Field of the invention
[0001] The present invention relates to a temperature-controlled method of casting.
Background of the Invention
[0002] There are many different types of casting known in the art. However, a common aspect
of many casting processes is the need to achieve certain temperature thresholds within
the mould. These temperatures need to be achieved accurately, as the material properties
of the cast substance are highly sensitive to even slight variations in casting temperature
and duration. These considerations are vitally important for creating particular material
properties in single material casts, and for optimizing the physical and chemical
bonding of dissimilar materials in alloys.
[0003] Presently, to achieve the desired mould temperatures, it is known in the art to heat
moulds by a number of different methods, including by introducing hot gas, water or
oil into the mould before casting, by infra-red heating, by electrical probes inserted
into the mould, and by placing the mould in a dedicated preheating oven from which
it is removed before casting. Further, it is also common in the art to use any of
the above preheating methods to crudely reach an approximate temperature domain, and
to then begin the casting process accepting that at least the first few castings will
produce poor quality scrap due to suboptimal mould temperature and/or uneven mould
temperature distribution. In this way, the scrap castings are used to further heat
the mould to reach the desired mould temperature.
[0004] However, these known heating methods suffer from a number of disadvantages, including
increased material cost due to scrap wastage, inaccurate temperature heating, and
uneven temperature distribution within the mould. Further, these methods are generally
not suitable for heating the system at any stage other than at the preheating stage,
before casting has begun.
[0005] Hence, it would be beneficial in the field if both the temperature of the mould,
and the materials within it, could be accurately and efficiently heated at multiple
stages of the casting process, and without wasting precious materials.
[0006] Further, manufacturers are ever more concerned with the impact that their processes
may be having on the environment around them. However, it is crucial that such concerns
can be addressed within the context of profitable business. As such, innovations that
can simultaneously decrease the adverse effects on the environment, whilst also increasing
efficiency, represent vital contributions to the field.
Statement of the Invention
[0007] According to an aspect of the invention, a method of casting is provided wherein
a molten material to be cast is flowed into, through and out of a mould. This flow
of molten material serves to heat the mould. Subsequently, once the mould temperature
reaches a desired temperature, the flow of the molten material out of the mould is
stopped, but the molten material continues to flow into the mould, such that the molten
material begins to at least partially fill the mould. This method allows the mould
to be heated using the same flow of molten material that is to be used to fill the
cast and subsequently be casted into the desired object. The molten material that
flows out of the mould may be collected in a container, such as a crucible.
[0008] The temperature of the mould may be measured to accurately determine when the desired
mould temperature is reached. The temperature of the mould may be measured close to
or at the interior surface of the interior cavity of the mould. Further, the temperature
may be measured by thermocouples or thermostats.
[0009] Alternatively, the temperature of the mould can be determined by determining that
a predetermined mass and/or volume of the molten material has passed through the mould,
that is sufficient to achieve the desired temperature of the mould. The predetermined
mass and/or volume of the molten material may be collected in a container, and the
container may include a means of measuring that the predetermined mass and/or volume
of molten material has been collected within it. Alternatively, the container may
be a sump with a fixed volume, designed to be equal to the predetermined volume of
molten material that is sufficient for the desired temperature of the mould to be
achieved. In this instance, the mould may automatically be filled by the flow of molten
material entering the mould due to the backlog of molten material prevented from entering
the filled sump.
[0010] The flow of the molten material through the system may be controlled using an outlet
valve located downstream of the mould, between the exit of the mould and any container.
There may also be an inlet valve upstream of the mould, located before the entrance
to the mould to further control the flow of molten material through the system when
used in combination with the outlet valve. The valves may be used to create different
flow rates of the molten material at the entrance and exit of the mould.
[0011] The mould may be empty before the molten material enters the mould. Alternatively,
the mould may already contain a material that has either previously been cast, or
that is prepared within the mould and is ready to be cast with the molten material
about to be introduced into the mould.
[0012] The mould may further include a retainer for retaining a material within the mould
during the introduction of the molten material and the final casting process.
