Technical Field
[0001] The present invention relates to a work vehicle including: work equipment that is
provided with a rotation member whose proximal end portion is coupled to a rotatable
support shaft member; a cabin disposed on one side of the work equipment; and a storage
part disposed on the other side of the work equipment, and particularly relates to
an installation and removal configuration for the support shaft member as exemplified
by a cylinder fulcrum pin that is disposed in the same plane as a floor member of
the cabin or disposed in a position lower than the floor member.
Background Art
[0002] A work vehicle such as a backhoe conventionally includes a rotating platform that
is supported on crawler-type traveling devices in such a manner that the rotating
platform is rotatable left and right; a cabin disposed in one side region on the rotating
platform, the cabin including a driver seat, various manipulation levers, a floor
member, and the like; a storage part disposed in the other side region, the storage
part storing a fuel tank, an oil tank, and the like; and work equipment provided between
the storage part and the cabin, the work equipment including a boom, an arm, a bucket,
and a cylinder configured to extend and retract for vertical and rotational movement
of the boom, the arm, and the bucket (see PTL 1, for example).
[0003] In the work equipment, a boom cylinder is provided so as to extend from left and
right vertical plates (hereinafter referred to as "cylinder brackets") standing on
the rotating platform to a distal end portion of the boom. A cylindrical body to which
a proximal end portion of the boom cylinder is secured is, in general, fitted onto
a pivot (hereinafter referred to as "cylinder fulcrum pin") that is rotatably and
horizontally laid between the cylinder brackets, so that the boom cylinder is provided
on the rotating platform in a vertically rotatable manner. Extension and retraction
of a piston rod of the boom cylinder causes vertical and rotational movement of the
boom which is rotatably coupled to the distal end of the cylinder rod.
Citation List
Patent Literature
[0004] PTL 1: Japanese Patent Application Laid-Open No.
2013-234470
Summary of Invention
Technical Problem
[0005] To pull the cylinder fulcrum pin out of the cylindrical body for replacement of the
cylinder fulcrum pin or detachment of the work equipment, insertion or extraction
of the cylinder fulcrum pin needs to be implemented after component parts disposed
on the cabin side are removed, because a fuel tank, an oil tank, and the like, which
should be handled with caution, are stored on the storage part side. This also raises
a problem that a working time taken for the replacement work and the detachment work
is prolonged and a burden on an operator is increased.
[0006] Particularly in a case where the cylinder fulcrum pin is disposed in the same plane
as the floor member of the cabin or disposed in a position lower than the floor member
due to the necessity to dispose the boom cylinder below an anterior surface of the
boom in order that the distal end of the cylinder rod can be coupled to the anterior
surface of the boom; a problem arises that the floor member which constitutes a lower
part of the cabin has also to be removed, which further prolongs the working time
taken for the detachment work and the replacement work, resulting in an increased
burden on an operator.
Solution to Problem
[0007] Problems to be solved by the present invention are as above, and solutions to the
problems will now be described.
[0008] In a first aspect, a work vehicle includes: work equipment including a rotation member
whose proximal end portion is coupled to a rotatable support shaft member; a cabin
disposed on one side of the work equipment; and a storage part disposed on the other
side of the work equipment, wherein a work hole is opened that extends from a side
wall of the cabin on the work equipment side to a floor member, and the support shaft
member is installable and removable through the work hole by inserting and extracting
the support shaft member from the cabin side into and out of a cylindrical body to
which the proximal end portion is fixed.
[0009] In a second aspect, the work hole may include a vertical opening portion and a lateral
opening portion, the vertical opening portion being formed by notching a bottom edge
portion of the side wall, the lateral opening portion being formed by notching a side
edge portion of the floor member, the lateral opening portion communicating with the
vertical opening portion; and a working space may be provided below the lateral opening
portion, the working space allowing the support shaft member to be inserted and extracted
in a tilted posture from the cabin side.
[0010] In a third aspect, an in-cabin apparatus disposed close to the work hole may be provided
with a moving mechanism configured to move the in-cabin apparatus in a direction of
opening the work hole.
Advantageous Effects of Invention
[0011] The present invention, which is configured as above, exerts the following effects.
[0012] According to the first aspect, at a time of replacing the support shaft member of
the work equipment or detaching the work equipment, the work hole may provide easy
access to the support shaft member from the cabin side without needing to remove either
the storage part or the cabin, and thereby installation and removal can be implemented,
thus shortening a working time taken for the replacement work or the detachment work
and reducing a burden on an operator. The shortening of the working time and the reduction
in the burden on the operator can more considerably obtained particularly when compared
to a case where the floor member of the cabin also needs to be removed because the
support shaft member is disposed in the same plane as the floor member of the cabin
or disposed in a position lower than the floor member.
[0013] According to the second aspect, even if a sufficient working space cannot be ensured
on the side wall side, the working space provided below the floor member may be used
for insertion and extraction of the support shaft member which is elongated. This
may allow applications to various specifications of the work equipment.
[0014] According to the third aspect, even in a case where the in-cabin apparatus disposed
close to the work hole makes access to the work hole difficult, the in-cabin apparatus
can be easily removed from a front of the work hole, thus enabling further improvement
in workability for various works including the replacement work of replacing the support
shaft member, the detachment work of detaching the work equipment, and the like.
Brief Description of Drawings
[0015]
[FIG. 1] A left side view showing an overall configuration of a backhoe according
to the present invention.
[FIG. 2] A front elevational view of the same.
[FIG. 3] A plan view of the same.
[FIG. 4] A perspective view when viewed from the cabin side toward the tank unit side.
[FIG. 5] A perspective view showing a boom shaft part, a cylinder shaft part, and
therearound.
