Object of the invention
[0001] The invention, as its title indicates, relates to a method for concreting railway
slab track, proceeding from an initial position in which the assembly formed by the
rails fixed to the sleepers and/or fastening elements (which are called premounted
track or skeleton track), once laid and premounted on an existing base or base plate
(bed of the future slab track) and then perfectly positioned with precision and fixed
by means of fixing/fastening means in the final suspended position, concreting of
the assembly takes place, thus constituting the concrete slab which forms the support
means which replace the ballast of a traditional track. In other embodiments, independent
concrete blocks or fastening plates of the rail are mounted instead of the sleepers,
(the track width being established until the setting of the concrete by way of provisional
elements called "false sleepers" in these latter cases), or even any other system
which either discretely or continuously serves for fastening the rail and serves as
reference thereof with the concrete and once the system has been positioned with precision
in each case, either with the premounted rail or even without it, concreting takes
place.
[0002] The invention also relates to a system for concreting a railway slab track which
joins a series of apparatuses which allow the concrete to be transported from one
supply point or area to the concreting point or area as well as for carrying out the
pouring of the concrete in a controlled and uniform manner, distributing it over the
skeleton track (between the sleepers or fastening system which is used in each case)
to the required level, the latter having been previously suitably position with the
strict tolerances required and fixed in the final suspended position thereof to form
the so-called railway slab track once the concrete has set.
Background of the invention
[0003] The slab track allows high geometric quality to be obtained and reduces the maintenance
costs with the respect to ballast track (amongst other advantages such as eliminating
the problem of ballast flight, etc.), however, the cost of the construction thereof
is higher. In Spain, slab track is not generally used, but it is used in particular
areas such as for example in tunnels, in which the problem and cost of maintenance
of the ballast track are especially high, particularly on high speed lines.
[0004] At present, there are various methods for carrying out the concreting of slab track,
which are described in general below:
In the case of there being sufficient space at the side of the track under construction,
for example in the case of a tunnel with a double track when the first of the two
tracks is intended to be constructed, the concreting can be carried out by means of
direct pouring, the trucks with concrete accessing through the lateral space to the
pouring point and then withdrawing, in the case of all this being possible - including
the necessary maneuvers and crossings. In these cases, the concreting of the second
track can be carried out from the first already constructed track, using concrete
tanks implemented on towed or motorized railway platforms.
[0005] In the cases where direct pouring is not possible due to lack of space, an alternative
is to concrete by means of pumping the concrete. To this end, a static pump can be
used which is placed in the interior of the tunnel, or in proximity thereto, which
carries out the pumping of the concrete by way of a pipe or tube to the concreting
point. As the concreting point advances, it is necessary to supplement the tube, the
pump also being able to move to advanced positions as the execution of the concreting
advances. In order to bring the concrete to the pump, it is necessary to use concrete
mixer trucks, in the case where there is space for this, or either railway platforms
equipped with tanks towed by means of a towing or motorized vehicle along the adjacent
track already constructed or along the track itself that is under construction on
the area where the concrete has already set, in this case they can travel only to
the area where the concrete has already acquired sufficient resistance, concreted
with sufficient time in advance.
[0006] The sections of pipe have to be cleaned in the interior thereof, moved, connected
and disconnected, the total pipe length being modified, sections implemented or removed
as the work advances, which is very laborious.
[0007] The lack of space is the main problem for carrying out these works appropriately.
In the case of tunnels with a single track, the problem is heightened even further.
In these tunnels, the difficulty of the work is greater, the options very limited
and the yields of concreting are reduced.
[0008] The traditional methods of concreting slab track described are laborious, the mechanical
means and above all manpower required are high, the degree of automation is low and
the yields are limited. The logistics of the supply and pouring process of the concrete
is not efficient, interferences among the different activities being frequent. The
coordination of the tasks is complex, the stoppages are usually frequent due to various
reasons and the stoppage times can be long. Other noteworthy problems are those associated
with pumping the concrete in the case where this system is used: blockages in the
pipe, etc. Moreover, it should be pointed out that one problem in any of the many
stages of the process usually causes the interruption of the concreting, with the
consequences which these stoppages cause under these conditions.
[0009] An alternative to the methods described is the one used in the construction of the
Guadarrama tunnels, with a single track, by means of a method consisting of introducing
a complete train with mixers to the point where a static pump is situated close to
the concreting point. The train travels along a provisional auxiliary track which
must be constructed expressly for this purpose in parallel to the track which is desired
to be concreted, on one side of the same, and in the narrow space present for it -
the distance between the two rails thereof must be reduced.
[0010] The work and the outline of the process are similar to those of the traditional method
already described, with some particularities:
- constructing a provisional auxiliary track in parallel to the track which is desired
to be concreted in order to allow access of a train with mixers.
- transporting concrete in concrete mixer trucks from the concrete factory to the train
with mixers initially situated at the exterior of the tunnel. Transferring the concrete
from the trucks to the train.
