BACKGROUND OF THE INVENTION
1. Field of the Invention
[0001] The present invention relates generally to a yarn winding apparatus including a bobbin
installation device that installs a bobbin, onto which a yarn is to be wound, at a
target position.
2. Description of the Related Art
[0002] Bobbin installation devices that, before starting yarn winding by a spinning machine
or after a spinning machine has discharged a fully wound package, or in similar situations,
supply a bobbin, onto which yarn is not yet wound, to a bobbin holding section of
the spinning machine or the like to make preparation (bunch winding or the like) to
start a winding operation are known in the art. Examples of a spinning machine known
to the inventor that include a bobbin installation device of this type are disclosed
in Japanese published unexamined application No.
2005-219880 and Japanese published unexamined application No.
H9-100066.
[0003] A doffing cart of a spinning machine disclosed in Japanese published unexamined application
No.
2005-219880 includes a chucker (bobbin gripping section) that grips a bobbin. The chucker is
caused to pivot toward a cradle (bobbin holding section) when supplying the bobbin
to the cradle. The bobbin installed on the cradle is in contact with a rotatable driving
drum (winding drum). The bobbin is rotated when the driving drum rotates. A yarn is
wound onto the bobbin as the bobbin rotates thereby forming a package.
[0004] A doffing cart of a spinning machine disclosed in Japanese published unexamined application
No.
H9-100066 includes an arm member that is pivotable about a shaft. A chuck mechanism that holds
a bobbin, onto which a yarn is to be wound, is provided on a distal end portion of
the arm member. A bobbin is supplied to the cradle by causing the arm member, which
is in a state where the chuck mechanism is gripping the bobbin, to pivot.
[0005] The spinning machine disclosed in Japanese published unexamined application No.
2005-219880 forms a cheese-shaped package. When a conical package is to be formed, the spinning
machine disclosed in Japanese published unexamined application No.
2005-219880 uses a bobbin installation device having the same layout as that for forming a cheese-shaped
package. Accordingly, there is a likelihood of occurrence of a collision between a
bobbin being supplied and the cradle. A reason for this is described below with reference
to FIG. 5A.
[0006] To perform yarn winding stably while securing a uniform contact between the winding
drum and a package, it is desirable to change, for example, an orientation of the
cradle used for forming a conical package with reference to an orientation of the
cradle used for forming a cheese-shaped package. However, if the orientation of the
cradle is changed but the bobbin is supplied to the cradle along a similar path to
that for forming a cheese-shaped package, a clearance between a bobbin 48 being supplied
and bobbin holders 72, which serve as the bobbin holding section, can sometimes become
very small as shown in FIG. 5A, for example. In the example shown in FIG. 5A, while
the bobbin 48 is supplied to a position between a pair of the bobbin holders 72, a
large-diameter end portion of the bobbin 48 is very close to one of the bobbin holders
72.
[0007] In general, the bobbin holders 72 cannot have a large clearance therebetween because
of requirements imposed on a layout of the spinning machine. Accordingly, in a situation
where a bobbin installation device of the same layout is used even when forming a
package of a different shape, a high positioning accuracy is required in a bobbin
supplying operation to avoid the collision between the bobbin and the bobbin holders,
thereby increasing cost of the bobbin installation device.
[0008] Meanwhile, a configuration for avoiding the collision described above in the bobbin
installation device has not been disclosed either in Japanese published unexamined
application No.
2005-219880 or Japanese published unexamined application No.
H9-100066. Accordingly, to avoid the collision between the bobbin and the bobbin holders in
the conventional bobbin installation device, it is necessary to change a bobbin supplying
path by changing the entire bobbin installation device. This disadvantageously creates
the need to perform a complicated operation when changing the bobbin installation
device or to prepare a plurality of bobbin gripping mechanisms, resulting in an increase
in cost or the like.
SUMMARY OF THE INVENTION
[0009] It is an object of the present invention to provide a yarn winding apparatus including
a bobbin installation device adapted to prevent a bobbin being supplied from colliding
with a bobbin holding section. This object is achieved by a yarn winding apparatus
according to claim 1.
[0010] According to a first aspect of the present invention, a yarn winding apparatus includes
a bobbin installation device and a bobbin holding section. The bobbin holding section
defines a target position. The bobbin installation device includes a bobbin gripping
section and a rocker shaft. The bobbin gripping section performs a bobbin supplying
operation by gripping a bobbin, onto which a yarn is to be wound, and supplying the
bobbin to the target position. The rocker shaft swings to bring the bobbin gripping
section to the target position. To hold the bobbin supplied from the bobbin installation
device, the bobbin holding section includes two holding mechanisms that hold the bobbin
at two ends of the bobbin in its axial direction. An axis of the rocker shaft is substantially
parallel to a line that passes through centers of the holding mechanisms.
[0011] If the holding line is not parallel to the rocker shaft, the bobbin being supplied
is likely to collide with the bobbin holding section. However, in the bobbin installation
device configured as described above, it is possible to supply the bobbin by effectively
utilizing a clearance between the holding mechanisms of the bobbin holding section
(without employing a layout in which the clearance is unnecessarily large). Accordingly,
the yarn winding apparatus can be made compact.
[0012] The bobbin installation device preferably further includes an adjustment section
capable of adjusting a path along which the bobbin is to be supplied by the bobbin
gripping section to the target position by adjusting an orientation of the rocker
shaft.
[0013] The adjustment section allows the bobbin installation device to perform adjustment
such that the bobbin is supplied through an appropriate path depending on the shape
of the bobbin to be supplied or the like.
[0014] The adjustment section of the yarn winding apparatus preferably includes a mounting
member and a fixture. The mounting member supports the bobbin gripping section. The
fixture fixes the mounting member that locks at least a change in an installation
orientation.
[0015] The adjustment section configured as described above allows the bobbin installation
device to change the installation orientation of the mounting member and fix the mounting
member at the changed orientation with the fixture so that the bobbin is supplied
through an appropriate path.
[0016] In the bobbin installation device described above, a plurality of selection holes
is preferably defined in the mounting member. The fixture is positioned in one of
the selection holes to lock at least the change in the installation orientation of
the mounting member.
[0017] The bobbin installation device configured as described above can adjust the path
along which the bobbin is supplied only by inserting the fixture into one of the selection
holes thereby defining the position of the mounting member. The selection hole is
selected based on a winding condition and/or the like. The adjustment section can
thus have a simple structure. This leads to reduction in the number of components
involved in the bobbin installation device.
