Technical Field
[0001] The present invention relates to a device for interconnection of two parts (panels)
of road barrier made of solid materials, particularly concrete, wherein the device
is disposed in an upper recess being performed on a front connecting end of each barrier
part.
[0002] The invention also relates to a method of mutually connecting the parts of road barrier
by means of the above device.
Background Art
[0003] Currently, the requirements for intercepting road systems formed by road barriers
are in the Czech Republic set by a valid standard

SN EN 1317, 1 to 5 "Silni

ni záchytné systémy" and TP

SD

R No. 114 "Svodidla na PK" and No. 139 "Betonové svodidlo".
[0004] These regulations specify both qualitative technical requirements and requirements
for safety barriers in terms of its retention, as well as terms of testing, including
the classification of level of detention group.
[0005] Briefly, these requirements can be summarized in the following areas:
- requirements for the class of level of detention, setting out the parameters of detention
action for passenger cars, buses, trucks,
- design of the shape of the individual components of crash barriers;
- requirements for joining the various parts of crash barriers;
- requirements for the resistance of the material of the elements of crash barriers
to the effects of frost and deicing chemical agents;
- safety requirements related to the behavior of materials under impact;
- security requirements of road barriers detention and deformation effects, both locally
and as a whole.
[0006] Beyond these regulations there are known observations of Road and Motorway Directorate
of the Czech Republic as a decisive and dominant user of currently used crash barriers
in the Czech Republic. They can be summarized into the following points:
- the issue of retention levels of the concrete that is used;
- splicing of components of crash barriers in the vertical and horizontal curvature
of the route of crash barriers;
- problematic function of connections between parts of crash barriers in terms of structural
behavior;
- labor-intensive assembly and disassembly in the exchange of one sheet of barriers;
- inability to dismantle the connection points of parts of crash barriers, resulting
in that the joints cannot be dismantled;
- the effect of corrosion and dirt, leaking over time into the joints of the individual
components of the barriers and causing that the joints cannot be dismantled;
- irregular contact between the parts of the crash barriers in the crash barrier crossing
angle castings, thereby losing their essential interception function;
- failure to comply with new requirements in terms of standards of behavior in its concrete
crushing in the process of intercepting function of crash barriers and the threat
to safety in adjacent lanes;
- occurrence of surface cracks in the concrete of road barriers between individual parts
as the initiation of destruction by frost and chemical deicing agents.
[0007] At present, the concrete barriers of all classes of retention level are massively
used on all types of roads, including adjacent areas (road shoulders) and parking.
[0008] Concrete barriers tend to have the same storage size, but differ in shape and particularly
in the way of how they are interconnected. Mostly, the individual parts of concrete
crash barriers are made of concrete with aeration, a measure addressing the durability
of concrete against the effects of frost and chemicals.
[0009] As the disadvantages of the current state of the art concrete road barriers the following
facts must be also considered:
[0010] The currently used dense concrete with sole use of aeration is very delicate to the
production, especially on the processing technology, while disorder in the area of
processing technology on the contrary always result in a reduction of concrete resistance
to the effects of frost and deicing chemical means or reducing the strength of concrete
- frequent crashes of parts of the road barriers are a good proof of that.
[0011] The currently used dense concrete with sole use of aeration is bursting spontaneously
and instantaneously during its destruction, while differently sized pieces of concrete
of the road barrier are spread all around, endangering other road users. Such concrete
does not have the characteristics which are required by EU and Czech CSN standards
and recommendations.
[0012] The connection of parts of road barriers is known from the utility model CZ UV-2970,
which is created by connecting plates, bolts and nuts and reinforcing rods with thread
and nut anchored in concrete crash barrier elements, where the reinforcing bars are
connected between different parts of the barrier line by connecting plates, bolts
and nuts. This joint is very laborious and expensive, statically impure with possible
dangerous additional forces caused by the deformation under load. The connection can
be easily alienated. Anchorage reinforcement bars coupling, held in the concrete barrier
cohesion components under load, causes destruction of the concrete around the joints
and allows spreading of large chunks of concrete road barriers, which is a big safety
issue. Connections allow the construction only at small angular displacement of parts
to each other.