[FIG. 6] A perspective view of a right side wall and therearound, in a case where
a unit body of an indoor unit of an air conditioner is in its initial position.
[FIG. 7] A perspective view of the right side wall and therearound, in a case where
the unit body of the indoor unit of the air conditioner is rotated leftward about
a front-rear shaft center.
[FIG. 8] A left side view of a work hole for a boom fulcrum pin.
[FIG. 9] A partial cross-sectional rear view with the boom fulcrum pin attached.
[FIG. 10] A partial cross-sectional side view with an anti-rotation pin attached.
[FIG. 11] Partial cross-sectional rear views with the boom fulcrum pin being taken
out of a cylindrical body, of which FIG. 11(a) is a partial cross-sectional rear view
of the boom fulcrum pin from which the anti-rotation pin is extracted, and FIG. 11(b)
is a partial cross-sectional rear view of the boom fulcrum pin being inserted to or
extracted from a cylindrical body.
[FIG. 12] A perspective view of the right side wall and therearound, in a case where
the unit body of the indoor unit of the air conditioner is rotated rearward about
a vertical shaft center.
[FIG. 13] A perspective view of a work hole for a cylinder fulcrum pin.
[FIG. 14] A partial cross-sectional rear view with the cylinder fulcrum pin attached.
[FIG. 15] Partial cross-sectional rear views with the cylinder fulcrum pin being taken
out of the cylindrical body, of which FIG. 15(a) is a partial cross-sectional rear
view of the cylinder fulcrum pin from which an anti-extraction pin is extracted, and
FIG. 15(b) is a partial cross-sectional rear view of the cylinder fulcrum pin being
inserted to or extracted from the cylindrical body.
Description of Embodiments
[0016] In the following, an embodiment of the present invention will be described in detail.
A direction indicated by an arrow F in FIG. 1 is defined as a frontward direction
of a backhoe 1 serving as a work vehicle, and a direction indicated by an arrow R
in FIG. 2 is defined as a rightward direction of the backhoe 1. Positions, directions,
and the like, of members in the following description are based on these frontward
and right directions.
[0017] First, an overall configuration of the backhoe 1 according to the present invention
will be described based on FIG. 1 to FIG. 3.
[0018] The backhoe 1, which is a rotating-type work vehicle, includes: a traveling unit
2 having a pair of left and right crawler-type traveling devices 6; a machine body
3 that is supported on a base platform 15 provided in a center portion above the traveling
unit 2 in such a manner that the machine body 3 is rotatable left and right; excavator
equipment 4 that is attached to a substantially center portion of the machine body
3 with respect to the lateral (left-right) direction; and an earth removing device
5 that is attached to a front portion of the crawler-type traveling devices 6.
[0019] In the machine body 3, a cabin 8 that covers a driving operation unit 10 including
a driver seat 11, various manipulation levers 12, and the like, is disposed in one
side portion, which means a left side portion in this example, above a rotating platform
7 that is provided on the base platform 15 so as to be rotatable left and right, while
the excavator equipment 4 and a tank unit 9 arranged in this order from the left are
disposed to the right of the cabin 8.
[0020] An engine 13 is mounted in a region extending from the rear side of the excavator
equipment 4 to a rear portion of the cabin 8. The rear, left, and right sides of the
engine 13 are covered by a hood 14. The tank unit 9 houses a fuel tank 9a for the
engine 13 and an oil tank 9b of a hydraulic oil for the excavator equipment 4 and
the earth removing device 5.
[0021] The excavator equipment 4 includes: a first boom 20 attached to the rotating platform
7 in a vertically rotatable manner; a second boom 21 attached to a distal end portion
of the first boom 20 in a laterally rotatable manner; a third boom 22 attached to
the second boom 21 in a laterally rotatable manner; an arm 23 attached to the third
boom 22 in a vertically rotatable manner; and a bucket 24 serving as a working attachment
attached to the distal end of the arm 23, the excavator equipment 4 being configured
to allow the arm 23 and the bucket 24 to be laterally offset by lateral rotation of
the second boom 21.
[0022] The first boom 20 is capable of vertical and rotational movement by extending and
retracting a boom cylinder 25. The arm 23 is capable of vertical and rotational movement
by extending and retracting an arm cylinder 26. The bucket 24 is capable of vertical
and rotational movement by extending and retracting a bucket cylinder 27.
[0023] The second boom 21 has its lower end portion coupled to an upper end portion of the
first boom 20 in a laterally rotatable manner. The second boom 21 has its upper end
portion coupled to a lower end portion of the third boom 22 in a laterally rotatable
manner. An offset cylinder 28 is interposed between the first boom 20 and the second
boom 21. An offset rod 29 is provided so as to extend between the first boom 20 and
the third boom 22.
[0024] Extension and retraction of the offset cylinder 28 causes the third boom 22 to be
eccentric relative to the first boom 20, thus obtaining lateral offset thereof. In
this case, the offset is obtained while the angle formed between the first boom 20
and the third boom 22 is unchanged and they are kept in parallel.
[0025] The earth removing device 5 includes: a pair of left and right blade arms 16, 16
extending in a front-rear direction and provided between the pair of left and right
crawler-type traveling devices 6, the pair of left and right blade arms 16, 16 having
their respective proximal end portions coupled to the base platform 15 in a vertically
rotatable manner; and a blade 17 extending in a lateral direction and provided between
distal end portions of the respective blade arms 16, 16. Furthermore, a blade cylinder
18 is interposed between the base platform 15 and a substantially center portion of
the blade 17 with respect to the lateral direction in such a manner that the blade
cylinder 18 is extendable and retractable so that the blade 17 is vertically swingable.