[0018] In the yarn winding apparatus, the bobbin installation device preferably includes
an operating section that operates the bobbin holding section to perform a dismounting
operation, which is an operation of dismounting the bobbin from the bobbin holding
section.
[0019] In many cases, the doffing operation including dismounting of the package is followed
by an operation of supplying a new bobbin to form a new package. In this regard, in
the spinning machine configured as described above, both the dismounting operation
and the bobbin supplying operation can be performed in one device. Accordingly, the
entire spinning machine can be configured compact.
[0020] In the yarn winding apparatus, the bobbin supplying operation performed by the bobbin
gripping section and the dismounting operation performed by the operating section
are independently operable.
[0021] The yarn winding apparatus configured as described above can perform the doffing
operation and the bobbin supplying operation independently. This makes it possible
to prevent an unnecessary bobbin supplying operation from being performed in a situation
where, for example, it is not necessary to form a new package immediately after one
package has been fully wound. Accordingly, working time of the bobbin installation
device can be shortened and hence a subsequent operation can be started quickly. This
leads to improvement in winding efficiency of the yarn winding apparatus.
[0022] The yarn winding apparatus preferably includes a yarn-catching-and-carrying device
that performs a yarn-catching-and-carrying operation, which is an operation of catching
a yarn and carrying the yarn to the bobbin that is supplied by the bobbin gripping
section to the bobbin holding section. The yarn winding apparatus preferably performs
the bobbin supplying operation performed by the bobbin gripping section, the dismounting
operation performed by the operating section, and the yarn-catching-and-carrying operation
performed by the yarn-catching-and-carrying device independently.
[0023] In the yarn winding apparatus configured as described above, it is possible to skip
unnecessary operation(s) depending on a situation that can vary. Accordingly, working
time of the bobbin installation device can be shortened and hence a subsequent operation
can be started quickly. This leads to improvement in winding efficiency of the yarn
winding apparatus.
[0024] The yarn winding apparatus preferably includes a plurality of winding units, each
of which includes the bobbin holding section and winds a yarn onto the bobbin held
by the bobbin holding section to form a package. A plurality of the winding units
is arranged in one direction. The bobbin installation device is movable in the direction
in which the winding units are arranged.
[0025] Accordingly, cost reduction can be achieved by reducing the number of the bobbin
installation devices provided in the yarn winding apparatus as compared to a configuration
in which the bobbin installation devices are provided on a per-winding-unit basis.
[0026] The above and other objects, features, advantages and technical and industrial significance
of this invention will be better understood by reading the following detailed description
of presently preferred embodiments of the invention, when considered in connection
with the accompanying drawings.
BRIEF DESCRIPTION OF THE DRAWINGS
[0027]
FIG. 1 is a schematic elevation view of an overall structure of a spinning machine
according to an embodiment of the present invention;
FIG. 2 is a longitudinal cross-sectional view of the spinning machine shown in FIG.
1;
FIG. 3 is a perspective view of a bobbin supplying section, shown in FIG. 2, when
supplying a bobbin;
FIG. 4 is a plan view of the configuration of the bobbin supplying section, shown
in FIG. 3, when supplying the bobbin;
FIGS. 5A and 5B are diagrams for explaining a difference between a conventional bobbin
supplying path and a bobbin supplying path according to the present embodiment;
FIG. 6 is a longitudinal cross-sectional view of the spinning machine in a state where
a spun yarn is caught by a suction pipe shown in FIG. 1 while a doffing operation
of a fully wound package is being performed;
FIG. 7 is a longitudinal cross-sectional view of the spinning machine in a state where
the suction pipe has moved to a predetermined position and is in a standby state while
the spun yarn remains sucked by the suction pipe;
FIG. 8 is a longitudinal cross-sectional view of the spinning machine at an instant
at which the bobbin is supplied to a cradle shown in FIG. 2;
FIGS. 9A to 9C are longitudinal cross-sectional views of a structure for moving a
cradle operating arm shown in FIG. 1; and
FIGS. 10A to 10C are longitudinal cross-sectional views of a structure for moving
the suction pipe.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0028] Exemplary embodiments of the present invention are described in detail below with
reference to the accompanying drawings.
[0029] A spinning machine (yarn winding apparatus) according to an embodiment of the present
invention is described below. Note that "upstream" and "downstream" used in this specification
are upstream and downstream, respectively, with respect to a running direction of
a yarn during spinning. FIG. 1 is a schematic elevation view of an overall structure
of a spinning machine 1 according to the embodiment. FIG. 2 is a longitudinal cross-sectional
view of the spinning machine 1.
[0030] The spinning machine 1 shown in FIG. 1 includes a plurality of spinning units (winding
units) 2 arranged in a line. The spinning machine 1 also includes a splicer carrier
3, a doffer carrier 4, a blower box 93, and a motor box 5.
[0031] As shown in FIG. 1, each of the spinning units 2 includes a drafting device 7, a
spinning device 9, a yarn pooling device 12, and a winding device 13, which are arranged
from upstream to downstream in this order. The drafting device 7 is provided near
a top end of a frame 6 of the spinning machine 1. A fiber bundle 8 fed from the drafting
device 7 is spun by the spinning device 9 into a spun yarn 10. The spun yarn 10 from
the spinning device 9 passes through a yarn clearer 49, which will be described later,
and then passes through the yarn pooling device 12. The winding device 13 winds the
spun yarn 10 on a bobbin 48 to form a package 45.
[0032] The drafting device 7 drafts a sliver 15 into the fiber bundle 8. As shown in FIG.
2, the drafting device 7 includes four pairs of rollers, or, more specifically, a
pair of back rollers 16, a pair of third rollers 17, a pair of middle rollers 19 around
each of which an apron belt 18 is laid, and a pair of front rollers 20.
[0033] Although a detailed structure of the spinning device 9 is not shown, in the present
embodiment, an air-jet-spinning-type spinning device is employed as the spinning device
9. More specifically, the spinning device 9 twists the fiber bundle 8 by using a swirling
airflow to form the spun yarn 10.
[0034] The yarn pooling device 12 is arranged downstream of the spinning device 9. The yarn
pooling device 12 has a function of drawing out the spun yarn 10 from the spinning
device 9 while applying a predetermined tension on the spun yarn 10, a function of
pooling the spun yarn 10 fed from the spinning device 9 to prevent a slack in the
spun yarn 10 during splicing performed by the splicer carrier 3, and a function of
adjusting a yarn tension so that variations in the yarn tension on the side of the
winding device 13 are not transmitted to the spinning device 9. As shown in FIG. 2,
the yarn pooling device 12 includes a yarn pooling roller 21, a yarn hook member 22,
an upstream guide 23, and an electric motor 25.
