Field of invention
[0001] This invention relates to a transport network, in particular to a railway network.
Background
[0002] Demand for high-quality rail links has increased in recent years, however substantive
redesign of railway networks is significantly constrained by available land, the difficulty
of constructing new infrastructure without adversely affecting the operation of existing
services and the consequent high cost of capacity improvements. Marginal improvements
to the efficiency of the service can only create a certain level of improvement. Thereby,
an improvement to a railway network whereby largely existing infrastructure can be
utilised at an improved efficiency would be desired.
[0003] The South-East of England has a particular problem with rail networks due to the
related issues of a high population, lack of space and the need for large numbers
of passengers and staff to access a large international airport.
[0004] According to one aspect of the invention there is provided a railway network comprising
a first rail line; a second rail line directly accessing said airport and sharing
at least a portion of the same track corridor as said first line, said second rail
line providing a through service via said airport; and a station on both said first
and second rail lines. In such a way, network resources can be utilised more efficiently.
[0005] Preferably, the first rail line provides direct access to a population centre.
[0006] Preferably, the second rail line provides access to a population centre via said
airport.
[0007] Preferably, the shared track corridor comprises a section between an airport junction
and a population centre. Preferably, in use, said shared track corridor defines the
limit of the number of trains per hour on the railway network.
[0008] Preferably, the second rail line follows a major road corridor; preferably wherein
the major road corridor is the M25 motorway.
[0009] Preferably, the airport is London Heathrow airport. Preferably the said second rail
line comprises a link from Woking to London Paddington via Heathrow airport.
[0010] Preferably, the shared track corridor comprises the portion east of an airport junction
of the Heathrow Express path.
[0011] Preferably the rail network further comprises a hub station serving the airport,
wherein passengers on said first rail line transfer at said hub station to access
the airport.
[0012] Preferably, the station on first rail line is a more major population centre station
and the first rail line further comprises a less major population centre station.
[0013] Preferably, the hub station is positioned between one and two thirds of the way,
preferably between three and five eights, more preferably half way between said more
major and less major population centre stations by at least one of: (a) number of
intermediate stopping stations; (b) distance; and (c) time.
[0014] Preferably, the less major population centre station is Reading and said more major
population centre station is London Paddington.
[0015] Preferably, the hub station comprises a less frequently stopping train platform and
a more frequently stopping train platform.
[0016] Preferably, said less frequently stopping train platform and said more frequently
stopping train platform are disposed on opposing sides of a single platform; preferably
wherein, in use, said less frequently stopping trains stop at said less frequently
stopping train platform and more frequently stopping trains stop at said more frequently
stopping train platform at substantially the same time.
[0017] According to another aspect of the present invention there is provided a railway
network comprising: a hub station serving an airport; a first rail line, wherein passengers
on said first rail line transfer at said hub airport to access said airport; and a
second rail line directly accessing said airport and sharing at least a portion of
the same track corridor as said first line, said second rail line providing a through
service via said airport.
[0018] Such an arrangement may provide an efficient use of rail resource so as to improve
utilisation of limited rail capacity.
[0019] Preferably, for access to a population centre said first rail link provides direct
access to a population centre.
[0020] Preferably, for access to an airport second rail line provides access to a population
centre via said airport.
[0021] Preferably, for increased utility the rail network further comprises a third rail
line providing a through service via said airport.
[0022] Preferably, for efficient use of rail resource said third rail line shares at least
a portion of the same track corridor as said second rail line.
[0023] Preferably, to reduce negative impacts said third rail line follows a major road
corridor.
[0024] Preferably, said third rail line comprises a Crossrail extension.
[0025] Preferably, said first rail line comprises a more major population centre station
and less major population centre station.
[0026] Preferably, said hub station is positioned between one and two thirds of the way,
preferably between three and five eights, more preferably half way between said more
major and less major population centre stations. This may be by number of intermediate
stopping stations, by distance and/or by time.
[0027] In one example, said less major population centre station is Reading and said more
major population centre station is London Paddington.
