Field of the invention
[0001] The present invention relates to a device to provide wet steam for the electric iron.
Background of the invention
[0002] A steam station is a device to provide wet steam for the electric iron. The structure
of the existing steam station, see fig.1: the existing steam station is equipped with
a housing 2, which is disposed with a water tank 3, a pump 4, boiler 5 and a power
switch 7. The first water pipe 21 is connected to the outlet of the water tank 3 and
the inlet of the pump 4. The second water pipe 22 is connected to the outlet of the
pump 4 and the inlet of the boiler 5. The third water pipe is connected to the steam
outlet of the boiler 5 and the steam pipe 24. The power switch 7 is disposed to work
for the AC power, the heating pan of the boiler 5 and the pump 4. When the power switch
7 is switched on, the AC power supplies power to the heating pan of the boiler 5 and
the pump 4, and then the pump 4 extracts the water in the water tank 3 to the boiler
5 where the wet steam is generated with the water heated by the heating pan. The wet
steam is transported to the external iron 1 through the steam outlet of the boiler
5 and the steam pipe 24. At the hard water area, the boiler is easily accumulated
with calcareous water scale. This water scale will affect the heating efficiency or
take up the inner space of the boiler 5, making the volume of the boiler 5 reduced
too much to work normally. To take the boiler 5 out of the iron to clean it, it's
difficult to remove the calcareous water scale from the boiler 5.
Summary of the invention
[0003] The objective of the invention is to provide a steam station which can remove the
calcareous water scale without the work to take out of the boiler.
[0004] The technical proposal of the present invention is: a steam station which can remove
the calcareous water scale, the housing of which is disposed with a water tank, a
pump, a boiler and a power switch; the outlet of the water tank is connected to the
inlet of the pump, the outlet of the pump is connected to the inlet of the boiler;
the power supply of the pump and the heating pan of the boiler is controlled by the
power switch; the housing is further equipped with a three-way solenoid valve and
a removing switch; the steam outlet of the boiler is connected to the inlet of the
three-way solenoid valve, the first outlet of the three-way solenoid valve is connected
to the steam pipe while the second outlet is connected to the water pipe; the three-way
solenoid valve is switched between a first status when the inlet is connected to the
first outlet and a second status when the inlet is connected to the second outlet
under the control of the removing switch. The three-way solenoid valve is situated
in the first status when the inlet is connected to the first outlet after the water
is put into the water tank and the power switch is switched on with the removing switch
is switched off. The pump and the heating pan of the boiler are powered by the AC
power. The water in the water tank is pumped to the boiler to be heated to make wet
steam by the heating pan. The wet steam is transported to the external iron through
the steam outlet of the boiler, the first outlet of the three-way solenoid valve and
the steam pipe successively. The three-way solenoid valve is situated in the second
status when the inlet is connected to the second outlet after the cleaning solution
is put into the water tank after the power switch and the removing switch is switched
on; the pump and the heating pan are power supplied by the AC power; the cleaning
solution is pumped to the boiler by the pump and heated by the heating pan, the cleaning
solution with the calcareous water scale dissolved is extracted out through the second
outlet of the three-way solenoid valve and the water pipe.
[0005] In the preferred embodiment, the boiler is equipped with a first thermostat and a
second thermostat with the temperature control value of the first thermostat is higher
than that of the second one; the housing is further disposed with a control circuit
board, the input port for AC power of which is connected to the power switch and the
cleaning controlling port is connected to the removing switch; the pump is controlled
by the first output port of the control circuit board; the boiler is temperature controlled
by the heating pan made from the first thermostat or the second thermostat under the
control of the second output port of the control circuit board; the switchover of
the three-way solenoid valve is controlled by the third output port of the control
circuit board. If there is not control information transmitted from the removing switch
to the removing control port of the control circuit board after the AC power input
port on the control circuit board is powered by the power switch, the water in the
boiler is heated to make steam in a higher temperature by the heating pan made from
the first thermostat under the control of the second output port on the control circuit
board, and the three-way solenoid valve is situated in the first status when the inlet
is connected to the first outlet under the control of the third output port on the
control circuit board. If there is control information transmitted to the cleaning
control port on the control circuit board from the removing switch, the cleaning solution
in the boiler is heated to remove the calcareous water scale in a lower temperature
by the heating pan made from the second thermostat under the control of the second
output port on the control circuit board, and the three-way solenoid valve is situated
in the second status when the inlet is connected to the second outlet under the control
of the third output port on the control circuit board, making sure that the cleaning
solution heated in the boiler with the dissolved calcareous water scale is extracted
out through the second outlet of the three-way solenoid valve and the water pipe.
