FIELD OF THE INVENTION
[0001] The present invention relates to a method for the temporary suspension of existing
buildings, in particular residential buildings and monumental buildings. The invention
specifically relates to a method of this type in which the existing building is entirely
suspended, in safe conditions and regardless of the type of foundations thereof, so
as to allow digging or new foundation operations in the area below the building in
conditions of top safety, ease and execution speed.
BACKGROUND ART
[0002] In the building sector the technique of erecting new foundation under existing buildings
is widely known, which is applied, for example, when it is necessary to restore or
reinforce the foundations of a building for the most disparate reasons, such as deterioration
of the foundations, absence or insufficient extent thereof, decline of the mechanical
features of the ground, need to increase the size and the load capacity of the foundations
due to an increase of the load resting on the same, for example following changes
of use of or additional storeys to the building.
[0003] The need to build an under-foundation arises also in the cases in which the erection
of a new basement storey of the building is required.
[0004] One of the under-foundation techniques widely used in the industry consists of digging,
according to a programmed sequence, a series of limited digs under individual portions
of the load-bearing walls of the building and then of erecting corresponding foundation
portions in said digs, until completion of the entire new foundation. However, this
method allows to obtain fairly good results only in the case of under-foundations
of a limited height, since with the increase of the digging height, the risk of landslides,
and of consequent possible localised subsiding of the above-standing building, becomes
too large to guarantee both adequate safety conditions to the operators and the absence
of structural damages to the existing building. Moreover, such method does not allow,
or allows only in a limited manner, a mutual binding of the individual foundation
portions built later and the overall mechanical performances of the new foundation
are hence not comparable with those of a corresponding concrete foundation made as
a single monolithic casting provided with continuous metal reinforcements.
[0005] In order to overcome these drawbacks, building methods have more recently been proposed
which provide to harness the entire building with a new grid of beams arranged immediately
above or immediately below the lower floor of the building. The beams are interconnected
and are furthermore connected to the load-bearing floor and walls. The new beam grid
is provided with a series of resting points on the ground with the interposition of
a plurality of corresponding hydraulic jacks. The progressive and even actuation of
the jacks hence allows to obtain the lifting of the building.
[0006] The lifting extent may be extremely limited, i.e. what suffices to release the entire
weight of the building on the plurality of jacks and to hence be able to freely remove
the soil under it to erect the under-building, or it may arrive up to even a few meters,
in order to obtain an actual lifting of the building, to allow the building of a new
above-ground storey of the building or of a building support system on stilts, depending
on the reasons which have led to the indication of lifting the building. Some specific
application modes of this technique are disclosed for example in
US-6 379 085,
US 5 722 798 and
WO 2009/087469.
[0007] However, the above-described building method implies a certain complexity, both concerning
the installation and the procedure and it furthermore has - when used to erect an
under-foundation or an under-building - serious drawbacks as far as the accessibility
to the digging area is concerned.
[0008] As a matter of fact, the accessibility to the digging area is limited precisely by
the same plurality of hydraulic jacks, which as a matter of fact must for obvious
reasons be located evenly and sufficiently close across the entire building perimeter/area,
so that it is not normally possible to accomplish a sufficiently large side entrance
to the digging area to allow access to mechanic digging means. Moreover, the dig size
and depth are seriously limited by the need not to impair, with the digging operations,
the stability of the ground on which such jacks temporarily rest.
[0009] Again, moreover, the typical coupling mode of the above-described beams with the
load-bearing walls, with structural connection elements arranged crosswise to the
same walls, causes an important surface deterioration thereof which, in case of historical
or monumental buildings, is often unacceptable due to the presence of coats of paintings
or other types of surface decorations or finishes.
[0010] In any case, finally, the lifting or the suspension of a building on a network of
hydraulic jacks for the extended period of time necessary for the building of an under-building,
is rather problematic both from the point of view of the safety of the staff who operate
under the building, and from the point of view of the possible differentiated subsidings
which the ground resting systems of said jacks may undergo over time, mainly due to
the same stresses induced by the digging operations necessary for the under-building.
PROBLEM AND SOLUTION
[0011] The problem at the basis of the present invention is hence that of proposing a new
suspension method of existing buildings for the erection of under-foundations or under-buildings
which is free from the above-cited drawbacks.
[0012] In particular it is a first object of the invention that such method provides a temporary
suspension system of the building with high stability and safety, both with respect
to the operators and with respect to the structural integrity of the building.
