[0001] The present invention relates to a material handling machine.
[0002] Known material handling machines such as excavators have a material handling arm
assembly. The arm assembly may have an arm, known as a boom, pivotally mounted about
a generally horizontal axis relative to a chassis of the machine. A further arm, known
as a dipper, may be attached to an end of the boom remote from the chassis and may
be pivotable about a generally horizontal axis. A material handling implement such
as a bucket may be pivotably mounted on an end of the dipper. The boom may be raised
and lowered by operation of a first hydraulic ram. The dipper may be moveable relative
to the boom by operation of a second hydraulic ram, the bucket may be moveable relative
to the dipper by operation of a third hydraulic ram.
[0003] In order to handle material, for example dig a trench, a machine operator must simultaneously
operate all three hydraulic actuators and this is a skilful process. A skilful operator,
when digging a trench, will quickly be able to fill the bucket with material, lift
bucket out of the trench and empty the bucket to one or other side of the vehicle.
This excavation cycle time or loading cycle time is markedly affected by the initial
penetration of the bucket into the ground. If the bucket penetrates too far into the
ground then the bucket cannot be drawn through the ground to be filled. Conversely
if the bucket does not penetrate far enough into the ground, then the bucket only
half fills. Less well trained operators tend to operate at lower excavation/ loading
cycle times.
[0004] Accordingly, there is a need for an improved material handling machine.
[0005] Thus, according to the present invention there is provided A method of operating
a material handling machine having a material handling implement moveable relative
to a chassis of the machine, the method including the steps of
- a) positioning the material handling implement in a first position of a first region,
- b) moving the material handling implement to a second region,
- c) providing a control system to automatically return the material handling implement
to the first region by positioning it at a second position of the first region different
to the first position of the first region,
- d) returning the material handling implement to the second region.
[0006] The first region may be a region where it is desired to dig a trench. The second
region may be a region where it desired to deposit spoil from the trench. Advantageously
step a) positions the implement in the first region, for example in the region where
it is desired to dig a trench but step c) positions the material handling implement
at a different position in the first region than step a). Advantageously the control
system automatically positions the material handing implement at an incrementally
different position in the trench, thereby assisting digging of the trench as it is
incrementally extended. The material handling implement is automatically placed directly
at the next sequential position in the trench as the length of the trench is progressively
extended. The different positions in the trench to which the material handling implement
is directly positioned as the trench is incrementally extended may successively progress
towards the machine or away from the machine. The direct positioning of the material
handling implement to the required position within the trench (i.e. the material handling
implement is not moved via a previous digging position) saves time and facilitates
more efficient digging.
[0007] The invention will now be described, by way of example only, with reference to the
accompanying drawings in which:-
Figure 1 is a schematic side view of a material handling machine according to the
present invention,
Figure 2 is a schematic plan view of part of the material handling machine of figure
1, and
Figure 3 is a schematic side cross-section view of a trench dug by the machine of
figure 1 according to the method of the present invention.
[0008] With reference to figures 1 and 2 there is shown a material handling machine 10 including
a chassis 12 and an operator cab 14. The operator cab is mounted on the chassis 12.
Ground engaging transport means in the form of a pair of tracks 16 are provided on
the chassis to move the machine over the ground.
[0009] Attached to a frame of the cab 14 is an arm assembly 18, the arm assembly includes
a first arm in the form of a boom 20, a second arm in the form of a dipper 22 and
a ground engaging implement in the form of a bucket 24. The boom 20 is pivotally mounted
by pivot 26 to link 12A at a first end 20A of the boom. Link 12A is pivotally mounted
at a generally vertical axis relative to the frame. Pivot 26 is orientated horizontally.
The dipper is pivotally mounted via pivot 28 to a second end 20B of the boom 20. Pivot
28 is orientated horizontally. The bucket is pivotally mounted via pivot 30 to an
end 22B of dipper 22 remote from end 22A of dipper 22. Pivot 30 is orientated horizontally.
[0010] A first hydraulic actuator in the form of a first hydraulic ram 32 has a first end
32A pivotally attached to the frame and a second end 32B pivotally attached to the
boom part way between the first and second ends of the boom. A second hydraulic actuator
in the form of a second hydraulic ram 34 has a first end 34A pivotally attached to
the boom part way between the first and second ends of the boom and a second end 34B
pivotally attached to the dipper proximate the first end 22A of the dipper. A third
hydraulic actuator in the form of a third hydraulic ram 36 has a first end 36A pivotally
attached to the dipper proximate the first end 22A of the dipper and a second end
36B pivotally attached to a linkage mechanism 38 proximate the second end of the dipper.
