Field of the Invention
[0001] The invention relates to piling for rail tracks, and in particular to a method and
system for piling railway tracks to improve the underlying foundation structure.
Background
[0002] A conventional rail track structure comprises a pair of continuously welded parallel
steel rails supported by a series of concrete, wood or steel sleepers laid on top
of a stone ballast foundation. The stone ballast foundation may be laid over a variety
of different substructures, generally including a formation layer that defines the
general form, i.e. the extent and gradient, of the rail track beneath the ballast
layer.
[0003] A problem with existing conventional rail track structures is that the substructure
can degrade over time, for example due to continued use of the track or due to environmental
factors such as erosion of movement of the underlying water table. The underlying
substructure may be unstable over time, or may become less suitable due to a requirement
to use increased speeds on the track, resulting in increased loading and a need to
maintain tighter tolerances on track uniformity. It may therefore become necessary
to upgrade an existing track in order to allow the track to be optimally used with
new rolling stock, otherwise the new rolling stock may be forced to travel along the
track at a reduced speed or not be allowed to use the track at all.
[0004] Upgrading existing rail tracks to improve the track and substructure, for example
to allow for increased speeds of travel, is generally extremely expensive, labour
intensive, time consuming and disruptive due to the need for extensive excavation
and construction works to be carried out around and underneath the track. In some
cases it may be more cost effective and less disruptive to simply build an entirely
new track rather than attempt to upgrade an existing track to meet more stringent
requirements.
[0005] Conventional track maintenance and renewal may involve replacement of the ballast
layer, which may be done at the same time as realigning the track and sleepers. This
does not, however, affect the underlying foundation structure, which can still be
subject to movement that may result in the track requiring further maintenance.
[0006] It is an object of the invention to address one or more of the above mentioned problems.
Summary of the Invention
[0007] In accordance with a first aspect of the invention there is provided a method of
modifying an existing rail track structure comprising a pair of rails laid over a
series of sleepers on top of a ballast layer, the method comprising forming a pile
structure extending vertically beneath and between adjacent ones of the series of
sleepers, wherein a top of the pile structure is separated from the series of sleepers
by the ballast layer. As well as being separated by at least a portion, if not the
whole of, the ballast layer, the top of the pile structure may also be separated from
the series of sleepers by other layers such as a sub-ballast layer and/or a formation
layer.
[0008] A feature of the invention is that the pile structure extends vertically between
the existing rails and sleepers, thereby allowing the method to be used on existing
rail tracks with reduced disruption to the track structure, reducing the need to excavate
and transport material for disposal. The invention allows for a reduction in plant
and maintenance activities, allowing such activities and plant to be redirected to
improving more existing rail track. The invention may also reduce or remove the need
for temporary speed restrictions, thereby reducing the impact on use of the rail track.
[0009] By having the pile structure not directly connected to the sleepers, but instead
via at least a portion of the ballast layer (and optionally also a sub-ballast layer
and/or a formation layer), the rail track is supported over a wider area and the method
of installing the pile structure is greatly simplified compared to one where a physical
connection may need to be made between the pile structure and the sleepers.
[0010] The top of the pile structure (or pile cap) may be at least 0.5m, 0.6m, 0.7m, 0.8m,
0.9m or 1m beneath the series of sleepers. The depth of the top of the pile structure
may vary depending on the support required. A deeper placed pile structure may, for
example, be used when the ballast contains higher levels of fine grained materials
to support the rail track, with each pile structure effectively supporting multiple
sleepers, whereas a shallower pile structure may be used when the ballast is clean,
i.e. with lower levels of fine grained materials.
[0011] The pile structure may have a length of 1 m or longer, optionally between 1 and 8
m, between 1 and 3 m, and in a particular example around 2 m long. The length of the
pile structure will depend on the type of subsurface material beneath the rail track,
and how deep any sound underlying material is upon which the pile structure transmits
any downward forces.
[0012] The pile structure may comprise a cemented column, optionally comprising one or both
of a cemented granular stone fill material and a metal reinforcement structure. An
alternative pile structure may comprise a metal (typically steel) tube, grouted internally
and externally with cement and with a grouted steel pile cap and cutting shoe. Either
form of pile may be formed using a temporary metal outer casing which is removed following
pile installation and reinstatement of the track ballast. The granular cemented pile
may be a free draining (porous) or solid (non-porous) structure.
[0013] The method may comprise vertically inserting a tube, typically a metal tube, between
adjacent sleepers of the rail track through the ballast layer using an auger. When
the tube is in place, the pile structure may be inserted or formed within the tube,
followed by backfilling with railway ballast material and removal of the tube. In
some embodiments, the hole formed by the auger and defined by the tube may be cemented
after the auger is removed, following which the tube is removed. The hole may alternatively
be cemented during removal of the auger. A membrane layer and/or a reinforcement structure
may be applied around the hole formed by the auger and tube to further strengthen
the pile and reduce ingress of any surrounding fine grained materials.