[0035] The yarn hook member 22 is capable of hooking (catching) the spun yarn 10. The yarn
hook member 22 rotates in one piece with the yarn pooling roller 21 in a state where
the spun yarn 10 is hooked by the yarn hook member 22 so that the spun yarn 10 is
carried onto an outer peripheral surface of the yarn pooling roller 21.
[0036] The yarn pooling roller 21 pools the spun yarn 10 by winding the spun yarn 10 on
an outer peripheral surface of the yarn pooling roller 21. The yarn pooling roller
21 is rotated at a predetermined rotational speed by the electric motor 25.
[0037] The yarn hook member 22 is rotatably supported relative to the yarn pooling roller
21. On the yarn hook member 22, a torque (resisting torque) against rotation of the
yarn hook member 22 relative to the yarn pooling roller 21 is applied by a torque
generating section (not shown) implemented as, for example, a magnetic-torque generating
section. With this structure, in a situation where the spun yarn 10 is hooked by the
yarn hook member 22, if a tension applied to the spun yarn 10 is large enough to overcome
the resisting torque, the yarn hook member 22 rotates independently of the yarn pooling
roller 21, thereby unwinding the spun yarn 10 from the yarn pooling roller 21. On
the contrary, if the tension applied to the spun yarn 10 is weaker than the resisting
torque, the yarn hook member 22 rotates in one piece with the yarn pooling roller
21, thereby winding the spun yarn 10 on the yarn pooling roller 21.
[0038] As described above, the yarn pooling device 12 winds the spun yarn 10 when the tension
applied to the spun yarn 10 decreases (i.e., when a slack is likely to be given to
the spun yarn 10), while the yarn pooling device 12 unwinds the spun yarn 10 when
the tension applied to the spun yarn 10 increases. Accordingly, the yarn pooling device
12 is capable of taking up a slack in the spun yarn 10 and applying an appropriate
tension on the spun yarn 10.
[0039] As described above, the yarn hook member 22 acts to accommodate variations in the
tension applied to the spun yarn 10 between the yarn pooling device 12 and the winding
device 13. Accordingly, it is possible to prevent the variations in the tension from
influencing the spun yarn 10 between the spinning device 9 and the yarn pooling device
12. Thus, the yarn pooling device 12 can draw out the spun yarn 10 from the spinning
device 9 at a relatively steady velocity.
[0040] The upstream guide 23 is arranged at a position slightly upstream with respect to
the yarn pooling roller 21. The upstream guide 23 serves as a guide member for an
appropriate carriage of the spun yarn 10 to the outer peripheral surface of the yarn
pooling roller 21. The upstream guide 23 also serves as a twist preventer that prevents
propagation of twisting of the spun yarn 10 to a downstream side beyond the upstream
guide 23.
[0041] The yarn clearer 49 is arranged on a front-surface side of the frame 6 of the spinning
machine 1 at a position between the spinning device 9 and the yarn pooling device
12. The spun yarn 10 spun by the spinning device 9 passes through the yarn clearer
49 before the spun yarn 10 is wound by the yarn pooling device 12. The yarn clearer
49 monitors the thickness of the running spun yarn 10. Upon detecting a yarn defect
of the spun yarn 10, the yarn clearer 49 transmits a yarn-defect detection signal
to a unit controller (not shown). The yarn clearer 49 can be configured to detect,
in addition to an abnormal thickness of the spun yarn 10, a foreign matter in the
spun yarn 10.
[0042] Upon receiving the yarn-defect detection signal from the yarn clearer 49, the unit
controller stops driving of the drafting device 7 while causing the winding device
13 to continue driving, thereby cutting the spun yarn 10. The unit controller then
stops the drafting device 7, the spinning device 9, and the like. The unit controller
transmits a control signal to the splicer carrier 3. Upon receiving the control signal,
the splicer carrier 3 travels to a position in front of the corresponding spinning
unit 2. Thereafter, the unit controller resumes driving of the spinning device 9 and
the like and causes the splicer carrier 3 to perform splicing to resume winding. The
yarn pooling device 12 successively pools the spun yarn 10, which is continuously
fed from the spinning device 9, on the yarn pooling roller 21 to take up a slack in
the spun yarn 10 over a period from when the spinning device 9 resumes spinning until
when winding is resumed.
[0043] As shown in FIGS. 1 and 2, the splicer carrier 3 includes a splicer (yarn splicing
device) 43, a suction pipe 44, a suction mouth 46, and wheels 42. When yarn breakage
or yarn cutting occurs in one of the spinning units 2, the splicer carrier 3 runs
on a travel lane 41 fixed to the frame 6 by driving the wheels 42. The splicer carrier
3 then stops in front of the spinning unit 2 where the yarn breakage or yarn cutting
has occurred to perform the splicing.
[0044] The suction pipe 44 is vertically pivotable about a shaft. The suction pipe 44 sucks
and catches a yarn end (upper yarn) of the spun yarn 10 fed from the spinning device
9, and carries the yarn end to the splicer 43. The suction mouth 46 is vertically
pivotable about a shaft. The suction mouth 46 sucks and catches a yarn end (lower
yarn) of the spun yarn 10 extending from the package 45, and carries the yarn end
to the splicer 43. Although description about a detailed structure of the splicer
43 is omitted, the upper yarn and the lower yarn can be spliced by twisting yarn ends
by using a swirling airflow.
[0045] The winding device 13 includes a cradle 70. The cradle 70 includes a support shaft
73, a cradle arm 71 that is pivotable about the support shaft 73, and a pair of bobbin
holders (bobbin holding section) 72 capable of holding the bobbin 48 at the ends of
the bobbin 48.
[0046] The winding device 13 includes a winding drum 74 and a traverse guide 76, on which
the spun yarn 10 can be hooked. The winding drum 74 is driven in contact with either
an outer peripheral surface of the bobbin 48 or an outer peripheral surface of the
package 45 that is formed by winding the spun yarn 10 on the bobbin 48. The winding
device 13 causes an electric motor (not shown) to drive the winding drum 74, thereby
rotating the package 45 that is in contact with the winding drum 74. Simultaneously,
the winding device 13 causes the traverse guide 76 to reciprocate by using a drive
mechanism (not shown). Thus, the winding device 13 winds the spun yarn 10 on the package
45 while causing the spun yarn 10 to traverse.
