layer of building wall and leaving the
upper zone of wall formwork unfilled with concrete. This zone is adjacent to the heat
insulating layer of the wall blank. Herewith frame beam formworks are set in the upper
zone, which are not filled with concrete, after taking off wall formworks on supporting
concrete layer of the wall. These frame beam formworks are adjacent to the wall blank.
Fixing elements for roof framework are pledged in the last floor before ceiling pouring
of last floor. Angular zones are left free during building wall pouring, and then
these zones are laid with bricks or blocks. Ceilings between floors are erected simultaneously
with balconies, and the lathing of ceilings is mounted with the help of supporting
legs outside of building walls before the pouring. Last floor ceiling is erected simultaneously
with visors, and the lathing of ceilings is mounted with the help of supporting legs
outside of building wall before the pouring. Void formers are used in the process
of ceiling pouring. The formwork is installed on the foundation or ceiling of the
regular floor. This formwork is adjusted vertically and horizontally by support-screw
regulators and fixing extensions of the formwork.
[0009] The invention is illustrated by drawings. Fig. 1 shows the building foundation with
reinforcing tabs and mounting lugs for the formwork in isometry. Fig. 2 indicates
the same with reinforcement for walls. Fig. 3 illustrates the same with formworks,
which are poured with concrete. Fig. 4 indicates the same with taken formworks. Fig.
5 shows the same with installed formworks and the reinforcement of frame beams. Fig.
6 indicates the same with the ceiling lathing of the first floor. Fig. 7 illustrates
the same with the substrate on the ceiling lathing. Fig. 8 shows the same with void
formers, reinforcement and mounting lugs for the formwork. Fig. 9 indicates the same
with ceilings, which are poured with concrete. Fig. 10 shows the same with the reinforcement
for the formwork of the second floor. Fig. 11 illustrates the second floor formworks,
which are poured with concrete. Fig. 12 shows the same with taken formworks. Fig.
13 illustrates the same with installed formworks and frame beam reinforcement of the
second floor. Fig. 14 indicates the same with the lathing for the ceiling of the second
floor. Fig. 15 shows the same with the substrate on the ceiling lathing of the second
floor. Fig. 16 illustrates the same with void formers, reinforcement and mounting
lugs for the roof framework. Fig. 17 indicates the same with second floor ceilings,
which are poured with concrete. Fig. 18 shows the same with mounted roof framework.
Fig. 19 illustrates the same with the roof lathing. Fig. 20 indicates the finished
building. Fig. 21 shows the finished building with corners, laid with bricks. Fig.
22 illustrates the wall formwork with bilayer wall blank, made at the factory. Fig.
23 shows the wall formwork with multilayer wall blank, made at the factory.
[0010] The method of the erection of cast-frame building with decorative external finish
is used for the construction of houses and buildings with the different number of
floors and different types. Reinforcing tabs 2, exposed vertically, and mounting lugs
3 for removable wall formworks 4 are laid preliminary before the pouring of the foundation
1. The reinforcement 5 for walls 6 of the first floor is tied to reinforcing tabs
2 after the drying of the foundation. This reinforcement 5 is set at the some distance
from each other (see fig. 1). These distances are due to the sizes of future windows
and doors. Partially hollow removable wall formworks 4 include multilayer wall blanks,
made at the factory, consisting of at least one decorative layer 7 and one heat insulating
layer 8. Wall blanks are situated in the pallet 9 of the formwork 4, which are closed
by the hollow cap 10 in the case of the assembled formwork. (see fig. 22 and fig.