[0013] Another connection of road barriers is described in the solution according to European
patent
EP 1528151, which is created by embedding "C" sections into concrete in the head of barriers
parts, while their connection is achieved by inserting the "I" profiles into those
C sections. This connection eliminates some of the deficiencies described above, but
new problems arise. At a higher angle of rotation of parts to each other, this joint
is hard to realize or even it is not feasible. After completion of the barrier function
under load, the joint is irreversibly deformed and, virtually, it cannot be dismantled.
[0014] A similar problem arises by incorrect assembly or in cases where impurities or chemical
de-icing agents are clogged into the joints. The behavior of concrete during its destruction
is identical as in case of the one described above, including the issue of quality
of concrete resistance to de-icing chemical agents, which is dependent on the age
of the concrete.
[0015] The issues of presence of fine crack structures on the barrier panel have not yet
been successfully solved in any of the contemporarily used road barriers.
Disclosure of the Invention
[0016] The objective of this invention is to create a solution that eliminates the above-mentioned
shortcomings of prior art.
[0017] Another task of this invention is to create a new system of connecting the parts
of road barriers in the line.
[0018] According to this invention was developed equipment for the connection between the
two parts of road barrier of solid material, particularly concrete, which is located
in the upper recesses, created by connecting the front end of each barrier panel.
The device includes on each side in mirror-like manner against each other arranged:
- an anchor and cover casing, firmly anchored at its inner end to the barrier part by
means of an anchoring element wherein the casings are provided at their outer ends
with an opening with an internal thread;
- an anchor plate attached to the anchor and cover casing and bearing against inner
wall of the recess in the barrier part;
- a connecting anchor pin attached by means of a threaded connection to the casing and
being provided on one side with an internal thread and on the other side with a round
head with a central opening for a tool;
- a thread end half of two-piece connecting head having its inner surface provided with
a recess of half-round shape corresponding to the outer shape of the round head, wherein
the connecting head half is passed over the corresponding round head for mutual connection
by means of the thread.
[0019] One half of the connecting head is preferably provided with external threads, while
the other half is provided with internal threads.
[0020] Preferably, there is created a space for the rectification of the length of connection
in the length of the thread of the two halves of the connecting head.
[0021] In accordance with another aspect of this invention, a method of connecting the road
barriers made of solid material, particularly concrete, by means of the above components
was also developed.
[0022] The method includes the following steps:
- each part of the coupling barrier at its front connecting end provided with the upper
connecting recess for the location of joints;
- the anchoring element is horizontally attached to barrier part;
- the anchor and cover casing provided at its outer end with opening with internal thread
and anchor plate, where the anchor plate touches the inner side of the recess, is
attached to the anchoring element;
- one half of the connecting head provided with thread is passed over the connecting
anchor pin, which is provided with the outer thread on one side and with half rounded
head with central opening for a tool on the other;
- the connecting anchor pin with dressed half connecting head is mounted in anchoring
and cover casing equipped with internal thread to the thread opening;
- the fitting of the connection is adjusted by turning the connecting anchor pins;
- to obtain firm mutual connection of both halves of the connecting anchor pins, both
halves of the two-piece connecting head are joined together by means of screw connection;
[0023] The solution of the new connection of individual parts of road barriers consists
of a steel plate, which is firmly attached to an anchoring and a cover casing with
internal thread which is screwed into the connecting anchor pin, the pin being provided
with thread on one side and with half round head with a square opening, preferably
hexagonal, on the other.
[0024] Anchoring and cover casing is firmly anchored to the part of the barrier by means
of anchoring element, which is located at the opposite end than the internal thread.
[0025] The two-piece connecting head provided with thread is passed over the half round
head of the connecting anchor pin.
[0026] One half of the two-piece connecting head is always passed over the connecting anchor
pin before the pin is screwed to the anchoring and cover casing.
[0027] With this half of two-piece connecting head it is possible to move it along the shaft
of the connecting anchor pin so that it does not impede to assemble the parts of the
barrier together.
[0028] The parts of the two-piece connecting head assembled by screw connection interconnect
both connecting anchor pins of adjacent parts of the barriers and the parts are firmly
mounted.
[0029] The connection can be rectified and adjusted by revolving the connection in its axis
by means of connecting anchor pin.
[0030] With clearance in the length of the thread of both halves of the connecting head,
the length of the connection can be rectified and adjusted.
[0031] The internal recesses of both halves of the two-piece connecting head has the half-round
shape identical in inverse formation and also is identical to the shape of the half-round
end of the anchor pin.