[0013] The molten material that flows out of the mould, which may or may not be collected
in a container, may be reheated and subsequently reintroduced to the system such that
it may once again flow into the mould.
[0014] The methods described above may be used in the context of a sand casting, a gravity
casting, or a pressure die casting process, or a combination of these. Further, the
measurement, control, and operation of any of the above components may be implemented
by a computer system that is connected to these components and the casting system
as a whole.
Brief Description of the Drawings
[0015] There now follows, by way of example only, a detailed description of preferred embodiments
of the present invention, with reference to the figures identified below.
- Figure 1
- is a schematic representation of the casting in a first embodiment.
- Figure 2
- illustrates a further embodiment of the process of Figure 1.
- Figure 3
- illustrates another embodiment of the process of Figure 1.
- Figure 4
- is a flow diagram illustrating the main process steps of Figure 1.
- Figure 5
- illustrates a further embodiment of the process of Figure 1.
Detailed Description of the Embodiments
[0016] In the following description, functionally similar parts carry the same reference
numerals between figures. Preferred embodiments of the invention are now described,
by way of example only, with reference to the accompanying drawings.
[0017] Figure 1 illustrates a schematic representation of the heating process in operation. The system
has a first crucible 1 that is suitable for containing any molten material, herein
referred to as a base material, that is to be cast in the casting process. The base
material exits the crucible 1 and is transported via a suitable connection means or
conduit to a runner system 3. The runner system 3 allows the base material to enter
the mould 5. The general configuration of the mould 5 will be known to the skilled
person, and the mould 5 may be any mould suitable for casting base materials. For
instance, the mould 5 may be for use in sand casting or gravity casting, but it is
not limited thereto. The mould 5 has an internal cavity 13 which is filled by the
base material in the casting process. The interior wall of this cavity 13 is called
the interface surface 15. In other words, the interface surface 15 is where the material
of the mould 5 contacts with the base material when the base material is in the mould
5. Further, the mould 5 has temperature measurement devices 11, such as thermocouples
or variable thermostats, located either at or close to the interface surface 15, such
that measurement of the temperature of the interface surface 15 may be achieved at
any point in the casting process. The temperature measurement devices 11 may be electrically
connected to a computer control system, and may be operated by suitable electrical
control circuitry.
[0018] The mould 5 also has an entrance 6 and an exit 8 that allows the base material to
flow from the runner system 3, through the mould 5, and out of the mould 5. The exit
8 to the mould 5 is attached to a suitable connection means or conduit that allows
the base material to continue to travel away from the mould 5. The flow of the base
material along this exit connection means is controlled by an outlet valve arrangement
7. The outlet valve arrangement 7 is operable to vary the flow of the base material,
and is able to provide a continuous or at least variable range of flow rates between
its fully closed and fully open states. The outlet valve 7 may be electrically connected
to the computer control system, and may be operated by suitable electrical control
circuitry. When the outlet valve 7 is in an open state, the base material flows away
from the mould 5 through the outlet valve arrangement 7 and into a second crucible
9 able to contain the base material. Hence, through the above arrangement, the base
material in the first crucible 1 is able to flow through the system in a controlled
manner, based on the state of operation of the outlet valve 7.
[0019] In operation, the temperature measurement devices 11 detect the temperature of the
interface surface 15. This information may be transmitted to a user by a display,
or to the computer control system described earlier. If the temperature of the interface
surface 15 as measured by the temperature measurement devices 11 is lower than a desired
temperature, any one of the heating processes described below may be implemented.
The desired temperature is a variable predetermined quantity, and is dependent on
the base materials being used and the desired material properties of the final cast
substance.
[0020] In each of the below described heating processes, the heating is advantageously achieved
using the base material itself, and harnessing the heat energy that has already been
used to liquefy the base material. The numerous advantages of this will be described
below.