[0047] A spring (not shown) is coupled to the cradle arm 71. The spring constantly applies
an urging force in an upright direction onto the cradle arm 71. Accordingly, as the
thickness of the package 45 increases with an increasing amount of the spun yarn 10
wound on the bobbin 48, the cradle arm 71 tilts toward the front-surface side of the
device, and hence a position of the axis of the package 45 is moved forward. A driving
section (not shown) (e.g., a cylinder) is coupled to the cradle arm 71. It is also
possible to perform control according to an instruction fed from the unit controller
so as to actively cause the cradle arm 71 to pivot in a direction away from the winding
drum 74 and a direction toward the winding drum 74.
[0048] The spinning machine 1 according to the present embodiment can form any one of a
cheese-shaped package and a conical package by changing some of the elements constituting
the cradle 70. Meanwhile, the same winding drum 74 is used for forming the cheese-shaped
package and also for forming the conical package.
[0049] When forming a cheese-shaped package, a bobbin for the cheese-shaped package is supported
by the cradle 70 in a manner that an axis of the bobbin is substantially parallel
to an axis of the winding drum 74. When forming the package 45 of a conical shape,
the bobbin 48 for the conical package is supported by the cradle 70 in a manner that
the axis of the bobbin 48 is slightly inclined relative to the axis of the winding
drum 74 so that the winding drum 74 is brought into stable contact with a conical
outer-peripheral surface of the package 45. Therefore, a position of the bobbin holders
72 for forming a cheese-shaped package differs from a position of the bobbin holders
72 for forming a conical package. Meanwhile, conical packages can have various taper
angles. Therefore, the cradle 70 supports the bobbin 48 in an orientation depending
on a taper angle of a package to be formed.
[0050] As shown in FIGS. 1 and 2, the doffing cart 4 includes a bobbin installation device
60. The bobbin installation device 60 performs a bobbin installing operation and a
doffing operation. The bobbin installing operation is an operation of supplying the
bobbin 48 to the cradle 70 to prepare for winding of the spun yarn 10 onto the bobbin
48. The doffing operation is an operation of dismounting the package 45 that is fully
wound from the cradle 70. The doffing cart 4 includes wheels 92 at a bottom of the
doffing cart 4. Upon receiving an instruction to perform the bobbin installing operation
or the doffing operation on one of the spinning units 2, the doffing cart 4 travels
on a travel lane 91 formed on the frame 6 to the corresponding spinning unit 2. The
doffing cart 4 stops in front of the spinning unit 2 for which the instruction was
issued, and then performs any one (or both) of the bobbin installing operation and
the doffing operation.
[0051] The bobbin installation device 60 includes, as the elements for performing the bobbin
installing operation, a bobbin supplying section 50, a suction pipe (yarn catching-and-carrying
device) 88, and a cradle operating arm (operating section) 89.
[0052] The suction pipe 88 has a pivotable and telescopic structure. The suction pipe 88
catches the spun yarn 10 discharged from the spinning device 9 by sucking the spun
yarn 10 and carries the spun yarn 10 to the winding device 13. A structure for moving
the suction pipe 88 is described later.
[0053] The bobbin supplying section 50 that includes a bobbin gripping section 52 is pivotable
about a rocker shaft 111 and is capable of gripping the bobbin 48 with the bobbin
gripping section 52. The bobbin supplying section 50, in which the bobbin gripping
section 52 grips the bobbin 48, is caused to pivot to supply the bobbin 48 to a position
(target position) between the bobbin holders 72 of the cradle 70. The bobbin supplying
section 50 includes a bunch winding roller 53 for performing bunch winding. Bunch
winding means winding the spun yarn 10 in a straight winding manner around the bobbin
48 to fix the spun yarn 10 onto the bobbin 48 at the start of winding to form a package.
A detailed structure of the bobbin supplying section 50 is described later.
[0054] The cradle operating arm 89 can operate the cradle arm 71 such that one of the bobbin
holders 72 is moved away from the other bobbin holder 72 (separating operation). Meanwhile,
as described above, as the thickness of the package 45 increases with increasing amount
of the spun yarn 10 wound on the bobbin 48, the orientation of the cradle arm 71 changes.
The position of the cradle operating arm 89 can be changed by using a moving mechanism,
which will be described later, or the like. Accordingly, the cradle operating arm
89 can perform the separating operation during each of the doffing operation (see
FIG. 6) of dismounting the fully wound package 45 and the bobbin installing operation
(see FIG. 7).
[0055] The bobbin installation device 60 includes, as the elements for performing the doffing
operation, a guiding section 61 shown in FIG. 2 in addition to the cradle operating
arm 89. The guiding section 61 receives the fully wound package 45 from the cradle
70 and put it on a sloping member 81. Accordingly, the fully wound package 45 is carried
to a receptacle 82. The guiding section 61 includes, as relevant elements, a guiding
plate 69, a bobbin guiding cylinder 62, and a roller member 67. The guiding section
61 is pivotable about a rotary shaft 101.
[0056] The guiding plate 69 includes a plate-like contact member and one or more plate-like
restricting members. The contact member is in contact with the outer peripheral surface
of the fully wound package 45 received from the cradle 70 while carrying the package
45. The restricting members restrict a movement of the package 45 in its axial direction
so that the package 45 does not fall from the contact member.
[0057] The bobbin guiding cylinder 62 applies a force on an acting shaft 104 by extending
or shortening a cylinder of the bobbin guiding cylinder 62, thereby causing the guiding
plate 69 to pivot about a rotary shaft 103 upward or downward. Thus, the guiding section
61 is capable of adjusting the position of the guiding plate 69 that is carrying the
package 45 or stopping an inertial rotation of the package 45 after completion of
winding of the spun yarn 10.
[0058] The roller member 67 rolls on the sloping member 81 when the package 45 is carried
along the sloping member 81. Accordingly, the guiding section 61 can carry the package
45 smoothly.
[0059] The bobbin supplying section 50 is described below in detail with reference to FIGS.
3 and 4. FIG. 3 is a perspective view of the bobbin supplying section 50 and illustrates
a situation where the bobbin supplying section 50 is supplying the bobbin 48 to the
cradle 70. FIG. 4 is a plan view of the bobbin supplying section 50 and illustrates
a situation where the bobbin supplying section 50 is supplying the bobbin 48.
[0060] As shown in FIGS. 3 and 4, the bobbin supplying section 50 includes, in addition
to the bobbin gripping section 52 and the bunch winding roller 53, a fixed arm 57,
a path adjusting plate (mounting member) 59, a pivot arm 58, a bobbin supplying cylinder
56, a bunch winding motor 54, and a gripping-section driving cylinder 55.