[0014] In accordance with a second aspect of the invention there is provided a rail track
structure comprising a pair of rails laid over a series of sleepers on top of a ballast
layer, a pile structure extending vertically beneath and between adjacent ones of
the series of sleepers, wherein a top of the pile structure is vertically separated
from the series of sleepers by the ballast layer.
[0015] A plurality of said pile structures may be provided in a regular array, extending
in a travel direction along the rail track. A horizontal spacing of the pile structures,
i.e. a spacing in a travel direction along the rail track, may be an integer multiple
of a horizontal spacing of the series of sleepers, i.e. a pile structure may be provided
between each pair of sleepers, between alternate pairs of sleepers or between pairs
of sleepers at regular intervals. Pairs of pile structures may be provided between
adjacent pairs of sleepers, i.e. each pile structure may be accompanied by another
pile structure positioned between the same pair of adjacent sleepers.
[0016] The various other optional features associated with the first aspect of the invention
may also be applied to the second aspect.
[0017] Pile structures formed according to the invention can enhance the properties of an
existing track bed, improving track quality and extending the life of the track system.
The pile structures act to regulate system stiffness and rate of change of stiffness,
thereby improving ride quality and reducing maintenance intervention. The properties
of the existing track bed can also be enhanced by improving stiffness to allow an
increased line speed as well as improving track drainage.
Detailed Description
[0018] The invention is described in further detail below by way of example and with reference
to the accompanying drawings, in which:
figure 1 is a schematic cross-sectional diagram of an existing rail track structure;
figure 2 is a schematic cross-sectional diagram of an exemplary series of pile structures
provided beneath an existing rail track; and
figure 3 is an further schematic cross-sectional diagram of an exemplary series of
pile structures provided beneath an existing rail track.
[0019] Figure 1 illustrates schematically a loading distribution of an existing rail track
structure 100, indicating a pair of sleepers 101 laid over a ballast layer 102. Vertical
forces P from the overlying track (not shown) and any rolling stock are transmitted
through the sleepers 101 into the ballast layer 102. Dotted lines 103 indicate the
general area the load is transmitted from each sleeper 101 through the ballast layer
102, an underlying formation layer 104, a weak soil layer 105 and a strong soil layer
(or bedrock layer) 106, the load footprint of the sleeper becoming progressively larger
as the load is transmitted further into the rail track substructure. The various layers
102, 104, 105, 106 are shown by way of example, are not illustrated to scale, and
should be taken as only illustrative of the type of arrangement of subsurface layers
that may be encountered typically.
[0020] Figure 2 illustrates a cross-sectional schematic diagram of a rail track structure
200 comprising an exemplary piling system in place beneath the rail track. As with
figure 1, a series of sleepers 101 are laid over a ballast layer 102 overlying a formation
layer 104, a weak soil layer 105 and a strong soil layer (or bedrock layer) 106. A
vertical pile structure 201 is provided between adjacent sleepers 101, the pile structure
201 extending through the formation layer 104, weak soil layer 105 and strong soil
layer 106. The loading from each sleeper 101, the spreading of which is indicated
by dotted lines 103, is transmitted to the top of each pile structure 201. The vertical
stiffness of the pile structure 201 transmits this load directly through the intervening
layers into the strong soil layer 106, thereby adding support to each of the sleepers
101 without a direct connection between the pile structure 201 and the sleepers 101.
The load is spread from the bottom of the pile structure 201 into the strong soil
layer 106, providing a matching upward force to that applied to the sleepers 101.
[0021] As can be seen in figure 2, the top 202 of each pile structure 201 is vertically
separated from the adjacent sleepers 101 by the ballast layer 102. In the embodiment
in figure 2, the top 202 of each pile structure 201 lies beneath the ballast layer
102 and extends through the underlying foundation layer 104, the pile structure 201
being separated from the sleepers by the ballast layer 102 and a portion of the foundation
layer 104. In alternative embodiments the top 202 of the pile structure 201 may extend
into the ballast layer 102, provided there is a vertical separation between the top
202 and the sleepers 101.
[0022] Figure 3 illustrates schematically a more detailed view of an exemplary embodiment
of a rail track structure 300 incorporating a piling system. Vertical pile structures
301 are provided between adjacent pairs of sleepers 101, on which a rail 309 is laid.
Dotted lines 303 indicate the approximate extent of the load footprint beneath each
sleeper 101, indicating that the top 302 of each pile structure 301 lies within the
footprint of four sleepers 101. The particular arrangement in figure 3 allows for
a pile structure 301 to be provided in alternate spaces between adjacent sleepers
101. The dimensions of the rail track structure 300 allow for a nominal 0.8 m vertical
distance between the bottom of the sleepers 101 and the top 302 of the pile structures
301, and a horizontal spacing of 1.3 m, i.e. around twice the 0.660 m horizontal spacing
of the sleepers 101 (sleeper spacings typically vary between 610 and 760mm). In a
general aspect, a horizontal spacing of the pile structures 301 may be an integer
multiple of a horizontal spacing of the sleepers 101, the multiple typically ranging
between one and four.
