FIELD OF THE INVENTION
[0001] The invention belongs to the field of round pit excavation technology and relates
to reusable telescopic, metal risers for digging pits, reinforcing pit walls, doing
construction work in the pit, and complete or partial filling of the pits.
BACKGROUND OF INVENTION
[0002] Excavating ground from pits is a dangerous and complex process requiring special
precautions and planning, particularly when digging work must be done at great depths
and in confined space because of proximity of other objects to the pit. Various ground
reinforcement equipment is used in real-world pit digging operations, but it is not
practicable for use in dense infrastructure locations or heavy traffic streets. Ground
reinforcement equipment is also used to reduce digging costs as well as for installing
and repairing various communications and for building manholes. One of the main purposes
in using pit riser systems is to ensure safety for people working in the pit by resisting
ground and groundwater pressure on the walls of risers. The risers provide the workers
with an easy way to protect pits from collapsing during digging and other work.
[0003] The patent
CN201756709 published on 9 March 2011 describes a pit digging method utilizing uniform risers of equal diameter that is
adjustable with shrink-rings located on their sides. An excavator is positioned inside
such a riser to dig ground from the inside of the pit. But the said embodiment of
the invention is applicable for digging pits of large diameter and not suitable for
use in dense infrastructure locations or heavy traffic streets close to objects that
must remain intact.
[0004] The patent
EP0708225 published on 24 April 1996 describes a method for digging small-diameter pits by using two telescopic longitudinal
risers. However, the said embodiment of the invention is applicable for digging pits
of small diameter and the pit dug in this way would not have space for a worker.
[0005] The closest related art can be found in the patent
GB1248085 published on 29 September 1971. It describes a pit digging method where round plastics receptacles of equal diameter
sealing off from the ground are inserted in the pit one after another. This invention
can be used for making burial vaults. However, this invention is tailored for digging
pits that are not deep and have small diameters and therefore such pits are not suitable
for repairs and other construction work on pipelines and communications placed deep
under ground. The risers according to this invention are not reusable as they are
not pulled out.
SUMMARY OF THE INVENTION
[0006] The essential uniqueness of this invention is that in digging 4-12 metre deep pits
in confined spaces where other objects (such as road, fence, building or some other
static object) are at least 1-1.5 metre away from the edge of the pit telescopic retractable
round reusable metal risers of different diameters are used to ensure stability of
walls of the pit being dug and safely achieve the desired depth of the pit, enable
doing the required repair or construction work; this work having been done the risers
are pulled out from the pit one after another and the pit gets gradually completely
or partially filled from the bottom as the risers are pulled out one after another.
BRIEF DESCRIPTION OF THE DRAWINGS
[0007]
Fig. 1 shows digging of initial pit (7).
Fig. 2 shows supporting riser (2) placed in the pit.
Fig. 3 shows supports (6) screwed to supporting riser (2).
Fig. 4 shows placing of the second riser (3) in the pit.
Fig. 5 shows two first risers placed in the pit.
Fig. 6 shows four risers placed in the pit.
Fig. 7 shows pulling out of risers from the pit.
Fig. 8 shows a photo of telescopic risers intended for reinforcing the pits.
Fig. 9 shows telescopic connection of the supporting riser (2) to the second riser
(3) and capturing members (12, 13) that are identical for all other risers.
Fig. 10 shows putting any two risers together by utilizing the connecting members
(12, 13).
DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0008] Pit telescopic riser structure (1) (also the term "riser" in this invention can be
called as "telescopic type formwork") may comprise of the components of the following
dimensions:
1) The first (supporting) round cross-section riser with lifting points (2) (dimensions:
diameter - 2000-3000 mm, height - 1500-2000 mm);
2) The second round cross-section riser with lifting points (3) (dimensions: diameter
- 1800-2800 mm, height - 1500-2000 mm);
3) The third round cross-section riser with lifting points (4) (dimensions: diameter
- 1600-2600 mm, height - 1500-2000 mm);
4) The fourth (deep) round cross-section riser with lifting points (5) (dimensions:
diameter - 1400-2400 mm, height - 1500-2000 mm);
5) Four 1000-1500 mm long supports (6) resting on the ground surface and attached
to the top part of the first/supporting riser (2).