[0028] Preferably, said hub station comprises a less frequently stopping train platform
and a more frequently stopping train platform. This may allow for a flexible service
to be provided to passengers.
[0029] Preferably, said less frequently stopping train platform and said more frequently
stopping train platform are disposed on opposing sides of a single platform. This
may allow simple interchange between different services.
[0030] Preferably, in use, said less frequently stopping trains stop at said less frequently
stopping train platform and more frequently stopping trains stop at said more frequently
stopping train platform at substantially the same time. This may allow passengers
to interchange without waiting at the station.
[0031] Preferably, said first rail line further comprises a rail connection departing from
said line at a first side of said hub station and crossing said first rail line a
second side of said hub station. This may allow trains to depart from said first rail
line whilst reducing the interference with the operation of said rail line.
[0032] Preferably said rail connection provides access to the airport for freight.
[0033] Preferably, said first side of said rail connection is more distal than said second
side of said hub station with respect to the more major population centre station.
[0034] Preferably wherein said rail connection connects with said second rail line after
crossing said first line. This may provide further flexibility for routes and/or resilience
for the network.
[0035] Preferably, said hub station comprises airport security so that passengers travel
air-side to said airport. This may provide a simpler journey for users.
[0036] Preferably, said access to the airport from said hub airport comprises a separate
baggage transit system. This may provide a simpler journey for users.
[0037] Preferably, said second rail line follows a major road corridor.
[0038] Preferably, said rail network further comprises a train link between said hub station
and said airport.
[0039] Preferably, said train link comprises an extension of an existing train link to said
airport from a population centre. In one example, the train link is the London Underground
Piccadilly line.
[0040] In one example, the airport is London Heathrow airport.
[0041] In one example, the first rail line comprises the Great Western Main Line.
[0042] In one example, the second rail line comprises the Heathrow Express line.
[0043] According to another aspect of the present invention there is provided a railway
network comprising: a railway line; a station on said railway line; and a rail connection
departing from and crossing said railway line; wherein said rail connection departs
from said railway line at a junction one side of said station, and crosses said railway
line the other side of said station. This may provide a more efficient rail network.
[0044] Preferably, said railway line splits at a junction on one side of said station and
recombines at a junction on the other side of said station; wherein the station comprises
a platform positioned between said split railway lines. This may allow multiple trains
to access the station at the same time.
[0045] Preferably, said split junction is closer to said station than the junction at which
the rail connection departs from said railway line. This may reduce the number of
tracks the rail connection is required to cross.
[0046] Preferably, said recombination junction is positioned closer to said station than
the junction at which the rail connection crosses said railway line. This may reduce
the number of tracks the rail connection is required to cross.
[0047] Preferably, said junction at which the rail connection crosses said railway line
comprises a grade separated junction. This reduces the chance of interference between
the rail connection and the rail line.
[0048] Preferably, said rail connection is bi-directional. This may allow a more flexible
service.
[0049] Preferably, wherein said station comprises means for two or more trains travelling
in the same direction to stop at substantially the same time. This may allow for multiple
trains travelling the same direction to avoid conflict with a train on the rail connection.
Preferably, said means comprises a junction splitting said rail line thereby allowing
two trains on the same line to access the station at substantially the same time.
[0050] Preferably, said station comprises a platform positioned after said split of said
rail line so that said two trains are able to access said station on opposing sides
of the same platform.
[0051] According to another aspect of the present invention there is provided a method of
scheduling a first and second train, the method comprising: directing the first train
to depart said departing station towards said interchange station; directing the second
train to depart said departing station towards said interchange station a time X1
after said first train departs, the second train having a greater average speed than
said first train so that the two trains arrive at said interchange station at substantially
the same time. This method may provide a more efficient service for passengers.
[0052] Preferably, said first and second trains wait at said interchange station for an
overlapping period so as to allow passengers to interchange.
[0053] Preferably, said first and second trains wait at opposing sides of the same platform
at said interchange station.
[0054] Preferably, said first and second trains utilise the same rail track between said
departing station and said interchange station. This may allow for efficient use of
rail resource.