[0026] In such a configuration, the driving operation unit 10 operates the traveling unit
2 to travel in translation in the front-rear direction and travel in rotation in the
left-right direction, operates the excavator equipment 4 to perform an excavating
work, and operates the earth removing device 5 to perform an earth removing work.
[0027] Next, an attachment configuration between the first boom 20 and the boom cylinder
25 of the excavator equipment 4, and the like, will be schematically described based
on FIG. 4 to FIG. 7, FIG. 9, and FIG. 14.
[0028] The first boom 20 has its proximal end portion 20a coupled to a boom shaft part 30,
and the boom shaft part 30 is horizontally laid between a left covering 32a of the
tank unit 9 and a right side wall 8a of the cabin 8.
[0029] The left covering 32a is a member forming a left side surface part of a covering
body 32 that covers the tank unit 9. A left vertical plate 33 and a right vertical
plate 34, which are arranged side by side with the left covering 32a interposed therebetween,
are provided on left and right side surfaces of the left covering 32a such that their
plate surfaces are oriented in the lateral direction. The left vertical plate 33 and
the right vertical plate 34 are arranged so as to fixedly stand on a rotating basal
plate 35 which constitutes a lower part of a frame unit of the rotating platform 7.
The left vertical plate 33 and the right vertical plate 34 are configured to rotatably
and tightly support a right end portion of the boom shaft part 30.
[0030] The right side wall 8a, which is a member constituting a lower half of a right side
surface of the cabin 8, includes a first covering 37 provided on the tank unit 9 side
and a second covering 38 provided on the cabin 8 side, both of which are arranged
so as to stand on a plate-like floor member 39 of the driving operation unit 10. A
vertical plate 36 which is a separate piece is incorporated in a gap between the first
covering 37 and the second covering 38, such that its plate surfaces are oriented
in the lateral direction. The vertical plate 36 as well as the left vertical plate
33 and the right vertical plate 34 is arranged so as to fixedly stand on the rotating
basal plate 35. The vertical plate 36 is configured to rotatably and tightly support
a left end portion of the boom shaft part 30.
[0031] The boom cylinder 25 has its proximal end portion 25a coupled to a cylinder shaft
part 31, and the cylinder shaft part 31 is horizontally laid between left and right
cylinder brackets 42L, 42R.
[0032] The cylinder brackets 42L, 42R are arranged so as to fixedly stand on an upper surface
of a support plate 41 such that its plate surfaces are oriented in the lateral direction.
The support plate 41 is arranged above the rotating basal plate 35 and between the
cabin 8 and the tank unit 9, so as to extend obliquely upward toward the rear from
a front portion of the rotating basal plate 35. The cylinder brackets 42L, 42R are
configured to rotatably and tightly support left and right end portions of the cylinder
shaft part 31.
[0033] The first covering 37 includes a sheet portion 37a and a bent edge portion 37b, the
sheet portion 37a being in the shape of a flat plate with its plate surfaces oriented
in the lateral direction, the bent edge portion 37b being formed by bending an upper
peripheral edge of the sheet portion 37a toward the cabin 8. An outdoor air inlet
port 37a1 having a rectangular shape is opened in a front upper portion of the sheet
portion 37a.
[0034] On the tank unit 9 side of the outdoor air inlet port 37a1, an outdoor air inlet
covering 43 is arranged so as to provide a covering, while on the cabin 8 side of
the outdoor air inlet port 37a1, a duct 44 having a thin box-like shape is provided
in a posture inclined obliquely downward toward the rear. A lower portion of the duct
44 communicates with the outdoor air inlet port 37a1, and an upper portion of the
duct 44 has an outdoor air inlet port 44a that communicates with the inside of the
cabin 8.
[0035] This allows outdoor air surrounding the excavator equipment 4 to be introduced into
the cabin 8 through the outdoor air inlet covering 43, the outdoor air inlet port
37a1, the duct 44, and the outdoor air inlet port 44a.
[0036] The second covering 38, which is arranged in a lower rear region on a left side surface
of the sheet portion 37a of the first covering 37, includes a sheet portion 38a and
an outer peripheral edge portion 38b, the sheet portion 38a being laterally bent at
a plurality of positions along vertically extending bending lines 103, 104, the outer
peripheral edge portion 38b covering a peripheral edge of the sheet portion 38a.
[0037] The outer peripheral edge portion 38b has its right end coupled to the left side
surface of the sheet portion 37a of the first covering 37, and the sheet portion 38a
is provided with a rear side plate 38a1, an inclined side plate 38a2, and a front
side plate 38a3 arranged in this order from the rear, the rear side plate 38a1 having
its plate surfaces oriented in the lateral direction, the inclined side plate 38a2
extending in a posture inclined obliquely rightward toward the front from the bending
line 103 as a boundary, the front side plate 38a3 extending frontward again from the
bending line 104 as a boundary such that plate surfaces of the front side plate 38a3
are oriented in the lateral direction.
[0038] The sheet portion 38a of the second covering 38 has work holes 49, 50 for insertion
and extraction of a boom fulcrum pin 45 of the boom shaft part 30 and a cylinder fulcrum
pin 46 of the cylinder shaft part 31, which will be detailed later, so that the boom
fulcrum pin 45 and the cylinder fulcrum pin 46 can be easily installed and removed
through the work holes 49, 50 from the cabin 8 side.
[0039] In addition, an indoor unit 40 of an air conditioner is disposed near and to the
left of the sheet portion 38a.
[0040] A unit body 40a provided in the indoor unit 40 of the air conditioner is configured
to be rotated away from the work holes 49, 50 by a moving mechanism 68.
[0041] The moving mechanism 68 will now be described based on FIG. 4, FIG. 6, FIG. 7, FIG.
12, and FIG. 13.