[0006] The temperature control value of the first thermostat is 220°C and the temperature
control value of the second thermostat is 100°C.
[0007] Especially in another preferred embodiment: the control circuit board is equipped
with a controller, a first switch, a second switch, a third switch and a power detector;
the zero line of the AC power input port on the control circuit board is connected
to the input of the first switch; the firing line of the AC power input port on the
control circuit board is connected to the input of the power detector, the input of
the second switch and the input of the third switch; the power on signal is transported
to the controller by the power detector; the cleaning control signal is transported
to the controller by the removing control port on the control circuit board; the three
switches are controlled separately by the three outputs of the controller; the output
of the first switch is the first output port of the control circuit board, the output
of the second switch is the second output port of the control circuit board, the output
of the third switch is the third output port of the control circuit board. The three
switches are controlled separately by the controller, which realizes the control function
of the three output port of the control circuit board.
[0008] It would be better in another preferred embodiment: the controller of the control
circuit board is disposed with an input port to receive the starting signal of the
external iron, the pump is powered under the control of the first switch after the
controller is received the starting signal. The boiler is pre-heated, and then the
pump starts; the water delivered to the boiler is heated to make wet steam quickly,
which promotes the efficiency of the generation of the wet steam.
[0009] The present invention of a steam station which can remove the calcareous water scale
is further equipped with a removing switch and a three-way solenoid valve compared
to the existing steam station. The steam station can provide wet steam for the external
iron, and also can remove the calcareous water scale in the boiler by heating the
cleaning solution. The present invention is very much simplified to remove the calcareous
water scale in the boiler and has high operability, practicability and service life.
The boiler is disposed with a first thermostat and a second thermostat with different
working temperature. The housing is disposed with a control circuit board. When the
wet steam is needed, the boiler is working in a higher temperature to make wet steam
controlled by the heating pan made from the first thermostat under the control of
the control circuit board, and the three-way solenoid valve is situated in the first
status when the inlet is connected to the first outlet under the control of the third
output port on the control circuit board. To remove the calcareous water scale in
the boiler, the cleaning solution is heated in a lower temperature in the boiler by
the heating pan made from the first thermostat under the control of the control circuit
board, and the three-way solenoid valve is controlled to be situated in the second
status when the inlet is connected to the second outlet. To work in different temperature
in different operation mode, the temperature control value of the first thermostat
is 220°C, and that of the second one is 100°C. It satisfies the actual demand to the
working temperature of the boiler in different operation mode such as to generate
the wet steam or to remove the calcareous water scale. It's professional designed
and power saved. The controller of the control circuit board to control the first
switch, the second switch and the third switch separately controls the three output
port with flexibility. The present invention is provided with better removing effect,
simple structure and easy to implement. The controller is equipped with an input port
to receive the activating signal from the external iron, making the steaming and the
pumping of the external iron in concordance. The present invention promotes the efficiency
to generate the wet steam and saves the energy as well.
Brief description of the drawings
[0010] Fig.1 illustrates the sectional view of the existing steam station;
[0011] Fig.2 illustrates the sectional view of the first embodiment of the steam station
which can remove the calcareous water scale in the present invention;
[0012] Fig.3 illustrates the sectional view of the second embodiment of the steam station
which can remove the calcareous water scale in the present invention;
[0013] Fig.4 is the circuit structure of the embodiment in the fig.3;
[0014] Fig.5 is the circuit frame of the control circuit board of the embodiment in the
fig.3;
[0015] Fig.6 is the working flow chart of the embodiment in the fig.3.
Detail description of the embodiment
[0016] The first embodiment:
[0017] The structure of the first embodiment in the present invention of a steam station
which can remove the calcareous water scale is figured in the fig.2. The housing 2
of the steam station is disposed with a water tank 3, a pump4, a boiler 5, a three-way
solenoid valve 6, a power switch 7 and a removing switch 8.