[0055] Preferably, said first train stops at a greater number of intermediate stations than
said second train. This may provide passengers with a flexible network.
[0056] Preferably, said second train departs said interchange station towards a further
station before said first train departs towards said further station. This may avoid
a further need for the trains to overtake one-another.
[0057] Preferably, said second train arrives at said further station at a time X2 before
said first train; wherein X2 is approximately the same as X1. This may assist in providing
a regular service for passengers.
[0058] Preferably, X2 is plus or minus 30% of X
1; more preferably, plus or minus 15% of X
1; yet more preferably, plus or minus 5% of X1.
[0059] Preferably, so as to provide a regular service, said interchange station is between
one third and two thirds of the distance; more preferably, between three eights and
five eighths of the distance; yet more preferably, approximately half way, between
said departing station and said further station.
[0060] Preferably, so as to provide a regular service, the number of intermediate stations
said first train stops at between said departing station and said intermediate station
is approximately the same as the number of intermediate stations said first train
stops at between said intermediate station and said further station.
[0061] Preferably, the number of intermediate stations said first train stops at between
said departing station and intermediate station is plus or minus 5 of the number of
intermediate stations said first train stops at between said intermediate station
and said further station. More preferably, the number of intermediate stations said
first train stops at between said departing station and intermediate station is plus
or minus 2 of the number of intermediate stations said first train stops at between
said intermediate station and said further station. Yet more preferably, the number
of intermediate stations said first train stops at between said departing station
and intermediate station is the same as the number of intermediate stations said first
train stops at between said intermediate station and said further station.
[0062] According to a further aspect of the present invention there is provided a railway
network comprising: a train line comprising a departing station and an interchange
station; a junction between said departing station and interchange station; said junction
splitting said line into at least two lines so that two trains on said line are able
to access said interchange station at substantially the same time. Such a rail network
may provide for a simple and efficient interchange for passengers.
[0063] Preferably, said interchange station comprises a platform positioned between said
two lines so that said two trains access said station at opposing sides of said platform.
[0064] Preferably, the railway network further comprising a plurality of intermediate stations
between said departing and said interchange stations, wherein only some trains stop
at said intermediate stations.
[0065] The invention extends to any novel aspects or features described and/or illustrated
herein. Further features of the invention are characterised by the other independent
and dependent claims
[0066] Any feature in one aspect of the invention may be applied to other aspects of the
invention, in any appropriate combination. In particular, method aspects may be applied
to apparatus aspects, and vice versa.
[0067] Furthermore, features implemented in hardware may be implemented in software, and
vice versa. Any reference to software and hardware features herein should be construed
accordingly.
[0068] Any apparatus feature as described herein may also be provided as a method feature,
and vice versa. As used herein, means plus function features may be expressed alternatively
in terms of their corresponding structure, such as a suitably programmed processor
and associated memory.
[0069] It should also be appreciated that particular combinations of the various features
described and defined in any aspects of the invention can be implemented and/or supplied
and/or used independently.
[0070] The invention extends to methods and/or apparatus substantially as herein described
with reference to the accompanying drawings.
[0071] The invention will now be described by way of example, with references to the accompanying
drawings in which:
Figure 1 is a schematic map of an example transport network serving an airport;
Figure 2 shows the transport network of Figure 1 including a rail connection;
Figure 3 shows the transport network of Figure 2 including an additional rail line;
Figure 4 shows the transport network of Figure 3 including a continuation of the rail
connection of Figure 2;
Figure 5(a) shows an example track layout for a hub station;
Figure 5(b) shows the track layout of Figure 5(a) including a rail connection; and
Figure 6 is a schematic map of a transport network implemented in the South East of
the United Kingdom.