[0021] In an embodiment, the mould 5 may be initially empty, and a preheating operation
is required. In this instance, preheating is begun by allowing the base material to
flow through the system from the first crucible 1, through the runner system 3, and
into the mould 5. As the base material enters the mould 5, it flows over the interface
surface 15 and transfers heat energy to the interface surface 15 in so doing. The
temperature of the interface surface 15 within the mould is continuously measured
by the temperature measurement devices 11, and this information is transmitted to
the user via a display or to the computer system as described above. During this preheating
operation, the outlet valve 7 is in an open state, thereby allowing the base material
to flow through and out of the mould 5 towards the second crucible 9, where it is
collected. Alternatively, the outlet valve 7 is initially in a closed state, or at
least partially closed, so as to allow the mould 5 to fill with the base material,
up to a predetermined level. When the predetermined level of base material within
the mould 5 is reached, the outlet valve 7 is fully opened to allow the base material
to flow through and out of the mould 5 towards the second crucible 9, where it is
collected. This alternating process of opening and closing or partially closing the
outlet valve 7, thereby alternately filling and emptying the mould 5, advantageously
leads to a more uniform distribution of heat within the mould 5.
[0022] The base material is allowed to continue flowing through the system in this manner
until a desired temperature of the interface surface 15 is measured by the temperature
measurement devices 11. At this point the mould 5 is at a suitable temperature for
casting the base material flowing through it, and the outlet valve 7 is switched to
a closed state. The closing of the outlet valve 7, combined with the continued flowing
of the base material from the first crucible 1, causes the mould 5 to begin to fill.
Once the mould 5 contains a desired quantity of the base material, either manually
or automatically determined, the flow of base material from the first crucible 1 is
stopped, and the casting process is begun. The casting process itself may be a conventional
casting process, and is not described further herein. The base material present in
the second crucible 9 is then returned directly to the first crucible 1 for reuse,
or reheated in a conventional manner and subsequently reintroduced to the first crucible
1.
[0023] This process has a number of distinct advantages over the known processes in the
field. In the first instance, by harnessing the heat energy already within the base
material to heat the mould, an efficiency of energy and cost is achieved by avoiding
the need to use any of the separate dedicated heating processes known in the art.
Further, a second distinct advantage over the prior art is the removal of the need
for scrap runs. This beneficially leads to an increase in resource efficiency as wastage
of the base material that is inherent to scrap runs has been removed. Indeed, this
advantage is particularly dramatic in embodiments of the present invention as there
is no wastage of base material at all, as all base material collected in the second
crucible 9 is recovered and reused.
[0024] These advantages further represent a distinct environmental benefit in the efficient
use of energy resources, and in the reduced of wastage of precious base materials.
[0025] Further, in embodiments of the present invention, the heating of the mould 5 by means
of a flow of the base material is distinctly advantageous over other methods of heating,
as the flow of the base material is able to cover all the relevant interface surfaces
15 of the mould 5 that the user is concerned with, thereby leading to an improved
uniform heating of the interface surface 15 and overcoming disadvantageous uneven
heating that results in poor quality casts. Further, the flow of the base material
in particular is distinctly advantageous over the use of other flow based heating
methods such as gas, oil or water, as each of these methods may leave deposits within
the mould 5 and lead to defects and impurities in the cast substance. Further, these
other methods inherently waste the precious natural resources of oil, water and gas
etc.
[0026] The process of heating the mould 5 as described in the embodiment of the present
invention is also particularly advantageous in that it is highly targeted, allowing
specific heating of the interface surface 15 of the mould 5 rather than the mould
5 as a whole, as in many known heating techniques. Indeed, the most important area
in which to accurately achieve certain temperature thresholds is at the interface
between different materials being cast. Hence, the present invention is particularly
advantageous in closed mould casting methods, where heating of the interior of the
mould can be difficult to accurately achieve. In combination with the specific location
of the temperature measurement devices 11 being at or close to the interface surface
15, these features synergistically lead to an increased accuracy in the determination
and control of the temperature of the interface surface 15 of the mould 5 during the
casting process, and thereby result in an increased quality of cast.