[0009] The optimum sizes for components of the telescopic riser system are:
- 1) First/supporting round cross-section riser with lifting points (2) (dimensions:
diameter - 2710 mm, height - 1500 mm);
- 2) Second round cross-section riser with lifting points (3) (dimensions: diameter
- 2540 mm, height - 2000 mm);
- 3) Third round cross-section riser with lifting points (4) (dimensions: diameter -
2370 mm, height - 2000 mm);
- 4) Fourth/deep round cross-section riser with lifting points (5) (dimensions: diameter
- 2200 mm, height - 2000 mm);
- 5) Four 1500 mm long supports (6) resting on the ground surface and attached on the
top part of the first riser (2).
[0010] Telescopic riser system may consist of less or more than 4 risers, but the optimum
quantity of telescopic risers is 4. The cross-section difference of the risers must
be 160-200 mm, the optimum difference in cross-sections is 170 mm. The weight of one
riser is approximately 500-800 kg.
[0011] Dimensions of telescopic riser structure are chosen with regard to the type of digging
work to be done. As metal telescopic risers are made to be reusable, they are adapted
for use in different ground conditions. The choice of pit reinforcement structure
for ground works is determined by engineering-geological surveys of the ground done
in advance and scheduled in technical documentation of the particular project underway.
Calculations of limiting pressure of ground on pit reinforcement structure exerted
when digging pits of different depths are based on the requirements in the PN-B-03010
standard. Safe project of riser wall structure can be produced only after making calculations
of limiting pressure by considering relevant ground properties at the planned digging
site. If during digging operations it is found that the actual ground condition does
not match the one in calculations done in advance, additional surveys of the ground
must be done and pressure of ground must be recalculated. To choose appropriate components
for the telescopic riser system for ground reinforcement the following conditions
must be taken into consideration: (i) planned depth of the pit; (ii) required cross-section
of the pit at the end point of the pit; (iii) planned type and technology of construction
and installation work in the pit; (iv) planned speed of work; (v) area of the zone
where digging operations are to take place.
[0012] Installation of telescopic riser system for pit reinforcement (1) comprises four
main stages. The first stage involves selection and fencing of work zone and marking
of existing communications. During the second stage (shown in Fig. 1 and Fig. 2),
before starting setting risers into the ground, initial pit (7) is dug (if asphalt
cover is present, then asphalt must be removed) to the depth of 0.5-2.0 m (actual
depth varies depending on stability of ground). The pit (7) must be about 10% larger
than cross-section of the first/supporting riser (2). During the third stage (shown
in Fig. 3 and Fig. 4), four supports (6) (the best choice) to rest on the ground surface
are attached on the first/supporting riser (2) and then the first/supporting riser
(2) is set into the prepared pit (7) by using a machine/vehicle. If the depth of the
prepared pit (7) is smaller than the height of supporting riser (2) then sinking of
the supporting riser (2) is started and continues until its lateral supports (6) touch
the ground surface. The sinking occurs as the digging machine (excavator) (8) digs
the ground from the inside of the supporting riser (2) evenly along the entire cross-section
and exerts pressure on the supporting riser (2) from time to time from the top. The
pressing must be even on the entire length of the circle of the supporting riser (2),
without pressing too much so that deformation and inclination of the supporting riser
(2) is avoided. During the fourth stage (shown in Fig. 5 and Fig. 6), when supports
(6) of the first/ supporting riser (2) touch the ground surface, the next telescopic
pit reinforcement system riser (3) is picked and its sinking process is started. The
sinking occurs as the digging machine digs the ground from the inside of the riser
evenly along the entire cross-section of the riser and exerts pressure on the riser
(3) from time to time from the top until the capturing member (12) (shown in Fig.
9 and Fig. 10) located in the top part of the riser (3) touches the capturing member
(13) located in the bottom part of the supporting riser (2) inserted before. The pressing
must be even along the entire length of the circle of the riser without pressing too
much so that deformation and inclination of the riser and therefore tripping of the
risers is avoided. With digging and gradual pressing on the risers the remaining risers
are inserted and the process is repeated until the required depth of the pit is achieved.