[0023] Each of the pile structures in the embodiment shown in figure 3 is nominally 2 m
long and 0.24 m in diameter. Each pile structure 301 is effectively a stone column
formed from compacted granular material such as ballast material. The pile structure
301 may be reinforced with an external grid reinforcement structure, which may be
formed from a polymer material, and may comprise a membrane layer (known as a geotextile
sock) to provide a barrier between the pile structure and the surrounding fine grained
materials.
[0024] The following paragraphs describe two specific exemplary embodiments of methods of
forming pile structures.
[0025] In a first exemplary embodiment, where a piling system is installed without removal
of the track, steel axial piles are installed, preferably in pairs, between the two
running rails within the sleeper crib, i.e. between adjacent sleepers. A temporary
275mm diameter steel tube is inserted into the ballasted sleeper crib by using an
auger inserted inside the tube. As the auger is rotated inside the tube, the tube
sinks into the ballast layer to a depth of around 700mm below ground level (i.e. the
sleeper top level), with approximately 100mm of tube left protruding above ground
level. The auger is removed, leaving the temporary steel tube in-situ during the installation
of the pile structure. A steel pile is rotated into the ground within the temporary
tube to the required depth, which can be up to several metres beneath the sleepers
depending on ground conditions. As the steel pile is installed it is simultaneously
grouted internally and externally, external grouting being applied via the pile head.
The finished steel pile cap is located at a depth of approximately 1m below ground
level and grouted on top to a depth of 200mm to increase the pile cap load bearing
area. The remainder of the tube is backfilled with track ballast to sleeper top level.
The temporary steel tube is then withdrawn using the on-track machine. The depth and
the length of the pile varies depending on the track bed & sub-grade conditions
[0026] In a second exemplary embodiment, also undertaken without removal of the track, stone
or granular pile structures are installed, preferably in pairs, between the two running
rails within the sleeper crib (i.e. the space between adjacent sleepers). A temporary
275mm diameter steel tube is first inserted into the ballasted sleeper crib by using
an auger inserted inside the tube. As the auger is rotated inside the tube the tube
sinks into the ballast layer to a depth of around 2200mm below ground level (sleeper
top level), with approximately 100mm of tube left protruding above ground level. The
auger is removed leaving the temporary tube in-situ during the installation of the
stone column pile structure. To form the pile structure, the steel tube is backfilled
with a granular / cement mix to a depth of approximately 700mm below ground level
(sleeper top level). The remainder of the tube is then backfilled with track ballast
to sleeper top level. The temporary steel tube is then withdrawn using the on-track
machine. The depth and the length of the pile varies depending on the track bed &
sub-grade conditions.
[0027] Other embodiments are intentionally within the scope of the invention as defined
by the appended claims.
1. A method of modifying an existing rail track structure comprising a pair of rails
laid over a series of sleepers on top of a ballast layer, the method comprising forming
a pile structure extending vertically beneath and between adjacent ones of the series
of sleepers, wherein a top of the pile structure is separated from the series of sleepers
by the ballast layer.
2. The method of claim 1 comprising:
inserting a tube between adjacent sleepers of the rail track structure through the
ballast layer using an auger;
removing the auger;
inserting or otherwise forming the pile structure within the tube; and
back-filling the tube with ballast material.
3. The method of claim 2 comprising removing the tube after forming the pile structure.
4. A rail track structure comprising a pair of rails laid over a series of sleepers on
top of a ballast layer, a pile structure extending vertically beneath and between
adjacent ones of the series of sleepers, wherein a top of the pile structure is vertically
separated from the series of sleepers by the ballast layer.
5. The method or rail track structure of any preceding claim wherein the top of the pile
structure is at least 0.5m, 0.6m, 0.7m 0.8m, 0.9m or 1m beneath the series of sleepers.
6. The method or rail track structure of any preceding claim wherein the pile structure
is greater than 1m long, optionally between 1m and 8m long.
7. The method or rail track structure of any preceding claim wherein the pile structure
comprises a cemented column.
8. The method or rail track structure of any preceding claim wherein the pile structure
comprises one or both of a cemented granular stone fill material and a reinforcement
structure.
9. The method or rail track structure of any preceding claim wherein the pile structure
comprises a metal outer casing.
10. The method or rail track structure of any preceding claim wherein a plurality of said
pile structures is provided in a regular array.
11. The method or rail track structure of claim 10 wherein a horizontal spacing of the
plurality of pile structures is an integer multiple of a horizontal spacing of the
series of sleepers.
12. The method or rail track structure of claim 10 or claim 11 wherein pairs of pile structures
are provided beneath adjacent pairs of sleepers.