Field of the invention
[0001] The invention falls within the technical sector of the creation of tunnels and perforations
for making linear construction projects, whether road, railroad, mining, communication,
and goods transport tunnels, and all those related with perforations for the extraction
of gases or combustible (solid or liquid) materials.
Background of the invention
[0002] The creation of the different types of tunnels and perforations in civil engineering
works is carried out mainly in earth of solid rocks with low bearing capacity or high
deformability, where a whole of systems annexed to the main excavation takes place
and they serve as support of the earth or solid rock in which the excavation is made.
[0003] As an anchor and support mechanism solid bolts are used normal to the direction of
advance of the main tunnel, they can be grouped in structures of bolt umbrella or
fiberglass bolts located on the advancing front, achieving the supporting of the structure
when reducing stresses and deformations (horizontal and vertical) that occur during
the excavation works, caused by the weight of the earth or solid rock located above
the excavation site, assuming these materials part of stress and deformation states
of the work.
[0004] Regardless of the constructive procedure considered for the creation (German, Belgian,
new Austrian method, tunnel boring machine in different formats), the bolts are very
important elements in the above-defined sector, since their correct sizing allows
a proper realization of the work, avoiding partial or complete collapses of both the
advancing front and the part already excavated. Currently, this whole set of annexed
systems needs for its creation both a complex equipment of work and high budget rates.
[0005] The aim would be to reduce stresses and deformations values in the main tunnel, moderating
and eliminating in turn the need to use systems annexed to the same and thus decreasing
both the time-frame for construction and the budget rates intended for that purpose,
allowing an increase in safety during the realization of the works.
Explanation of the invention
[0006] The present invention focuses on the creation of one or several tunnels or perforations
(called tunnel or sacrificial tunnels) with section circular and small diameter and
located concentrically at some distance from the main tunnel or perforation, they
can be coated or not, such that they assume stresses and deformations (horizontal
and vertical) caused by the earth strata or solid rocks located above the main tunnel
or perforation.
Brief description of the drawings
[0007] In the event that the sacrificial tunnel (1) is unique, as shown in figures 1 and
2, the sacrificial tunnel (1) is located above the vertical of the keystone of the
main tunnel (2), at a distance of between 30% and 50% of the height of the latter,
and with a diameter of between 10% and 20% of the height of the main tunnel, keeping
the axis of the sacrificial tunnel parallel to the axis of the main tunnel.
Figure 1
Cross section of a tunnel in any section of earth, made with semicircular shape with
elephant leg in the support area, being represented only and because of symmetry,
the left side of the work. Above the keystone of the main tunnel (2), is located the
sacrificial tunnel (1), in order to assume part of the stress and deformational state
of the earth above it to the zero height of the same.
Figure 2
Cross-longitudinal section of the same tunnel shown in Figure 1, in which can be seen
as the sacrificial tunnel (1) is parallel to the main tunnel (2), at a distance defined
above the keystone of the latter.
Detailed description of the invention
[0008] The sacrificial tunnel (1), located in the vertical or in the vicinity of the keystone
of the main tunnel or perforation, will be in circular section acting similarly to
a sacrificial anode for the protection of corrosive processes, being responsible for
taking the stresses and deformations due to the existence of the different earth strata
or solid rocks located above the main tunnel or perforation, being deformed under
these loads and thus avoiding that they are transmitted to the main section of the
tunnel or perforation.
[0009] To do this, and depending on the mechanical and resistance characteristics of the
earth or solid rock on which the works are carried out, the sacrificial tunnel (1)
must be made prior to the main tunnel or perforation and by suitable mechanical methods
during the excavation, being considered the best possible solution to its subsequent
coating, in terms of the type of earth or solid rock object of the excavation works.
[0010] Numerical models carried out on different types of earth and rocky materials show
that the diameter of the sacrificial tunnel (1) must have a value of between 10% and
20% of the height of the main tunnel (2) (or in the case of perforations, of the diameter
of the same), being coated with hollow steel tube, gunite or hollow concrete, hollow
glass fiber or geogrid with low transverse stiffness. In the event that the sacrificial
tunnel (1) is unique, the results of numerical models carried out demarcate that it
must be located at a distance from the keystone of the main tunnel (2) of between
30% and 50% of the height of the main tunnel or perforation; in the case of considering
the need that they are several, they will be distributed in a horizontal plane symmetrically
with respect to a vertical plane containing the guideline of the main tunnel (2) and
the keystone of the same.
Exemplary embodiment
[0011] The present invention is further illustrated by the following two examples, which
are not intended to be limiting of its scope:
Example 1
[0012] The main tunnel of 6 m in height (with semicircular section and elephant leg in the
lower sides) and coating of gunite, is located in an earth of low bearing capacity,
the sacrificial tunnel is a concrete circular hollow tube with high transverse stiffness
(EI = 2,25.104 KN.m
2/m), located on the vertical of the keystone of the main tunnel, 2.50 meters above
the keystone and with a radius of 0.25 meters.
Example 2
[0013] In an area with high deformation capacity, the main tunnel is 6 meters in height
(with semicircular section and elephant leg in the lower sides) and coating of gunite.
The sacrificial tunnel would be in circular section of steel hollow tube with low
transverse stiffness (EI = 1000 KN.m
2/m), located on the vertical of the keystone of the main tunnel, 2 meters above the
keystone and with a radius of 0.35 meters.
1. Method for making tunnels or perforations in civil engineering works to reduce or
eliminate the use of supporting systems for earth or solid rock, characterized by the creation of a sacrificial tunnel, with a diameter of between 10% and 20% of the
height of the main tunnel, and at the vertical of the keystone of the main tunnel
at a distance of between 30% and 50% of the height of the main tunnel.
2. Method according to the claim 1, where the sacrificial tunnel is coated with hollow
steel, gunite or hollow concrete, hollow glass fiber or geogrid.
3. Method according to previous claims, where there are several sacrificial tunnels,
located in a horizontal plane of symmetrically shape with respect to a vertical plane
containing the guideline of the main tunnel and the keystone of the same.
4. Use of method according to the claim 3 to reduce the stress state and deformations
affecting the main tunnel during its creation.