Detailed description
[0072] The present invention relates to a transport network incorporating a station serving
an airport. Airports are often served by designated 'express' trains which run from
a city to and from an airport. However, such services, whilst convenient for users
travelling solely between a city and an airport, often run at very low capacity, in
particular during peak hours. This is because airport services need to run at high
frequencies in order to attract time sensitive airport passengers to use rail. However
the smaller number of airport passengers compared to non-airport passengers (even
where trains serve a densely populated city) results in low load factors and therefore
an inefficient use of scarce rail network capacity. Airport services also prevent
other trains (for example, commuter or inter-city trains) from using the same network
at a potentially increased efficiency.
[0073] The present invention offers a solution in so far as enabling a frequent service
to an airport whilst making the most efficient use of network resources.
[0074] In the below description, the term 'city station' may be understood to include a
station in, or providing access to, a population centre such as a city. The term 'intercity
station' may be understood to include a station in, or providing access to, a less
major population centre as compared to a city. The term 'hub station' or 'hub' may
be understood to include a station or other transport infrastructure providing access
to more than one form of transport, potentially of different types (e.g. inter-city
rail and mass-transit).
[0075] Figure 1 shows a schematic of a simplified transport network around an airport 102
comprising two airport stations 104. An express train line 106 serves this station
from a city station C1. Another train line 110 which serves the city from stations
such as S1 is provided which shares the same rail corridor as the express service
106 for a section towards the city from the airport. Train line 110 may be used by
commuters or inter-city travellers who do not wish to go to the airport 102.
[0076] A hub station 112 is provided on train line 110 providing access to the airport 102
via a transit system 111 to the airport stations 104. By providing a hub station 112
on an existing train line serving a city means that only a relatively small increase
in journey time is introduced for commuters / inter-city travellers and a fast, frequent
service to the airport is afforded for air passengers and airport staff.
[0077] The transit system 111 for passengers may be an automated system, for example driverless
trains, which travel the relatively short distance to and from the hub station 112
and the airport terminals served by the airport stations 104. Such a system minimises
waiting time for passengers arriving at the hub station 112 wishing to travel to the
airport terminals.
[0078] In one example, passengers may pass through airport security at the hub station 112.
This reduces the need to increase capacity of the existing security infrastructure
at the airport 102.
[0079] Furthermore, users may be able to check in baggage which is then transported to their
airport via a separate transit system following the same alignment as the passenger
system. As above, this reduces the need to increase the capacity of the existing baggage
handling system on the basis of increased passenger numbers, and simplifies the passengers'
ongoing journey to the airport.
[0080] In such a scenario, following security at the hub station 112, the remainder of the
users' journeys are under 'air-side' conditions, and are separated from users accessing
the airport via different routes.
[0081] The network shown in Figure 1 also includes a train line 113 terminating at the airport
from the city. Such a route provides an alternative route from the city to the airport
102, but does not increase the efficiency of the route 110 from the direction of station
S1 to the city.
[0082] Train line 114 is provided which is a continuation of line 106. Terminating trains
are typically less efficient than through trains as all passengers must disembark,
and the driver walk to the other end of the train before it can depart. In the arrangement
of Figure 1, through trains are utilised as there are routes through the airport which
are useful to passengers, for example from station S3 to the city C1. Line 114 follows
the same track corridor as line 113, but continues away from the city. This line provides
an alternative route to the city (via the airport) for commuters, intercity passengers
and airport passengers, and relieves overcrowding on the existing route between S3
and the city. Such a route increases the utilisation of train line 106 by introducing
non-airport passengers. This results in the same number of trains per hour on the
existing shared section of railway, but an increased number of passengers per train.
[0083] In one example, the shared section of railway between lines 113 and 114 follows a
major road corridor, for example, a motorway corridor. This avoids the need for junctions
with minor roads (such as level-crossings which introduce delays on roads, or grade
separation which are costly to build and maintain), and also is less objectionable
to local residents from a visual and audial perspective.
[0084] Figure 1 also shows a freight train line 116a accessing an area near the airport
102, for example to deliver aircraft fuel and/or air-freight to be loaded onto aircraft
and/or delivery or removal of material and waste in connection with construction activities
on and around the airport. This line is provided for trains arriving from the city.