- Once the mixers of the train are full, it is moved to the point where the pump is
located, travelling along the constructed provisional auxiliary track.
- the concreting is carried out by means of pumping, by means of a pump which is moved
gradually, always maintaining it close to the concreting point.
- Vibrating to ensure the compactness of the concrete. Manual leveling of the surfaces
to achieve the prescribed tolerances. Floating the concrete of the track and cleaning
the fastenings and the rail.
- Once all the concrete has been discharged from the train, it is pulled out to receive
another load at the exterior of the tunnel. At this time, the concreting is interrupted
until this train arrives once it has reloaded, or until another train already loaded
and previously prepared arrives.
[0011] This method involves an improvement with respect to the traditional methods when
it is necessary to concrete sections of great length since introducing a train full
with mixers avoids discontinuous supply. However, on the other hand, it has significant
disadvantages which ultimately limit its competitiveness:
- the cost is very high due to the high cost involved with a special train with mixers
and due to the cost involved with constructing the provisional auxiliary track
- the flexibility of the method is low. The concrete volume to be pumped is limited
by the capacity of the train (no. of mixers). And in turn, the initial dimensioning
of the train and the volume with which it is loaded will limit the process. In this
aspect, it is difficult to scale.
- once the concrete of the train has been depleted, it must exit in order to reload,
the concreting process being interrupted.
- given the process described and the cost thereof, this system is only cost-effective
for constructing long lengths of slab track
- in the case of there not being sufficient space for constructing the adjacent auxiliary
track, or in the case of it not being possible to construct it for any reason, the
use of this method would not be viable
- the use of the pump continues bringing with it certain related problems. The flow
rate of concrete is limited by the capacity of the pump.
[0012] Among the recent developments intended to improve the application of concrete, the
particular work of the new tunnel at the base of San Gottardo stands out. This is
a railway tunnel beneath the Swiss Alps. The length of the infrastructure is 57 km
and with a total of 151.84 km of tunnel and galleries it is the longest railway tunnel
in the world. The slab track is currently being implemented and the German method
is being used for concreting the track, using a train with unprecedented dimensions
(24 mixers). The improvement variant consists of introducing a system for allowing
the loading of the train within the tunnel itself, at the mouth of the same. This
avoid the train having to exit the tunnel and cover great distances when it has to
be reloaded. However, the system still has all the drawbacks described, even being
heightened, given the implemented dimensions. Bringing the loading point of the train
closer is all that has been achieved, but if we consider the lengths of the tunnel,
each time the train has to reload, the stoppage time (movement + loading + return)
amounts to many hours, time during which the concreting remains interrupted.
[0013] In the patent literature, we can see document
EP 0715023 in which a mobile concrete mixing machine is described for concreting housing mechanisms
for railway tracks with the aid of shuttering during the course of the construction
of a superstructure system without ballast with a concrete roadway slab for at least
one railway track. This machine has a portal frame with lateral uprights extending
in the direction of manufacture and crossbars which connect them above, being mounted
on moving assemblies, preferably on caterpillars such that the frame of the machine
is moved in the direction of manufacture and eventually in the return direction. On
the longitudinal frame, there are sliding rails for a gantry crane and on these a
gantry crane is guided. A plurality or number of concreting frames is housed on the
frame which can be moved in the direction of manufacture and have mechanisms for vertical
adjustment.
Description of the invention
[0014] In conclusion, the slab track concreting system existing at present have substantial
disadvantages and it is necessary to develop alternative methods which allow the process
to be optimized. Therefore, the slab track concreting process requires an alternative
which improves the existing methods and avoids the disadvantages thereof.
[0015] The new method should optimize the supply and provision of concrete by minimizing
the risk of stoppages and waiting times, it should allow the maximum utilization of
the space and avoid interferences between the different tasks, it should be flexible
for different situations, dimensionable and scalable for works of different length
and sizes and should provide high yields; the development of new specific equipment
to be able to carry out this new method and optimally applying the concrete is also
necessary, with a limited cost and without the risk of blockages. It would also be
desirable to achieve maximum automation of the process. This method and the equipment
necessary for carrying it out are the object of the present invention.
[0016] The method for concreting object of the present invention presents the utilization
of the space on the track under construction itself for supplying and applying the
concrete. To this end, the equipment responsible for transporting and applying the
concrete travels in a self-propelled manner and by means of railway wheels on two
rails or guide profiles, auxiliary rails, situated one at each side of the track under
construction and parallel thereto, transporting the concrete, transferring it, in
case it is necessary, and ultimately applying it at the desired point (all of which
following different possible strategies/configurations). This concept therefore allows,
since the concreting equipment is not supported on the rails of the track itself,
travel to take place on the track under construction during any phase of said construction,
even when the premounted track is suspended pending concreting, thereby providing
the space on the same which is not available in other methods, thus minimizing the
problem associated with the lack of space and the interference with other works.