[0018] Inside the housing 2: the outlet of the water tank 3 is connected to the inlet of
the pump 4 by the first pipe 21. The outlet of the pump 4 is connected to the inlet
of the boiler 5 by the second pipe 22.The steam outlet of the boiler 5 is connected
to the inlet of the three-way solenoid valve by the third pipe 23. The first outlet
of the three-way solenoid valve 6 is connected to the steam pipe 24, the leading-out
end of which is connected to the external iron 1. The second outlet of the three-way
solenoid valve 6 is connected to the water pipe 25, the leading-out end of which is
connected to the external container 10.
[0019] The power switch 7 is disposed to control the power supply of the pump 4 and the
heating pan. The three-way solenoid valve 6 is switched over between a first status
when the inlet is connected to the first outlet and a second status when the inlet
is connected to second outlet under the control of the removing switch 8.
[0020] When the wet steam is needed for the external iron 1: the water is injected into
the water tank 3. Then the power switch 7 is switched on but the removing switch is
not. The three-way solenoid valve 6 is situated in the first status when the inlet
is connected to the first outlet. The pump 4 and the heating pan of the boiler 5 are
powered by the AC power; the water in the water tank 3 extracted to the boiler by
the pump 4 is heated by the heating pan to make wet steam, which is transported to
the external iron 1 to iron the cloth through the steam outlet, the first outlet of
the three-way solenoid valve 6 and the steam pipe 24.
[0021] To remove the calcareous water scale in the boiler 5: the cleaning solution is injected
to the water tank 3. Then the power switch 7 and the removing switch 8 are powered
on. The three-way solenoid valve is switched over to the second status when the inlet
is connected to the second outlet. The pump 4 and the heating pan of the boiler 5
are powered by the AC power. The cleaning solution in the water tank 3 extracted to
the boiler by the pump 4 is heated by the heating pan. The cleaning solution heated
with the dissolved calcareous water scale is extracted out to the container 10 through
the second outlet of the three-way solenoid valve 6 and the water pipe 25.
[0022] The second embodiment:
[0023] The structure of the second embodiment in the present invention of a steam station
which can remove the calcareous water scale is figured in the fig.3. The housing 2
of the steam station is disposed with a water tank 3, a pump 4, a boiler 5, a three-way
solenoid valve 6, a power switch 7, a removing switch 8 and a control circuit board
9.
[0024] Inside the housing 2: the outlet of the water tank 3 is connected to the inlet of
the pump 4 by the first pipe 21. The outlet of the pump 4 is connected to the inlet
of the boiler 5 by the second pipe 22. The steam outlet of the boiler 5 is connected
to the inlet of the three-way solenoid valve 6 by the third pipe 23.The first outlet
of the three-way solenoid valve is connected to the steam pipe 24, the leading-out
end of which is connected to the external iron 1. The second outlet of the three-way
solenoid valve is connected to the water pipe 25, the leading-out end of which is
connected to the external container 10.
[0025] Refer to the fig.4: the boiler 5 is equipped with a heating pan 51, a first thermostat
52, a second thermostat 53 and a thermal fuse 54, which are series connected. Thereinto,
the temperature control value of the first thermostat is 220°C, and that of the second
one is 100°C.
[0026] Refer to the fig.4 and the fig.5: two input ports of the power switch are connected
to the firing line L and the zero line N of the AC power separately. The output port
of the firing line of the power switch 7 is connected to the input port 91 of the
firing line of the AC power on the control circuit board 9, the firing line of the
pump 4, the firing line port of the three-way solenoid valve 6 and the free end of
the second thermostat 53 of the boiler 5. The output port of the zero line of the
power switch 7 is connected to the input port 92 of the zero line of the AC power
on the control circuit board 9 and the free end of the heating pan 51 of the boiler
5. The cleaning controlling ports 93, 94 of the control circuit board 9 are connected
to the both ends of the removing switch 8 separately. The pump controlling input port
90 on the control circuit board 9 is connected to the external iron 1 to activate
the sensor 12. The first output port 95 of the control circuit board 9 is connected
to the zero line of the pump 4 to control it. The second output port 96 of the control
circuit board 9 is connected to the joint of the first thermostat 52 and the second
thermostat 53 to control heating pan to control the temperature of the boiler by the
heating pan 51 made from the first thermostat 52 and the second thermostat 53. The
third output port 97 of the control circuit board 9 is connected to the zero line
of the three-way solenoid 6 to control the switchover of the three-way solenoid 6.