[0032] The half round ends of the connecting anchor pins are interconnected by combining
both halves of the two-piece connecting head. This means that the barrier parts connection
is of a ball joint.
[0033] In the upper side of the part of the barrier there is an upper recess in which the
anchoring of the above described connection of the barrier parts is disposed.
[0034] When mounting components to the barrier line, the two opposing halves of the head
of two adjacent anchor elements are screwed into each other so that they are firmly
interconnected.
[0035] Such a line of interconnected parts of road safety barriers to the desired integral
length has the following features:
- the connection is created by ball joint, which is fully able to carry the burden that
is placed on him during functional load of the barrier,
- such ball joint allows angular rotation of one the part of the road barrier to another
one by ± 10 °, which is a reserve sufficient for the needs of mounting barrier parts
in different road directional curvatures and elevation,
- both the connecting anchor pin and the connecting head allow the longitudinal rectification,
adjustment and setting of the connection,
- both the connecting anchor pin and the connecting head are easy to assemble with low
labor inputs during the assembling, rectification or even after the disruption of
the part of the barrier or when the replacement is required so that the joint has
to be dismantled,
- the connection of the set of the barrier parts is statically pure and does not introduce
additional side forces into the construction,
- the connection is not sensitive to pollution including the effects of frost and chemical
de-icing agents, its functionality and ability to be dismantled is maintained even
after the destruction of the part of the road barrier,
- the construction of the connection allows easy and on other parts of the barrier independent
change of any part of the barrier anywhere in the line of the road barrier,
- the method of anchoring the connection to the part of the barrier eliminates the destruction
of the concrete in the surroundings of the anchor point caused by cohesion failure
with anchoring element.
[0036] For the production of parts of the road barrier the concrete of special formula has
been developed. Such special formula contains both the classic components of concrete,
i.e. water, cement, gravel, aggregates, plasticizers and aerating agents, which also
contains a combination of two unusual ingredients, which is the amorphous silica and
reinforcing fibers, which are mostly plastic.
[0037] Using a novel combination of special additives in concrete, the parallel creation
of bubbles in the concrete gel and a multiple augmentation of formation of the crystals
of hardening cement and blending of concrete with plastic fibers is achieved.
[0038] By adding these two special ingredients in the process of concrete formation, concrete
processing and maturing of the concrete, the aerated concrete with significant crystallization
of cement gel, thereby increasing its density and strength, reducing absorption of
reinforcing fibers, is obtained.
[0039] Due to aeration and by enhanced crystallization of amorphous silica cement, the resistance
of concrete to freezing and defrosting chemical agents is few times higher.
[0040] In fact, the resistance is doubled, which practically eliminates the accidents of
the parts of the barrier commonly seen today.
[0041] Using fiber reinforcement, the durability of the concrete is further protected against
massive development of cracks and surface layers of concrete barriers with a significant
reduction of concrete fragmentation, causing that a large parts of the barrier fall
off when carrying out its safety function.
[0042] Parts of crash barriers made of new concrete mixtures, exhibit new properties, thereby
removing some of the above described shortcomings of existing barriers.
[0043] Before casting the barrier parts, an anchor plate with securely attached anchor and
cover casing are inserted in the casting mould, while those elements are firmly attached
to the anchor element.
[0044] These parts of the new connections are firmly fixed to mould of the part of the barrier,
and this is in the area of the recess in future upper side of barrier part. Then the
pouring of mould by concrete follows.
[0045] After hardening of the concrete and removing the part of the barrier, the connecting
anchor pin is screwed into the required depth of the anchor and cover casing. Before
screwing the connecting anchor pin, the one half of the connecting head is passed
over the anchor pin so that the half round recesses of the head including the thread
is orientated towards the half round head of the connecting anchor pin.
Brief Description of Drawings
[0046] The invention will be further illustrated by example of its practical implementation
and the description will be given with regard to the drawings attached thereto, where:
Figure 1 shows a plan view of connection of two parts of the barrier;
Figure 2 shows a sectional view of this connection.
Example of Embodiment of the Invention
[0047] The embodiment of the connection of the parts of road barrier, displayed on Fig.
1 and 2, comprises of the steel anchor plate
2 and anchor and cover casing
3 with internal thread, the casing
3 is firmly attached to the anchor plate
2, further it comprises connecting anchor pin
5 which is screwed into the above internal thread and the pin
5 is provided with thread on one side and with half round head
9 with tool opening
7 on the other, where the opening
7 is preferably of hexagonal shape.
