[0001] The present invention relates to a large-caliber casing construction for preventing
a collapse or an inflow of an earth layer during excavation of the ground for laying
a foundation in the process of building a underwater structure, such as a dam, a bridge,
and an offshore wind structure under water, such as sea and river, and more particularly,
to a temporary structure of a large-caliber casing type and a method of constructing
the same, which enables batch installation after prefabrication to thereby reduce
field work and can flexibly cope with irregular underwater ground.
Background Art
[0002] In order to stably construct an underwater structure, such as a dam, a bridge, and
an offshore wind structure under water, such as sea and river, a stable foundation
work on the underwater ground must be preceded. The foundation work of the underwater
ground is carried out through a method of constructing mono piles after excavating
the underwater ground. Before excavation of the underwater ground, it is necessary
to install a temporary structure of a large-caliber casing type in the foundation
work area in order to prevent an inflow of weak soil or water into the foundation
work area or a collapse of the underwater ground. A method of embedding large-caliber
casing steel pipes (large-caliber steel pipe pile type) is a representative method
of constructing temporary structures.
[0003] The large-caliber steel pipe pile type is a method of manufacturing integrally large-caliber
casing steel pipes with steel materials around a factory or a construction field,
carrying the manufactured steel pipes into the construction field and constructing
them while sinking them in water. Such a method can reduce field work but has several
problems in that it needs large-scale equipment for carrying and lifting the large-sized
casing steel pipes and in that stabilization work of the underwater ground must be
previously carried out in order to stably settle and install the casing steel pipes
in the underwater ground. Moreover, in the case that the underwater ground is developed
irregularly, for instance, the bedrock is exposed or the earth layer is distributed
very thinly, because the casing steel pipes cannot flexibly cope with the underwater
ground, the method cannot prevent a collapse or an inflow of an earth layer while
the casing steel pipes excavate the underwater ground.
Disclosure
Technical Problem
[0004] Accordingly, the present invention has been made in an effort to solve the above-mentioned
problems occurring in the prior arts, and it is an object of the present invention
to provide a temporary structure of a large-caliber casing type and a method of constructing
the same, which enables batch installation after prefabrication to thereby reduce
field work and can flexibly cope with irregular underwater ground.
Technical Solution
[0005] To achieve the above objects, the present invention provides a underwater large-caliber
casing structure which is completed by installing sheet piles between steel pipes
through a claw connection method and a construction method of a large-caliber casing
including the steps of prefabricating steel pipes and sheet piles, installing them
in a lump, and embedding and installing center piles and the sheet piles in the ground
under water.
Advantageous Effects
[0006] The temporary structure of the large-caliber casing type and the method of constructing
the same according to the present invention have the following effects.
[0007] First, the large-caliber casing work can be carried out in the minimized field work
because sheet piles are installed after being prefabricated. Accordingly, the present
invention can reduce the construction period of time and construction expenses in
relation with foundation work of the underwater structure.
[0008] Second, because the underwater large-caliber casing is constructed in such a manner
that the sheet piles and the steel pipes are first installed in an assembled state
and H-piles are installed inside the steel pipes of the assembled body, there is little
possibility to cause a construction error, and as a result, the present invention
can enhance the construction quality due to a schemeful construction.
[0009] Third, because the present invention can install sheet piles while coping with an
irregular underwater ground even though the surface of a hard layer (or a rock layer)
on the seabed or a riverbed is in a very irregular state, it can prevent a collapse
of soil during excavation of the underwater ground inside the casing for laying the
foundation.
Description of Drawings
[0010]
FIGS. 1 and 2 are a plan view and a perspective view of a temporary underwater large-caliber
casing structure according to the present invention.
FIG. 3 is a detailed diagram showing a connected state of a steel pipe and a sheet
pile of the temporary underwater large-caliber casing structure according to the present
invention.
FIGS. 4 to 7 are flow charts showing a construction method of the temporary underwater
large-caliber casing structure according to the present invention.
FIGS. 8 to 10 are flow charts showing a process of constructing an underwater structure
while applying the construction method of the temporary underwater large-caliber casing
structure according to FIGS. 4 to 7, wherein the flow charts respectively show construction
sequences of a mono-pile for offshore wind and a pier for a bridge.
Best Mode
[0011] The present invention provides a temporary batch-installation-type underwater large-caliber
casing structure using sheet piles including: steel pipes having a plurality of claw
connectors disposed on the outer peripheral surface thereof, the steel pipes being
spaced apart from each other at predetermined intervals and installed in the ground
under water in such a manner that the claw connectors are opposed to each other; sheet
piles having a plurality of claw connectors disposed at end portions thereof, the
sheet piles being installed in such a way as to close spaces between the steel pipes
and being embedded in the ground under water while engaging with the steel pipes through
the claw connectors; a horizontal strut fixed inside or outside the casing to horizontally
connect the steel pipes; and center piles respectively inserted into the steel pipes
and fixed to the steel pipes while being embedded into the ground under water.
