Field of invention
[0001] The present invention relates to mooring and tensioning of mooring lines for floating
structures or vessels, such as Floating Production, Storage and Offloading vessels
(FPSO's), semi-submersible platforms, turret moored vessels, floating drilling rigs,
drilling ships and other floating structures which are moored to the seabed.
[0002] The invention is more specifically directed to a mooring arrangement and an installation
method.
Background of the invention
[0003] Structures and vessels that are supposed to stay moored at the same location for
a long time, such as months or years, have to be moored with a prescribed tension.
The traditional method is to use chain tensioning equipment on deck for pull-in and
tensioning. Normally this equipment is used during the installation period and left
on the vessel for a number of years without being used or maintained. When the mooring
lines slacken sufficiently over time, due to wear of chains, shifting of anchors,
creep in fiber mooring lines etc, the mooring lines have to be re-tensioned, repositioned
(typically move the chain one or two chain links in order to engage the chain stopper
on a new chain link) or replaced. In this period between installation and next operation,
the equipment has normally seized or corroded and requires refurbishment.
[0004] Another issue is the weight and deck space. Deck space is often limited and weight
on deck is an important factor for the stability of the vessel.
[0005] The aim of this patent application is to provide arrangements and methods where there
is little or no requirement for equipment on the deck of the vessel and still be able
to perform the installation, tensioning, re-tensioning, repositioning and replacement
operations.
[0006] US 2014/0216323 describes a mooring arrangement and a method of installing the mooring arrangement.
An anchor chain is attached to the seabed by an anchor. A submerged chain stopper
is attached to an upper end of the anchor chain. A pull chain or installation chain
extends from the structure to be anchored through the chain stopper. The lower end
of the installation chain is pulled upwards by the use of a winch on the support vessel
until the installation chain passes through the chain stopper, a prescribed tension
is achieved and the chain stopper engages on the permanent part of the mooring line,
here described as the work chain.
[0007] The main difference between the above mentioned patents are that the
US 2014/0216323 A1 may use a wire from a winch on the anchor handler towards the platform. By doing
this it is possible to tension the mooring line with a force based on the winch capacity.
The actual tension force will depend on factors such as angle of the mooring chain
with respect to the platform and the support vessel. If the mooring line is close
to vertical, the effect of this method is close to zero.
[0008] In these references, the arrangement and method are relied on pulling the installation
chain of the mooring chain vertically or close to vertically upwards to an installation
vessel in order to tension the chain. The benefit of both these systems is that there
is no chain and chain handling equipment on the deck of the FPSO. However, the main
disadvantages are that all mooring line tensioning requires an installation vessel
and fine tuning of each mooring line may be difficult. Additionally the installation
requires an additional length of installation chain.
[0009] US 2002/0189522 describes a similar arrangement and method as above.
[0010] WO 03/013950 also describes a similar mooring arrangement and method.
[0011] It is expensive to use an installation or support vessel every time a re-tensioning
of the mooring is required.
[0012] The vertical, or close to vertical, pulling of the chain will also pull the submerged
chain tensioner upwards, so that an obtuse angle is created between the chain below
the chain tensioner and the chain above the chain tensioner extending between the
anchor at the seabed and the moored structure, as can readily be seen in the figures
of the two references. The size of this angle will depend on several factors, such
as pulling tension, weight of the chain, friction in reversing pulley of the chain
tensioner, sea currents etc. Due to the angle, the length of chain between the anchor
and the floating structure is somewhat greater than the linear distance between the
anchor and the floating structure.
[0013] Especially if the anchor is at a great distance from the floating structure or the
water depth is small, the mooring line can extend at a very shallow angle from the
seabed. In such cases the pull to tighten the mooring can be almost at right angle
to the mooring line. This will result in the angle between the two parts of the mooring
line, below and above the chain tensioner, becoming smaller and thus the length of
the mooring line during tensioning will become far greater than the direct distance
between the anchor and the floating structure.
[0014] When the mooring has been tightened to the prescribed tension, the upper end of the
installation chain will be released. Hence, the chain tensioner will sink until it
finds itself approximately on the straight line between the anchor and the floating
structure. This inevitably leads to a slackening of the mooring. Hence, the mooring
must be tightened somewhat beyond the required tension to account for this slackening.