[0017] Lastly, the concreting of the slab track is carried out by pouring concrete from
the vertical itself of the track under construction, on the assembly formed by the
rails fixed to the sleepers and/or fixing systems, which is commonly known as skeleton
track, which have been previously laid and premounted on the existing base which forms
the base plate of the future slab track, the assembly being positioned with precision
and being fixed by means of support means in a suspended position. Once the concrete
has set, it constitutes the slab which forms the support means which replaces the
ballast of a traditional track.
[0018] The conceived process comprises the following phases:
- the phase which must firstly be executed is a phase prior to the concreting process
itself and consists of placing two parallel rails or guide profiles, situated at the
exterior of the track under construction, and the future slab to be concreted, at
both sides of said slab and parallel to the same, which are supported and fixed in
a stable manner on the platforms, semi-platforms or in the space present at both sides.
These rails or profiles, which we can call auxiliary rails, are to allow for the movement
of at least one self-propelled autonomous device or self-propelled autonomous hopper
capable of loading concrete and/or moving it and/or pouring it in a controlled manner
on the track under construction, according to the different possible configurations
which are described below.
- the following phase, first phase of the concreting process per se, consists of receiving
the concrete at the supply point and then transporting the same on the auxiliary rails,
fixed at both sides of the track to be concreted, to the pouring area. The transport
of the concrete is carried out by means of devices especially designed for this purpose
and which are also object of the present invention, although hoppers can also be used
or any other type of device suitably adapted for being able to travel on the auxiliary
rails transporting and pouring concrete. The devices or hoppers thus move by rolling
on the two auxiliary rails previously fixed to both sides of the track in a self-propelled
manner.
[0019] In terms of the location thereof, the concrete supply point to the system can be
established at any area of the tunnel or even at the exterior of the same, that is
to say, it will be located at a point on the auxiliary rails of the track under construction
or adjacent thereto, to which it is possible to introduce the concrete from the exterior.
It will therefore be located either at the mouth of the tunnel (or even outside the
same, extending the auxiliary rails outside the tunnel) or in the interior of the
same. In this last case, the supply point will be an internal point to which it is
possible to introduce the concrete from the exterior using traditional methods: either
the point to which the concrete mixer trucks can access, the point to which a train
with mixers or platforms which transport concrete can access, travelling along the
adjacent track in the case of it being a tunnel with 2 or more tracks, along the track
itself to a concreting point with sufficient time in advance such that it has already
acquired the sufficient consistency for it to be passable or along an auxiliary track
at a side of the track under construction either a point in an area with ventilation
shafts, in an area with gaps or gangways connected with the parallel tunnel for example
in a tunnel with 2 tubes, 1 track per tube or in any other types of openings by way
of which it is possible to introduce the concrete by traditional methods, etc.
[0020] The location of the supply point can always be the same or it can vary as a function
of the advance of the concreting, of the needs in this aspect and of the possibilities
in terms of possible concrete supply points available.
[0021] In terms of the device or hopper for receiving the concrete, it could directly be
the device or hopper responsible for carrying out the transport of the concrete, or
it could be a receiving device or hopper per se which in this case would have the
function of "regulating tank of the concrete", that is to say, storing the discontinuous
supply coming from the exterior and carrying out the transfer to the transport device
or hopper when it is required. In this last case, the "receiving" hopper could move
on the auxiliary parallel rails or on the principal track if the concrete which forms
the slab is already conveniently set in this area, it can also remain static on the
auxiliary rails, on the rails of the track or even at a lateral point adjacent to
both.
[0022] In the case that the transport device is not responsible for receiving/regulating,
it will be necessary to carry out the transfer of concrete from the latter to the
former, for which the receiving device itself will be provided with means for transferring
the content thereof to the transport device or hopper, such as a conveyor belt, direct
discharge, etc. In the case of the transport device being responsible for also carrying
out the receiving, it will not be necessary to transfer the concrete to it.
[0023] Both the receiving and transport devices could be a single device or various devices
as a function of the different configurations which are set up.
- The following phase consists of the pouring of the concrete on the track under construction
in a controlled manner, distributing it uniformly along the same to form the concrete
slab, this operation being carried out by means of at least one device or hopper which
moves in an autonomous and controlled manner on the auxiliary rails.
[0024] The transport and pouring of the concrete could be carried out by means of the same
device or hopper, in which case this could have at least two advance speeds, one fast
in order to carry out the transport and return journeys and another slower speed which
will be used when it pours the concrete on the track under construction. It is also
possible to carry out the pouring of concrete by means of a specific device or hopper
for this, in which case the transport of the concrete from the supply point to said
concreting device or hopper is carried out by means of a specific device or hopper
for transporting which we could called a satellite device or hopper which is provided
with means for transferring the content thereto to the concreting device or hopper.
Any of these devices or hoppers moves by rolling on auxiliary rails.