[0012] The present invention provides a construction method of a temporary batch-installation-type
underwater large-caliber casing structure including the steps of: (S11) assembling
steel pipes, sheet piles and a horizontal strut in such a manner that the sheet piles
are not located lower than the steel pipes; (S12) carrying the assembled body of the
step (S11) into a construction field and seating the steel pipes on the ground under
water; (S13) inserting and driving center piles into the steel pipes so as to embed
them into the ground under water; (S14) fixing the center piles to the steel pipes;
and (S15) driving the sheet piles so as to embed them into the ground under water.
Mode for Invention
[0013] Reference will be now made in detail to the preferred embodiment of the present invention
with reference to the attached drawings.
[0014] FIGS. 1 and 2 are a plan view and a perspective view of a temporary underwater large-caliber
casing structure according to the present invention. The underwater large-caliber
casing is a temporary structure for preventing a collapse or an inflow of an earth
layer during excavation of the ground for laying a foundation in the process of building
an underwater structure, such as a dam, a bridge, and an offshore wind structure under
water, such as sea and river. The underwater large-caliber casing assembling structure
includes steel pipes 10, sheet piles 20, a horizontal strut 30, and center piles 50.
[0015] The steel pipe 10 is an empty hollow member and has a claw connector 13 disposed
on the outer peripheral surface thereof. A plurality of the steel pipes 10 are arranged
at predetermined intervals and are seated on the bottom under water in such a manner
that the claw connectors 13 are opposed to each other. Such steel pipes 10 serve as
a guide pipe of the center piles 50 respectively inserted and mounted inside the steel
pipes.
[0016] The sheet piles 20 are sheet type pile members which respectively have claw connectors
23 disposed at ends thereof so as to be joined to each other through a claw connection,
and are generally the same as typical sheet piles used for retaining walls or cofferdams.
In other words, the sheet piles 20 are arranged in mutual claw connection one by one
and are installed under the ground while being driven into the ground. The sheet piles
20 are embedded and installed to the underwater ground while being engaged and connected
with the steel pipes 10 through the claw connectors 13 and 23 between the steel pipes
10 so as to form a casing of a closed structure together with the steel pipes 10.
[0017] The sheet piles 20 are joined one another in engagement with one another and with
the steel pipes 10 so as to close spaces between the steel pipes 10 by the sheet piles
20.
[0018] The horizontal strut 30 is fixedly mounted while horizontally connecting the steel
pipes 10 inside or outside the casing. A plurality of the steel pipes 10 are restricted
and reinforced into one body by the horizontal strut 30. For a stable reinforcing
structure, it is preferable that the horizontal strut 30 includes an outer strut 31
which is continuously mounted from the outside of the casing. The horizontal strut
30 is fixed only to the steel pipes 10 and simply gets in contact with the sheet piles
20, such that the sheet piles 20 can be embedded and installed in the underwater ground
while being driven even in a state where the steel pipes 10, the horizontal strut
30 and the sheet piles 20 are assembled together. In the meantime, the horizontal
strut 30 may be disposed parallel to each other in multistage, and in this instance,
vertical strut 40 may be additionally disposed for vertically connecting the multistage
horizontal strut 30. The horizontal strut 30 and the vertical strut 40 may be adopted
from general steel members having a proper cross section, such as H-shaped steels,
□-shaped channels, angles, and others, according to structural designs, and FIG. 1
illustrates the outer strut 31 having the H-shaped steel and the vertical strut 40
having the □-shaped channel.
[0019] The center pile 50 is inserted into the steel pipe 10 and fixed to the steel pipe
10 while being embedded to the underwater ground. The center piles 50 are embedded
and mounted in the underwater ground together with the sheet piles 20 and serve to
stably settle the temporary casing structure to the underwater ground. It is possible
that the center piles 50 are embedded deeper than the sheet piles 20 if possible because
the center piles 50 are H beams. Preferably, the center piles 50 are properly adopted
from general steel members, such as H-shaped steels, and FIG. 1 illustrates the center
piles 50 having the H-shaped steels. Meanwhile, the center piles 50 are fixed to the
steel pipes 10, and for this, couplers may be used properly. Considering that the
underwater large-caliber casing according to the present invention is the temporary
structure which will be demolished before long, it is preferable that the couplers
are mounted by a wedge type fixing method or a bolt fastening method so as to be easily
attached and detached rather than the welding method.