[0015] However, it is difficult to predict how much overtightening is required to achieve
the correct tension.
Objectives of the present invention
[0016] The present invention has as a main objective to avoid the problem of having to account
for a certain amount of overtightening when installing a mooring or re-tensioning
a mooring.
[0017] A further objective of the present invention is to provide an arrangement and method
for installation, tensioning and replacement of mooring lines where there is no requirement
for chain handling on the deck of the floating structure.
[0018] Tensioning can be performed from an installation vessel and in particular smaller
vessels due to multiplication of the tensioning force from the pulley arrangement.
The multiplication factor is close to 3 depending on actual angle and friction.
[0019] Additionally, a slightly longer work chain can be used instead of an installation
chain. An installation wire may act as the main part of the installation chain.
[0020] Yet another advantage of the invention is that the chain tensioning may be operated
from the FPSO by a wire, rope or hydraulic cylinder.
[0021] Another advantage of the present invention is that the weight of the excess top chain
is carried mainly by the hull bracket.
[0022] A further advantage of the invention is that half of the capacity of the mooring
line winch or installation vessel pull is required.
[0023] It is yet another advantage of the invention to provide an easy tensioning arrangement
for a floating structure with no requirement for chain handling on deck of the vessel
and which also requires less/minimum of the tensioning force.
[0024] It is yet another advantage of the invention that the tensioning can be performed
from an installation vessel or the moored unit, whichever most convenient.
Summary of the invention
[0025] The invention relates to a mooring tensioning arrangement for a floating structure
or vessel, comprising an anchor, a mooring line, a mooring tensioner and a working
line, said mooring tensioner having a tensioning pulley, said mooring line being attached
at a first end to said anchor and at a second end to said mooring tensioner, said
working line is adapted to be attached at a first end to said floating structure or
vessel and extending over said tensioning pulley, and said working line being attached
to a pulling unit at a second end, said pulling unit being remotely arranged from
the offshore structure; said working line having a first flight that extends between
said attachment to said floating structure or vessel and said tensioning pulley. The
invention being distinctive in that a second flight extends from said tensioning pulley
towards said pulling unit that said second flight of said working line is substantially
parallel to said first flight of said working line so that a tensioning force from
said pulling unit, acting upon said mooring line, does not pull said mooring line
out of a straight line between said anchor and said floating structure or vessel.
[0026] In this first aspect of the invention, the second flight of said working line may
extend over a fairlead pulley that is attached to said floating structure or vessel
close to, or at the same position as, said attachment of said first end of said working
line to said floating structure or vessel, so that said second flight of said working
line extends substantially parallel with said first flight between said tensioning
pulley and said fairlead pulley.
[0027] In an alternative of said first aspect of the invention, the pulling unit may be
situated close to said attachment of said first end of said working line to said floating
structure or vessel, so that said second flight of said working line extends substantially
parallel with said first flight between said tensioning pulley and said pulling unit.
[0028] In a second of these aspects of the mooring tensioning arrangement of the invention,
it comprises an anchor, a mooring line, a mooring tensioner and a pulling unit, said
mooring tensioner having a tensioning pulley, said mooring line being attached at
a first end to said anchor, which is characterized in that said mooring tensioner
is attached to said floating structure or vessel, and that said mooring line extends
over said tensioning pulley towards said pulling unit, so that said mooring line extends
substantially in a straight line between said anchor and said floating structure or
vessel while being tensioned.
[0029] In one embodiment, the mooring line or said working line may be coupled to a pull-line,
which in turn is coupled to said pulling unit.
[0030] In a further embodiment, said mooring tensioner comprises a chain stopper that is
adapted to lock said mooring line or said working line and prevent the same form moving
relative to said mooring tensioner.
[0031] The pulling unit is conveniently a winch on an installation vessel, said vessel and
its propulsion system or a winch on said floating structure or vessel.
[0032] In a third aspect the present invention relates to a method for tensioning a mooring
arrangement wherein the tensioning force that is imposed on said mooring line is directed
towards said floating structure or vessel.
[0033] In one embodiment said tensioning force is acting via a block and tackle configuration,
which multiplies the tensioning force on the mooring line.
[0034] The tensioning force is conveniently created by a pulling unit, which is a winch
on an installation vessel, said vessel and its propulsion system or a winch on said
floating structure or vessel.