[0042] To move the unit body 40a away from the work holes 49, 50, firstly, in the driving
operation unit 10, the driver seat 11 is moved rearward, and then a device covering
40b is detached from the indoor unit 40 of the air conditioner so that the unit body
40a is exposed.
[0043] A vertically elongated fixed stay 52 is provided on and protrudes from a front side
surface 40a1 of the unit body 40a, and a box-shaped fixed frame 54 whose front face
is opened protrudes leftward from a front edge of the sheet portion 37a of the first
covering 37.
[0044] Accordingly, placing fixed holes 52a, 52a formed at the vertical ends of the fixed
stay 52 so as to overlap threaded holes 54a, 54a formed at the vertical ends of a
left side surface of the fixed frame 54, and then threadedly inserting bolts 53, 53
into the threaded holes 54a, 54a via the fixed holes 52a, 52a, allows the fixed stay
52 to be fastened to the fixed frame 54, so that a front portion of the unit body
40a is removably secured to the sheet portion 37a of the first covering 37.
[0045] A front support frame 55 and a rear support frame 56 are provided so as to stand
on a right front portion and a right rear portion of the floor member 39. A top portion
55a of the front support frame 55 has its front end fixed to a rear surface 54b of
the fixed frame 54 and its right end fixed to the sheet portion 37a of the first covering
37, while a top portion 56a of the rear support frame 56 has its right end fixed to
the rear side plate 38a1 of the sheet portion 38a of the second covering 38, so that
both the front support frame 55 and the rear support frame 56 are tightly supported
on the right side wall 8a.
[0046] The front support frame 55 and the rear support frame 56 have inclined sides 55b,
56b, respectively, which are inclined obliquely downward toward the left. Vertically
in the middle of the inclined sides 55b, 56b, a front support portion 58 and a rear
support portion 59 are provided so as to protrude obliquely upward toward the left.
On a bottom surface 40a2 of the unit body 40a, on the other hand, a front support
stay 60 and a rear support stay 61 are provided so as to suspend at front and rear
positions in a substantially central region with respect to the shorter side direction.
[0047] Accordingly, placing a shaft hole 60a of the front support stay 60 so as to overlap
a shaft hole 58a of the front support portion 58, inserting a fulcrum bolt 62 therethrough,
placing a shaft hole 61 a of the rear support stay 61 so as to overlap a shaft hole
59a of the rear support portion 59, and inserting the fulcrum bolt 62 therethrough,
results in formation of a rotational support structure 47 capable of rotating the
unit body 40a around a front-rear shaft center 63 that passes through the shaft holes
58a, 60a, 59a, and 61a, as shown in FIG. 6 and FIG. 7.
[0048] Vertical hinge plates 64a, 65a are provided so as to protrude leftward from a left
side surface of the rear side plate 38a1 of the sheet portion 38a of the second covering
38, while vertical hinge plates 64b, 65b are provided so as to protrude rearward from
a rear side surface 40a3 of the unit body 40a. The hinge plates 64b, 65b are removably
coupled to the hinge plates 64a, 65a, respectively, by a shared hinge pin 66.
[0049] Thus, with a hinge 64 made up of the hinge plates 64a, 64b coupled to each other
by the hinge pin 66 and a hinge 65 made up of the hinge plates 65a, 65b coupled to
each other by the same hinge pin 66, a rotational support structure 48 capable of
rotating the unit body 40a is formed around a vertical shaft center 67 that passes
through a pin shaft center of the hinge pin 66, as shown in FIG. 6 and FIG. 12.
[0050] To move the unit body 40a of the indoor unit 40 of the air conditioner away from
the work hole 49 by the moving mechanism 68 including the rotational support structures
47, 48 described above, the bolts 53, 53 are loosened and the fixed stay 52 is detached
from the fixed frame 54, to disconnect the front portion of the unit body 40a from
the sheet portion 37a of the first covering 37.
[0051] In addition, the hinge pin 66 of the rotational support structure 48 is pulled out,
to decouple the hinge plates 64a, 64b from each other and the hinge plates 65a, 65b
from each other, so that a rear portion of the unit body 40a is disconnected from
the sheet portion 38a of the second covering 38.
[0052] In this state, as shown in FIG. 7, the unit body 40a is rotated about the front-rear
shaft center 63 and thereby moved from a position 69 to a position 70, in a direction
of opening the work hole 49 which means the leftward direction in this example, thus
enabling the unit body 40a to be largely away from the work hole 49.
[0053] To move the unit body 40a of the indoor unit 40 of the air conditioner away from
the work hole 50 as well as the work hole 49, the bolts 53, 53 are loosened and the
front portion of the unit body 40a is disconnected from the sheet portion 37a of the
first covering 37.
[0054] In addition, the fulcrum bolt 62 of the rotational support structure 47 is loosened
and extracted, to decouple the front support portion 58 from the front support stay
60 and the rear support portion 59 from the rear support stay 61, so that a lower
portion of the unit body 40a is disconnected from the floor member 39 of the driving
operation unit 10.
[0055] In this state, as shown in FIG. 12, the unit body 40a is rotated about the vertical
shaft center 67 and thereby moved from the position 69 to the position 71, in a direction
of opening the work hole 50 which means the rearward direction in this example, thus
enabling the unit body 40a to be largely away from the work hole 50.
[0056] Next, a structure of the boom shaft part 30 and an installation and removal configuration
for the boom fulcrum pin 45 which is a support shaft member of the boom shaft part
30 will be described based on FIG. 6 to FIG. 11.
[0057] As shown in FIG. 9 and FIG. 10, the boom shaft part 30 is configured with the boom
fulcrum pin 45 penetrating through a shaft center 83 of a cylindrical body 72 to which
the proximal end portion 20a of the first boom 20 is fixed.