[0061] As described above, the bobbin supplying section 50 is pivotable about the rocker
shaft 111. A torsion spring 112 is wound around the rocker shaft 111. The torsion
spring 112 urges the pivot arm 58 in a direction (in which the bobbin gripping section
52 approaches the doffing cart 4) opposite from a direction in which the pivot arm
58 is pivoted to supply the bobbin 48.
[0062] The bobbin supplying cylinder 56 is a cylinder that can be extended or shortened
in response to an instruction issued by the bobbin installation device 60. One end
of the bobbin supplying cylinder 56 is attached to a basal end of the fixed arm 57.
The pivot arm 58 that is pivotable about the rocker shaft 111 is pivotably attached
to the other end of the bobbin supplying cylinder 56.
[0063] Extending the bobbin supplying cylinder 56 configured as described above in a manner
to overcome an urging force of the torsion spring 112 causes the pivot arm 58 to pivot
about the rocker shaft 111, and hence the bobbin 48 to be supplied to the cradle 70.
As shown in FIG. 4, the bobbin holders 72, i.e., a pair of holding mechanisms 72a,
hold the bobbin 48 therebetween in an axial direction of the bobbin 48. In the discussion
below, a straight line that connects holding centers 72b, which are the centers of
the holding mechanisms 72a, is referred to as a holding line L1. The holding line
L1 is, put another way, a rotation axis of the bobbin 48 when the bobbin 48 is arranged
between the bobbin holders 72. A straight line passing through the center of the rocker
shaft 111 in the longitudinal direction is referred to as a pivot axis L2.
[0064] The bobbin supplying section 50 includes an adjustment section that includes the
path adjusting plate 59 and a fixture. By inserting the fixture, such as a bolt, into
one of selection holes 115 defined in the path adjusting plate 59, the bobbin supplying
section 50 is fixed onto an appropriate member of the doffing cart 4. The selection
holes 115, which can be formed in an appropriate number, for example, five in the
present embodiment, are defined in the path adjusting plate 59. The position and the
orientation of the path adjusting plate 59 (accordingly, the position and the orientation
of the rocker shaft 111) can be adjusted as desired by inserting the fixture in an
appropriate selection hole 115. In the present embodiment, as illustrated in FIG.
4, the orientation of the rocker shaft 111 is adjusted in such a manner that the holding
line L1 becomes substantially parallel to the pivot axis L2.
[0065] A path of movement of a distal end of the pivot arm 58 is changed to a desired path
by adjusting the position and the orientation of the rocker shaft 111 as described
above. Thus, the bobbin installation device 60 can change the path of the bobbin 48,
along which the bobbin 48 is supplied to the bobbin holder 72. In the discussion below,
this path is referred to as a "bobbin supplying path" in some cases.
[0066] The bunch winding motor 54 generates a driving force for rotating the bunch winding
roller 53. This driving force is transmitted through a transmission mechanism (not
shown) (e.g., a belt and a pulley) to the bunch winding roller 53.
[0067] Meanwhile, to perform the bunch winding, it is necessary to bring the bunch winding
roller 53 into contact with the bobbin 48. For this reason, the bobbin supplying section
50 includes a moving mechanism (more specifically, the gripping-section driving cylinder
55, which will be described later) that moves the bunch winding roller 53 so that
it comes into contact with the bobbin 48.
[0068] As shown in FIG. 3, the bobbin gripping section 52 includes a fixed gripping member
113 and a movable gripping member 114. The movable gripping member 114 is coupled
to the gripping-section driving cylinder 55. The movable gripping member 114 is moved
toward or away from the fixed gripping member 113 by an action of the gripping-section
driving cylinder 55. The bobbin gripping section 52 can grip or ungrip the bobbin
48 in this way.
[0069] In the present embodiment, switching between a state where the bunch winding roller
53 is in contact with the bobbin 48 and a state where the bunch winding roller 53
is away from the bobbin 48 can be performed by using the gripping-section driving
cylinder 55. The action of the bobbin gripping section 52 is linked to the action
of the bunch winding roller 53. More specifically, when the bobbin 48 is gripped by
the bobbin gripping section 52, simultaneously the bunch winding roller 53 is separated
from the bobbin 48. When the bobbin 48 is ungripped by the bobbin gripping section
52, simultaneously the bunch winding roller 53 is brought into contact with the bobbin
48.
[0070] A conventional bobbin supplying path and the bobbin supplying path according to the
present embodiment are described below based on comparison therebetween with reference
to FIGS. 5A and 5B. FIGS. 5A and 5B are diagrams for explaining the differences between
the conventional bobbin supplying path and the bobbin supplying path according to
the present embodiment.
[0071] As described earlier in the discussion related to the conventional technology, collision
was likely to occur between the bobbin 48 being supplied and the bobbin holder 72
(see FIG. 5A). However, the bobbin supplying section 50 according to the present embodiment
performs adjustment whereby the holding line L1 is substantially parallel to the pivot
axis L2 as illustrated in FIG. 5B. Accordingly, parallelism between a central axis
of the bobbin 48 and the holding line L1 can be maintained during the course where
the bobbin 48 is being supplied. The bobbin supplying section 50 can supply the bobbin
48 along a circular path that lies along a plane orthogonal to the holding line L1.
[0072] Thus, the bobbin supplying section 50 is capable of supplying the bobbin 48 to a
position between the bobbin holders 72 in a manner that the bobbin 48 is inserted
in a relatively straight orientation and favorably fitted at the position. Accordingly,
it is possible to effectively utilize the space, on which a limitation in terms of
size is generally imposed, between the bobbin holders 72 to thereby avoid collision
between the bobbin 48 being supplied and the bobbin holder 72. In the spinning machine
1, it is difficult to have a relatively large space between adjacent ones of the spinning
units 2 because a large number of the spinning units 2 are installed in a limited
installation space.
[0073] As described above, the spinning machine 1 according to the present embodiment can
form, by changing some of the elements constituting the cradle 70, any one of a cheese-shaped
package and conical packages of different types that differ from one another in taper
angle. Put another way, the positions of the bobbin holders 72 and accordingly the
orientation of the holding line L1 are changed depending on the shape of the package
to be formed. In the bobbin installation device 60 according to the present embodiment,
it is possible to position the pivot axis L2 substantially parallel to the holding
line L1 irrespective of the shape of the package to be formed by attaching the path
adjusting plate 59 by using a corresponding one of the selection holes 115. Accordingly,
the bobbin installation device 60 can supply the bobbin 48 to the cradle 70 smoothly
in various situations and hence can be used for a wide variety of general purposes.