[0035] In one embodiment of the mooring tensioning arrangement of the present invention
it comprises an anchor, a mooring line, a mooring tensioner and a working line, said
mooring tensioner having a tensioning pulley, said mooring line being attached at
a first end to said anchor and at a second end to said mooring tensioner, said working
line being attached at a first end to said floating structure or vessel and extending
over said tensioning pulley, and said working line being attached to a pulling unit
at a second end; said working line having a first flight that extends between said
attachment to said floating structure or vessel and said tensioning pulley. The invention
being distinctive in that a second flight that extends from said tensioning pulley
towards said pulling unit, said second flight of said working line is substantially
parallel to said first flight of said working line.
[0036] In another embodiment of the invention, the mooring tensioning arrangement for a
floating structure or vessel, comprising an anchor, a mooring line, a mooring tensioner
and a pulling unit, said mooring tensioner having a tensioning pulley, said mooring
line being attached at a first end to said anchor, characterised in that said mooring
tensioner is attached to said floating structure or vessel, and that said mooring
line extends over said tensioning pulley towards said pulling unit, so that said mooring
line extends substantially in a straight line between said anchor and said floating
structure or vessel while being tensioned, so that a tensioning force from said pulling
unit, acting upon said mooring line, does not pull said mooring line out of a straight
line between said anchor and said floating structure or vessel.
Brief description of the drawings
[0037] The foregoing features of the invention will be more readily understood by reference
to the following detailed description taken with reference to the accompanying drawings.
Figure 1 shows a tensioning system of the invention in a first aspect and a first
embodiment,
Figure 2 shows a tensioning system of the invention in a first aspect and a second
embodiment,
Figure 3 shows a mooring system that has been tensioned according to the invention
after the tensioning has been completed in a first configuration,
Figure 3a shows a mooring system that has been tensioned according to the invention
after the tensioning has completed in a second configuration,
Figure 4 shows a mooring tensioner to be used in the present invention with a chain
passing through,
Figure 4a shows a mooring tensioner to be used in the present invention with a wire
or rope passing through,
Figure 5 shows a fairlead of the present invention in a first embodiment,
Figure 6 shows a fairlead of the present invention in a second embodiment,
Figure 7 shows a fairlead of the present invention in a third embodiment,
Figure 8 shows a fairlead of the present invention in a fourth embodiment,
Figure 9 shows a first step in a first embodiment of a method of tensioning according
to the present invention,
Figure 10 shows a second step in a first embodiment of a method of tensioning according
to the present invention, where a mooring tensioner has been attached to the mooring
line,
Figure 11 shows a third step in a first embodiment of a method of tensioning according
to the present invention, where a pendant is about to be coupled to a working line,
Figure 12 shows a fourth step in a first embodiment of a method of tensioning according
to the present invention, where the working line and pull-in line has been deployed
into the sea,
Figure 13 shows a fifth step in a first embodiment of a method of tensioning according
to the present invention, where a pull-in line is about to be coupled to a winch on
board the installation vessel,
Figure 14 shows a sixth step in a first embodiment of a method of tensioning according
to the present invention, where the pull-in line has been coupled to the winch on
board the installation vessel,
Figure 15 shows a seventh step in a first embodiment of a method of tensioning according
to the present invention, where the pull-in line is tensioned and thereby tensioning
the mooring,
Figure 16 shows a first step in a second embodiment of a method of tensioning according
to the present invention,
Figure 17 shows a second step in the second embodiment of a method of tensioning according
to the present invention, where a mooring line has been brought up to the installation
vessel and a working line has been coupled to the floating installation,
Figure 18 shows a third step in the second embodiment of a method of tensioning according
to the present invention, where a pull-in line has been connected between a winch
on the floating installation and the installation vessel,
Figure 19 shows a fourth step in the second embodiment of a method of tensioning according
to the present invention, where a mooring tensioner has been connected to the mooring
line,
Figure 20 shows a fifth step in the second embodiment of a method of tensioning according
to the present invention, where the mooring tensioner, working line and pull-in line
has been deployed to the sea,
Figure 21 shows a sixth step in the second embodiment of a method of tensioning according