[0048] The anchor and cover casing
3 is firmly attached into the part
8 of the road barrier by anchoring element
4.
[0049] The two-piece connecting head
6, equipped with thread, is passed over the half round head
9 of the connecting anchor pin
5.
[0050] One half of the two-piece connecting head
6 is always attached to the anchor pin
5 before the pin 5 is screwed to the anchor and cover casing
3.
[0051] With this half of two-piece connecting head
6 it is possible to move it along the shaft of the connecting anchor pin
5 so that it does not impede to assemble the parts
8 of the barrier together.
[0052] The parts of the two-piece connecting head
6 assembled by screw connection interconnect both connecting anchor pins
5 of parts
8 of the barriers and the parts of the head
6 are firmly mounted.
[0053] The connection can be rectified and adjusted by revolving the connection in its axis
by means of connecting anchor pin
5.
[0054] The length of the connection can be rectified and adjusted with use of clearance
in the length of the thread of both halves of the connecting head
6.
[0055] The internal recesses of both halves of the two-piece connecting head
6 has the half-round shape identical in inverse formation with the shape of the half
round ends, that is with the half round head
9 of the connecting anchor pin
5.
[0056] The connection of half round ending of half round head
9 of the connecting anchor pins
5 and a creation of ball joint is performed by connecting both halves of the two-piece
connecting head
6.
[0057] The anchor and cover casing
3 with internal thread is firmly anchored with its opposite end to the part
8 of the road barrier by anchoring element
4.
[0058] In the upper side of the part
8 of the road barrier there is a recess
1 in which the anchoring of the above described connection of the parts
8 is performed.
Industrial Utilization
[0059] Road barriers, formed preferably of concrete parts that are connected according to
the present invention, meet the required standards and are suitable for use in areas
where it is necessary to build a solid retention system of the above described qualities.
1. A device for mutually connecting two parts (8) of road barrier of mass material, especially
mass concrete, wherein the device is disposed in an upper recess (1) being performed
on a front connecting end of each barrier part (8),
characterized by that the device comprises:
- an anchor and cover casings (3) that are arranged in mirror like manner on each
side and that are fixedly anchored at their inner end in the barrier part (8) by means
of an anchoring element (4) wherein the casings are provided at their outer end with
an opening with an internal thread;
- an anchor plate (2) being attached to the anchor and cover casing (3) and bearing
against inner wall of the recess (1) in the barrier part (8);
- a connecting anchor pin (5) being attached by means of a threaded connection to
the casing (3) and being provided on one side with an internal thread and on the other
side with a round head (9) with a central opening for a tool;
- a thread end half of two-part connecting head (6) having its inner surface provided
with a recess of half-round shape corresponding to the outer shape of the round head
(9), wherein the connecting head (6) half is passed over the corresponding round head
(9) for mutual connection by means of the thread.
2. A device according to claim 1, characterized by that one half of the connecting head (6) is provided with external thread, while the other
half is provided with internal thread.
3. A device according to claim 1 and 2, characterized by that in the length of the thread of both halves of the two-piece connecting head (6) the
device is provided with a clearance for rectification and adjustment of the length
of the connection.
4. A method of connecting the two parts (8) of road barrier of mass material, especially
mass concrete, by means of the device according to any of claims 1 to 3,
characterized by that:
- each part (8) of the barrier at its front connecting end provided with the upper
recess (1) for the location of connection;
- the anchoring element (4) is horizontally attached to barrier part (8);
- the anchor and cover casing (3) provided at its outer end with opening with internal
thread and anchor plate (2) thereto, where the anchor plate touches the inner side
of the recess (1), is attached to the anchoring element (4);
- one half of the connecting head (6) provided with thread is passed over the connecting
anchor pin (5), which is provided with the outer thread on one side and with half
rounded head (9) with central opening (7) for a tool on the other;
- the connecting anchor pin (5) with dressed half of connecting head (6) is mounted
to the thread opening in anchoring and cover casing (3) equipped with internal thread;
- the fitting of the connection is adjusted by turning the connecting anchor pins
(5);
- both halves of the two-piece connecting head (6) are joined together by means of
screw connection to obtain firm mutual connection of both halves of the connecting
anchor pins (5).