[0074] A sequence of the doffing operation and a sequence of the bobbin installing operation
performed by the bobbin installation device 60 are described below with reference
to FIGS. 6 to 8. The doffing operation is described first with reference to FIG. 6.
FIG. 6 is a longitudinal cross-sectional view of the spinning machine in a state where
the spun yarn 10 is caught by the suction pipe 88 while the doffing operation of the
fully wound package 45 is being performed.
[0075] When it is detected by a sensor (not shown) that the package 45 of one of the spinning
units 2 is fully wound, the unit controller causes the corresponding spinning device
9 to stop, and simultaneously commands the doffing cart 4 to travel to the corresponding
spinning unit 2. Substantially concurrently therewith, the unit controller performs
control operations to cause the cradle arm 71 of the corresponding winding device
13 to pivot leftward of FIG. 2 (toward a front-surface side of the spinning unit 2),
thereby separating the fully wound package 45 from the corresponding winding drum
74, and to stop rotation of the package 45.
[0076] Even after the package 45 is separated from the winding drum 74, the package 45 continues
the inertial rotation. The bobbin installation device 60 extends the bobbin guiding
cylinder 62 of the guiding section 61, thereby causing the guiding plate 69 to pivot
upward to come into contact with the package 45. As a result, the inertial rotation
of the package 45 is stopped.
[0077] Until the inertial rotation of the package 45 is stopped completely, the bobbin installation
device 60 moves the cradle operating arm 89 to a position shown in FIG. 6. When the
inertial rotation of the package 45 is stopped completely, the bobbin installation
device 60 causes the cradle operating arm 89 to move the cradle arm 71 in a manner
that one of the bobbin holders 72 moves away from the other bobbin holder 72, thereby
dismounting the fully wound package 45 from the cradle 70.
[0078] The dismounted fully wound package 45 is conveyed to the sloping member 81 while
the weight of the package 45 is supported by the guiding plate 69 (more specifically,
the contact member) of the guiding section 61. The guiding section 61 causes the package
45 to roll down the sloping member 81 to thereby move the package 45 while remaining
in the state of contacting the package 45. Meanwhile, at this time, the roller member
67 of the guiding section 61 rolls on the sloping member 81. Thereafter, the package
45 is carried to the receptacle 82.
[0079] In the present embodiment, the receptacle 82 functions as a conveyer. The receptacle
82 conveys the package 45 in the direction, in which the spinning units 2 are arranged,
to thereby automatically deliver the package 45 to a subsequent process. Alternatively,
a configuration can be employed in which the receptacle 82 does not function as a
conveyer and the package 45 on the receptacle 82 is manually collected by an operator.
The doffing operation is performed as described above.
[0080] The bobbin installing operation is described below with reference to FIGS. 6 to 8.
FIG. 7 is a longitudinal cross-sectional view of the spinning unit 2 in a state where
the suction pipe 88 has moved to a predetermined position and is in a standby state
with the spun yarn 10 remaining sucked by the suction pipe 88. FIG. 8 is a longitudinal
cross-sectional view of the spinning unit 2 at an instant at which the bobbin 48 is
supplied to the cradle 70.
[0081] When the doffing cart 4 reaches a position in front of the corresponding spinning
units 2 as commanded, the unit controller of the spinning unit 2 causes the drafting
device 7 and the spinning device 9 to resume driving. Substantially simultaneously
therewith, the suction pipe 88 is extended upward (see FIG. 6). The suction pipe 88
catches the spun yarn 10 by sucking a yarn end of the spun yarn 10 discharged from
the spinning device 9.
[0082] The bobbin installation device 60 moves the suction pipe 88 downward with the spun
yarn 10 remaining sucked by the suction pipe 88. At this time, the unit controller
performs control operations so that the spun yarn 10 sucked by the suction pipe 88
is wound around the yarn pooling device 12. Meanwhile, a suction force of the suction
pipe 88 is relatively small and does not overcome the resisting torque of the yarn
pooling device 12. Accordingly, as shown in FIG. 7, the spun yarn 10 is pooled on
the yarn pooling device 12.
[0083] After the suction pipe 88 has been moved downward, the bobbin installation device
60 leaves the suction pipe 88 in the standby state at the predetermined position (see
FIG. 6). When the suction pipe 88 is moved as described above, substantially simultaneously,
the bobbin installation device 60 moves the cradle operating arm 89 to a position
where the cradle operating arm 89 can operate the cradle 70. Before the bobbin 48
is supplied, the bobbin installation device 60 operates the cradle arm 71 in advance
to move one of the bobbin holders 72 away from the other bobbin holder 72.
[0084] Subsequently, the bobbin installation device 60 grips the bobbin 48 stocked in an
upper portion of the doffing cart 4 with the bobbin supplying section 50 (the bobbin
gripping section 52). Thereafter, the bobbin installation device 60 extends the bobbin
supplying cylinder 56, thereby causing the pivot arm 58 to pivot. Thus, the bobbin
installation device 60 causes the bobbin supplying section 50 to advance from the
side of the doffing cart 4, thereby supplying the bobbin 48 to the cradle 70. The
bobbin installation device 60 actuates an appropriate yarn guiding mechanism (not
shown) of the bobbin supplying section 50, thereby placing the spun yarn 10 caught
by the suction pipe 88 at a position between an axial end portion of the bobbin 48
and one of the bobbin holders 72. In this state, the cradle operating arm 89 operates
the cradle arm 71 such that one of the bobbin holders 72 approaches the other bobbin
holder 72. As a result, the spun yarn 10 is fixed by being pinched between the end
portion of the bobbin 48 and the bobbin holder 72.
[0085] Subsequently, the bobbin installation device 60 performs the bunch winding by actuating
the gripping-section driving cylinder 55 to cause the bobbin gripping section 52 to
ungrip the bobbin 48 and bringing the bunch winding roller 53 into contact with the
bobbin 48. Meanwhile, the structure of the bobbin installation device 60 can be simplified
because, as described above, the action of the bobbin gripping section 52 is linked
with the action of the bunch winding roller 53.
[0086] When the bunch winding is completed, the bobbin supplying cylinder 56 is shortened,
causing the bobbin supplying section 50 to retreat to the side of the doffing cart
4. Substantially concurrently therewith, the unit controller causes the cradle 70
to pivot so as to bring the bobbin 48 into contact with the winding drum 74 (i.e.,
toward a back-surface side of the spinning unit 2). As a result, a winding tension
is applied on the spun yarn 10, causing the spun yarn 10 to be gradually unwound from
the yarn pooling roller 21 and the winding device 13 to start winding to form the
package 45.