[0058] The right end of the boom fulcrum pin 45 penetrates through a right ring 73, the
left vertical plate 33 with the right ring 73 secured to a left side surface thereof,
and the right vertical plate 34, to protrude toward the tank unit 9, while the left
end of the boom fulcrum pin 45 penetrates through a left ring 74 and the vertical
plate 36 with the left ring 74 secured to a right side surface thereof, to protrude
toward the cabin 8.
[0059] A first through hole 45a and a second through hole 73a having the same inner diameter
are formed in the boom fulcrum pin 45 and the right ring 73, respectively. For an
excavating work, a pin body 77a of an anti-rotation pin 77 is inserted through a through
hole 76 formed by a combination of the first through hole 45a and the second through
hole 73a. As a result, the boom fulcrum pin 45 is fixed to the right ring 73.
[0060] In this manner, the cylindrical body 72 to which the proximal end portion 20a of
the first boom 20 is fixed is fitted onto an outer circumferential surface of the
boom fulcrum pin 45 and supported such that it is freely rotatable concentrically
with the boom fulcrum pin 45.
[0061] The pin body 77a of the anti-rotation pin 77 has, at its one end, a pin head portion
77b whose diameter is larger than that of the pin body 77a. The pin head portion 77b
protrudes beyond an outer circumferential surface of the right ring 73, and an anti-dropout
structure 78 is provided near the pin head portion 77b.
[0062] The anti-dropout structure 78 includes a restriction plate 79 and a fixture 80, the
restriction plate 79 having its distal end portion extending to the radially outside
of the pin head portion 77b of the anti-rotation pin 77, the fixture 80 fixing a proximal
portion of the restriction plate 79 to an outer circumference of the right ring 73.
[0063] The restriction plate 79 is stacked on an upper end surface of a nut 80a of the fixture
80 fixed to the outer circumferential surface of the right ring 73, the restriction
plate 79 including a bottom end portion 79a that serves to prevent the nut 80a from
rotating. A bolt 80b is threadedly inserted through the restriction plate 79 and the
nut 80a, into the right ring 73.
[0064] Thus, even when the anti-rotation pin 77 almost drops out of the through hole 76
as a result of being rotated by, for example, vibrations caused in traveling or working,
the pin head portion 77b comes into abutment with a bottom surface of the restriction
plate 79, so that radially outward movement is restricted, which can prevent the anti-rotation
pin 77 from dropping out.
[0065] In the boom shaft part 30 having such a configuration, a pin operation plate 82 for
use in installation and removal of the boom fulcrum pin 45 is fitted onto and fixed
to the end of the boom fulcrum pin 45 protruding toward the cabin 8, as shown in FIG.
8 to FIG. 10.
[0066] In a side view, the pin operation plate 82 has, in a substantially central portion
thereof, a fitting hole 82b for a small-diameter left end portion 45b of the boom
fulcrum pin 45 to be inserted and fitted therein so that the pin operation plate 82
is coupled and fixed to the boom fulcrum pin 45, and also has engagement holes 82a,
82a on opposite sides of the fitting hole 82b with respect to the radial direction.
A pin operation jig (not shown) is engaged with the engagement holes 82a, 82a, to
allow the boom fulcrum pin 45 to be pushed or pulled along the shaft center 83, or
to be rotated about the shaft center 83.
[0067] On an outer peripheral edge 82c of the pin operation plate 82, a single arc-shaped
outer edge 82cm and a first straight outer edge 82c2 to a seventh straight outer edge
82c8 which are a plurality of straight line portions are formed in this order counterclockwise
in a left side view.
[0068] In the sheet portion 38a of the second covering 38, the work hole 49 is opened in
the rear side plate 38a1 of the sheet portion 38a. In a left side view, the work hole
49 is formed so as to enclose the pin operation plate 82. On an inner peripheral edge
49a of the work hole 49, a first straight inner edge 49a1 to an eighth straight inner
edge 49a8 which are a plurality of straight line portions are formed in this order
counterclockwise in a left side view.
[0069] The second through hole 73a is preliminarily set in a predetermined rotation position
(hereinafter referred to as "reference rotation position") 84 where dropout of the
anti-rotation pin 77 due to gravity does not occur.
[0070] Moreover, setting is made such that, until the first through hole 45a reaches the
reference rotation position 84, rotation of the boom fulcrum pin 45 makes the first
through hole 45a and the second through hole 73a combined to allow the anti-rotation
pin 77 to be inserted therethrough, and also makes a parallel state between the second
straight outer edge 82c3 and the fourth straight inner edge 49a4 opposed to each other,
between the third straight outer edge 82c4 and the fifth straight inner edge 49a5
opposed to each other, and between the fourth straight outer edge 82c5 and the sixth
straight inner edge 49a6 opposed to each other.
[0071] Thus, the boom fulcrum pin 45 is automatically set in the reference rotation position
84 by rotating the boom fulcrum pin 45 from the cabin 8 side through the work hole
49 while visually checking the pin operation plate 82 which locates on the near side
until forming a parallel edge pair 86 of the second straight outer edge 82c3 and the
fourth straight inner edge 49a4, a parallel edge pair 87 of the third straight outer
edge 82c4 and the fifth straight inner edge 49a5, and a parallel edge pair 88 of the
fourth straight outer edge 82c5 and the sixth straight inner edge 49a6. Although this
example provides a visual check structure 85 including three parallel edge pairs 86,
87, and 88, the number of parallel edge pairs is not limited because it is possible
to define the rotation position of the pin operation plate 82 as long as at least
two parallel edge pairs are provided.
[0072] On the left side surface of the rear side plate 38a1, a rim member 121 for sealing
purpose is provided along the inner peripheral edge 49a of the work hole 49.