[0027] To supply the wet steam to the external iron 1: the water is injected to the water
tank 3. And then the power switch 7 is switched on to supply power to the input ports
91, 92 of the AC power on the control circuit board 9 while the removing switch is
switched off. The removing switch 8 does not transfer control information to the cleaning
controlling port 93, 94 on the control circuit board 9. The second output port 96
on the control circuit board 9 is connected to the firing line L of the AC power.
Both ends of the second thermostat 53 are connected to the firing line L of the AC
power separately, so the second thermostat 53 does not work. The boiler 5 is heated
to work in a temperature of 220°C by the heating pan 51 made from the first thermostat
under the control of the second output port 96 on the control circuit board 9. The
first output port 95 on the control circuit board 9 is connected to the zero line
N of the AC power, and the pump 4 is powered on. The water in the water tank 3 pumped
to the boiler 5 is heated by the heating pan 51 to make wet steam. The third output
port 97 on the control circuit board 9 is disconnected to the AC power. So the three-way
solenoid valve powered off is situated in the first status when the inlet is connected
to the first outlet. The wet steam is transported to the external iron 1 for ironing
the cloth through the steam outlet of the boiler 5, the first outlet of the three-way
solenoid valve 6 and the steam pipe 24.
[0028] On the contrary, to remove the calcareous water scale in the boiler 5: the cleaning
solution is injected to the water tank 3. The power switch 7 is switched on to supply
power to the input ports 91, 92 of the AC power on the control circuit board 9; the
removing switch 8 is switched on, and the removing control port 93, 94 of the control
circuit board 9is received the control information from the removing switch 8. The
second output 96 on the control circuit board 9 is disconnected from the firing line
L of the AC power. The second thermostat 53 works. The temperature control value of
the second thermostat is 100°C, which is lower than that of the first one with 220°C.
When the temperature of the boiler 5 reaches to 100°C, the second thermostat 53 turns
to the cut-off status and the heating pan 51 is powered off. So that the boiler 5
is heated in a temperature of 100°C by the heating pan 51 made from the second thermostat
under the control of the second output port 96 of the control circuit board. The first
output port 95 on the control circuit board 9 is connected to the zero line N of the
AC power, and the pump 4 is powered on. The cleaning solution in the box 3 is pumped
to the boiler 5 by the pump 4 and heated by the heating pan 51. The calcareous water
scale is dissolved with the heated cleaning solution. At the same time, the third
output port 97 on the control circuit board 9 is connected to the AC power. And the
three-way solenoid valve 6 is powered on and situated in the second status when the
inlet is connected to the second outlet. The cleaning solution in the boiler is extracted
out to the container 10 with the dissolved calcareous water scale through the second
outlet of the three-way solenoid valve and the pipe 25.
[0029] For better cleaning effect, the internal structure the control circuit board 9 applied
is figured as the fig.5. The control circuit board 9 is equipped with a controller
991, a power detector 992, a first switch 993, a second switch 994 and a third switch
995. The controller 991 is adopted with a programmable control unit or a microprocessor.
The power detector 992 is adopted with a step-down/rectification combination circuit
consisting of divider resistance and diode. The first switch 993, the second switch
994 and the third switch 995 can be adopted with some kind of switch device such as
a relay or bidirectional triode thyristor.
[0030] The zero line input port 92 of the AC power on the control circuit board 9 is connected
to the input of the first switch 993. The firing line input port of the AC power on
the control circuit board 9 is connected to the input of the power detector 992, the
input of the second switch 994 and the input of the third switch 995. One of the inputs
of the controller 991 is serviced as the pump control input port 90 to receive the
activating signal from the activating sensor 12 of the external iron1.