[0020] Through the above structure, the temporary underwater large-caliber casing structure
is finished. The casing of the closed structure is completed through the claw connection
of the steel pipes 10 and the sheet piles 20, and the temporary structure can keep
a stable construction state through settlement of the center piles 50 and the sheet
piles 20 in the underwater ground. The temporary underwater large-caliber casing structure
according to the present invention may have a circular closed structure or a polygonal
closed structure.
[0021] FIGS. 1 and 2 show a temporary casing structure of the polygonal closed structure.
As shown in the drawings, the steel pipes 10 are arranged in such a way as to be located
at edges of a polygon and the sheet piles 20 are arranged in such a way as to be located
as sides of the polygon to thereby complete the polygonal closed structure. The polygonal
closed structure can be easily completed when general straight steel members are applied
as the horizontal struts 30 as they are.
[0022] Furthermore, in FIGS. 1 and 2, the horizontal strut 30 has inner and outer struts
31 and 32 which are spaced apart from each other and respectively mounted in parallel
with each other inside and outside the casing, and the sheet piles 20 are contactingly
mounted between the inner and outer struts 31 and 32. Such an installation structure
of the horizontal strut 30 is favorable in securing a stable reinforcing structure
by the inner and outer struts 31 and 32 and keeping perpendicularity of the sheet
piles 20 during the process of embedding and installing the sheet piles 20.
[0023] FIG. 3 is a detailed diagram showing a connected state of a steel pipe and a sheet
pile of the temporary underwater large-caliber casing structure according to the present
invention. In FIG. 3, the steel pipes 10 are formed by properly transforming conventional
steel pipes. Concretely, the steel pipe 10 includes: a steel pipe body 11; a wing
sheet 12 welded on the outer peripheral surface of the steel pipe body 11; and a claw
connector 13 formed by an end portion of the wing sheet 12 curved. In other words,
the sheet pile 20 is divided in half and joined to both sides of the steel pipe body
11, such that the steel pipe 10 having the claw connector 13 is completed. The steel
pipe 10 is simply joined during the claw connection of the sheet pile 20.
[0024] FIGS. 4 to 7 are flow charts showing a construction method of the temporary underwater
large-caliber casing structure according to the present invention, and illustrate
the method of constructing the temporary underwater large-caliber casing structure
of FIGS. 1 and 2. Now, the construction method of the temporary underwater large-caliber
casing structure according to the present invention will be described.
[0025] First, the steel pipes 10, the sheet piles 20 and the horizontal strut 30 are assembled,
and the vertical struts 40 may be further assembled in the case that the vertical
struts 40 are installed (S11, See FIG. 4). The sheet piles 20 are equal to or longer
than the steel pipes 10, and preferably, are not located lower than the steel pipes
10. The reason is not to be interfered by the sheet piles 20 and to stably install
the steel pipes 10 in the ground under water.
[0026] Next, the assembled body assembled in the step S11 is carried into a construction
field, and the steel pipes 10 are seated and installed in the ground under water (S12,
See FIG. 5). The steel pipes 10 are installed while being lifted by a crane, and the
assembled body is held not to be moved after the installation.
[0027] Next, the center piles 50 of the H-shaped steels are inserted and driven into the
steel pipes 10 so as to be embedded in the ground under water (S13, See FIG. 6). After
that, the center piles 50 are fixed in the steel pipes 10 (S14), and the sheet piles
20 are driven to be embedded and installed in the ground under water (S15, See FIG.
7). In this instance, a crane, a hammer, or others may be used properly.
[0028] Through the above steps, the temporary large-caliber casing structure is completely
constructed. Because arrangement of the previously assembled body, insertion and driving
of the center piles 50, and driving of the sheet piles 20 are just carried out in
the construction field, the present invention can reduce a work amount in the construction
field and allow rapid construction work.
[0029] FIGS. 8 to 10 are flow charts showing a process of constructing an underwater structure
while applying the construction method of the temporary underwater large-caliber casing
structure according to FIGS. 4 to 7, wherein the flow charts respectively show construction
sequences of a mono-pile for offshore wind and a pier for a bridge.
[0030] FIGS. 8 and 9 illustrate a construction sequence of the mono-pile (MP). First, the
temporary underwater large-caliber casing structure is constructed in a construction
position (See FIG> 8), and the construction method is the same as FIGS. 4 to 7. A
drilling rig is inserted into the temporary casing structure and fixed to the top
of a jackup barge, and then, a drilling base machine and the drilling rig are connected
with each other so as to drill the inside of the temporary casing structure (See FIG.