[0013] A second object of the invention is furthermore that such method does not limit the
size of the dig in the area underlying the existing building, which dig can hence
be sized at pleasure until reaching and possibly even exceed the size of the building,
at least in the case of buildings which fall within non exceptional size classes.
[0014] A third object of the invention is then that such method allows the formation of
wide lateral accesses to the area underlying the building, so that the digging operations
may be performed, where desirable, with mechanical means having free access from the
outside.
[0015] A fourth object of the invention is finally that of allowing an easy, effective and
integral making safe of existing buildings with respect to seismic events.
[0016] This problem is solved and these objects are achieved through a suspension method
of existing buildings having the features defined in claim 1. Other preferred features
of the method are defined in the dependent claims.
BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Further features and advantages of the invention will be in any case more apparent
from the following detailed description of preferred embodiments of the building suspension
method of the invention, provided purely as a non-limiting example and illustrated
in the attached drawings, wherein:
fig. 1 is a plan view of an existing building, which illustrates the schematic arrangement
of a grid of main and secondary beams, for the suspension of the building using the
method of the present invention;
fig. 2 is a section view in a vertical plane according to line A-A in fig. 1, which
illustrates the structure of a main support beam;
fig. 3 is a view similar to fig. 2 which illustrates schematically some possible under-building
works;
figs. 4A and 4B are section views similar to fig. 3 which illustrate two different
modes of seismic insulation of the building of fig. 1.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0018] The suspension method of existing buildings according to the present invention is
articulated in different steps and precisely:
- 1. building of foundations, more or less deep depending on the mechanical features
of the ground, erected in safe conditions outside the building perimeter;
- 2. defining a provisional foundation of the existing building consisting of a grid
of main beams and of secondary beams;
- 3. modular building, with adjacent ashalrs, of the main and secondary beams of the
grid;
- 4. alternative building of continuous secondary beams, possibly provided with tie-beams
and counterthrust rafters;
- 5. making integral the ashlars of the modular beams through post-tensioning on-site;
- 6. digging in the area below the existing building;
- 7. building a new foundation of the under-building;
- 8. connecting the new foundation to the provisional foundation;
- 9. possible laying of the building on the new system of foundations and partial demolishing
of the main beams;
- 10. forming of the seismic insulation;
which will be briefly illustrated in the following.
Step 1 - Forming of new deep, outside foundations
[0019] These are works which, depending on the overall building project, can alternatively
have only a temporary function during the building suspension period (so-called provisional
works), or be then integrated in a permanent manner in the new building body being
erected. In both cases, such works are preferably erected outside the building perimeter
and are planned and sized to bear the overall load of the existing building and of
the grid of main and secondary beams meant to be a provisional foundation thereof.
[0020] Such deep foundations may be built with microposts, bored posts, sheet piles, etc.,
with or without top plinth, or, in the presence of ground water:
- on water-sealed slurry walls, with or without edge beams;
- on microposts berlinese, intersecting posts, jet-grouting, sheet piles or any other
foundation work comprising the erection of watertight compartments.
[0021] In the absence of ground water the foundations may have the simple form of two parallel
linear elements 1 (figs. 1 and 2), while in the presence of ground water they must
necessarily have a continuous and closed shaped, normally rectangular or square (fig.
1), which in addition to elements 1 comprises crosswise elements 1a to allow the dig
to be formed as a watertight compartment until work completion.
Step 2 - Definitioa of the provisional grid foundation
[0022] The building suspension method of the present invention provides the forming of a
beam grid, along the same axis of the load-bearing walls M of the building, as schematically
illustrated in fig. 1. A first series of beams 2, here also defined as main beams,
extends outside the perimeter of the building, until resting on the above-described
deep foundations 1. A second series of beams 3, here also defined as secondary beams,
rests instead on main beams 2 thus completing the above-said provisional foundation
grid of the load-bearing walls M of the existing building.
Step 3 - Building of the main and secondary beams of the grid, in a modular configuration
with adjacent ashlars
[0023] The building of the main and secondary beams of the grid is accomplished with a similar
technique to the traditional one of under-foundations, i.e. forming a series of adjacent
foundation portions 4, here defined as ashlars, through partial digging at the impost
depth of the foundations of building E according to a preset sequence. The impost
depth of ashlars 4 must preferably be above or equal to the intrados depth of the
existing foundations of the building in order not to reduce the load-bearing capacity
thereof. It is nevertheless possible to extend the depth of ashlars 4 also below the
impost depth of the existing foundations.