[0027] In another embodiment of the invention, the heating of mould 5 as described in the
preferred embodiment may be used or repeated at a later stage in a multi-stage casting
process. In this instance, the mould 5 may have a layer of alloy material already
within it. In such cases, the alloy material already in the mould 5 may be different
from the base material to be added to the mould 5. Hence, there may be a second desired
temperature within the mould 5 that was different to the original first desired temperature.
As the heating of the mould 5 in embodiments of the present invention is achieved
using the base material about to be used in the cast, it is advantageously possible
to heat the mould 5 at any stage of a casting process, not just during the initial
preheating stage as is the case in many conventional heating systems. In such a mid-cast
heating process, the flow of the base material is carried out in the same way as described
in the above embodiments, with the difference that the temperature measurement devices
11 are at this stage measuring the temperature between the interface surface 15 of
the mould 5 and the alloy material already within the mould 5, and as such the measurement
of the interface surface temperature between the alloy material and the base material
may be inferred from the temperature as measured at the interface surface 15 between
the alloy material and the mould 5. The rest of the heating process is carried out
as described in the embodiments above.
[0028] Figure 2 illustrates another embodiment of the invention. In this embodiment, before casting,
the mould 5 may be prepared with an alloy material 17 already within it. In this embodiment,
the temperature measurement devices 11 may be arranged at or close to the interface
surface 19 between the alloy material 17 already within the mould 5 and inner cavity
13 where the base material will be when it enters the mould. In all other respects,
the heating process of this embodiment is carried out as described in the above embodiments.
Advantageously, these embodiments are therefore able to heat either the interface
surface 15 of the mould 5, or the interface surface 19 of the alloy material in the
mould 17, in each instance by using the base material about to be cast.
[0029] Figure 3 illustrates another embodiment of the invention, features of which may be combined
with features of any of the embodiments described above. As well as the above described
systems, there is also provided an inlet valve 21 located between the runner system
3 and the mould 5. This inlet valve 21 is configured to control the flow of the base
material along the connection means before entry to the mould 5. In a similar manner
to the outlet valve arrangement 7, the inlet valve 21 is operable to vary the flow
of the base material in a manner known to the skilled person, and is able to provide
a continuous or at least variable range of flow rates between its fully closed and
fully open states. The inlet valve 21 may be electrically connected to the computer
control system, and may be operated by suitable electrical control circuitry. When
the inlet valve 21 is in an open state, the base material flows into the mould 5.
Advantageously, the combination of the inlet valve 21 and the outlet valve 7 allows
an improved control of the flow rate of the base material through the system. This
is particularly beneficial if an alloy material 17 is already in the mould, as described
above, as it is possible to achieve a flow rate of the base material that does not
cause such turbulence as to disturb the alloy material 17. Further, it is advantageous
in that it allows the mould 5 to be heated in different time periods as a result of
different heat transmission characteristics related to varying flow rates of the base
material over the interface surfaces 15, 19.
[0030] In each of the embodiments described above, the temperature measurement devices 11,
the inlet valve 21 and the outlet valve 7 may be electrically connected to a computer
control system, and may be operated by suitable electrical control circuitry. Advantageously,
this allows improved accuracy in the heating of the system, as the computer system
may be configured to electronically operate the outlet valve 7 and/or inlet valve
21, for instance to automatically close the outlet valve 7 once the desired temperature
is achieved. Further, it allows automation of the system such that human error can
be removed.
[0031] In an alternative embodiment of the invention, for certain heating processes such
as repeat castings, it may be possible to derive a correlation between the mass and/or
volume of collected base material in the second crucible 9, and the temperature at
the interface surface within the mould 5. Hence, it is possible to avoid using the
temperature measurement devices 11, or to remove them entirely, and to rely solely
on the mass and/or volume of base material in the second crucible 9 to determine the
temperature of the interface surface 15, 19. Hence, the time at which to close the
outlet valve 7 and fill the mould 5 for casting could be determined by measurement
of the desired mass and/or volume achieved in the second crucible 9. In a similar
manner to features described above, the mass and/or volume measurements of the second
crucible 9 may be taken by electronic components connected to the computer control
system and the closing of the outlet valve 7 could be automatically achieved. Alternatively,
the measurement of mass and/or volume of the base material in the second crucible
9 could be achieved using a mechanical cut-off configuration, thereby mechanically
closing off the outlet valve 7 once the required mass and/or volume is achieved. In
this embodiment, other variables of the system, including for instance temperature
of the base material and flow rate of the base material, should be kept the same as
they were under the initial conditions when the correlations were derived.