Freight trains wishing to access the airport from the direction of station S1 are
required to pass the line 116a to an area where it is possible for the locomotive
to run round the train in order to reverse direction. This introduces a significant
delay in such trains accessing the airport and reduces the capacity of the lines in
each direction for passenger trains.
[0085] Figure 2 shows the same rail network as that shown in Figure 1, but including a rail
connection 116b providing access to an area near the airport 102 directly from station
S1, simplifying operation for some freight trains and increasing the capacity of the
rail network.
[0086] Freight connection 116b allows for a designated track for freight trains, as opposed
to such trains having to cross tracks intended for passenger trains. This avoids the
situation where freight trains travel towards the city going past the hub station
112 and then reverse back along line 116a, which is a slow process and can affect
the operation of passenger-carrying lines. Such a connection 116b improves the capacity
of the network for freight services without adversely affecting capacity for passengers.
Providing such a connection allows passenger-carrying trains to 'overtake' freight
trains by passing through hub station 112, reducing or removing the need for sidings
or 'up goods' lines elsewhere for freight trains to pull into to allow other trains
to overtake. The radius of curvature of the connection 116b is configured for the
particular length and design of freight trains intended to use it.
[0087] Figure 3 shows a further addition to the rail network in the form of a line 118 providing
a through-service from the city to a station S2 via the airport 102. Station S2 is
closer to the city than the airport 102 on line 113. Through services are more efficient
than stopping services as they spend less time stopped at the station. By providing
a through service to a station S2 via the airport 102 allows a fast connection to
the airport 102 from the city without congesting the airport station 104 by requiring
a train to stop, empty of passengers, and reverse back the way it came. This action
can be performed at a station S2 as opposed to at the congested airport station 104,
which also provides passengers an alternative route into the city, alleviating the
pressure on line 113. The line 118 may continue past the city station C1 - for example
as a cross-city connection.
[0088] Figure 4 shows the same network as shown in Figure 3, but freight connections 116a
and 116b continue as line 117 which connects to one or more of the rail lines 113,
114 and/or 118, Such a continuation provides access to an area near the airport 102
(e.g. for freight) from locations not on line 110. Such a continuation may also be
used by passenger-carrying trains which increases the flexibility and resilience of
the network.
[0089] The placement of the hub station 112 allows for particularly efficient operation.
In the example shown, the hub station 112 is approximately equidistant (in terms of
intermediate stations and actual distance) between an intercity station S1 and the
city station C1. This allows for an efficient mix of different speed class trains
(e.g. 'slow' services that stop at relatively more intermediate stations (labelled
'A' in Figure 5), and 'express' services that stop at relatively fewer intermediate
stations (labelled 'B' in Figure 5)). In such a way, the hub station 112 can be used
as an interchange station.
[0090] A relatively more frequently stopping service A (i.e. a 'slow train') leaves station
S1 towards C1; a certain time 'X
1' later, a relatively less frequently stopping service B (i.e. an 'express train')
leaves S1. The relatively more frequently stopping service A arrives at the hub station
112 shortly before the relatively less frequently stopping service B at opposing sides
of the same platform. Passengers can interchange by walking between trains. Such an
arrangement allows passengers who require to embark or to disembark at an intermediate
station to take advantage of an express service up to the hub station 112. This makes
the express services B an attractive alternative for passengers from station S1 compared
to long distance services originating from or going to stations beyond S1. This effectively
provides more capacity for long distance passengers without increasing the number
of trains.
[0091] The relatively less frequently stopping train B then departs shortly before the relatively
more frequently stopping train A, and arrives at the city station C1 approximately
'X
2' minutes before the relatively more frequently stopping train A.
[0092] A timetable can be created which provides a regular service utilising the network
efficiently. A relatively more frequently stopping train A ('slow train') departs
from a departing station, then at a time 'X
1' later, a relatively less frequently stopping train B ('express train') departs.