to the present invention, where the pull-in line is about to be tensioned,
Figure 22 shows a seventh step in the second embodiment of a method of tensioning
according to the present invention, where the pull-in line and the working line is
tensioning the mooring line, using a winch on the floating structure,
Figure 23 shows the mooring after completing the tensioning using the second embodiment
of a method of tensioning according to the present invention, where
Figure 24 shows a cluster of moorings, with a first mooring completed, a second mooring
about to be tensioned and a third mooring yet not installed,
Figure 25 shows a close-up of the upper parts of the moorings in figure 24 and a tensioning
winch,
Figure 26 shows an alternative mooring tensioner,
Figure 27 shows a tensioning arrangement according to a second aspect of the present
invention,
Figure 28 shows a first step in a first installation method for installing a tensioning
arrangement according to the second aspect of the present invention,
Figure 29 shows a second step in the first installation method for installing a tensioning
arrangement according to the second aspect, where a pull-in line is about to be coupled
to the mooring line and a winch,
Figure 30 shows a third step in the first installation method for installing a tensioning
arrangement according to the second aspect, where the pull-in line is about to be
deployed to the sea,
Figure 31 shows a fourth step in the first installation method for installing a tensioning
arrangement according to the second aspect, where the pull-in line is being tensioned,
Figure 32 shows a first step in a second installation method for installing a tensioning
arrangement according to the second aspect,
Figure 33 shows a second step in the second installation method for installing the
tensioning arrangement according to the second aspect, where a pull-in line has been
coupled between two winches on the installation vessel,
Figure 34 shows a third step in the second installation method for installing the
tensioning arrangement according to the second aspect, where a mooring line has been
coupled to one of the winches,
Figure 35 shows a forth step in the second installation method for installing the
tensioning arrangement according to the second aspect, where the pull-in line and
the mooring line has been connected, and
Figure 36 shows a fifth step in the second installation method for installing the
tensioning arrangement according to the second aspect, where the pull-in line is being
tensioned.
Detailed description of embodiments of the invention
[0038] Figure 1 shows a mooring arrangement of the present invention installed between an
anchor 2 that has been attached to the seabed 1 and a floating structure, such as
an FPSO 11. How the installation has been achieved will be explained in detail later.
[0039] The anchor 2 is conveniently a suction anchor, but may alternatively be any type
of anchor known in the field.
[0040] The mooring arrangement further comprises a mooring chain 3, a chain tensioner 4
with pulley 20, a working chain 5, a pendant line 6, a hull bracket 33, a fairlead
7 and a pull-in wire 8.
[0041] The mooring chain 3 may also be a steel wire, polyester rope or a combination of
these and the working chain 5 and pendant 6 may also be a mooring chain, steel wire,
polyester rope or a combination of these. The working chain 5 may also extend all
the way to the fairlead 7. The installation wire 8 may be steel wire, polyester rope
or a combination. It may comprise several segments of these.
[0042] Conveniently, the fairlead 7 is attached to the hull bracket 33 and the fairlead
7 may rotate about a vertical axis.
[0043] As seen in figure 1, the mooring chain extends between the anchor 2 and the chain
tensioner 4. The pendant wire 6 is attached to the fairlead 7 at an upper end. The
lower end of the pendant wire 6 is attached to the working chain 5. The working chain
5 extends around the pulley 20 of the chain tensioner 4 and is at the opposite end
of the pendant wire 6 attached to the pull-in wire 8.
[0044] The pull-in wire also called installation wire 8 extends around a pulley 22 in the
fairlead 7 and further to a winch 10 on a support or installation vessel 9.
[0045] Figure 2 shows an alternative mooring arrangement. It is similar to the arrangement
of figure 1 except that the installation wire 8 extends to a winch 13 on the floating
structure 11 instead of to a winch on a support vessel. A pulley 12 mounted at the
edge of the deck of the floating structure 11 ensures proper guiding of the installation
wire 8. Alternatively, the winch 13 may be located on the edge of the deck with the
pull-in wire 8 extending directly downwards. In this case the pulley 7 is not required,
as shown and explained in connection with figure 22.
[0046] The arrangements of figures 1 and 2 may be used as alternatives, but they may also
be used in stages, where the first part of the tensioning is done with the arrangement
of figure 1 and the installation wire 8 is then transferred to the winch 13 on the
floating structure 11 so that the final tensioning is done with the arrangement of
figure 2. This is especially convenient when the final tensioning has to be done after
all the moorings have been installed.