The linkage mechanism 38 per se is known and simply converts extension and retraction
movement of the third hydraulic ram 36 into rotary movement of the bucket 24 about
pivot 30.
[0011] Extension of the first hydraulic ram causes the boom to raise, and contraction of
the first hydraulic ram causes lowering of the boom. Extension of the second ram causes
the dipper to pivot in a clockwise direction (when viewing figure 1) about pivot 28,
i.e. causes the boom to move in a "dipper in" direction, and retraction of the second
hydraulic ram 34 causes the dipper to move in an anticlockwise direction when viewing
figure 1 about pivot 28, i.e. in a "dipper out" direction. Extension of the third
hydraulic ram 36 causes the bucket 24 to move in a clockwise direction about pivot
30, i.e. in a "crowd" direction, and retraction of the third hydraulic ram 36 causes
the bucket to move in an anticlockwise direction about pivot 30, i.e. in a "dump"
direction.
[0012] The first, second and third hydraulic rams are all double acting hydraulic rams.
Double acting hydraulic rams are known per se. They include a piston within a cylinder.
The piston is attached to a rod which extends beyond the end of the cylinder. The
end of the rod remote from the piston defines one end of the hydraulic ram. The end
of the cylinder remote from the rod defines an opposite end of hydraulic ram. A "head
side chamber" is defined between the piston and the end of the cylinder remote from
the rod. A "rod side chamber" is defined between the piston and the end of the cylinder
proximate the end of the rod. Pressurisation of the head side pressure chamber extends
the ram and pressurisation of the rod side chamber causes the ram to retract.
[0013] The machine includes a system for operating the first, second and third hydraulic
rams, as described below.
[0014] A hydraulic pump (not shown) is driven by a prime mover. Prime mover may be an internal
combustion engine, though other prime movers are suitable. A boom spool valve (not
shown) can be operated by an operator manipulating boom control (not shown) to extend
or retract hydraulic ram 32. A dipper spool valve (not shown) can be controlled via
a dipper control (not shown) to extend or retract hydraulic ram 34. A bucket spool
valve (not shown) can be controlled by a bucket control (not shown) to extend or retract
hydraulic ram 36. Thus, the operator can manually manipulate the boom control, dipper
control and bucket control in order to manoeuvre and handle material.
[0015] The material handling machine also includes a control system 52.
[0016] The control system 52 can be selectively enabled or disabled at the option of the
operator. In order to enable the control system 52 the operator actuates a switch,
button or other operator input device (not shown). In order to disable the control
system 52 the operator actuates the button, switch or other operator input device.
[0017] When the control system is disabled, the operator can manually manipulate the boom
control, dipper control and bucket control, as described above, in order to manoeuvre
and handle material.
[0018] With the control system enabled, operation is as follows:-
[0019] The control system 52 allows a pre-programmed sequence of manoeuvres to be carried
out automatically.
[0020] Thus, by way of example when it is required to dig a trench or the like the operator
enables the control system 52. The control system 52 then controls movement of the
boom, dipper and bucket in a pre-programmed sequence of manoeuvres. In a typical sequence
of movements of the arm assembly is as follows:-
[0021] Firstly, the control system 52 lowers the boom and the dipper is moved in a "dipper
out" direction thereby moving the bucket teeth 25 of the bucket 24 away from the chassis
12. The boom is then further lowered such that the bucket teeth 25 engage the ground.
The bucket is then crowded slightly so as to start to move the bucket teeth through
the ground. The dipper, boom and bucket are then simultaneously operated by the control
system 52 to progressively move the dipper in a "dipper in" direction and to move
the boom in a "boom raised" direction and to move the bucket in a "crowd" direction
such that the bucket teeth move generally towards the chassis to fill the bucket with
ground material. Once the bucket is full, the boom is raised, the arm assembly is
swung laterally relative to the machine and the ground material is then dumped by
moving the bucket to a dumped position. The sequence is then generally repeated. However,
as the bucket is returned to the trench it is not positioned in the same position
as when the first bucket load of ground material was removed, rather it is positioned
at an incrementally different position ready to take the second bucket load of ground
material.
[0022] Thus, with regard to figures 2 and 3, in order to dig the trench the cutting edge
24B of the bucket must first be positioned on the ground surface G at point 101. The
control system then moves the boom, dipper and bucket so as to draw the leading edge
24B to point 102. The control system then crowds the bucket to draw the cutting edge
24B to point 103 following which the boom is raised to move the bucket out of the
ground. This results in the removal of portion A of the ground shown cross-hatched
in figure 3. The frame is then swung clockwise relative to the chassis (when viewing
figure 2) so as to move the bucket towards a second region 60, where it is intended
to dump the spoil from the trench. Once the bucket 24 is above second region 60 the
bucket is then "dumped" thereby depositing spoil A on the ground at region 60. The
frame is then swung anticlockwise and the cutting edge 24B is returned to the trench.