As the 'slow train' A stops more frequently than the 'express train' B, the express
train B catches up to the slow train A. This occurs at an interchange station 112
where passengers can interchange between services as necessary. The increased average
speed (Δv
1) of the express train B over the distance between the departing station and interchange
station (D
1) is thus:

[0093] The 'express train' B then departs and arrives at a further station at a time 'X
2' before the 'slow train' A. In order to create a regular service, X
1 and X
2 are preferably similar (
X1 ≈
X2). In one example, X
1 and X
2 are plus or minus 30% of one-another, preferably plus or minus 15%, and preferably
plus or minus 5% of one-another. This puts a constraint on the increased speed of
the express train B compared to the slow train A over the first and second parts of
the journey.

[0094] The increase in speed of the 'express train' B compared to the 'slow train' A is
predominately determined by the number of additional stops the 'slow train' A makes
(n):

[0095] In the case where D
1 and D
2 are approximately the same, the number of additional stops on each leg would also
be approximately the same so as to provide a regular timetable. In one example, the
number of stops in each leg is within 5 of each other, preferably between 2, and more
preferably the same.
[0096] Other arrangements could be envisaged, for example where D2 is larger than D1, and
therefore there are fewer intermediate stops on the second leg than the first leg
(or vice versa).
[0097] It should be noted that there may be other factors which affect the increased speed
of an 'express train' B (for example, a different type of train with a higher top
speed), and that this would mean Equation (1) would be used as opposed to equation
(3).
[0098] The placement of the hub station 112 allows for a regular timetable to be provided
whilst ensuring both trains will be at the hub station 112 at the same time. For example,
if the journey time for the slow train A is 1 hour, and the express train B is 30
minutes, the following timetable could be provided with a hub station at the half-way
point:
Table 1: Example timetable
Intercity station S1 |
Hub station 112 |
City station C1 |
'Slow' A |
'Express' B |
'Slow' A |
'Express' B |
'Slow' A |
'Express' B |
12:00 |
|
12:30 |
|
1:00 |
|
|
12:15 |
|
12:30 |
|
12:45 |
12:30 |
|
1:00 |
|
1:30 |
|
|
12:45 |
|
1:00 |
|
1:15 |
[0099] As can be seen, four equally spaced-apart trains depart from station S1 and arrive
equally spaced apart at station C1, whilst stopping at the hub station at the same
time as another train to allow for passengers to interchange. Such a timetable could
be duplicated, for example, so that there are 8 trains per hour rather than the four
listed above. Furthermore, the timetable could be extended by duplicating the arrangement
of Figure 5(a), for example by providing three or four platforms instead of two.
[0100] Figure 5(a) shows an example track layout allowing for the express/stopping service
described above. The track going towards the city station C1 splits at a junction
before the hub station 112 and a relatively more frequently stopping train A pulls
into the platform. A relatively less frequently stopping train B pulls into the opposing
side of the same platform shortly after. Both trains then wait at the platform, allowing
passengers to interchange as required by walking across the platform. The relatively
less frequently stopping train B then departs shortly before the relatively more frequently
stopping train A. A similar arrangement is provided for trains going away from the
city. Such an arrangement allows a single track to be used by both 'express' and 'slow'
services without the trains interfering with one-another.
[0101] Figure 5(b) shows the same track layout as shown in Figure 5(a), but including freight
paths 116a and 116b. In such a way, freight trains avoid passenger-carrying tracks
around the station, and therefore avoid conflict with passenger trains. Freight connections
116a and 116b are shown crossing the passenger-carrying line 110 by way of a grade
separated junction such as an underpass or bridge; this avoids conflicts between passenger
trains and freight trains which have the effect of reducing network capacity. As can
be seen from Figure 5(b), the freight connection 116b departs from line 110 at a junction
before the tracks split going into the station 112. The freight connection 116b then
crosses the line 110 at a junction after the tracks split after the station 112. This
provides simpler junctions and therefore takes less space and is easier to manage.