[0013] Interconnection of telescopic risers is shown in Fig. 9 and Fig. 10. At the top part
of each telescopic riser there is an externally encircling and outwardly protruding
capturing member (12). Furthermore, at the bottom part of each telescopic riser there
is an internally encircling and inwardly protruding triangular capturing member (13).
As the telescopic risers are being set into the pit one after another they attach
to each other at the said capturing members (12, 13). For example, as the second riser
(3) is being set into the pit through the first/supporting riser (2) the capturing
member (12) of the second riser (3) makes a firm grip with the capturing member (13)
of the first/supporting riser (2) and prevents the being set risers from coming off
each other and falling into the pit. Accordingly, all telescopic risers get connected
to each other in the pit.
[0014] The required depth of the pit having been achieved, construction work that necessitated
digging this pit can be started: for example, installation of manholes to reach underground
pipelines, underground communication network accident recovery, pumping station installation,
or other construction work underground. Often the ground properties of the particular
location require that such a telescopic riser system (1) for pit reinforcement is
used in combination with ground drainage systems. In such a case the particularities
of riser installation (insertion) remain the same except that needle filters (9) are
installed around the risers at the beginning of the works. The needle filters enable
removal of groundwater from the ground in the pit or lowering of groundwater level
in the pit.
[0015] Removal of telescopic risers from the pit (shown in Fig. 7) starts with pulling out
the inner riser located the deepest in the pit, afterwards the remaining risers are
pulled out one by one. Before starting pulling the risers out ground is poured to
the bottom part of the pit to achieve thickness of at least 0.5 metre and then this
ground is compacted. Once the riser has been elevated to the level of compacted ground,
the gaps resulting from lifting the riser must be filled with compacted ground so
that no cavities remain after filling up the unneeded part of the pit with the ground.
The remaining risers are pulled out in the same manner until the entire pit gets filled
up with the ground.
[0016] The working properties of the telescopic riser system (1) are intended for use of
risers in digging operations at construction sites and communications channels and
therefore the entire construction site must be well protected from entry of unauthorized
persons to the area of digging operations. Given the large dimensions and weight of
the risers (1) it is absolutely necessary to, inter alia, follow these rules for their
safe storage: (i) all components of the telescopic riser system (1) must be placed
on the plane of the riser ring, preferably grouped by dimensions and type; (ii) holders
and ladders (10) must be cleaned and properly protected and stored indoors. Every
time the risers are brought from the construction site to storage location they must
be washed. Riser capturing members (12, 13) must be protected with anticorrosive agent.
[0017] Installation and uninstallation of the telescopic risers for pit reinforcement (1)
are subject to the following special safety requirements. Only the factory-made and
undamaged components are to be used when installing the telescopic riser system. Use
of damaged or incomplete riser structures may lead to an accident at the construction
site and endanger life and health of staff. When installing risers in the pit cables
and hooks must be used for positioning the risers so that the workers do not come
into contact with these components as they are rotated or relocated. The following
rules must be obeyed to prevent damage to risers when working: when sinking (setting)
the risers equal pressure must be applied to the entire length of the circle of the
riser so that deformation and inclination of the riser and therefore tripping of the
risers is avoided. The risers must not be hit with excavator bucket or other digger
machinery. The risers must be used for pit wall reinforcement only. Moreover, risers
must be protected from getting damaged while they are stored at the construction site.
[0018] A telescopic riser system (1) enables digging a pit at smaller area compared to that
needed when digging a pit in other ways. To prevent pit collapse when digging a pit
without using risers it is usually necessary that a pit radius at the surface is equal
to or more than the depth of the pit being dug multiplied by approximately 40 degree
tangent. For example, when digging a 7.5 metre deep pit the pit radius at the surface
should be at least 7.65 metre (if manholes with radius equal to the radius of the
first / supporting riser 1.35 metre were to be used). When using telescopic risers
(1), however, the minimum radius at the pit surface might be about 2.35 metre (calculated
by adding the radius of the first / supporting riser (2) 1.35 metre to 1 metre long
support). Despite that the nature of these calculations is rough and the ground characteristics
have not been taken into consideration, they still show that by using telescopic risers
(1) the radius of the 7.5 metre deep pit being dug (7) at the pit surface might be
reduced by about 10 times. The deeper the pit being dug, the greater reduction can
be achieved. This enables much more efficient pit digging operations at dense infrastructure
locations.