[0087] Subsequently, a structure for moving the cradle operating arm 89 and the suction
pipe 88 as described above is explained below. The structure related to the cradle
operating arm 89 is explained first with reference to FIGS. 9A to 9C. FIGS. 9A to
9C are longitudinal cross-sectional views for explaining the structure for moving
the cradle operating arm 89.
[0088] As shown in FIGS. 9A to 9C, the bobbin installation device 60 includes a driving
mechanism 30 for changing the position of the cradle operating arm 89. The drive mechanism
30 includes a first driving cylinder 31 and a second driving cylinder 32 that are
extended or shortened in response to a change in pressure of air supplied to the cylinders.
The drive mechanism 30 includes a first link member 36, a second link member 37, and
a third link member 38 that are coupled into one piece.
[0089] FIG. 9A illustrates a state where the cradle operating arm 89 is at a standby position.
When the first drive cylinder 31 is extended from the state shown in FIG. 9A to cause
the first link member 36 to rotate, the third link member 38, which is coupled to
the first link member 36 via the second link member 37, is rotated. As a result, the
distal end of the cradle operating arm 89 supported by the third link member 38 is
brought to a lower position (see FIG. 9B). The cradle operating arm 89 at the position
shown in FIG. 9B can operate the cradle arm 71 that receives the bobbin 48 as shown
in FIG. 7.
[0090] When the second drive cylinder 32 is extended from the state shown in FIG. 9B to
cause the cradle operating arm 89 to rotate relative to the third link member 38,
the distal end of the cradle operating arm 89 is brought to a further lower position
(see FIG. 9C). The cradle operating arm 89 at the position shown in FIG. 9C can, when
the package 45 is fully wound, dismount the package 45 from the cradle arm 71 as shown
in FIG. 6.
[0091] The structure for changing the position of the suction pipe 88 is described below
with reference to FIGS. 10A to 10C. FIGS. 10A to 10C are longitudinal cross-sectional
views of the structure for moving the suction pipe 88.
[0092] As shown in FIGS. 10A to 10C, the bobbin installation device 60 includes, as elements
for changing the position of the cradle operating arm 89, a coupling arm 123 and a
suction cylinder 124 that is extended or shortened in response to a change in pressure
of air supplied to the suction cylinder 124.
[0093] The coupling arm 123 is pivotably supported on the doffing cart 4 via a pivot point
121 that is arranged at an appropriate position on the doffing cart 4. A drive mechanism
(not shown) including, for example, a motor and a cam, that drives the coupling arm
123 is coupled to the coupling arm 123. The suction cylinder 124 and the suction pipe
88 are pivotably coupled to a leading end of the coupling arm 123 via a pivot point
122.
[0094] The suction pipe 88 is extendable because the suction pipe 88 has, for example, a
telescopic structure. The suction cylinder 124 is connected to a leading end of the
suction pipe 88. The suction pipe 88 can be extended or shortened by changing the
pressure of air supplied to the suction cylinder 124.
[0095] FIG. 10A illustrates the suction pipe 88 at a standby position. By extending the
suction cylinder 124 while causing the coupling arm 123 to pivot toward the winding
device 13, the suction pipe 88 can be moved to a position where the suction pipe 88
can catch the spun yarn 10 discharged from the spinning device 9 (see FIGS. 10B and
6). By causing the cradle operating arm 89 and the suction cylinder 124 to pivot about
the pivot point 122 from this state, the spun yarn 10 caught by the suction pipe 88
can be carried downward (see FIGS. 10C and 7).
[0096] Meanwhile, the drive mechanism 30 of the cradle operating arm 89 can operate the
cradle operating arm 89 singly by actuating the first drive cylinder 31 and the second
drive cylinder 32. Similarly, with regard to the suction pipe 88, the suction pipe
88 can be moved singly (without causing other members to move) to a desired position
by actuating the drive mechanism and the suction cylinder 124.
[0097] As described above, with the configuration according to the present embodiment, it
is possible to move the bobbin supplying section 50, the cradle operating arm 89,
and the suction pipe 88 that have conventionally been linked with one another, separately
(independently). Accordingly, in a situation where, for example, it is desired to
dismount the package 45 that is fully wound, but it is not necessary to supply the
bobbin 48, which is a new one, it is possible to move only the cradle operating arm
89 while leaving the bobbin supplying section 50 and the suction pipe 88 in a stopped
state. As a result, the bobbin installation device 60 can skip unnecessary operation(s),
thereby achieving reduction in cycle time.
[0098] As described above, the bobbin installation device 60 according to the present embodiment
includes the bobbin gripping section 52 and the path adjusting plate 59. The bobbin
gripping section 52 grips the bobbin 48, onto which the spun yarn 10 is to be wound,
and supplies the bobbin 48 to the bobbin holders 72 serving as the target position
(more specifically, the position between the bobbin holders 72). The path adjusting
plate 59 can adjust the path (bobbin supplying path), along which the bobbin 48 is
supplied by the bobbin gripping section 52 to the bobbin holders 72.
[0099] Accordingly, the bobbin installation device 60 can perform adjustment such that the
bobbin 48 is supplied through an appropriate path depending on the shape of the bobbin
48 to be supplied or the like. This adjustment prevents the bobbin 48 from colliding
with the bobbin holder 72 when the bobbin 48 is supplied by the bobbin installation
device 60 to the bobbin holders 72.
[0100] In the bobbin installation device 60 according to the present embodiment, the adjustment
section includes the path adjusting plate 59 and the fixture. The path adjusting plate
59 supports the bobbin gripping section 52. The fixture locks at least a change in
an installation orientation of the path adjusting plate 59.
[0101] Accordingly, by changing the installation orientation of the path adjusting plate
59 and fixing the path adjusting plate 59 in the changed orientation, the bobbin installation
device 60 can perform the adjustment to cause the bobbin 48 to be supplied through
an appropriate path.
[0102] In the bobbin installation device 60 according to the present embodiment, a plurality
of the selection holes 115 is defined in the path adjusting plate 59. The fixture
is positioned in one of the selection holes 115 to lock at least the change in the
installation orientation of the path adjusting plate 59.
[0103] The bobbin installation device 60 configured as described above is capable of adjusting
the path, along which the bobbin 48 is to be supplied, only by inserting the fixture
into one of the selection holes 115, which is selected based on a winding condition
and/or the like, to fix the path adjusting plate 59. The adjustment section that adjusts
the bobbin supplying path can thus have a simple structure. This leads to reduction
in the number of components involved in the bobbin installation device 60.