[0025] In this way, in one of the possible configurations, the same device can be responsible
for carrying out the receiving of the concrete at the supply point, the transport
to the pouring point and the pouring itself of the concrete. In this case, it is not
necessary to carry out any transfer of concrete between devices, and the single device
will be equipped with at least two speeds (fast for transporting and returning and
slow for the concreting). In this configuration, being considered a supply point,
only one device can be used (concreting at a "front" of the track under construction)
or two devices can be used (concreting at two front, at both sides of the supply point)
or even more.
[0026] In this last configuration of the process (two concreting devices or hoppers being
used simultaneously), with the supply point situated at an internal area of the tunnel),
the two devices will be responsible for concrete at the supply point and will each
transfer it to each side of the same. Once the respective initially fixed pouring
points have been reached, they carry out the return concreting, that is to say, at
both sides from the initial points to the supply point, that is to say, in opposite
directions. Both devices will return to the supply point once the concrete has been
depleted in order to be reloaded, transporting the concrete once again to the pouring
point and once again proceeding to pour the concrete, thereby advancing both concreting
fronts until completing the concreting of this section (contained between the two
initial points fixed at both sides of the supply point and preferably, although not
exclusively, equidistant from the same). The use of two devices means the productivity
of this operation is doubled. The loading of concrete at the supply point of the two
devices in this last case could be carried out in an alternative manner, for which
purpose they can be offset in time. Alternative configurations based on this described
configuration can be used with slight variants: such as the two devices concreting,
approaching the supply point, the two in the same direction or even carrying it out
at the same side of the supply point.
[0027] Once the concrete has been poured, the traditional vibrating operations are carried
out, floating and the rest of the work required for the correct finishing of the slab.
These operations can be carried out according to traditional methods, using conventional
means operated by operators; however, the present invention provides for self-propelled
platforms which move on the two auxiliary rails following the pouring devices or hoppers,
behind them in the direction of advance of the concreting. These platforms will have
the means required for carrying out these operations as well as the required operators,
who can carry out the operations manually from the self-propelled platform with conventional
means, or in the following manner: the vibrating means could be provided vertically
on supports movable on the self-propelled platform and carry out the vibrating with
greater automation; in order to carry out the floating in a more automated manner,
the possibility of incorporating a tray movable on the platform is also provided for.
[0028] In this way, the vibrating operation of the concrete is carried out after the pouring
either in a conventional manner or in a more automated manner. However, this method
also allows the vibrating and floating means of the concrete to be mounted directly
on the pouring devices or hoppers, actuated and supported from the hopper itself.
It is also possible to even couple the self-propelled platform to the pouring hopper
so that it pulls it. These two last possibilities can be used especially when hoppers
intended exclusively for pouring the concrete are used.
[0029] The system required for the concreting of railway slab track using the method previously
described comprises a series of essential devices
- Firstly two parallel rails or guide profiles situated at the exterior of the track
under construction and, therefore the slab to be concreted, at both sides thereof
and parallel to the same which are supported and fixed in a stable manner on the platforms,
semi-platforms or in the space present at both sides. These rails will serve as a
roller track for the movement of a series of apparatuses or hoppers which will be
detailed below.
- At least one device or hopper is required for transporting and pouring the concrete,
which carries out the transport from a concrete collection or supply area - supply
point - to the pouring area on the track under construction, rolling in an autonomous
and controlled manner on the previously fixed auxiliary rails, and it will be provided
with concrete pouring means, capable of carrying out the pouring in a controlled manner
along the track under construction to form the concrete slab.
- In the case it is considered preferable for the transport and pouring to be carried
out by means of independent devices, instead of the previously described device, at
least two devices or hoppers will be required: at least one transport device or hopper,
which will carry out the transport from a concrete collection or supply area - supply
point - to the pouring device, rolling in an autonomous and controlled manner on previously
fixed auxiliary rails; and at least once pouring device or hopper which will be provided
with concrete pouring means, capable of carrying out the pouring in a controlled manner
along the track under construction to form the concrete slab.
[0030] As has been previously described, it is envisaged that the transport devices or hoppers
can be either the pouring devices or hoppers themselves with the capacity to move
at a higher speed when they carry out this operation or specific devices or hoppers
for the transport - satellite hoppers - in which case they must be provided with means
for transferring concrete to the pouring hoppers. This gives rise to different possible
configurations of the process and the selection of one option or another will depend
on the external conditions present in each case or work and on the study of timings
which is carried out, with the aim of achieving the maximum yield of concreting, various
factors should be considered such as for example the distance to which the concrete
supply point is from the pouring point (for example in a construction in which both
points can always be relatively close, the option of using only pouring devices or
hoppers for both operations could be considered; in other conditions, it may be preferable
to use specific transport devices or hoppers - satellite hoppers - for transporting
the concrete to the pouring device or hopper, thereby enabling the pouring process
to also be continuous). The satellite hoppers will be equipped with outlet means for
the content to transfer the concrete to the pouring device or hopper in an automatic
and fast manner.