[0047] Figure 3 shows the mooring arrangement after the tensioning has been completed. The
installation wire 8 will then typically be removed and figure 3 shows that the installation
wire 8 has been detached from the working chain 5 and removed.
[0048] Figure 3a shows an alternative to removing the installation wire 8. Here a part 8a
of the installation wire has been left as a non-tensioned length.
[0049] Figure 4 shows the chain tensioner 4 in detail. Although it acts as the main component
during the tensioning of the mooring, it also includes a chain stopper 16, which has
the function locking the two mooring line parts together to maintain a specific length.
[0050] The chain tensioner 4 comprises a steel structure 14 that solid enough to act as
a member of the mooring line and as such can withstand at least the same Minimum Breaking
Load (MBL) as the mooring chain 3. The structure 14 has a channel 14a through which
the working chain 5 can pass. At one end the structure 14 is connected to the mooring
line 3 with a connecting bolt 15 or alternatively shackle. Any kind of connecting
links, shackles or other connecting elements may be used.
[0051] At the other end where the working chain 5 enters the channel 14a of the structure
14 there is a chain stopper 16. The chain stopper 16 is shown with a single latch
16a but may consist of two latches, as is known per se. The latch 16a is connected
to a spring 19 that biases the latch 16a towards a closed position, to ensure safe
closing of the latch 16a. Additionally, there may be a temporary installed hydraulic
cylinder 18, which is capable of opening the latch 16a if the chain has to be paid
out. The hydraulic cylinder 18 may be operated from the installation vessel 9 or an
ROV (not shown). After the tensioning is finished, the hydraulic cylinder 18 is preferably
removed to avoid fouling and corrosion due to prolonged exposure to sea water.
[0052] At the upper end, i.e. towards the floating structure or FPSO 11 there is a guide
17 to guide the working chain 5 into the channel 14a.
[0053] The chain tensioner 4 also has a chain tensioner pulley 20 that is rotatable about
a shaft 21 that is mounted in the structure 14. The purpose of the chain tensioner
pulley 20 is to guide the working chain 5 out of the chain tensioner 4 and back towards
the fairlead 7.
[0054] In Figure 4A, the same chain tensioner 4 is shown as in figure 4 but with the installation
wire 8 running through the channel 14a, as will be the case during the installation
phase. The latch 16a is open at this stage.
[0055] Figure 5 shows the hull bracket 33 and the fairlead 7. The fairlead that comprises
a steel structure 26 and a pulley 22. The hull bracket 33 comprises a lower hull support
27 and an upper hull support 28. A vertical shaft 29 connects the steel structure
with the supports 27, 28, so that the structure 26 can rotate about a vertical axis.
[0056] At the outer end of the structure 26 the pendant wire 6 is attached by means of a
connection bolt 24 that attaches an end termination 23 of the pendant wire to the
structure 26. The end termination 23 can rotate about the bolt 24 in a vertical plane.
[0057] The fairlead pullet 22 is rotatably supported in the structure 26 by a shaft 25.
The structure 26 has a channel 26a that receives the installation wire 8, which extends
about the fairlead pulley 22.
[0058] The hull bracket 33, structure 26 and shaft 24 and 29, all these elements are part
of the mooring load line and has to be strong enough to carry the mooring load.
[0059] An alternative fairlead construction can be seen in Figure 6. Here the steel structure
26 is welded to the hull and is not capable of rotating in a horizontal plane as in
Figure 5. Instead, a connecting link 30 with a vertical shaft 31 has been added between
the end termination 23 and the bolt 24, to endure free movement in two planes for
the pendant 6.
[0060] A further another alternative solution for the fairlead construction is shown in
Figure 7. As for the previous embodiments, the pendant 6 with end termination 23 is
connected to the steel structure 26 via a shaft 24. However, the steel structure 26
is connected to the hull via a bracket 33 and a connecting link 30. Two shafts 31,
32 ensures freedom of movement in two planes.
[0061] In the alternative embodiment of Figure 8, the connecting link 30 and shaft 32 has
been replaced by a connector comprising a male part 34 and a female part 35, the female
part 35 being capable of retaining the male part 34 within a hole (not shown) in the
female part 35. The female part 35 is rotatable about a horizontal axis with respect
to the bracket 33.