23). Removable formworks 4 are put down vertically on the reinforcement 5. Wall blank
is set with the decorative layer outside in that way, when the reinforcement is inside
the hollow cap 10 of the formwork 4 (see fig. 3). The hollow part of the formwork
4 is limited to the heat insulating layer 8 of the wall blank, which is installed
in the pallet 9 of the formwork 4, with the one side and the cap 10 of the formwork
4 with the other side. In the case of wall blank production in pallets 9 at the factory
the decorative layer 7 and the heat insulating layer 8 are linked with each other
by reinforcement elements 11 in that way, when reinforcement elements 11 protrude
beyond the heat insulating layer 8 in the hollow zone of the formwork 4, which are
formed by the cap 10. Formworks 4, installed on the reinforcement 5, are fixed in
mounting lugs 3. The hollow part of the formwork 4 with the reinforcement 5 and reinforcement
elements 11 are poured with concrete, forming supporting concrete layer 12 of the
wall 6 of the building, leaving the upper zone 13 of the formwork 4 unfilled with
concrete. Wall formworks 4 are taken off (see fig. 4), and frame beam formworks 14
are fixed in the upper zone 13 (see fig. 5) after concrete solidification. Then the
wooden lathing 16 for the first floor ceiling 17 is mounted with the help of supporting
legs 15, and the substrate 18, for example, laminated plywood is mounted on this lathing
(see fig. 7). Void formers 19, the reinforcement of the first floor ceiling 20 and
mounting lugs 21 for the formwork 4 are installed on the substrate 18, and then there
is the concrete pouring for the ceiling formation 17. Walls 6, erected on the foundation
1, are located at the some distance from each other with the formation of apertures
22 for windows and doors (windows and doors are not illustrated in a figure). The
internal surface of walls, poured immediately at the level of the floor with the help
of the formwork 4, does not require the additional finish and plaster due to the quality
production of the internal surface of the cap 10 of the formwork 4.
[0011] Second floor and subsequent floors are erected in the same manner as the first floor,
starting from the tying of the reinforcement 5 for the installation of second floor
formworks 4 to the ceiling formation 23 of next floor. Herewith reinforcement elements,
linking the decorative layer 7, heat insulating layer 8 and supporting concrete layer
12, tightly bind wall blanks with the construction of the wall 6. And the construction
of the wall is linked with the foundation 1, ceilings 17 and 23, building frame beams
24 and 25 by the reinforcement 5. Tabs 26 for the fixation of the framework 27 of
the half dome roof 28 are set on the ceiling 23 of the last floor before the process
of concrete pouring (see fig. 16). The framework 27 of the half dome roof 28 is welded
to tabs 26 on the ceiling 23 after the process of concrete solidification. Then this
framework is sheathed, for example, by boards 29 and cut by roofing materials 30.
[0012] This method provides the possibility of the erection of house walls 5 with corners
31, which are free from concrete constructions. This fact allows using corners of
the different geometry. In this case corners 31 of the building are laid by bricks
or blocks after roof erection 28. Windows and doors are set in apertures 22 between
walls (windows and doors are not illustrated in a figure). Also the method provides
the balcony erection 32 simultaneously with the ceiling erection 17. For these purposes
the lathing 16 of ceiling 17 are mounted beyond walls 6 of the building with the help
of supporting legs 15, which are situated on console parts of the ceiling 17, during
the process of the mounting (see fig. 10). Supporting legs 33 are used for the erection
of the visor lathing 34, which is made of the roofing material. The lathing 16 of
ceilings 23 are mounted with the help of supporting legs 33 beyond walls of the building
before the process of the concrete pouring (see fig. 19-20). Due to the above properties
of this method, there is the possibility of the varying of the building appearance,
number of floors, position and performance of windows, doors, balconies, loggia, and
also internal planning, saving advantages of the monolithic construction of the low-rise
building with the wall blank, which are made at the factory.
[0013] The use of void formers 19 and 35 in the case of the ceiling erection 17 and 23 gives
the opportunity to reduce the weight of the construction and costs of materials without
loss of the strength of the ceiling construction 17 and 23. As this method provides
the erection of the building framework, using reinforced concrete monolithic walls
6, which are tightly linked by means of the concrete and reinforcement 5 with the
foundation 1, ceilings 17 and 23, then strong seismic resistant construction, forming
unified spatial monolith, is obtained as a result of the process of the construction.
There is high accuracy level of walls, erected by means of simple devices, due to
the fact that wall formworks 4, which are stringed on the reinforcement 5, installed
on the foundation 1 or the ceiling of the regular floor, regulated vertically and
horizontally by fixing extensions 36 and support-screw regulators (this is not shown
in figure). The erection of the half dome roof 28 on the metallic framework 27 improves
properties of the strength and seismic resistance of the building by loads, which
are distributed along a curved path. The metallic framework 27 is linked with the
reinforcement 5 of walls 6 and ceilings 23 of the building. The use of removable wall
formwork 4 with the wall blank, which is made preliminary at the factory, allows increasing
the strength of the cast-frame construction of the building, because all vertical
and horizontal elements are tightly linked with each other. The wall blank consists
of the decorative layer 7 and heat insulating layer 8, linked by reinforcing elements
11, loop ends of which protrude beyond the heat insulating layer 8. The use of removable
wall formwork also allows erection of the building, which does not require the heat
and noise insulation, additional internal and external finishing works and has decorative
form.