[0024] As an example, in fig. 2 the building diagram of a main beam 2 consisting of six
ashlars 4 is reported, which ashlars are built according to an ordinate sequence which
has been overall designed for the entire grid of beams 2 and 3, also as a function
of the length of the individual ashlars 4, in order not to impair in any way the integrity
of load-bearing walls M under which it is being built. Each ashlar 4 is provided with
a slack longitudinal reinforcement in a minimum extent, apt to comply with legal provisions,
and with crosswise reinforcement (brackets) in the amount necessary to offer shear-resistance
adequate to the transient and working stresses.
[0025] With respect to what occurs in traditional under-foundation works, ashlars 4 furthermore
have two features which are peculiar of the method of the present invention.
[0026] Firstly, ashlars 4 are provided within with tubular elements made of metal or of
other materials, for example knurled metal tubular sheaths, arranged according to
a preset path in the longitudinal direction of the beams so as to form overall, once
the building of ashlars 4 is completed, one or more continuous channels T which run
across longitudinally the entire beam 2 or 3. Channels T are suited to house metal
wires by which it is possible, once the building of the different ashlars 4 making
up the beam has been completed, to impart a post-tensioning condition to the beam
in the permanent configuration thereof.
[0027] Secondly, the individual ashlars are laterally shaped with mutually complementary
shear keys 4a, sized in order to transmit, in part or wholly, the plan shearing stress
between adjacent ashlars 4.
[0028] The completion of the building of ashlars 4 hence leads to the forming of a plurality
of concrete beams 2, 3 which add to and/or replace the pre-existing foundations of
the building, each beam consisting of a series of close ashlars 4, already in continuity
due to the shear stresses for the presence of the shear keys, but still disjoined
for bending stresses.
Step 4 - Building of part of the secondary beams of the grid, in a continuous configuration
[0029] Depending on the particular configuration of the building, at least part of secondary
beams 3 of the grid may be built in the form of continuous concrete or steel beams,
and such beams may be formed directly in the wall thickness or outside said thickness,
preferably in a symmetrical way, i.e. on both sides of the wall. In both cases, the
sizes of the opening and the loads resting on beams 3 may require the adoption of
inclined tie-rods fastened in an intermediate position of beam 3 and apt to release
on adjoining load-bearing walls M part of the load which rests on the beam. When said
tie-rods are used, they are preferably fastened, at the upper end thereof, to a horizontal
strut rather than directly to wall M. Said horizontal strut extends between the two
opposite walls M to which it is suitably constrained and acts both as element neutralising
the tie-rod-induced lateral thrusts, and as stabilising element of the highest part
of the existing building.
Step 5 - Post-tensioning of the modular beams
[0030] When the beam grid meant to form the provisional foundation of the existing building
is completed, the method of the invention provides the laying of harmonic-steel wires
within the channels T formed inside ashlars 4, through manual or automatic insertion
using so-called "strand-threading machines". In correspondence of the outer sides
of the terminal ashlars 4 of beams 2, 3 metal stretching heads are rested, to which
the wires are then connected according to the specific operation modes of the supplier
of the post-tensioning system.
[0031] The post-tensioning degree and the wire stretching sequence of the individual beams
2, 3 are defined and sized in the structural project. The path of the wires within
the beams may be rectilinear or curvilinear with upward concavity. The post-tensioning
- normally adopted only for the main beams 2 resting on deep foundations 1 - accomplishes
a contractive state which causes a limited suspension of the entire building, with
resulting progressive transfer of the load of the same from the old to the new foundations.
The passage of the loads occurs with the utmost gradualness and hence in highly safe
conditions and furthermore having the possibility to check any displacements of the
axis line of beams 2, 3, while the post-tensioning load is gradually increased. In
this step it is hence possible to carry out a validation of the project hypotheses
and of the previsional subsidings.
[0032] The post-tensioning system of the beams may be accomplished through any one of the
methods known in the sector, for example:
- through harmonic-steel strands and subsequent injection of special cement grout to
achieve the anti-corrosion protection of the wires (so-called "bonded" wires);
- through free strands covered by a sheath of Vipla®, known as "viplated strands" (so-called "unbonded" wires);
- through bars of the Dywidag® type, with or without grout injection.