[0032] Further, given the above correlation, it is also be possible to replace the second
crucible 9 with a sump of a fixed volume that corresponds to the desired temperature
at the interface surface 15, 19. In this instance, the outlet valve 7 could be dispensed
with as the flow of base material through the mould 5 would automatically begin to
fill the mould 5 once the fixed volume sump was full. Advantageously, this results
in a simplified process for repeat casting systems, wherein filling of the mould 5
is automatically achieved once the desired temperature is reached.
[0033] Figure 4 is a flow diagram illustrating the main process steps of Figure 1. At step S1, the
base material is introduced into the mould such that the base material flows through
the mould. At step S2, it is determined whether a desired temperature of the mould
is achieved. If so, at step S3, the base material is prevented from flowing out of
the mould. At step S4, it is determined whether the mould has been filled to the desired
level. If so, the process is complete and casting may continue in a conventional manner.
[0034] In order to achieve certain material properties in the final cast, for instance strength,
lubricity, or resistance to wear et cetera, it is often desirable to use interstitial
elements suspended in matrices of the 'parent' base material. In a conventional casting
process, this may be achieved by preparing the mould before casting with an interstitial
material already within it. However, in the above described heating and casting processes,
if a mould is prepared for use with an interstitial material already within it, in
certain circumstances the flow of the base material through the mould, either during
the heating stage or otherwise, may displace the pre-placed interstitial materials.
The turbulence created by the fluid base material as it travels through the system
may be sufficient to displace the interstitial material. In other words, the pre-placed
interstitial material may be washed out of position or out of the mould entirely by
the flow of the base material.
[0035] Figure 5 illustrates an embodiment of the invention that addresses this problem. The features
of this embodiment may be combined with features of any of the embodiments described
above. Before casting, the mould 5 may be prepared with an interstitial material 23,
such as tungsten carbide or molybdenum or any other suitable material, already within
its inner cavity 13. Instead of leaving the interstitial material 23 exposed, the
interstitial material 23 is then covered or otherwise retained by a retainer 25. The
retainer 25 may be made of steel or any other suitable material for use within the
temperature domains of the casting process. The retainer 25 is then attached to the
mould 5 by any suitable means, for instance by means of nails, staples or pins, such
that it is able to retain its position within the mould 5 whilst the base material
flows through the inner cavity 13 of the mould 5. The retainer 25 may take any suitable
form, for instance the retainer 25 may be a mesh, grid or array of wires or bars.
The retainer 25 comprises openings to allow the base material to flow through the
retainer 25, wherein the openings may take any suitable form, for instance the openings
may be gaps, slits, pores or perforations. The dimensions of the retainer 25 openings
are chosen to be suitably sized such that the base material may flow freely through
the retainer 25, but such that the interstitial material 23 may not pass through the
retainer 25. In other words, the openings of the retainer 25 are sized such that the
interstitial material 23 is unable to escape through the openings and be washed away,
and hence is instead held in position both before and during the heating or casting
processes. For instance, when the interstitial material is granular, the openings
of the retainer 25 are dimensioned to be smaller than the dimensions of any single
grain of the interstitial material 23, thereby preventing movement of the interstitial
material 23 through the retainer 25.
[0036] In operation, when the base material flows through the mould 5 in a manner as described
in any previous embodiment, the base material also flows through the openings of the
retainer 25 and through the interstitial material 23. In this way, the base material
comes into physical and thermal contact with both the retainer 25 and the interstitial
material 23. Advantageously, the retainer 25 maintains the interstitial material 23
in its original location in the mould 5 throughout any of the heating or casting processes
as described above.