[0073] The parallel edge pairs 86, 87, and 88 have adjustment gaps 89, 90, and 91, respectively,
formed between the outer peripheral edge 82c of the pin operation plate 82 and the
inner peripheral edge 49a of the work hole 49.
[0074] Accordingly, even in a case where the pin operation plate 82 is rotated to form the
parallel edge pairs 86, 87, and 88 but the boom fulcrum pin 45 cannot be set in the
reference rotation position 84 because of an insufficient machining accuracy, an insufficient
assembling accuracy, or the like; it is possible to combine the first through hole
45a and the second through hole 73a so as to allow the anti-rotation pin 77 to be
inserted therethrough, by making fine adjustment of the rotation position by additionally
rotating the pin operation plate 82 in the front-rear direction to a degree corresponding
to the adjustment gaps 89, 90, and 91 while visually checking the pin operation plate
82 from the cabin 8 side through the work hole 49.
[0075] In the above-described configuration, to detach the boom shaft part 30 pivotally
supporting the proximal portion of the first boom 20, which is horizontally laid between
the left covering 32a of the tank unit 9 and the right side wall 8a of the cabin 8
provided on the rotating platform 7, the boom fulcrum pin 45 is pulled out of the
cylindrical body 72 of the boom shaft part 30, thus enabling detachment of the boom
shaft part 30 horizontally laid between the left covering 32a and the right side wall
8a, that is, the proximal portion of the first boom 20. At this time, before the boom
fulcrum pin 45 is pulled out, the following pre-operation is performed.
[0076] Referring to FIG. 6 and FIG. 7, the driver seat 11 is moved rearward, and then the
device covering 40b is detached from the indoor unit 40 of the air conditioner so
that the unit body 40a is exposed, as mentioned above. After the bolts 53, 53 of the
fixed stay 52 of the unit body 40a are loosened and detached, the unit body 40a is
rotated leftward about the front-rear shaft center 63 and thereby moved from the position
69 to the position 70 through the rotational support structure 47 of the moving mechanism
68, so that the unit body 40a is away from the work hole 49.
[0077] In other words, to facilitate an operation of horizontally pulling the boom fulcrum
pin 45 out to the left, the left side of the work hole 49 is opened so as to ensure
a space wider than the entire length of the boom fulcrum pin 45, to thereby prevent
the unit body 40a from obstructing the pull-out of the boom fulcrum pin 45.
[0078] Thereafter, as shown in FIG. 8, FIG. 10, and FIG. 11, the bolt 80b of the fixture
80 is loosened, and the restriction plate 79 is detached to ensure a space in the
radially outside of the pin head portion 77b of the anti-rotation pin 77. Then, the
pin head portion 77b is gripped, and the anti-rotation pin 77 is extracted from the
through hole 76.
[0079] While the pin operation jig is engaged with the engagement holes 82a, 82a of the
pin operation plate 82, the pin operation plate 82 is drawn out through the work hole
49 in a direction indicated by an arrow 81, so that the boom fulcrum pin 45 can be
pulled out of the cylindrical body 72 of the boom shaft part 30 toward the cabin 8.
[0080] On the other hand, to assemble the boom fulcrum pin 45 by inserting it into the cylindrical
body 72 of the boom shaft part 30, in the same manner as when taking it out of the
cylindrical body 72, the unit body 40a is firstly moved away from the work hole 49
by means of the rotational support structure 47. Thus, the unit body 40a is kept from
obstructing an insertion work of inserting the boom fulcrum pin 45 into the cylindrical
body 72.
[0081] Then, while the pin operation jig is engaged with the engagement holes 82a, 82a of
the pin operation plate 82, the pin operation plate 82 is pushed and moved in a direction
indicated by an arrow 92 through the work hole 49, to insert the boom fulcrum pin
45 into the cylindrical body 72 until a right side surface 82d of the pin operation
plate 82 comes close to an adjustment ring 93 secured to a left side surface 36a of
the vertical plate 36, as shown in FIG. 8, FIG. 10, and FIG. 11.
[0082] Then, while the pin operation plate 82 which locates on the near side is being visually
checked from the cabin 8 side through the work hole 49, the boom fulcrum pin 45 is
rotated about the shaft center 83 by using the pin operation jig until the parallel
edge pairs 86, 87, and 88 are formed, thereby setting the first through hole 45a in
the reference rotation position 84. As a result, the first through hole 45a and the
second through hole 73a are combined to form the through hole 76, and inserting the
anti-rotation pin 77 into the through hole 76 provides prevention of rotation of the
boom fulcrum pin 45.
[0083] Next, a structure of the cylinder shaft part 31 and an installation and removal configuration
for the cylinder fulcrum pin 46 which is a support shaft member of the cylinder shaft
part 31 will be described based on FIG. 5, FIG. 6, and FIG. 12 to FIG. 15.
[0084] As shown in FIG. 5 and FIG. 14, the cylinder shaft part 31 is configured with the
cylinder fulcrum pin 46 penetrating through a shaft center 95 of a cylindrical body
94 to which the proximal end portion 25a of the boom cylinder 25 is fixed.
[0085] The right end of the cylinder fulcrum pin 46 penetrates through the right cylinder
bracket 42R, to protrude toward the tank unit 9. Onto this protruding end is fitted
a right ring 96 for preventing the cylinder fulcrum pin 46 from being extracted leftward.
[0086] A first through hole 46a and a second through hole 96a having the same inner diameter
are formed in the radial direction in the cylinder fulcrum pin 46 and the right ring
96, respectively. For an excavating work, a pin body 99a of an anti-extraction pin
99 is inserted through a through hole 98 formed by a combination of the first through
hole 46a and the second through hole 96a.