[0104] The spinning machine 1 according to the present embodiment includes the bobbin installation
device 60 and the spinning units 2. Each of the spinning units 2 includes a pair of
the bobbin holders 72 that hold the bobbin 48 supplied from the bobbin installation
device 60.
[0105] Accordingly, in the spinning machine 1, collision between the bobbin 48 and the bobbin
holder 72 can be prevented by adjusting the path, along which the bobbin 48 is to
be supplied.
[0106] In the spinning machine 1 according to the present embodiment, the bobbin holders
72 include the holding mechanisms 72a that hold the bobbin 48 at the two ends in the
axial direction of the bobbin 48. When the line extending through the holding centers
72b, which are the centers of the holding mechanisms 72a, is referred to as the holding
line L1, the path adjusting plate 59 can adjust the orientation of the rocker shaft
111 so as to make the pivot axis L2 of the rocker shaft 111 substantially parallel
to the holding line L1.
[0107] If the holding line L1 is not parallel to the rocker shaft 111, the bobbin 48 being
supplied is likely to collide with the bobbin holder 72. However, the bobbin installation
device 60 configured as described above can smoothly supply the bobbin 48 to the bobbin
holders 72 without employing a layout, in which a clearance between the holding mechanisms
72a of the bobbin holders 72 is unnecessarily large. Therefore, the spinning machine
1 can be configured compact.
[0108] In the spinning machine 1 according to the present embodiment, the bobbin installation
device 60 includes the cradle operating arm 89 that operates the cradle 70 to dismount
the bobbin 48 from the bobbin holders 72 of the cradle 70.
[0109] The doffing operation, such as dismounting of the package 45, is in many cases followed
by the operation of supplying the bobbin 48, which is a new one, to form the package
45, which is a new one. In the spinning machine 1 configured as described above, both
of the dismounting operation and the bobbin supplying operation can be performed in
one bobbin installation device 60. Accordingly, the spinning machine 1 can be configured
compact as a whole.
[0110] The spinning machine 1 according to the present embodiment can perform the operation
of supplying the bobbin 48, which is performed by the bobbin supplying section 50,
and the operation of dismounting the package 45, which is performed by the cradle
operating arm 89, independently.
[0111] Accordingly, the doffing operation and the operation of supplying the bobbin 48 can
be performed independently. This makes it possible to prevent an unnecessary operation
of supplying the new bobbin 48 from being performed in a situation where, for example,
it is not necessary to form the package 45, which is a new one, immediately after
one of the packages 45 has been fully wound. Accordingly, working time of the bobbin
installation device 60 can be shortened. Furthermore, the doffing cart 4 can travel
to another one of the spinning units 2 to start a subsequent operation quickly. This
leads to improvement in efficiency in winding of the spun yarn 10 by the spinning
machine 1.
[0112] The spinning machine 1 according to the present embodiment includes the suction pipe
88 that catches and carries the spun yarn 10 to the bobbin 48 that is supplied to
the bobbin holders 72 by the bobbin gripping section 52. The spinning machine 1 can
perform the operation of supplying the bobbin 48, which is performed by the bobbin
gripping section 52, the operation of dismounting the package 45, which is performed
by the cradle operating arm 89, and the yarn-catching-and-carrying operation, which
is performed by the suction pipe 88, independently.
[0113] In the spinning machine 1 configured as described above, unnecessary operation(s)
can be skipped depending on a situation that can vary. Accordingly, working time of
the bobbin installation device 60 can shortened and a subsequent operation can be
started quickly. This leads to improvement in efficiency in winding of the spun yarn
10 by the spinning machine 1.
[0114] In the spinning machine 1 according to the present embodiment, the spinning units
2 are arranged in one direction. The bobbin installation device 60 can travel in the
direction in which the spinning units 2 are arranged.
[0115] Such a structure allows reduction in the number of the bobbin installation devices
60 that need to be provided as compared to a structure in which the bobbin installation
devices 60 are provided on a per-spinning-unit-2 basis, thereby achieving cost reduction.
[0116] Although the preferred embodiments of the present invention are described above,
the structures discussed above can be modified as described below, for example.
[0117] The structure of the spinning machine 1 can be modified appropriately according to
a situation. For example, the structure can be modified to a structure in which a
yarn feeding device including a pair of rollers is provided in lieu of the yarn pooling
device 12 of the spinning machine 1 according to the embodiments or in addition to
the yarn pooling device 12 downstream of the spinning device 9.
[0118] The scope of application of the present invention is not limited to spinning machines.
The present invention is applicable to any yarn winding apparatus, other than a spinning
machine, so long as the yarn winding apparatus supplies a bobbin and winds a yarn
onto the bobbin.
[0119] In the embodiment described above, when a yarn defect is detected or when a like
situation occurs, the spun yarn 10 is cut by stopping the drafting device 7 with the
winding device 13 continuing driving. However, a structure in which a cutter is provided
near the yarn clearer 49 and the cutter cuts the spun yarn 10 can alternatively be
employed.
[0120] The spinning machine 1 according to the embodiment described above has the structure,
in which the fixture, such as a bolt, is inserted into an appropriate one of the selection
holes 115 defined in the path adjusting plate 59 to thereby fix the bobbin supplying
section 50 onto the doffing cart 4. In lieu of this structure, the spinning machine
1 can have a structure, in which a projection is formed on a surface of the spinning
machine 1 where the path adjusting plate 59 is provided, and the projection is inserted
into one of the selection holes and the path adjusting plate 59 is fixed with a nut
or the like. The structure of the adjustment section is not limited to that described
above, and can have any structure that can adjust at least the installation orientation
(the bobbin supplying path) of the path adjusting plate 59. In lieu of the structure,
in which the adjustment section adjusts the position and the orientation of the rocker
shaft 111, a structure, in which the adjustment section can adjust only the orientation,
can alternatively be employed.
[0121] In the embodiment described above, moving the guiding section 61 away from the bobbin
holders 72 and moving the bobbin supplying section 50 toward the bobbin holders 72
are performed concurrently and simultaneously. Alternatively, the bobbin installing
operation can be performed after completion of the doffing operation. However, from
a viewpoint of operation efficiency of the spinning machine 1, the doffing operation
and the bobbin installing operation are desirably performed concurrently and simultaneously.
[0122] Although the invention has been described with respect to specific embodiments for
a complete and clear disclosure, the appended claims are not to be thus limited but
are to be construed as embodying all modifications and alternative constructions that
may occur to one skilled in the art that fairly fall within the basic teaching herein
set forth.