[0037] The interstitial material 25 could be placed anywhere within the inner cavity 13
of the mould 5, as it can be held in position by the retainer of the retainer 25,
and as the base material can flow through both the retainer 25 and the interstitial
material 23. Further, there may be a plurality of different sections of interstitial
material 23 within the mould 5, each of which is held in a particular location by
a respective separate retainer 25.
[0038] In order to improve the binding, retention and overall material properties of these
interstitial materials in the final cast, it is often desirable to promote a degree
of sintering between the interstitial materials and the parent material during the
cast process. To achieve this, the interstitial materials must be raised to above
their sintering temperature at some time before the casting process is concluded.
This sintering process is facilitated by the openings of the retainer 25 which allow
the base material to flow through retainer 25 and come into direct physical and thermal
contact with the interstitial material 23, thereby transferring heat energy from the
base material to at least a part of the interstitial material 23. For instance, at
least the boundary areas of the grains of the interstitial material 23 may be exposed
to sufficient thermal energy to sinter. Advantageously, the material of the retainer
25 may also be chosen to facilitate this by having a heat transfer characteristic
that allows sufficient heat energy to conduct from the base material through the retainer
25 and into the interstitial material 23 to allow sintering of at least a part of
the interstitial material 23.
[0039] In operation, the interstitial material 23 is initially prepared in the mould 5.
The retainer 25 is then located so as to cover the interstitial material 23, and the
retainer 25 is then attached to the mould 5 by any suitable means, as described above.
The mould 5 is then prepared for preheating and casting. To achieve at least partial
sintering of the interstitial material 23, a desired predetermined temperature of
the retainer 25 will need to be reached. The requisite heating is achieved using any
of the above described preheating or casting methods, in which the base material will
flow through the mould 5, through the retainer 25, and through the interstitial material
23, whereby thermal energy will be transferred from the base material to the interstitial
material 23, such that sintering of at least the boundary areas of the interstitial
material 23 will cause the interstitial material 23 to chemically and/or physically
bond to the base material in the final cast.
[0040] In particular, any of the above described methods of preheating the mould 5 to a
particular temperature may be used, such as opening and closing the valves 7 and 21
to control the base material flow rate, filling the mould 5 to a predetermined level
of base material, or collecting a certain amount of base material in a second crucible
9.
[0041] To determine the desired temperature of the interstitial material 23 has been achieved,
for instance to achieve sintering of the interstitial material 23, the temperature
measurement devices 11 are located in the interstitial material 23 as shown in
Figure 5. Alternatively, the temperature measurement devices 11 may be arranged to be located
at or close to the interface surface 15 between the inner cavity 13 of the mould 5
and the interstitial material 23, in which case the temperature of the interstitial
material 23 as a whole may be inferred from the temperature as measured at this location.
[0042] The information received by the temperature measurement devices 11 may be transmitted
to a user by a display, or to the computer control system, both as described earlier.
If the temperature of the interstitial material 23 as measured by the temperature
measurement devices 11 is lower than a desired temperature, any one of the heating
processes described above may be implemented.
[0043] In all other respects, the heating process of this embodiment is carried out as described
in the above embodiments. Hence, the base material is allowed to continue flowing
through the system, flowing in through the retainer 25, and through the interstitial
material 23, until a desired temperature of the interstitial material 23 is measured
by the temperature measurement devices 11. At this point the mould 5 is at a suitable
temperature for casting the base material flowing through it, and the outlet valve
7 is switched to a closed state, and the mould 5 fills with base material as described
in previous embodiments.
[0044] As further described in previous embodiments, a multi-stage casting process may also
be applied, wherein two separate desired temperatures are to be achieved at different
stages of the cast. This may be carried out as described in previous embodiments above.