[0019] To illustrate and describe this invention, descriptions of preferred embodiments
are given above. This is not a complete or limiting description aimed at prescribing
a precise embodiment or implementation option. The description given above should
be regarded more as an illustration than a constraint. Obviously, the specialists
in this field may clearly see a multitude of modifications and variations. The preferred
embodiments have been selected and described so as to enable the specialists in this
field to best understand the principles behind this invention and their best practical
application for different embodiments with different modifications fit for a specific
application or embodiment customisation. The invention scope is defined by the attached
claims and their equivalents wherein all these terms have the broadest possible meanings
unless stated otherwise. It must be admitted that embodiments described by specialists
in that field may contain changes that do not depart from the scope of this invention,
as described in the claims given next.
1. A telescopic-type riser structure for digging round pits that are used for enabling
construction or repair work at underground pipelines and communications,
which comprises of:
at least two round cross-section risers: the supporting and the deep one where four
supports are attached to the top part of the supporting riser and rest on the ground
surface to prevent the supporting riser from sinking into the pit being dug;
machine for setting into / pulling out of the pit;
riser insertion and pulling out cables,
loops for attachment of cables to supporting riser; and
riser interconnections,
the difference being that it comprises:
- reusable round metal risers that can easily pass through each other and that make up the telescopic
riser system (1) where the narrower/insertable riser can be inserted from above through
the wider/receiving riser into the pit being dug (7) and can be pulled out telescopically
once the work has been done;
- inwardly protruding capturing member (13) that is along the entire perimeter attached
to the inside of the bottom part of each receiving riser into which another riser
is inserted from above and that keeps the narrower riser inserted from above from
falling out because of presence of a capturing member (12) in the inserted riser;
- outwardly protruding capturing member (12) that is along the entire perimeter attached
to the outside of the top part of each insertable riser and that has a capturing member
(13) keeping the insertable riser from completely passing through and out of the receiving
riser;
- supports (6) to ensure stability of the supporting riser (2) and the entire riser
system (1); the optimum length of the supports is 1-1.5 m;
where
- the said risers have such cross-sections that make it possible for one or two workers
to descend through them to the pit bottom and do the required repair or construction
work; the optimum cross-section of the supporting riser (2) is 2-3 m and height is
1.5-2 m, the optimum cross-section of the bottommost riser is 1.4-2.4 m, and height
is 1.5-2 m;
- distance between the centre point of the supporting riser (2) set into the pit (7)
and the infrastructure objects near the pit, which must receive no impact, is equal
to or more than the sum of the length of the supports used (6) and the radius of the
supporting riser (2).
2. Where space is limited because of dense infrastructure the riser setting and removal
method used for digging pits comprises:
selection of the pit digging work zone,
its fencing,
marking of existing communications,
digging of 0.5-2.0 m deep initial pit that is 10% larger than the cross-section of
the supporting riser,
use of pit digging and filling machine,
the difference being that
- supports (6) are attached to the edge of supporting riser (2);
- supporting riser (2) is gradually set into the pit (7) and sunk until its supports
(6) touch the ground surface, where riser sinking occurs as the digging machine (8)
digs the ground from the inside of the said supporting riser (2) evenly along the
entire cross-section of the supporting riser (2) and exerts pressure on the said riser
(2) from time to time from the top, where pressing is even on the entire length of
the circle of the riser (2), without pressing too much so that deformation and inclination
of the supporting riser (2) is avoided, and when the supports (6) of the supporting
riser (2) touch the ground surface the sinking of remaining risers into the pit (7)
one through another is started in the same way and the process is continued until
the required depth of the pit (7) is achieved,
- pulling the telescopic risers out of the pit (7) after completion of construction
or repair work at underground pipelines and communications is started by gradually
pulling the riser (5) located the deepest in the pit up while filling the resulting
unnecessary cavity with ground until the entire pit or part of it is filled up.