[0031] All the devices or hoppers are preferably metallic and automotive structures. They
are formed by: a peripheral structure with a regulatable width, formed by metallic
profiles which are laterally supported by means of at least two wheels at each side
on the corresponding auxiliary rail (that is to say, at least four wheels in total),
it being responsible for carrying out the rolling of the device on the auxiliary rails
and supporting the central structure; a central structure or hopper per se responsible
for containing the concrete, supported on the peripheral structure, the internal width
thereof is approximately equivalent or similar at the lower portion thereof to that
of the slab which is going to be concreted and which incorporates means for suitably
carrying out the operations with the concrete, either the loading, pouring or transfer
thereof.
[0032] Provision is also made for the wheels to be mounted on two vertical support structures,
or profiles, regulatable in height (either with the possibility of being supplemented
or telescopic) such that the device or hopper can remain in a horizontal position
or parallel to the plane of the track and in a stable position independent of the
heights at which the two auxiliary rails are arranged.
[0033] In the interior of the central structure or hopper per se there are, at the bottom,
a motorized endless screw, the revolutions of which are facilitated and regulated
by the outlet flow, directing it and therefore controlling the concreting, in line
with the opening of lower opening gates and with the advance speed of the device during
the pouring. Provision is made for there to be one single or various pouring mouths
arranged at the bottom, in this last case these mouths can be separated by blind areas
matching the position of the rails and fastenings of the track under construction.
These pouring mouths are controlled by gates, the opening of which is controlled by
means of hydraulic actuations.
Description of the figures
[0034] In order to complement the description being given and with the aim of facilitating
the understanding of the characteristics of the invention, a set of drawings accompany
the present description in which, in an illustrative and non-limiting manner, the
following has been depicted:
Figure 1 depicts a section of a tunnel in which the premounted track fixed in suspension,
in the final position thereof, (2) is being concreted to form the slab (3) of the
slab track.
Figure 2 shows, in two views, in plan and lateral elevation, a slab track under construction
in which a concrete pouring device or hopper (6) is working (which, as has been described,
can be exclusively for pouring concrete or transporting + pouring concrete).
Figure 3 shows, in two views, in plan and lateral elevation, a track under construction
in which two concrete pouring devices or hoppers (6) (or for transporting + pouring
concrete) are working.
Figure 4 shows, in two views, in plan and lateral elevation, a track under construction
in which a concrete pouring device or hopper (6), a concrete transporting satellite
device or hopper (7) and a regulating device or hopper (8) are working which in this
case constitutes the receiving point of the concrete coming from the external supply,
that is to say, which constitutes the concrete supply point and accumulates it in
order to regulate the inlet flows.
Figures 5 and 6 respectively depict a sectional transversal and longitudinal view
of a concrete pouring device or hopper (6) (or concrete transporting + pouring device).
Preferred embodiment of the invention
[0035] In the figures, the basis of the method of the present invention for concreting the
slab (3) of a slab track can be observed, said concreting is carried out on the previously
mounted track, suspended and fixed in the final position (2), in a tunnel area (1),
in which this type of track (2-3) is usually constructed in this manner, without a
ballast. The concreting method envisages the placement of two rails (5) or guide profiles
which we can call auxiliary rails, supported on the platforms, semi-platforms or lateral
spaces (4) at one side and the other side of the track and the transfer and pouring
of the concrete by means of devices or hoppers (6) which move along said rails in
an autonomous manner and at a controlled speed.
[0036] The pouring operation is carried out by means of types of devices or hoppers (6)
which are internally equipped at the bottom with a mechanism for controlling this
operation; while the transport operations of the concrete from the supply point (PS)
to the pouring point can be carried out by means of the pouring device or hopper (6)
itself, in which case it is desirable for it to have at least two speeds for being
able to carry out the transport at a greater speed than the pouring or by means of
a specific device or hopper, which we can call a satellite device (7) which moves
from the supply point (PS) to the pouring device or hopper (6), in which it deposits
its load, for the purposes of which these types of devices or hoppers (7) are equipped
with a lower pouring mechanism and a conveyor belt (72) to transfer the content thereof
from the lower portion thereof to the upper mouth of the pouring device or hopper
(6), or alternatively any other means for carrying out this transfer. This satellite
device (7) can be one single device or it could even be various devices functioning
in a chain.
[0037] The controlled concrete-pouring operation is observed in Figure 2. The device or
hopper (6) moves by rolling in an autonomous and controlled manner supported on the
auxiliary rails (5) on at least four roller means (61) situated at both sides on the
front and rear part of the peripheral structure of the device.