[0031] The power on signal is transmitted to the controller 991 from the power detector
992. The removing signal is transmitted to the controller 991 from the removing control
port 93, 94. the first control output port of the controller is connected to the control
input port of the first switch 993; the second control output port of the controller
991 is connected to the control input port of the second switch 994; the third control
output port of the controller 991 is connected to the control input port of the third
switch 995; the three switches are controlled by the three control output port of
the controller 991 separately.
[0032] The output of the first switch 993 is the first output port 95 on the control circuit
board 9, the output of the second switch 994 is the second output port 96 on the control
circuit board 9, and the output of the third switch 995 is the third output port 97
on the control circuit board 9.
[0033] The controlling method of this embodiment applying the control circuit board 8 is
figured as in the fig.6.
[0034] Step 100, the controller 991 is received with the power-on signal transmitted from
the power detector 992, make sure that the power switch 7 is shut down, and then go
to the step 101.
[0035] Step 101, the controller 991 detects that whether the controlling information is
transported from the removing switch 8 to the cleaning controlling port 93, 94 on
the control circuit board 9. That is whether the button of the removing switch 8 is
pushed down and switched on. If is, go to the step 103 to remove the calcareous water
scale; if not, go to the step 111 to generate the wet steam.
[0036] Step 111, the gate signal to breakover the second switch 994 is transmitted to the
control input port of the second switch 994 from the second control output port of
the controller 991. The output of the second switch 994 as the second output port
96 of the control circuit board 9 is connected to the firing line L of the AC power.
Meanwhile, the second thermostat 53 doesn't work. The boiler is heated to work at
the temperature of the 220°C by the heating pan 51 made from the first thermostat
52 under the control of the second output port 96 of the control circuit board 9.
Then go to the step 112.
[0037] Step 112, the controller 991 detects that whether the activating signal is transmitted
to the activating sensor 12 of the external iron 1 from the pump control input port
90 of the control circuit board 9. That is whether the activating button 11 of the
iron 1 is pushed down to activate the sensor 12. If is, go to the step 113 to make
the wet steam; if not, go to the step 111 to pre-heat the boiler and wait for the
activating button 11 to be pushed down.
[0038] Step 113, the gate signal to breakover the first switch 993 is transmitted to the
control input port of the first switch 993 from the first control output port of the
controller 991. The first control output port of the controller 991 as the first output
port 96 of the control circuit board 9 is connected to the zero line N of the AC power
to power on the pump. The water in the water tank 3 is pumped by the pump 4 to be
heated to make wet steam in the boiler by the heating pan 51. Meanwhile, the third
output port 97 of the control circuit board is disconnected from the AC power, and
the three-way solenoid valve is powered off and situated in the first status when
the inlet is connected to the first outlet. The wet steam is transported to the external
iron 1 through the steam outlet of the boiler, the first outlet of the three-way solenoid
valve 6 and the steam pipe 24. Go to the step 120 after the power switch 7 is shut
down.
[0039] Step 102, there is not gate signal transmitted to the control input port of the second
switch 994 from the second control output port of the controller, so the second switch
994 is shut down. The second output port 96 of the control circuit board 9 is disconnected
from the firing line L of the AC power. The second thermostat works. As the temperature
control value of the second thermostat 53 is 100°C, which is far lower than that of
the first one with 220°C, the second thermostat 53 is cut off and the heating pan
51 is powered off when the temperature of the boiler reaches to 100°C. The boiler
is heated to work at the temperature of 100°C by the heating pan 51 made from the
second thermostat under the control of the second output port 96 on the control circuit
board 9. Then go to the step 103.
[0040] Step 103, the gate signal to breakover the first switch 993 is transmitted to the
control input port of the first switch 993 from the first control output port of the
controller 991. The output port of the first switch 993 as the first output port 95
of the control circuit board 9 is connected to the zero line N of the AC power to
power on the pump. The cleaning solution in the water tank 3 is pumped to the boiler
5 heated by the heating pan 51. The calcareous water scale in the boiler 5 is dissolved
by the heated cleaning solution. The gate signal to breakover the third switch 995
is transmitted to the control input port of the third switch 995 from the third control
output port of the controller 991. The output port of the third switch 995 as the
third output port 97 of the control circuit board 9 is connected to the zero line
N of the AC power to power on the three-way solenoid valve, which is situated to the
second status when the inlet is connected to the second outlet. The cleaning solution
in the boiler 5 is extracted out to the container 10 through the second outlet of
the three-way solenoid valve 6 and the water pipe 25 with the dissolved calcareous
water scale. Then go to the step 104.