9(a)). In this instance, drilling water is supplied to the inside of the temporary
casing structure in a reverse cycle, and then, drilling water and rock fragments are
discharged out through a drill pipe. Next, the mono-pile (MP) is inserted and installed
inside an excavation hole (FIG. 9(b)), various grouting materials, such as concrete,
mortar, or other filling materials, fill between the mono-pile and the excavation
hole (FIG. 9(c)), and then, the temporary casing structure is removed (FIG. 9(d)).
The removal work is carried out in reverse. In other words, first, the sheet piles
20 are drawn out from the ground under water, the fixed state of the center piles
50 is released to draw out the center piles 50 from the ground under water and remove
the center piles 50 from the steel pipes 10, and then, the assembled body of the steel
pipes 10, the sheet piles 20 and the horizontal strut 30 is lifted and carried. Through
the above process, the underwater structure like the mono-pile can be constructed
completely.
[0031] FIG. 10 illustrates a construction sequence of a pier under water. In order to construct
the underwater pier, as shown in FIG. 8, first, the temporary underwater large-caliber
casing structure is constructed at the construction position. Next, water is supplied
to the inside of the temporary casing structure by a water lift pump (FIG.10(a)),
and then, when the underwater ground is exposed inside the temporary casing structure,
a foundation of the pier (P1) and a pier body (P2) are constructed in the ground under
water (FIGS. 19(b) and (c)). Next, after water is supplied to the inside the temporary
casing structure (FIG. 10(d)), the temporary casing structure is removed (FIG. 10(e)).
In this instance, the removal of the temporary structure is the same as the construction
process of the mono-pile described above. Through the above process, the underwater
structure such as the pier of the bridge is constructed completely.
[0032] As described above, while the present invention has been particularly shown and described
with reference to the example embodiments thereof, it will be understood by those
of ordinary skill in the art that the above embodiments of the present invention are
all exemplified and various changes, modifications and equivalents may be made therein
without departing from the scope of the present invention. Therefore, it would be
understood that the technical and protective scope of the present invention shall
be defined by the technical idea as defined by the following claims.
1. A temporary batch-installation-type underwater large-caliber casing structure using
sheet piles comprising:
steel pipes (10) having a plurality of claw connectors (13) disposed on the outer
peripheral surface thereof, the steel pipes (10) being spaced apart from each other
at predetermined intervals and installed in the ground under water in such a manner
that the claw connectors (13) are opposed to each other;
sheet piles (20) having a plurality of claw connectors (23) disposed at end portions
thereof, the sheet piles (20) being installed in such a way as to close spaces between
the steel pipes (10) and being embedded in the ground under water while engaging with
the steel pipes (10) through the claw connectors (13, 23);
a horizontal strut (30) fixed inside or outside the casing to horizontally connect
the steel pipes (10); and
center piles (50) respectively inserted into the steel pipes (10) and fixed to the
steel pipes (10) while being embedded into the ground under water.
2. The temporary batch-installation-type underwater large-caliber casing structure according
to claim 1, wherein the horizontal strut (30) comprises: an outer strut (31) located
outside the casing; and an inner strut (32) located inside the casing, and the inner
and outer struts (31, 32) are spaced apart from each other and arranged in parallel
with each other, and
wherein the sheet piles (20) get in contact with the inner and outer struts (31, 32).
3. The temporary batch-installation-type underwater large-caliber casing structure according
to claim 1 or 2, wherein the steel pipe (10) comprises: a steel pipe body (11); a
wing sheet (12) welded on the outer peripheral surface of the steel pipe body (11);
and a claw connector (13) formed by an end portion of the wing sheet 12 curved.
4. The temporary batch-installation-type underwater large-caliber casing structure according
to claim 1 or 2, wherein the steel pipes (10) are arranged at edges of a polygonal
composition,
the sheet piles (20) are arranged on sides of the polygonal composition while connecting
the steel pipes (10) with each other, and
the horizontal strut (30) comprises an outer strut (31) mounted in a polygonal composition
while surrounding the outer periphery of the steel pipes (10).
5. The temporary batch-installation-type underwater large-caliber casing structure according
to claim 1 or 2, wherein the center piles (50) are H-shaped steels.
6. A construction method of the temporary batch-installation-type underwater large-caliber
casing structure according to claim 1 or 2, comprising the steps of:
(S11) assembling steel pipes (10), sheet piles (20) and a horizontal strut (30) in
such a manner that the sheet piles (20) are not located lower than the steel pipes
(10);
(S12) carrying the assembled body of the step (S11) into a construction field and
seating the steel pipes (10) on the ground under water;
(S13) inserting and driving center piles (50) into the steel pipes (10) so as to embed
them into the ground under water;
(S14) fixing the center piles (50) to the steel pipes (20); and
(S15) driving the sheet piles (20) so as to embed them into the ground under water.