[0038] In Figure 3, a configuration is observed which allows the concreting operation of
the slab (3) to be doubled. Two devices or hoppers (6) are used in this case, each
one of which carries out successive transport and pouring operations of the concrete
- from which they are loaded at a supply point (PS) situated at an intermediate point
between the pouring area of each one of these. This configuration and operation is
possible when there are possible concrete supply points in the interior of the tunnel
(for example by way of ventilation shafts, by way of the communication spaces with
the parallel tunnel, for example in tunnels with 2 tubes, 1 track per tube, etc.);
in these cases, the filling of both devices, hoppers (6) is carried out at the intermediate
supply point, which once loaded transport the concrete to the respective concreting
points thereof, proceeding to carry out the pouring in the advance direction towards
the supply point. Once the concreting of the section contained between the 2 initial
points has been completed, the new supply point is taken as the next intermediate
point available for this purpose, the same process focused on the same is initiated
once again. In order for the method according to this configuration to be effective,
it is necessary to have intermediate supply points (PS), each a certain distance inside
the tunnel along the length which is going to be concreted such that the transport
distance of both devices or hoppers is not excessive.
[0039] This described configuration (Figure 3) can be carried out with different variants:
both devices can carry out the concreting in the direction opposed to the supply point
(moving away from it) instead of towards it, or for example both devices can work
at the same side of the supply point instead of at both sides of it, either concreting
towards the supply point or moving away from it, or any combination which is desired
in these aspects.
[0040] In Figure 4, a form of operation is observed which, in this case, uses satellite
devices or hoppers (7) which carry out the transport of the concrete from the supply
point to the pouring device or hopper (6). In this case, work is carried out in only
one direction and with one pouring device or hopper. The concrete supply point in
this case would be set up, situated on a regulating device or hopper (8) which moves
on the auxiliary rails (5). The concrete supply would arrive to here from the exterior,
either on a train with concrete or with mixers (or tanks on towed platforms) along
the track itself under construction to the concreting point with sufficient time in
advance such that it has conveniently hardened and is passable, or along the adjacent
track in the case of there being 2 tracks, or along an auxiliary track, or by means
of mixing trucks in the case of there being space for this, or by means of pumping,
or by any other possible means. This regulating device (8) which would therefore establish
the supply point, would be responsible for accumulating the concrete coming from the
exterior and providing it to the satellite device (7), acting as an accumulator or
regulator of the exterior flow of concrete in the case of it being discontinuous,
or for maintaining the supply to the satellite device in the case of the external
supply being interrupted for any reason. This regulating device (8) would move on
the auxiliary rails to more advanced points, as required.
[0041] However, alternatively, this regulating device or hopper (8) could also move on the
principal track (2) instead of on the auxiliary rails; in this case it could only
do this on section concreted with sufficient time in advance and conveniently hardened,
and therefore passable without therefore being able to surpass a certain point. Other
alternatives would also be possible, for example setting up a regulating hopper on
the adjacent track in the case that one exists, or directly at the side of the track
without the possibility to move on rails (outside of the track and the auxiliary rails),
etc.
[0042] Another alternative within this configuration consists of dispensing with the regulating
device (8). In this case, the loading of the satellite device (7) would be carried
out directly at the supply point, to which the concrete supply would arrive from the
exterior by any of the means described or other possible means.
[0043] Another alternative within this configuration consists of dispensing with the satellite
device (7), therefore the concrete pouring device (6) itself being responsible for
carrying out the transport and pouring operations of the concrete. To this end, this
device would have at least two speeds. In this case, the transport and pouring device
would be loaded with concrete at the supply point (either receiving the concrete from
the regulating device or directly from the external supply) it would transport the
load to the pouring point, preferably at high speed, and once situated at the concreting
point, the pouring of the concrete would be carried out at the required speed.
[0044] The apparatuses that form part of this system are observed in Figures 5 and 6. In
this case, a pouring device or hopper (6) is depicted, which is supported on the auxiliary
rails (5) by means of wheels (61) which support the peripheral structure (62) on which
the central body itself or hopper per se (60) is supported, responsible for containing
the concrete. The peripheral structure (62) is formed by preferably metallic profiles
and is regulatable in width at both sides in relation to the degree of approximation
to the supports on both auxiliary rails (5) such that the central body or hopper per
se (60) is always situated on the vertical of the slab track (3) to be concreted.
[0045] In Figure 6, it is observed that at each side, this hopper is supported on at least
one pair of wheels (61) which are supported by a cylinder (66) or other telescopic
means or with the possibility of being supplemented which allows the height of each
wheel to be varied with the aim that, independently of the height of the two auxiliary
rails (5) and of these being at the same height or not, the hopper (60) is situated
transversally in a noticeably level position and it can function in a horizontal position
or parallel to the plane of the track and therefore in a position that is always stable.
A second pair of wheels (64), with a greater size than the previous wheels (61), is
observed in this figure, also supported on a telescope means (65) or with the possibility
of being supplemented. In the figure, the wheels (61) are in an operative position,
therefore being situated below the wheels (64); it is like this when the device is
carrying out the pouring function and a slower and more controllable speed is required.
The wheels (64) are placed in an operative position, that is to say, below the wheels
(61), when the device carries out the transport function. This duality can be avoided
by regulating the rotational speed transmitted to the wheels, by incorporating, to
this end, a change of speeds in the motor which moves the hopper (6), an electronic
regulation if it is an electric motor or any other system, with which only one pair
of wheels would be necessary at each side.