Step 6 - Execution of the digging works underneath the existing building
[0033] Once completed, as described above, the suspension of the existing building on the
grid-like foundation system formed by main beams 2 and secondary beams 3, which system
in turn rests on deep foundations 1 outside the building perimeter, it is possible
to proceed to digging in the area below the building. Such operations, as should be
clear from the preceding description, can be performed in conditions of high safety
and of full freedom of access to the area. The vertical elements on which the building
now rests as a matter of fact consist of the sole deep foundations 1 outside the building
and hence the digging may be carried out fully on the entire area occupied by the
building, and possibly also on the entire area of greater extension limited precisely
by said deep foundations 1.
[0034] It is hence evident that such digging operations may be carried out also through
large mechanical means, and hence with a remarkable savings of working times, regardless
of course from the above-standing structure of the existing building, which as a matter
of fact is securely resting - moreover with no possible change of the stability in
time and regardless from the digging progress conditions - on the grid of provisional
foundations.
Step 7 - Forming of the new foundations system
[0035] Once the dig down to the depth of the planned dig bottom has been completed, it is
possible to proceed to the building of new foundations 5, for example in the shape
of a concrete bed or upturned beam, in a manner well-known per se.
[0036] Starting from this step of the construction, the building method of the present invention
may develop in two different variants. According to a first variant, the provisional
foundation consisting of the grid of beams 2 and 3 is maintained integrally as permanent
foundation of the building; in this variant the new foundation built on the bottom
of the dig will hence have to be sized only for supporting of the under-building erected
under the ground floor of the building, which under-building will be structurally
fully independent from the existing building. With the erection of the under-building
the method of the invention, according to this first variant, is hence completed.
[0037] In a second variant, on the contrary, the new foundation 5 is meant to support at
the end the entire building - normally due to the fact that the provisional foundation
system must at least in part be dismantled for architectural or logistic requirements
- and it must hence be sized accordingly to support the entire load of the building.
In this second variant the method of the invention still comprises steps 8 and 9 briefly
described in the following.
Step 8 - Connection of the new foundation to the existing building
[0038] As shown in fig. 3 with discontinuous lines, should beams 2 have to be later partially
demolished and/or detached from deep foundations 1, limited to the portion thereof
which does not cooperate to said new foundation system, in the space formed between
the new foundation 5 and the impost depth of beams 2 (which space can of course be
of such a height as to comprise within the same multiple below-ground storeys of the
building) load-bearing pillars or walls 6 are built in such positions as to then be
able to adequately release on the new foundations 5 the entire load of the existing
building as well as of the provisional foundation portion 2 which will be left at
the end of the reconstruction intervention.
Step 9 - Laying of the building (in the possible) amended embodiment
[0039] When the connection elements 6 are able to support the loads entrusted thereto, the
post-tensioning degree of main beams 2 is gradually reduced, so as to obtain a gradual
limited lowering of the building onto new foundations 5 and 6, which are thus loaded
with the weight of the building, simultaneously releasing from the same weight the
provisional grid-like foundation of beams 2 and 3 and deep foundation 1. Beams 2 and
3 may hence be partially removed according to the project indications and/or detached
from deep foundations 1, for example in order to perform the restoration of the area
outside the existing building in identical conditions to the original ones.
Step 10 - Seismic insulation
[0040] The method for the suspenson of buildings of the present invention is finally particularly
well-suited to accomplish the seismic insulation of existing buildings, without having
to carry out invasive works on the existing masonry, which works, in addition to being
extremely expensive, do not reach an equal safety level against seismic events and
are in any case very difficult to accomplish in buildings of great historical or artistic
value subject to the protection by the Ministry of Cultural Heritage and Activities,
which precisely for this reason provides a derogation from the otherwise compulsory
seismic adaptation.
[0041] In the first variant of the method of the invention, i.e. the one in which the existing
building is permanently supported on the grid of beams 2 and 3 and on deep foundations
1, it is sufficient for this purpose to insert seismic insulators I, well-known per
se, capable of insulating the building from the horizontal accelerations of the ground
in the resting points of main beams 2 on deep foundations 1 (fig. 4A). In this case
the new portion of under-building remains foreign to the seismic insulation and must
hence be maintained disjoined, from a structural and plant-engineering point of view,
from the above-standing building, to allow mutual oscillations of the two buildings
during a seismic event.
[0042] In the second variant of the method, i.e. that in which the entire building is laid
on the new foundations, being main beams 2 at least partly dismantled, it will instead
be necessary to build a flooring slab 7 horizontally connected to pillars or load-bearing
walls 6. The insulators are arranged- in a plan view depending on the static and dynamic
requirements between the new foundation structures and the elevation pillars/walls.