[0087] The left end of the cylinder fulcrum pin 46 penetrates through the left cylinder
bracket 42L, to protrude toward the cabin 8. Onto this protruding end is fitted and
fixed a pin operation plate 97 for preventing the cylinder fulcrum pin 46 from being
extracted rightward and also for installation and removal of the cylinder fulcrum
pin 46.
[0088] The pin operation plate 97 has an engagement hole 97a. A pin operation jig (not shown)
is engaged with the engagement hole 97a, to allow the cylinder fulcrum pin 46 to be
pushed or pulled along the shaft center 95.
[0089] The anti-extraction pin 99 is provided with an anti-dropout structure 100. The anti-dropout
structure 100 includes a restriction plate 101 and a fixture 102, the restriction
plate 101 having its distal end portion extending to the radially outside of a pin
head portion 99b of the anti-extraction pin 99, the fixture 102 fixing a proximal
portion of the restriction plate 101 to an outer circumference of the right ring 96.
[0090] The restriction plate 101 is stacked on an upper end surface of a nut 102a of the
fixture 102 fixed to the outer circumferential surface of the right ring 96, the restriction
plate 101 including a bottom end portion 101a that serves to prevent the nut 102a
from rotating. A bolt 102b is threadedly inserted through the restriction plate 101
and the nut 102a, into the right ring 96.
[0091] Thus, even when the anti-extraction pin 99 almost drops out of the through hole 98
as a result of being rotated by, for example, vibrations caused in traveling or working,
the pin head portion 99b comes into abutment with a bottom surface of the restriction
plate 101, so that radially outward movement is restricted, which can prevent the
anti-extraction pin 99 from dropping out.
[0092] In the sheet portion 38a of the second covering 38, the work hole 50 is opened so
as to extend from the front side plate 38a3 to the floor member 39, as shown in FIG.
13 and FIG. 14. The work hole 50 is made up of a vertical opening portion 50a and
a lateral opening portion 50b, the vertical opening portion 50a being formed by notching
the front side plate 38a3 upward from its bottom edge portion 38a4, the lateral opening
portion 50b being formed by notching the floor member 39 leftward from its side edge
portion 39a, the lateral opening portion 50b communicating with the vertical opening
portion 50a.
[0093] Below the lateral opening portion 50b, a working space 108 is provided to allow the
cylinder fulcrum pin 46 to be inserted and extracted from the cabin 8 side.
[0094] For an excavating work, the work hole 50 is covered with a closure covering 105 having
an L-like shape in a front elevational view, with an upper half of the closure covering
105 fastened to the front side plate 38a3 via front and rear upper bolts 106, 106
and with a lower half of the closure covering 105 fastened to the floor member 39
via front and rear lower bolts 107, 107.
[0095] As shown in FIG. 5, FIG. 13, and FIG. 14, a front half of the sheet portion 37a of
the first covering 37 has its bottom edge portion 37a2 inclined obliquely downward
toward the front, and an under space 114 below the bottom edge portion 37a2 is closed
by an attachment member 115 that is fixed to a right side surface 36b of the vertical
plate 36.
[0096] The attachment member 115 includes a support plate portion 115a and an attachment
plate portion 115b, the support plate portion 115a having tis front portion fixed
to the right side surface 36b of the vertical plate 36, the attachment plate portion
115b being removably fastened to a bottom edge of the support plate portion 115a with
a bolt 116. An angle sensor 109 is inserted and fitted in an attachment hole 115b1
of the attachment plate portion 115b.
[0097] The angle sensor 109 is removably secured to the attachment plate portion 115b with
a plurality of bolts 110. A detector (not shown) of the angle sensor 109 is connected,
by a link arm 111, to a sensor stay 112 that protrudes leftward from the proximal
end portion 25a of the boom cylinder 25.
[0098] Accordingly, as the boom cylinder 25 is tilted during an excavating work, the sensor
stay 112 moves frontward or rearward, to actuate the detector of the angle sensor
109 via the link arm 111, so that an angular signal from the angle sensor 109 is outputted
from a lead wire 113.
[0099] To take the cylinder fulcrum pin 46 out of the cylindrical body 94 in the above-described
configuration, firstly, the driver seat 11 is moved rearward, and then the device
covering 40b is detached from the indoor unit 40 of the air conditioner so that the
unit body 40a is exposed in the above-mentioned manner, as shown in FIG. 6 and FIG.
12.
[0100] After the bolts 53, 53 of the fixed stay 52 of the unit body 40a are loosened and
detached, the unit body 40a is rotated rearward about the vertical shaft center 67
and thereby moved from the position 69 to the position 71 through the rotational support
structure 48 of the moving mechanism 68, so that the unit body 40a is away from the
work hole 50.
[0101] Thereafter, as shown in FIG. 5 and FIG. 13 to FIG. 15, the bolts 106, 107 are loosened
and then the closure covering 105 is detached from the front side plate 38a3 and the
floor member 39, while the bolts 116 are loosened and then the attachment plate portion
115b having the angle sensor 109 attached thereto is detached from the support plate
portion 115a.
[0102] Moreover, the bolt 102b of the fixture 102 is loosened, and the restriction plate
101 is detached to ensure a space in the radially outside of the pin head portion
99b of the anti-extraction pin 99. Then, the pin head portion 99b is gripped, and
the anti-extraction pin 99 is extracted from the through hole 98.
[0103] While the pin operation jig is engaged with the engagement holes 97a, 97a of the
pin operation plate 97, the pin operation plate 97 is drawn out from the under space
114 through the working space 108 and the work hole 50, the drawing-out being implemented
initially in a horizontal direction along an arrow 117 and then obliquely upward in
a tilted posture toward the left along an arrow 118, thereby enabling the cylinder
fulcrum pin 46 to be pulled out of the cylindrical body 94 toward the cabin 8.