[0062] A rope or wire 36 is initially connected at the end of the male part 34. The rope
or wire 36 is fed through the hole in the female part, and by pulling the rope or
wire 36, the male part 34 can be brought to enter the hole of the female part 35.
[0063] The male connector 34 and female connector 35 will engage automatically or with the
intervention of ROV, a diver or by other mechanic means, depending on the environment.
[0064] The pendant 6 may in some cases be replaced by extending the working chain 5.
[0065] In some cases, the pendant 6 or working chain 5 may be fixed directly to the hull
of the floating structure 11 by a bolt through a bracket. In such a case the pulley
22 may be arranged separately of the attachment of the pendant 6 or working chain
to the hull.
[0066] The arrangement of the present invention has the benefit that the feeding of the
pull-in line 8 over the pulleys 20 and 22 ensures both that the mooring line 3 and
working chain 5 are in the same line and extends directly between the anchor 2 and
the floating structure 11, and due to the fact that the system has the configuration
of a block and tackle, the tensioning of the mooring arrangement can be done with
double tension force by the winch 10 or 13 as compared to the prior art configurations.
[0067] In the case where the installation wire 8 is connected to the pull-in winch 10 on
the installation vessel the tensioning can be done both by rotating the winch and
by moving the installation vessel 9 relative to the floating structure 11. This will
provide the possibility of achieving a much higher tension force than the winch can
achieve alone. Instead of using the winch 10 as the point of attachment of the pull-in
line 8 on the support vessel 9, the installation line 8 can also be attached to the
vessel 9 itself. This way a vessel 9 without a powerful winch can also be used to
tension the mooring.
[0068] An installation sequence according to the invention will now be described, referring
to figures 9-15.
[0069] During the installation, a number of additional ropes, wires and winches than described
above are typically used. These items will be described below.
[0070] Figure 9 shows the FPSO 11 at the start of the installation of the mooring arrangement.
The pendant line 6 is connected to the fairlead 7,a forerunner 8a of the installation
wire 8 has been passed through the fairlead pulley 22. The installation vessel 9 or
specialized anchoring vessel 2 has installed the anchor at the seabed. Typically,
the mooring chain 3 has been left on the seabed attached to a rope 37 with a buoy
(not shown) at the free end.
[0071] In figure 9 the buoy and rope 37 has been picked up and the winch 10 of the vessel
9 is pulling in the mooring line 3.
[0072] In Figure 10, the chain tensioner 4 has been attached to the mooring line and the
pull-in line 8 has been fed through the chain tensioner 4. The installation line 8
has the working chain 5 attached to the training end. The free end of both the pull-in
line 8 and the working chain 5 are on board the vessel 9, with the free end of the
installation line connected to the winch 10, and the free end of the working chain
5 is fixed to the installation vessel 9, typically in shark jaws (not shown).
[0073] The installation winch 10 on the installation vessel 9 now pays out and lowers the
chain tensioner 4 to reduce the tension in the mooring line 3. This operation conveniently
takes place at a safe distance from the FPSO 11.
[0074] In Figure 11, the installation vessel 9 has moved closer to the FPSO 11. When close
enough the free end pendant 6, which has been kept on board the FPSO, is transferred
to the deck of the installation vessel 9. This free end is connected to the working
chain 5.
[0075] In Figure 12, the pendant 6 and the working chain 5 is lowered from the installation
vessel 9 using a wire 37 that is connected to the winch 10 at one end and at the connection
point between the working chain and the installation line 8 at the other end. The
upper end of the installation line 8 has now temporarily been attached to the vessel
9. During the lowering of the connection point between the working chain 5 and the
pull-in line 8, the installation vessel 9 moves away from the FPSO 11.
[0076] As shown in Figure 13, both ends of the forerunner 8a are transferred from the FPSO
11 to the installation vessel 9. The lower end of the forerunner 8a, i.e. the end
that had been fed downwards through the fairlead 7, is connected with the upper end
of the installation wire 8, that extends upwards from the chain tensioner 4. The other
end of the forerunner, i.e. that extends upwards from the fairlead 7, is connected
to the installation winch 10. Figure 14 shows the pull-in wires 8 and the forerunner
8a connected.