[0102] In use, a freight train approaching the station 112 from the West (from left to right
on Figure 5(b)) departs line 110 at a point before the station 112, and before the
passenger carrying lines split for 'slow' and 'express' services. The freight train
then loops around the station 112 and crosses the line 110 at a grade-separated junction
after the station 112. The freight trains can then access an area such as a depot,
or other train lines as indicated by line 117 in Figure 4. For trains departing the
depot, or other line 117, they utilise the appropriate bi-directional single track
116a or 116b depending on the direction required. If returning to the West (to the
left on Figure 5(b)), the train is required to cross the Eastbound line 110. Such
an activity may require signalling so as it does not interfere with passenger-carrying
trains. A similar approach may be taken for trains coming from the East (from right
to left on Figure 5(b)).
[0103] The arrangement of the rail connection 116b and the hub station 112 as an interchange
station provides a further advantage of multiple trains on a line in a particular
direction being able to 'overtake' a freight train whilst passing through the hub
station 112. For example, the arrangement shown in Figure 5(b) allows two passenger-carrying
trains (A and B) travelling from West to East to 'overtake' a freight train at the
same time. Such an arrangement, together with suitable timetabling, reduces the need
for passenger carrying trains to wait behind freight trains for an opportunity to
overtake - and thus minimise any associated infrastructure (such as signalling and
additional track crossings).
[0104] In one example the freight connections 116a and 116b are single-track, bi-directional
connections. Alternatively, two uni-directional tracks could be provided for one or
both connections, for example if frequency of use necessitated this.
[0105] It should be appreciated that the features shown in Figures 1-5 may be provided independently
of one-another; for example the additional line 118 shown in Figure 3 may be provided
in a network without the freight connection 116b.
Heathrow Airport
[0106] The transport network described above is particularly suited for providing access
to Heathrow airport in the South East of the United Kingdom. This area has a very
congested rail network, but one in which the express trains to the airport run significantly
below full capacity. Furthermore, access to Heathrow from locations other than London
typically requires passengers to interchange in London, adding to journey times.
[0107] Figure 6 shows a schematic map of the transport network, with common reference numerals
indicating analogous elements in Figures 1, 2 3, and 4 implemented in the South East
of the United Kingdom.
[0108] The network described herein adopts an integrated approach to rail planning and provides
greater benefits (to airport passengers, non-airport passengers, and freight operators),
higher rail revenues and lower environmental impacts. Key elements include:
- 1. Construction of a new hub station (112) on the Great Western Main Line (GWML -
line 110) between existing stations at Iver and West Drayton, to enable direct services
between Heathrow airport and destinations in the Great Western catchment area. The
hub station 112 provides significantly faster rail journey times to and from the airport
102, and, unlike the alternative "WRAtH" proposal (Western Rail Access to Heathrow),
avoids the need for the majority of passengers to interchange at Reading (S1).
- 2. Construction of a section of new railway immediately alongside the eastern side
of the M25 between Terminal 5 (T5) and a connection to the Virginia Water - Weybridge
route north of Chertsey at its crossing of the motorway. This new section of railway
provides advantages including:
- Providing a high quality rail link 114 from towns such as Basingstoke, Guildford and
Woking to Heathrow (c16 minutes from Woking to Terminal 5).
- Through integration with Heathrow Express (HEx) paths 106 on the Great Western Main
Line east of the Airport Junction, making optimum use of scarce network capacity.
- providing a high quality connection to HS2 at Old Oak Common, direct access to the
proposed Old Oak Common development site.
- An attractive alternative route from Woking and beyond to central London, giving relief
to the heavily congested South Western Main Line 113 and the Underground lines serving
Waterloo.
[0109] The design of the Hub interchange 112, located north of the airport, allows fast
"Crossrail Express" services calling only at the Hub station 112 between Reading (S1)
and Paddington (C1), and then going on to serve all central London stations and the
eastern branches.
[0110] These express services provide attractive services for London passengers from Reading,
relieving capacity on GWML long distance services, and providing cross platform interchange
at the Hub with stopping services. The 8 minute journey time penalty compared to non-stop
Reading-Paddington services would be more than compensated by avoiding the need for
an interchange between GWML and Crossrail services at Paddington.