[0045] Once the casting process has been completed, the finished cast including the interstitial
material 23 and the retainer 25 may be removed from the mould 5 as in conventional
casting processes. As a result of the sintering facilitated by the retainer 25, the
resulting cast comprises the base material, the retainer 25, at least a portion of
partially sintered interstitial material 23, and the remaining interstitial material
23. Hence, using the retainer 25 as herein described, it is possible to create a final
cast including interstitial materials for improved material properties, even within
the context of the previously described heating and casting processes. Advantageously,
as the retainer 25 is present in the final cast, it also serves to provide extra reinforcement
to the final cast.
[0046] Advantageously, the retainer as herein described provides the possibility of using
interstitial materials in casts created using the above-described heating processes,
wherein the retainer is simultaneously able to retain the interstitial material in
its required location during heating or casting, whilst also facilitating the desired
level of sintering of the interstitial materials in the process.
[0047] Any of the above described embodiments may be controlled and operated by a computer
system (not described here), so that the each of the components, measurements and
operations described above may be controlled by suitable electrical control circuitry
connected to the computer system.
Alternative Embodiments
[0048] The embodiments described above are illustrative of, rather than limiting to, the
present invention. Alternative embodiments apparent on reading the above description
may nevertheless fall within the scope of the invention.
1. A method of casting, comprising:
a. introducing a molten material into a mould (5), such that the molten material flows
out of the mould (5);
b. subsequently preventing the molten material from flowing out of the mould (5) once
a desired temperature of the mould (5) is achieved, such that the molten material
at least partially fills the mould (5).
2. The method of claim 1, wherein a temperature of the mould (5) is measured so as to
determine that the desired temperature of the mould (5) is achieved, wherein the temperature
is preferably measured using one or more thermocouples (11) or thermostats (11).
3. The method of claim 1, wherein determining that the desired temperature of the mould
(5) is achieved comprises determining that a predetermined mass and/or volume of the
molten material has flowed out of the mould (5).
4. The method of any preceding claim, wherein the molten material that flows out of the
mould (5) is collected in a container (9), wherein the container is preferably a crucible
(9).
5. The method of claim 4, wherein:
the container (9) is a sump of a fixed volume, wherein when the sump is filled with
molten material, the molten material in the mould (5) is prevented from flowing out
of the mould (5); or
a predetermined mass and/or volume of the molten material in the container (9) is
measured so as to determine that the desired temperature of the mould (5) is achieved.
6. The method of any preceding claim, further comprising controlling the flow of the
molten material using a valve (7) downstream or upstream of the mould (5), wherein
preferably preventing the molten material from flowing out of the mould (5) is achieved
using the valve (7) downstream of the mould (5).
7. The method of any preceding claims, wherein the mould (5) contains a second material
(17, 23) before the flow of molten material is introduced into the mould (5).
8. The method of claim 7, wherein the second material (17, 23) is an interstitial material
(23).
9. The method of claim 8, further comprising providing at least one retainer (25) within
the mould (5), wherein the retainer (25) is suitable for retaining the interstitial
material (23) within the mould (5).
10. The method of claim 9, wherein the retainer (25) retains the interstitial material
(23) in a location within the mould (5).
11. The method of claim 10, wherein when the molten material is introduced into the mould
(5), heat energy is conducted from the molten material to the interstitial material
(23), wherein preferably the desired temperature is a temperature sufficient to cause
sintering of at least a part of the interstitial material (23).
12. The method of one of claims 9 to 11, wherein the retainer (25) comprises openings,
wherein the openings are dimensioned so as to prevent the transport of the interstitial
material (23) through the openings, but so as to allow the transport of molten material
through the openings, and wherein the retainer (25) is preferably made of steel and
wherein the interstitial material (23) is preferably at least one of tungsten carbide
or molybdenum.
13. The method of any preceding claim, wherein the molten material that flows out of the
mould (5) is reheated and then reintroduced to the mould (5).
14. A computer readable medium having stored thereon processor executable instructions
that cause a computer to perform the method of any of the preceding claims when executed
by a computer arranged to operate a casting apparatus.
15. A mould (5) for use in a temperature-controlled casting process as described in any
one of claims 1 to 13, the mould including interstitial material (23) and a retainer
(25) for retaining the interstitial material (23) within the mould.