[0077] As shown in Figure 15, the wire 37 has been detached, and the forerunner 8a has been
wound in so that the installationline 8 has reached the winch 10. The connection between
the working chain 5 and the installation line 8 has passed through the chain tensioner
4. Tensioning is now in progress by the installation winch 10 on the installation
vessel 9 or alternatively by the installation winch 13 on the FPSO 11.
[0078] As stated above, after final tensioning has been completed, the installation wire
8 is usually removed, as shown in figure 3. The installation winch 13 on the FPSO
11 may also be removed. Alternatively, a short part of the installation wire 8 may
be left for further work on the mooring line, as shown in Figure 3A.
[0079] An alternative installation method according to the present invention will now be
explained, referring to Figures 16-21.
[0080] The main difference between this installation method and the one described above
is that in the following all the tensioning of the mooring line 3 is performed from
the FPSO 11.
[0081] Figure 16 shows the FPSO 11 with the installation winch 13, a hull bracket 33, which
in this case is mounted close to the deck of the FPSO, for the work chain 5 or pendant
6 and the installation vessel 9 with the installation winch 10. This is the initial
state of the installation operation.
[0082] In Figure 17, the mooring line 3 has been pulled up from the seabed and locked on
the deck of the installation vessel 9. The installation of the anchor and retrieval
of the mooring line 3 is done in the same way as explained above with regard to figure
9. The free end of the pull-in wire 8 has been transferred to the installation vessel
9 and connected to the work chain 5 and is being pulled over towards the FPSO 11 using
the winch 13.
[0083] In Figure 18, the working chain 5 has been connected to the hull bracket 33 with
a bolt, shackle, H-link or any kind of connecting link. The other end of the working
chain 5 is fixed to the installation vessel 9.The installation wire 8 is connected
to one end of a forerunner 8a that has its opposite end attached to the vessel 9.
[0084] In Figure 19, the mooring line 3 is connected to one end of the chain tensioner 4,
which is resting on the deck of the installation vessel 9. The position of the mooring
chain 3 is arbitrary as it will most likely be coming in from the stern of the vessel
9. The forerunner 8a is pulled over the pulley 20 of the chain tensioner 4, through
the chain stopper 16, and is then connected to the working chain 5. The chain tensioner
4 is now ready to be deployed into the sea.
[0085] In Figure 20 the chain tensioner 4 together with the mooring line 3, working chain
5, installation line 8 and forerunner 8a are lowered from the installation vessel
9 with the installation winch 10 with a wire 37 that is attached to the chain tensioner
4.
[0086] In Figure 21, the installation winch 13 is pulling in the working chain 5 through
the chain tensioner 4 to tension the mooring line 3.
[0087] In Figure 22, the installation vessel 9 has disconnected from the chain tensioner
pulley 4 and final tensioning is performed by the winch 13 on board the FPSO 11. All
of the pull-in wire 8 is now on the drum of the winch 13 when final tension is achieved.
[0088] Figure 23 shows the finished mooring. The forerunner 8a has been attached at its
upper end to the FPSO for further tensioning operations if required. This line may,
however, be removed. The installation winch 13 has also been removed.
[0089] As an alternative to using a two-part installation wire 8, 8a, only one may be used.
This requires disconnection of the pull-in wire 8 from the working chain 5 after the
tensioning operation.
[0090] Figure 24 shows a cluster for three mooring lines. One has already been installed
and tensioned, and the second is under tensioning and a third mooring has not yet
been initiated. The installation winch 13 on the FPSO 11 is fixed in one position
and can handle all mooring lines from this position.
[0091] Figure 25 is a close-up of the mooring line interface to the FPSO 11. The installation
winch is fixed in one position. An auxiliary winch 38 may be used for pulling in the
working chain 5 during the initial stages of the operation. This auxiliary winch 38
can be moved to suitable positions each hull bracket 33. The figure shows that the
forerunner 8a is fixed to a hull bracket 33.
[0092] Figure 26 shows a modified version of the chain tensioner 4 as compared with Figure
4 and 4A. Here a lifting yoke 39 has been added for lifting or holding the chain tensioner
4 by a wire 37 from the installation vessel 9. Conveniently, the lifting yoke 39 is
rotatably attached to the chain tensioner 4 at a common rotation axis with the pulley
21. This ensures that the chain tensioner 4 does not rotate if the pulling force from
the wire 37 or the working chain 5 changes.