[0111] A west facing chord on the Great Western Relief (Slow) Lines allows freight trains
from the west to access the Colnbrook branch 116b without the need to reverse at Acton
or West Drayton which would conflict with Crossrail services.
[0112] This benefits intermodal services. It would also be possible to extend the Colnbrook
branch 116b to the south to provide a connection with new section of railway 117 south
of Heathrow Terminal 5 104 and therefore the South Western Main Line, increasing flexibility
and network resilience.
[0113] We propose an extension of the Piccadilly Line to the Hub interchange 112, opening
up new journey opportunities to the west of London. This may be in the form of transit
line 111, or as a separate line (for example, if the transit line 111 is 'air side').
[0114] To the south of the airport 102, our proposals allow fast direct services between
the airport and the South Western Main Line (SWML), and avoid the problem of uncompetitive
journey times and extended level crossing barrier downtimes that led to the failure
of the previous Airtrack scheme promoted by BAA.
[0115] This allows direct trains to Woking, Basingstoke (and potentially on to Southampton)
and Guildford (potentially Portsmouth). Importantly these services would run through
the airport and make use of the existing HEx paths to run through to Paddington. By
providing direct access to Crossrail, these would be attractive to non-airport passengers,
taking only 10 minutes longer from Woking to Paddington than existing fast services
to Waterloo.
[0116] These would provide valuable capacity relief, not only to the heavily constrained
SWML but also to the London Underground network serving Waterloo.
[0117] In summary of one embodiment of the invention, a rail network comprising through
trains from the south (Woking) serving both Heathrow and also running through the
airport to Paddington, with an interchange with Crossrail, is provided. In such a
way, network resources can be utilised more efficiently - in particular the shared
rail corridor portion east of the Heathrow Express airport junction can be better
utilised by commuter passengers using the same trains as airport passengers.
[0118] The transport network as envisaged herein provides a modal shift from road to rail
which reduces emissions and thus assists in meeting legally binding air quality limits.
[0119] The addition of rail connections 116 provides the facility to transport materials
and consumables (such as fuel, building materials and waste) to and from the airport
102. In the event of an airport expansion, there would be an increased need for fuel,
waste removal and building materials. A freight connection to an airport is more flexible,
and capacious for such goods compared to pipelines or road haulage. Such an airport
expansion would also bring an increased demand for passenger capacity so it is important
for the freight paths to provide additional capacity without displacing or otherwise
adversely affecting passenger-carrying paths.
[0120] The railway network described herein allows for trains to overtake one-another in-between
Reading and Paddington by way of a 'dynamic loop' at the hub station 112. This avoids
the need for designated overtaking train lines requiring trains to cross tracks. The
journey time impact of overtaking is potentially minimised as the Hub station layout
provides a "dynamic loop" in each direction, between Iver and West Drayton towards
London, and between Heathrow Hub and Iver towards Reading
[0121] The hub station's location is also well situated for this purpose - approximately
equidistant between Paddington (C1) and Reading (S1) - in one example 14 miles from
Paddington and 22 miles from Reading, with 7 stations towards Paddington and 7 towards
Reading.
[0122] A "Crossrail Express" train which does not stop at any such intermediate stations
will take only 8 - 10 minutes longer than current InterCity direct services from Reading,
and would be attractive for many Reading commuters, as it provides a direct service
to central London Crossrail stations, avoiding the need to interchange at Paddington.
Alternatives and modifications
[0123] Various other modifications will be apparent to those skilled in the art for example,
intermediate stations may be provided between any two stations depicted in Figures
1-6.
[0124] Furthermore, it should be appreciated that the hub station 112 may not be precisely
equidistant from stations S1 and C1. In one example it is approximately one third
to one half of the way from either station. This may be in terms of distance, time
taken, or number of intermediate stations (for example).
[0125] It will be understood that the present invention has been described above purely
by way of example, and modifications of detail can be made within the scope of the
invention.
[0126] Reference numerals appearing in the claims are by way of illustration only and shall
have no limiting effect on the scope of the claims.