However, since ground material A has been moved, the leading edge 24B of the bucket
24 needs to be positioned at position 102 by the control system rather than at position
101. In order to fill the bucket for the second time the cutting edge is positioned
at position 102, moved to position 104 and then moved to position 105 in order to
collect ground material B shown cross-hatched in figure 3. The boom is then raised
to lift the bucket out of the ground, the frame is swung clockwise and the spoil B
is deposited at the second region 60 thereby forming a spoil pile. For the third bucket
load the cutting edge is initially positioned at position 104 by the control system
and then moved to position 106 and 107. For the fourth bucket load the cutting edge
is positioned at position 106 by the control system and then moved to position 108
and 109. The fifth bucket load is positioned at position 108 by the control system
and then moved to position 110 and then 111. The sixth bucket load is positioned at
position 110 by the control system and then moved to position 112 and 113. Thus, each
time the bucket is returned to the trench, the cutting edge is positioned by the control
system incrementally differently from the previous occasion.
[0023] The desired position of the trench represents a first region 59 (see figure 2). The
spoil pile of the trench represents second region 60 (see figure 2). The invention
provides for moving the material handling implement (in this example the bucket 24)
repeatedly between the first and second regions. However, the implement is not moved
to the same position when at the first region, rather it is moved automatically to
an incrementally different position of the first region. In this way a trench or the
like can progressively be dug.
[0024] Where short trenches are required to be dug, then the movement of the boom, dipper
and bucket alone may be sufficient to dig the short trench, in other words it may
not be necessary to move the vehicle via tracks 16. However, in other circumstances
where a longer trench is required then the first part of the trench may be dug (for
example by removing ground material A, B and C whilst the chassis is positioned at
position 1 of figure 1. In order to remove ground material D, E and F it may be necessary
to move the chassis to position 2 as shown in figure 2. In spite of movement of the
chassis the bucket nevertheless returns to the first region, i.e. returns to the trench
in order to remove ground material D, E and F.
[0025] In one embodiment the system allows automatic digging of a trench or the like, and
as such there is no need for an operator to be physically present in the machine,
rather the operator can be remote from the machine. This is particularly advantageous
in dangerous environments where the operator can be remote from the machine in a safe
location.
[0026] When in a remote location, the operator need not control all aspects of the machine.
In one example all that the operator needs to define is the first position of the
first region and the second region. Once this has been done the control system can
automatically cause a sequence of predefined movements to occur thereby handling material
in a desired manner, for example digging a trench or a hole at the first region and
depositing the spoil at the second region.
[0027] Alternatively, in another embodiment only certain steps may be controlled by the
controller. For example, it is only necessary for the step of returning the material
handling implement to the first region by positioning it at a second position of the
first region different to the first position of the first region be carried out automatically.
This enables the implement to be quickly returned to an appropriate position (for
example in a trench) different from the previous position of implement (for example
in the trench). The control system therefore can quickly return the implement to an
incrementally different position. This then enables the operator to control movement
of the implement, for example to handle material, until such time as it is required
to return the implement to another incrementally different position. This is advantageous
when the material being handled is not uniform, for example where the ground includes
occasional large rocks or other such material. For example, when digging a trench
the first three bucket loads may contain loose material such as soil. Pickling up
of this soil requires a particular implement manoeuvre. However, a fourth load may
require the digging up of a rock or the like which will require a slightly different
implement manoeuvre. The operator will be able to determine the required implement
manoeuvre required to pick-up the soil or rock, as appropriate, but nevertheless once
the earth/rock has been deposited on the spoil heap, the machine can nevertheless
return the implement to an appropriate incrementally different position ready for
a further material handling implement manoeuvre to pick-up further soil or a further
rock as appropriate and as will be seen by the operator.
[0028] As described above, and as shown in figure 3, the leading edge 24B of the bucket
starts at position 101. For each successive bucket load it is positioned at positions
102, 104, 106, 108 and 110. These incrementally different starting positions generally
progress towards the machine. However, in further embodiments the incrementally different
positions need not progress towards the machine, rather they can progress in any direction.
In particular, when digging a deep hole, or a deep trench, certain of the incrementally
different position may be directly below a previous position.
[0029] The control system may be pre-programmed at the manufacturing factory with a sequence
of manoeuvres to be carried out. Alternatively, the control system may be pre-programmed
in the field. In particular the control system may be pre-programmed in the field
by recording a sequence of material handling manoeuvres and then arranging for those
manoeuvres to be repeated with an offset. For example, an alternative way of digging
the trench of figure 3 is with the control system disabled, the operator removes soil
A and B.