[0093] Another alternative configuration can be seen in Figure 27 where the chain tensioner
4 has been attached to the FPSO 11 via the hull bracket 33 possibly via a link or
shackle.
[0094] In this embodiment, the vessel 9 installs and tensions the mooring line 3 via a pull-in
wire (8) that at one end is connected to the winch 10 or a fixed point on the vessel
9. In the latter case, the mooring is tensioned using the bollard pull of the vessel
9.
[0095] A typical installation method for this embodiment will be explained referring to
Figures 28-31.
[0096] In Figure 28, the chain tensioner 4 has been installed with a forerunner 38 passing
through it. The vessel 9 is pulling up the mooring line 3 from the seabed, which has
been installed as explained in connection with figure 9 above.
[0097] In Figure 29, the vessel 9 has already pulled the mooring line 3 to the deck and
attached a hook 39 to the mooring line 3. The hook 39 is attached to a wire 37 running
from the winch 10 and the mooring line 3 has been lowered. As the vessel 9 moves closer
to the FPSO 11 while the winch 10 pays out the wire 37 to reduce the tension in the
mooring line 3. The forerunner 38 is passed from the FPSO 11 and connected to another
winch 10a at one end, i.e. the end on the upper side of the chain tensioner 4. The
other end, i.e. the end on the lower side of the chain tensioner 4 is connected to
the upper end of the pull-in wire 8.
[0098] In Figure 30 the vessel 9 has moved away from the FPSO 11, the forerunner 38 has
been pulled onto to the winch 10a and the mooring line 3 is being held by the first
winch 10 via the wire 37 and hook 39.
[0099] In Figure 31, the hook 39 and wire 37 has been disconnected. Tension is now on the
pull-in wire 8 and mooring line 3 via the chain tensioner 4. The pull-in line 8 is
pulled in until the upper end of the mooring chain 3 has passed through the chain
tensioner 4, as shown in figure 27, which represent the final tensioning. After final
tensioning, the installation wire 8 is disconnected from the mooring line 3.
[0100] An further alternative method to the one described in Figures 28-31 can be seen in
Figures 32-36.
[0101] In Figure 32, the vessel 9 approaches the FPSO 11. On the FPSO 11 the chain tensioner
4 is attached to the FPSO 11 via a hull bracket 33 via a possible link, shackle or
shaft. A forerunner 38 has been installed through the chain tensioner 4.
[0102] In Figure 33, the vessel 9 moves closer to the FPSO 11 and both ends of the forerunner
38 are transferred to the vessel 9. One end of the forerunner 38, i.e. the end emerging
from the lower side of the chain tensioner 4, is connected to the installation wire
8. The installation wire 8 is spooled onto the winch 10. The other end of the forerunner
38, i.e. the one emerging from the upper side of the chain tensioner 4, is connected
to another winch 10a. By paying out the installation wire 8 and pulling in on the
other winch 10a, the pull-in line passes through the chain tensioner 4.
[0103] In Figure 34, the vessel 9 moves away from the FPSO 11 while paying out the pull-in
wire 8. The mooring line 3 is pulled up from the seabed with a wire 37 and the winch
10. The mooring line 3 and anchor 2 has been installed, and the mooring line 3 has
been retrieved as explained above in connection with figure 9.
[0104] In Figure 35, the vessel 9 has already pulled the mooring line 3 to the deck and
attached a hook 39 to the mooring line 3. The hook 39 is attached to a wire 37 running
from the winch 10 and the mooring line 3 has been lowered. The installation wire 8
has been attached at one end to the mooring line 3 and the mooring line 3 is in the
process of being tensioned by the winch 10 by pulling the installation line 8.
[0105] In Figure 36, the hook 39 and wire 37 has been disconnected, tension is now on the
installation wire 8 and mooring line 3 via the chain tensioner 4. The tensioning will
continue until the upper end of the mooring line 3 has passed through the chain tensioner
4.
[0106] Final tensioning can be done as shown and described in connection with Figure 27.
After final tensioning, the installation wire 8 is disconnected from the mooring line
3, as explained above.
[0107] It is to be understood that the present invention is not to be limited by the embodiments
of the invention described herein. Indeed, those skilled in the art will readily understand
that various modifications and embodiments of the invention may be made and practiced
without departing from the scope of the invention.