[0041] Step 104, a ten seconds gate signal to breakover the first switch 993 for ten seconds
is transmitted to the control input port of the first switch 993 from the first control
output port of the controller 991. The output port of the first switch 993 as the
first output port 95 of the control circuit board 9 is connected to the zero line
N of the AC power for ten seconds. The pump is powered on for ten seconds. The cleaning
solution in the water tank 3 is pumped by the pump 4 to be heated for ten seconds.
The calcareous water scale in the boiler 5 is dissolved by the heated cleaning solution.
Then the gate signal is cut off for fifteen seconds to the control input port of the
first switch 993 from the first control output port of the controller 991, making
the first switch 993 shut down for fifteen seconds. The output of the first switch
993 as the first output port of the control circuit board 9 is disconnected from the
zero line N of the AC power for fifteen seconds. The pump 4 is powered off for fifteen
seconds. The cleaning solution in the water tank 3 is stopped to be pumped to the
boiler 5 by the pump 4 and heated by the heating pan 51 for fifteen seconds. The pump
4 is controlled to work for ten cycles by the controller 991, and then go to the step
105.
[0042] Step 105, the first control output port of the controller 991 stops to transmit the
gate signal to the first switch 993 for three minutes, making the first switch shut
down for three minutes. The output of the first switch 993 as the first output port
of the control circuit board 9 is disconnected from the zero line N of the AC power
for three minutes. The pump 4 is powered off for three minutes. The pump 4 stops to
pump the cleaning solution in the water tank 3 to the boiler 5 to heat the cleaning
solution by the heating pan 51 for three minutes. Then go to the step 106.
[0043] Step 106, a ten seconds gate signal to breakover the first switch 993 for ten seconds
is transmitted to the control input port of the first switch 993 from the first control
output port of the controller 991. The output port of the first switch 993 as the
first output port 95 of the control circuit board 9 is connected to the zero line
N of the AC power for ten seconds. The pump is powered on for ten seconds. The cleaning
solution in the water tank 3 is pumped by the pump 4 to be heated for ten seconds.
The calcareous water scale in the boiler 5 is dissolved by the heated cleaning solution.
Then the gate signal is cut off for fifteen seconds to the control input port of the
first switch 993 from the first control output port of the controller 991, making
the first switch 993 shut down for fifteen seconds. The output of the first switch
993 as the first output port of the control circuit board 9 is disconnected from the
zero line N of the AC power for fifteen seconds. The pump 4 is powered off for fifteen
seconds. The cleaning solution in the water tank 3 is stopped to be pumped to the
boiler 5 by the pump 4 and heated by the heating pan 51 for fifteen seconds. The pump
4 is controlled to work for ten cycles by the controller 991, and then go to the step
107.
[0044] Step 107, the gate signal to breakover the first switch 993 is transmitted to the
control input port of the first switch 993 from the first control output port of the
controller 991. The output port of the first switch 993 as the first output port 95
of the control circuit board 9 is connected to the zero line N of the AC power to
power on the pump. The cleaning solution in the water tank 3 is pumped to the boiler
5 heated by the heating pan 51. The calcareous water scale in the boiler 5 is dissolved
by the heated cleaning solution. The gate signal to breakover the third switch 995
is transmitted to the control input port of the third switch 995 from the third control
output port of the controller 991. The output port of the third switch 995 as the
third output port 97 of the control circuit board 9 is connected to the firing line
L of the AC power to power on the three-way solenoid valve, which is situated to the
second status when the inlet is connected to the second outlet. The cleaning solution
in the boiler 5 is extracted out to the container 10 through the second outlet of
the three-way solenoid valve 6 and the water pipe 25 with the dissolved calcareous
water scale. The gate signal is transmitted to the control input of the second switch
994 from the second control output port of the controller 991 for one minute to breakover
the second switch for one minute. The output of the second switch 994 as the second
output port 96 of the control circuit board 9 is connected to the firing line L of
the AC power for one minute. The boiler 5 is heated for one minute at a temperature
of 220°C by the heating pan 51 made from the first thermostat 52 under the control
of the second output port 96. Then go to the step 120.