[0030] With the control system still disabled, the operator enables a recording system which
then records the sequence of manual manipulations of the boom control, dipper control
and bucket control used to remove soil C and D. That sequence of recorded manoeuvres
becomes the pre-programmed sequence of manoeuvres in order to remove soil E and F
except with an offset. In other words sequence of manoeuvres used to remove soil D
and E are repeated to remove soil E and F except they are repeated with an offset
according to the distance between position 104 and 108.
[0031] In an embodiment additional sensors can be provided to provide a feedback loop for
the positional control of the implement. However, in an embodiment no sensors or the
like are required and accordingly no positional feedback loop. Such an arrangement
is therefore relatively inexpensive (since no feedback sensors are required) and is
relatively easy to maintain (since there are no sensors which require maintenance.
[0032] As described above, the material handling machine is an excavator. However, the present
invention is not limited to excavators and other material handling machines could
be used, for example a back hoe loader, a telescopic handler, a fork lift truck etc.
As described above, the implement used is a bucket. However, in further embodiments
it is not necessary to use a bucket and other implements should be used, for example
fork lift truck or telescopic handler forks could be used etc.
[0033] As described above, the step of positioning the material handling implement in a
first position of a first region and the step of returning the material handling implement
to the first region by positioning it at a second position of the first region different
to the first position of the first region are carried out with the machine stationary,
either with the machine stationary in the same position, or with the machine stationary
in different positions. In further embodiments it is impossible to carry out one or
both of these steps whilst the machine is in motion, i.e. whilst the machine is travelling
over the ground.
1. A method of operating a material handling machine having a material handling implement
moveable relative to a chassis of the machine, the method including the steps of
a) positioning the material handling implement in a first position of a first region,
b) moving the material handling implement to a second region,
c) providing a control system to automatically return the material handling implement
to the first region by positioning it at a second position of the first region different
to the first position of the first region,
d) returning the material handling implement to the second region.
2. A method as defined in claim 1 wherein step a) is carried out automatically by the
control system, preferably step a) includes carrying out a material handling manoeuvre
with the implement, preferably the manoeuvre picks up material.
3. A method as defined in claim 1 or 2 wherein step b) is carried out automatically by
the control system, preferably step b) includes moving material carried by the implement
to the second region.
4. A method as defined in any preceding claim wherein step b) is carried out automatically
by the control system, wherein step b) includes carrying out a material handling manoeuvre
with the implement at the second region, preferably the manoeuvre deposits material.
5. A method as defined in any preceding claim wherein step c) is carried out automatically
by the control system, wherein step c) includes returning the material handling implement
to the first region absent any material.
6. A method as defined in any preceding claim wherein step c) is carried out automatically
by the control system, wherein step c) includes carrying out a material handling manoeuvre
with the implement, preferably carrying out a material handling manoeuvre of claim
2.
7. A method as defined in any preceding claim wherein step d) is carried out automatically
by the control system, preferably step d) includes moving material carried by the
implement to the second region.
8. A method as defined in any preceding claim wherein step d) is carried out automatically
by the control system, wherein step d) includes carrying out a material handling manoeuvre
with the implement at the second region, preferably carrying out the material handling
manoeuvre of claim 4.
9. A method as defined in any preceding claim wherein step b) is carried out automatically
by the control system, wherein step b) includes moving the material handling implement
to a first position of the second region and is carried out automatically by the control
system, wherein step d) includes returning the material handling implement to a second
position of the second region different from the first position of the second region.
10. A method as defined in any preceding claim wherein the method is used to dig a hole,
and/or wherein the material is frangible material and/or loose material, for example
wherein the method is used to transfer the frangible and/or loose material from the
first region to the second region.
11. A method as defined in any preceding claim wherein the material handling implement
is a bucket or a shovel, and/or wherein steps a), b), c) and d) are carried out whilst
the chassis of the machine is stationary.
12. A method as defined in any preceding claim including:-
e) arranging a control system to automatically return the material handling implement
to the first region by positioning it at a third position of the first region different
to the first and second positions of the first region, the second position of the
first region being intermediate, the first position of the first region and the third
position of the first region,
f) returning the material handling implement to the second region.
13. A method as defined in claim 12 wherein step f) is carried out automatically by the
control system.
14. The method as defined in claim 12 wherein steps a), b), c), d), e) and f) are carried
out whilst the chassis of the machine is stationary.
15. The method as defined in claim 12 wherein steps a), b), c) and d) are carried out
whilst the chassis of the machine is stationary and prior to carrying out steps e)
and f) the chassis of the machine is moved to a different and/or adjacent location.