Flooring slab 7 is suspended on a layer of seismic insulators I which allows the free
sliding thereof save for friction forces. Thereby the seismic insulation of the entire
building E is obtained, including the part added as under-building, with respect to
the foundation system consisting of deep foundations 1 and of new foundation 5.
[0043] From the preceding description it should be clear how the present invention has fully
reached all the set objects in a particularly simple and effective way and without
the need for special machinery or equipment which are not already commonly available
at the building companies. In particular, the method of the invention allows the execution
of under-buildings of existing buildings in conditions of high safety and, at the
same time, of great rapidity, without altering in any way the structure and the finishes
of the existing building and furthermore allowing, with the sole additional costs
of seismic insulators I, the full anti-seismic making safe of the building.
[0044] However, it is understood that the invention must not be considered limited to the
particular arrangements illustrated above, which represent only exemplifying embodiments
thereof, but that different variants are possible, all within the reach of a person
skilled in the field, without departing from the scope of protection of the invention,
which is exclusively defined by the following claims.
1. Method for the temporary or permanent suspension of an existing building comprising
the steps of:
a. building deep foundations (1) outside the perimeter of the existing building (E);
b. modular building, with reinforced adjacent ashlars (4), of a provisional foundation
of the building (E) consisting of a grid of main beams (2) and of secondary beams
(3) in correspondence of the load-bearing walls (M) of the building (E), wherein
i. said main beams (2) extend beyond the perimeter of the building (E) until resting
on said deep foundations (1);
ii. said ashlars (4) are provided within with tubular elements arranged according
to a preset design so as to form, all together, one or more continuous channels (T)
which longitudinally cross said main beams (2) or secondary beams (3);
iii. said ashlars (4) are laterally shaped with mutually complementary shear keys
(4a) apt to transmit the shearing stresses between adjacent ashlars (4);
c. post-tensioning on-site said main beams (2) through the insertion and subsequent
tensioning of steel wires within said channels (T);
d. limited lifting of the building (E) by post-tensioning said main beams (2), wherein
said channels (T) have a polygonal or curvilinear shape with upward concavity.
2. Method for the suspension of buildings as claimed in claim 1, furthermore comprising
the subsequent steps of:
e. execution of a dig in the area underlying said grid-like provisional foundation;
f. building of a new foundation (5) and/or under-building inside said dig.
3. Method for the suspension of buildings as claimed in claim 2, furthermore comprising
the further steps of:
g. connecting the new foundation (5) to at least part of said provisional foundation
(2, 3) through the building of pillars or load-bearing walls (6);
h. laying of the building (E) on the foundation system comprising said new foundation
(5), said connecting pillars and/or load-bearing walls (6) and at least part of said
provisional foundation (2, 3), through the progressive release of the post-tensioning
condition of said main beams (2).
4. Method for the suspension of buildings as claimed in claim 3, comprising the additional
step of:
i. possible partial demolition of said main beams (2) limited to the portion thereof
which does not cooperate to said new foundation system.
5. Method for the suspension of buildings as claimed in claim 2, furthermore comprising
a plurality of seismic insulators (I) arranged in correspondence of the resting points
of said main beams (2) on said deep foundations (1).
6. Method for the suspension of buildings as claimed in claim 3 or 4, furthermore comprising
a flooring slab (7) connected to said pillars or load-bearing walls (6), free to slide
on the new foundation (5), through the interposition of a plurality of seismic insulators
(I) between said new foundation (5) and said slab (7).
7. Method for the suspension of buildings as claimed in any one of the preceding claims,
wherein at least part of said secondary beams (3) are in the form of continuous concrete
or steel beams.
8. Method for the suspension of buildings as claimed in claim 8, wherein said beams are
provided with inclined tie-rods anchored at intermediate points of the beam and apt
to release on the neighbouring load-bearing walls (M) part of the load which rests
on said beams (3), said tie-rods being fastened at their upper end to horizontal struts
for the neutralisation of the lateral thrusts induced thereby.
9. Method for the suspension of buildings as claimed in any one of the preceding claims,
wherein the post-tensioning of said beams (2, 3) is alternatively obtained through
the use, within said channels (T), of:
- strands of harmonic steel and injection of special cement grout;
- vipla covered strands;
- Dywidag®-type bars, with or without grout injection.