[0045] Step 120, the end.
[0046] During the control procedure, the calcareous water scale removing step is adopted
with an alternation mode of dissolving, washing and drying. Then dissolve and wash
the remaining calcareous water scale in the boiler in a high temperature. The effect
of removing is well, the cleaning solution is saved, besides, it shortens the removing
working hours.
[0047] Although the present invention has been fully described by ways of preferred embodiments
with reference to the accompanying drawings, it is to be noted that various changes
and modifications will be apparent to those skilled in the art. Therefore, unless
otherwise such changes and modifications depart from the scopes of the present invention,
they should be construed as being included therein.
Industrial applicability
[0048] The present invention of a steam station which can remove the calcareous water scale
is equipped with a three-way solenoid valve to switch the draw-off from the boiler.
It can supply wet steam for the external iron, and remove the calcareous water scale
by heating the cleaning solution in the boiler as well. The present invention is provided
with well industrial applicability.
1. A steam station which can remove the calcareous water scale, the housing of which
is disposed with a water tank, a pump, a boiler and a power switch; the outlet of
the water tank is connected to the inlet of the pump, the outlet of the pump is connected
to the inlet of the boiler; the power switch controls the pump and the power supply
of the heating plate of the boiler; wherein the housing is further disposed with a
three-way solenoid valve and a removing switch; the steam outlet of the boiler is
connected to the inlet of the three-way solenoid valve, the first outlet of the three-way
solenoid valve is connected to the steam pipe, the second outlet of the three-way
solenoid valve is connected to the water pipe; the removing switch controls the three-way
solenoid valve to change over between the first status when the inlet is connected
to the first outlet and the second status when the inlet is connected to the second
outlet; the water pipe is disposed with an external container.
2. The steam station which can remove the calcareous water scale according to the claim
1, wherein the steam station further includes:
A first thermostat and a second thermostat disposed inside the boiler, the temperature
control value of the first thermostat is higher than that of the second one;
a control circuit board disposed inside the housing, the cleaning control port of
the control circuit board is connected to the removing switch; the first output port
of the control circuit board is disposed to control the pump, and the second output
board of the control circuit board is disposed to control the temperature of the boiler
by the heating pan made from the first thermostat or the second thermostat; the third
output port on the control circuit board is disposed to control the switchover of
the three-way solenoid valve.
When powered, there is not control information transmitted to the cleaning control
port on the control circuit board from the removing switch, the water in the boiler
is heated to make steam in a higher temperature by the heating pan made from the first
thermostat under the control of the second output port on the control circuit board,
and the three-way solenoid valve is situated in the first status when the inlet is
connected to the first outlet under the control of the third output port on the control
circuit board.
If there is control information transmitted to the cleaning control port on the control
circuit board from the removing switch, the cleaning solution in the boiler is heated
to remove the calcareous water scale in a lower temperature by the heating pan made
from the second thermostat under the control of the second output port on the control
circuit board, and the three-way solenoid valve is situated in the second status when
the inlet is connected to the second outlet under the control of the third output
port on the control circuit board.
3. The steam station which can remove the calcareous water scale according to the claim
2, wherein the temperature control value of the first thermostat is 220°C, the temperature
control value of the second thermostat is 100°C.
4. The steam station which can remove the calcareous water scale according to the claim
2 or claim 3, wherein a controller, a first switch, a second switch, a third switch
and power detector is disposed on the control circuit board; the zero line of the
AC power input port on the control circuit board is connected to the input of the
first switch; the firing line of the AC power input port on the control circuit board
is connected to the input port of the power detector, the input port of the second
switch and the input port of the third switch; the power on signal is transmitted
to the controller from the power detector, the cleaning control port on the control
circuit board transmits the cleaning control signal to the controller, the three output
ports of the controller separately control the first switch, the second switch and
the third switch; the output port of the first switch is the first output port of
the control circuit board, the output port of the second switch is the second output
port of the control circuit board, the output port of the third switch is the third
output port of the control circuit board.
5. The steam station which can remove the calcareous water scale according to the claim
4, wherein the controller on the control circuit board is equipped with an input port
to receive the activating signal for the external iron, the first switch is controlled