[0046] On the lower portion of the hopper (60), means are observed for facilitating the
pouring of the concrete constituted by a motorized endless screw (68), with the revolutions
of which the pouring of the concrete is facilitated, also orientating the outlet thereof
in the desired direction, thereby regulating the concreting in line with the advance
speed of the device or hopper during the pouring, the quantity of concrete distributed
on the track (2) under construction for forming the slab (3) of the same thus being
controlled. The outlet mouth is closed by gates (69) which are actuated by means of
hydraulic cylinders (67) which allow the discharge mouth to open and close, either
completely or by sectors. In one preferred embodiment, there are three pouring mouths
along the width of the hopper (60) separated by blind areas (63) which match the approximate
position of the rails and the heads of the sleepers of the track under construction
(2) with the aim of avoiding the pouring of concrete on these. The three mouths can
be opened simultaneously, or independently in order to orientate the concreting to
an area of the section as desired.
[0047] The central body or hopper (60) per se is formed by profiles or metallic plates.
The interior walls of the hopper can be covered with sheets or antiadhesive material
for preventing the concrete adhering to them and thus facilitating the pouring. This
device can be disassembled, by separating the central body (60) from the peripheral
structure (62).
[0048] The satellite device or hopper (7) used specifically for the transport of concrete
and the regulating device or hopper (8) have a structure equivalent to the pouring
device or hopper (6) depicted. They have two sets of wheels (71) and (81) respectively
and in this case the pouring means deposit the content thereof on conveyor belts (72,
82) by way of which it is possible to transfer the concrete from the hopper (8) to
the hopper (7) and from this hopper to the pouring hopper (6) as can be observed in
Figure 4. In these cases, the opening gates of the lower outlet mouths are configured
to match the conveyor belt(s) or the transfer apparatus used.
[0049] The pouring device (6) can also incorporate the vibrating means (9), on the rear
part thereof, in the advance direction, which would be actuated for carrying out the
vibrating of the concrete once it has been poured. The means for carrying out the
floating could also be incorporated in the same place.
[0050] The present invention also provides for self-propelled platforms which move on the
two auxiliary rails after the pouring devices or hoppers, behind them in the advance
direction of the concreting. These platforms have the means required for carrying
out these operations as well as the required operators who can carry out the operations
from the self-propelled platform manually with conventional means or in the following
manner: the vibrating means can be arranged vertically on supports movable on the
self-propelled platform and carry out the vibrating with a greater degree of automation;
in order to carry out the floating in a more automated manner, the possibility of
incorporating a tray movable on the platform is also provided for.
[0051] In this way, the vibrating operation is carried out after the pouring either in a
conventional manner, or in a more automated manner. It is also even possible to couple
the self-propelled platform to the pouring hopper so that both advance inseparably.
[0052] All the devices envisaged in the present invention are preferably automotive devices.
[0053] With the nature of the invention sufficiently described as well as a preferred exemplary
embodiment, it is stated for the appropriate purposes that the materials, form, size
and arrangement of the elements described could be modified, provided this does not
involve an alteration of the essential characteristics of the invention which is claimed
below.
1. A method for concreting railway slab track, proceeding from an initial position in
which the track is previously mounted, suspended and fixed in the final position and
pending concreting on the existing base on which it has been settled so that once
the concrete has set, it constitutes the slab of the slab track,
characterized in that it comprises the following phases:
- placing two auxiliary parallel rails (5) one at each side and at the exterior of
the track (2) under construction and the slab (3) once it has been concreted, supported
on platforms, semi-platforms or adjacent lateral spaces (4), on which one or various
autonomous devices or hoppers (6) move which are capable of loading concrete, transporting
it and pouring it in a controlled manner on the track to be concreted, all these operations
therefore being carried out in the space present on the track itself under construction;
- transporting the concrete from a concrete supply point (PS) to the pouring area
on the track under construction (2) in devices or hoppers which move by rolling on
said auxiliary rails (5);
- pouring the concrete on the track under construction (2) in a controlled manner,
distributing it uniformly along the same to form the concrete slab (3), by means of
at least one device or hopper (6) which moves in an autonomous and controlled manner
on the auxiliary rails (5).
2. The method according to claim 1, characterized in that receiving, transporting, distributing and pouring the concrete is carried out with
at least one device (6) which moves by rolling on the auxiliary rails (5), loading
concrete at the supply point (PS) when it is emptied and returning loaded to the pouring
point, where this concrete-pouring operation is carried out in a controlled manner,
while it advances at a controlled speed.
3. The method according to claim 1, characterized in that pouring the concrete is carried out by a device (6), while transporting the concrete
from the supply point (PS) to this pouring device (6) is carried out by means of at
least one additional satellite device (7) provided with means for emptying and transferring
the content thereof to the pouring device (6) or to another satellite device (7),
all of these moving by rolling on the auxiliary rails (5).