[0104] On the other hand, to assemble the cylinder fulcrum pin 46 by inserting it into the
cylindrical body 94, in the same manner as when taking it out of the cylindrical body
94, the unit body 40a is firstly moved away from the work hole 50 by means of the
rotational support structure 48.
[0105] Then, as shown in FIG. 13 to FIG. 15, the closure covering 105 is detached from the
front side plate 38a3 and the floor member 39, while the attachment plate portion
115b having the angle sensor 109 attached thereto is detached from the support plate
portion 115a.
[0106] Then, while the pin operation jig is engaged with the engagement holes 97a, 97a of
the pin operation plate 97, the pin operation plate 97 is pushed and moved in a tilted
posture obliquely downward toward the right in a direction indicated by an arrow 119
through the work hole 50, and then pushed and moved in a horizontal posture in a direction
indicated by an arrow 120. At this time, the cylinder fulcrum pin 46 is inserted into
the cylindrical body 94 until a right side surface 97b of the pin operation plate
97 comes into abutment with the left cylinder bracket 42L.
[0107] Then, the anti-extraction pin 99 is inserted through the through hole 98 formed by
a combination of the first through hole 46a and the second through hole 96a, so that
the cylinder fulcrum pin 46 is fixed to the right ring 96, thereby enabling the boom
cylinder 25 to rotate frontward or rearward about the cylinder fulcrum pin 46.
[0108] In a backhoe 1 serving as a work vehicle including: excavator equipment 4 serving
as work equipment including a boom cylinder 25 serving as a rotation member whose
proximal end portion 25a is coupled to a cylinder fulcrum pin 46 serving as a rotatable
support shaft member; a cabin 8 disposed on one side of the excavator equipment 4;
and a tank unit 9 serving as a storage part disposed on the other side of the excavator
equipment 4, wherein a work hole 50 is opened that extends from a right side wall
8a serving as a side wall of the cabin 8 on the excavator equipment 4 side to a floor
member 39, and the cylinder fulcrum pin 46 is installable and removable through the
work hole 50 by inserting and extracting the cylinder fulcrum pin 46 from the cabin
8 side into and out of a cylindrical body 94 to which the proximal end portion 25a
is fixed. Accordingly, at a time of replacing the cylinder fulcrum pin 46 of the excavator
equipment 4 or detaching the excavator equipment 4, the work hole 50 provides easy
access to the cylinder fulcrum pin 46 from the cabin 8 side without needing to remove
either the tank unit 9 or the cabin 8, and thereby installation and removal can be
implemented, thus shortening a working time taken for the replacement work or the
detachment work and reducing a burden on an operator.
[0109] The shortening of the working time and the reduction in the burden on the operator
can more considerably be obtained particularly when compared to a case where the floor
member 39 of the cabin 8 also needs to be removed because the cylinder fulcrum pin
46 is disposed in the same plane as the floor member 39 of the cabin 8 or disposed
in a position lower than the floor member 39, as illustrated in this example in which
the cylinder fulcrum pin 46 is disposed in the same plane as the floor member 39.
[0110] Furthermore, the work hole 50 is made up of a vertical opening portion 50a and a
lateral opening portion 50b, the vertical opening portion 50a being formed by notching
a bottom edge portion 38a4 of the right side wall 8a serving as the side wall, the
lateral opening portion 50b being formed by notching a side edge portion 39a of the
floor member 39, the lateral opening portion 50b communicating with the vertical opening
portion 50a, and a working space 108 is provided below the lateral opening portion
50b, the working space 108 allowing the support shaft member to be inserted and extracted
in a tilted posture from the cabin side. Accordingly, even if a sufficient working
space cannot be ensured on the right side wall 8a side, the working space 108 provided
below the floor member 39 can be used for insertion and extraction of the cylinder
fulcrum pin 46 which is an elongated support shaft member. This allows applications
to various specifications of the excavator equipment 4 which is the work equipment.
[0111] In addition, the indoor unit 40 of the air conditioner serving as an in-cabin apparatus
disposed close to the work hole 50 is provided with a moving mechanism 68 configured
to move the indoor unit 40 of the air conditioner in a direction of opening the work
hole 50. Accordingly, even in a case where the indoor unit 40 of the air conditioner
disposed close to the work hole 50 makes access to the work hole 50 difficult, the
indoor unit 40 of the air conditioner can be easily removed from a front of the work
hole 50, thus enabling further improvement in workability for various works including
the replacement work of replacing the cylinder fulcrum pin 46 serving as the support
shaft member, the detachment work of detaching the excavator equipment 4 serving as
the work equipment, and the like.
Industrial Applicability
[0112] The present invention is applicable to all of work vehicles including: work equipment
including a rotation member whose proximal end portion is coupled to a rotatable support
shaft member; a cabin disposed on one side of the work equipment; and a storage part
disposed on the other side of the work equipment.
Reference Signs List
[0113]
- 1
- backhoe (work vehicle)
- 4
- excavator equipment (work equipment)
- 8
- cabin
- 8a
- right side wall (side wall on work equipment side)
- 9
- tank unit (storage part)
- 25
- boom cylinder (rotation member)
- 25a
- proximal end portion
- 38a4
- bottom edge portion
- 39
- floor member
- 39a
- side edge portion
- 40
- indoor unit of air conditioner (in-cabin apparatus)
- 46
- cylinder fulcrum pin (support shaft member)
- 50
- work hole
- 50a
- vertical opening portion
- 50b
- lateral opening portion
- 68
- moving mechanism
- 94
- cylindrical body
- 108
- working space