[0014] The production of the wall blank in the pallet 9 at the factory provides high quality
of the decorative layer 7, which forms the external surface of the pallet after the
process of building erection. The decorative layer 7 are made of the fibrous concrete,
which contains mineral, steel, polymer fibers or made of other similar materials,
which allow getting of beautiful relief drawing of the external surface of the building,
which does not require the finish and repair. The heat insulating layer 8 can be made
of lightweight concrete such as foam concrete, aerated concrete, foam polystyrene
concrete, pumice concrete or other materials, which provide high properties of noise
and heat insulation. The use of multilayer wall blank of removable formwork 4 is illustrated
in fig. 23. The wall blank can contain at least one additional decorative layer 37,
intended for hardening of the main decorative layer. Also this blank includes at least
one additional heat insulating layer 38, intended for improvement of heat and noise
insulation properties of building walls.
[0015] Thus, the technical result, achieved with the use of the claimed invention, includes
the reducing of the labor content and building erection terms, the increasing of the
construction flexibility of the building framework with monolithic walls and the improving
of building operating characteristics, which do not require additional finish and
repair of internal and external wall surface. Also this technical result provides
the simplification of the concrete pouring during the process of building wall erection,
the enhancing of the reliability, durability and aseismic stability of the construction.
1. Method of the erection of the cast-frame building with decorative external finish, which comprises the foundation pouring, tying of the reinforcing construction of
the first floor, pouring of walls of the first floor with the help of removable formworks,
installation of the frame beam reinforcement and pouring of ceilings and frame beams,
tying of the reinforcing construction of the second floor and subsequent floors with
the wall pouring, installation frame beam reinforcements and pouring of ceilings and
frame beams of subsequent floors and roof erection, whereby reinforcing tabs, which
are installed vertically, and mounting lugs for removable wall formworks are laid
preliminary in the foundation during the process of the foundation pouring, whereby
reinforcing tabs are tied to the reinforcement of walls of the lower floor and mounting
lugs for removable wall formworks are laid and during the process of the ceiling pouring,
whereby the reinforcing construction of walls is tied to reinforcing tabs, leaving
vertical apertures for windows and doors, then removable wall formworks are put down
on the reinforcing construction of walls, said removable wall formworks consist of
the hollow cap and the pallet with the wall blank, which is situated inside the pallet
and made at the factory, said wall blank includes at least one decorative layer and
at least one heat insulating layer, said layers are linked with each other by reinforcing
elements and are placed outside together with the decorative layer, and the reinforcing
construction of the supporting layer of walls is set in the hollow cap of removable
wall formwork, then said removable wall formworks are fixed in mounting lugs of the
foundation by fixing extensions, and voids around the reinforcement inside hollow
caps of removable wall formwork are poured with concrete, forming supporting concrete
layer of the building wall and leaving the upper zone of removable wall formwork unfilled
with concrete, said zone is adjacent to the heat insulating layer of the wall blank,
whereby after removable wall formworks are taken off frame beam formworks, which are
adjacent to the wall blank, are set on supporting concrete layer of the wall in the
upper zone, which is unfilled with concrete, whereby fixing elements for the roof
framework are laid in the ceiling before the ceiling pouring of the last floor.
2. Method of the erection of the cast-frame building with decorative external finish on p. 1, characterized by the fact that angular zones are left free in the process of the wall pouring of the
building, and then these zones are laid with bricks or blocks.
3. Method of the erection of the cast-frame building with decorative external finish on p. 1, characterized by the fact that ceilings between floors are erected simultaneously with balconies,
so the lathing of ceilings is mounted by means of supporting legs beyond walls of
the building before the pouring.
4. Method of the erection of the cast-frame building with decorative external finish on p. 1, characterized by the fact that the ceiling of the last floor is erected simultaneously with visors,
so the lathing of ceilings is mounted by means of supporting legs beyond walls of
the building before the pouring.
5. Method of the erection of the cast-frame building with decorative external finish on p. 1, characterized by the fact that void formers are used in the case of the ceiling pouring.
6. Method of the erection of the cast-frame building with decorative external finish on p. 1, characterized by the fact that the removable wall formwork, installed on the foundation or ceiling
of the regular floor, is regulated vertically and horizontally by support-screw regulators
and fixing extensions of the formwork.