4. The method according to any one of the preceding claims, wherein the concrete supply
point is situated at a point to which it is possible to introduce a train or other
transport means loaded with concrete, characterized in that between the supply point and the concrete pouring area a regulating device (8) is
situated which moves on the auxiliary rails (5) or on the principal track (2) once
the concrete, which forms the slab of the same, has conveniently hardened.
5. The method according to any of claims 1 to 3, characterized in that the concrete supply point (PS) is situated in the interior of the tunnel at a point
to which it is possible to introduce the concrete from the exterior by way of ventilation
shafts, connection galleries with a parallel tunnel, by way of an auxiliary track
or by any available space.
6. The method according to claim 5, characterized in that the concrete supply point (PS) varies as a function of the advance of the concreting,
of the needs in this aspect and of the possibilities in terms of possible concrete
supply points available along the total length of the track to be concreted.
7. The method according to claim 5, characterized in that pouring the concrete is carried out by means of two devices (6) which work from a
concrete supply point (PS) at both sides of the same.
8. The method according to any of claims 1 to 7, characterized in that vibrating and/or floating the concrete is carried out by means of apparatuses (9)
supported on the pouring device (6) and actuated from the same.
9. The method according to any of claims 1 to 7, characterized in that vibrating and/or floating the concrete is carried out by using an auxiliary platform
which moves on the auxiliary rails (5).
10. The method according to claim 9, characterized in that the platform from which it is suitable to carry out the vibrating and floating of
the concrete moves coupled to the pouring device (6) at the rear part thereof.
11. The method according to claim 9, characterized in that the platform from which it is suitable to carry out the vibrating and floating of
the concrete moves in an autonomous manner behind the pouring device.
12. A system for concreting railway slab track which, proceeding from an initial position
in which the track is previously mounted, suspended and fixed in the final position
and pending concreting on the existing base on which it has been settled so that once
the concrete has set, it constitutes the slab of the slab track,
characterized in that it comprises:
- two auxiliary parallel rails (5), one fixed at each side and at the exterior of
the track (2) under construction and of the slab (3) once it has been concreted, supported
on the platforms, semi-platforms (4) or in adjacent lateral spaces, on which at least
one autonomous device or hopper (6) moves which is capable of loading and/or transporting
and/or pouring the concrete in a controlled manner on the track under construction;
- at least one concrete pouring device (6) provided with motorization and autonomous
roller (61, 64) and movement means on the auxiliary rails (5) and concrete pouring
means capable of carrying out pouring in a controlled manner and distributed uniformly
along and on the track under construction (2) forming the concrete slab (3);
- at least one device for transporting concrete from a collection area or concrete
supply point (PS) to the pouring area on the track under construction (2), provided
with motorization and autonomous roller and movement means on the auxiliary rails
(5), which is or is not the same as the pouring device (6).
13. The system according to claim 12, characterized in that any of the pouring and/or transport devices have a peripheral structure (62) with
a regulatable width formed by preferably metallic profiles which are laterally supported
by means of at least two wheels (61) at each side on the corresponding auxiliary rail
(5), on which the central body or hopper per se (60) is supported which has an interior
width in the lower portion thereof similar to that of the slab (3) which is going
to be concreted.
14. The system according to claims 12 and 13, characterized in that the pouring device (6) has, as pouring means, a motorized endless screw (68), which
facilitates the pouring of the concrete and the direction thereof, with the revolutions
of which, in conjunction with the opening of lower gates (69) and the movement speed
of the device (6) during the pouring, the quantity of concreted distributed on the
track (2) under construction to form the slab (3) is controlled.
15. The system according to claims 12 to 14, characterized in that the pouring device (6) has, at the bottom, three pouring mouths separated by blind
areas (63) matching the position of the rails of the track under construction (2)
and gates (69) which open or close each one of the pouring mouths, the opening of
which is controlled in a combined or independent manner.
16. The system according to claims 12 to 15, characterized in that the roller means (61, 71, 81, 64) of the devices are mounted on a telescopic support
(65, 66) regulatable in height such that, depending on the levelling, or otherwise,
of the auxiliary rails (5) and on the height of each one of these, the device is leveled,
being situated in the horizontal position or parallel to the plane of the track.
17. The system according to claims 12 to 16, characterized in that the transport devices are either the pouring devices (6) themselves which move at
a higher speed than when they carry out this operation, or are satellite devices (7)
provided with means for automatically emptying and transferring (72) the concrete
to the pouring devices (6) or even to other satellite devices (7).
18. The system according to claim 17, characterized in that the means (72) for transferring concrete from the lower portion of the satellite
device (7) to the upper portion of the pouring device (6) is formed by at least one
conveyor belt.
19. The system according to claim 12, characterized in that it optionally comprises a regulating device or hopper (8) which establishes the concrete
supply point, which has means for movement on the auxiliary rails (5), or on the already
concreted track once the concrete has sufficiently hardened, acting as an accumulator
or regulator of the concrete flow coming from the exterior in the case of it being
discontinuous, or maintaining the supply to the transport device in the case of the
external supply being interrupted for any reason.