Technical Field
[0001] The present invention relates to a yarn winding system, a spinning frame, an automatic
winder, and a yarn winding method.
Background Art
[0002] Conventionally, a yarn winding system including: a spinning frame including a plurality
of spinning units each configured to form a yarn supply bobbin; and an automatic winder
including a plurality of winder units each configured to wind yarn from the yarn supply
bobbin to form a package has been known (see Patent Literature 1, for example). In
a yarn winding system described in Patent Literature 1, a medium is provided to a
tray on which a bobbin is mounted and that is conveyed so as to travel between a spinning
frame and an automatic winder. Onto this medium, information on yarn processing of
the winder is written by a writing device. This yarn processing information written
on the medium is read by a reading device to be managed by a management computer.
Citation List
Patent Literature
[0003] [Patent Literature 1] Japanese Examined Patent Publication No.
H6-76177
Summary of Invention
Technical Problem
[0004] In the yarn winding system described above, from a viewpoint of improving production
efficiency and working quality, it is desired to optimize operation control of the
automatic winder. Examples of such optimization of operation control may include appropriately
changing the processing speed of the automatic winder in accordance with the processing
status of the spinning frame as a previous step machine for the automatic winder,
and causing the automatic winder to appropriately operate in accordance with a condition
for completing spinning in the spinning frame.
[0005] In view of this, various aspects of the present invention aim to provide a yarn winding
system, a spinning frame, an automatic winder, and a yarn winding method that enable
optimization of operation control of the automatic winder.
Solution to Problem
[0006] A yarn winding system according to one aspect of the present invention is a yarn
winding system including a spinning frame configured to form a yarn supply bobbin
and an automatic winder configured to wind yarn from the yarn supply bobbin to form
a package. The spinning frame includes: a generating unit configured to generate spinning
information including information on at least one of a processing status of forming
the yarn supply bobbin and a condition for completing spinning of the yarn supply
bobbin; and a transmission unit configured to transmit the spinning information generated
by the generating unit to the automatic winder. The automatic winder includes: a receiving
unit configured to receive the spinning information; and a control unit configured
to control operation of the automatic winder based on the spinning information received
by the receiving unit.
[0007] In this yarn winding system, from the spinning frame to the automatic winder, the
spinning information including information on at least one of the processing status
of forming the yarn supply bobbin and the condition for completing spinning of the
yarn supply bobbin is transmitted. Based on the spinning information received from
the spinning frame, the automatic winder controls operation of the automatic winder.
By controlling the operation of the automatic winder on the basis of the spinning
information received from the spinning frame in this manner, operation control of
the automatic winder can be optimized.
[0008] The spinning information may include information on the processing status of forming
the yarn supply bobbin. The control unit may, based on the information on the processing
status of forming the yarn supply bobbin, determine a winding speed when the automatic
winder winds yarn from the yarn supply bobbin, and control operation of the automatic
winder so as to wind yarn from the yarn supply bobbin at the determined winding speed.
By this configuration, based on the processing status of forming the yarn supply bobbin
in the spinning frame (e.g., supply timing of the yarn supply bobbin transferred from
the spinning frame to the automatic winder), the automatic winder can appropriately
control the winding speed of the automatic winder.
[0009] The spinning information may include information on a state at the end of yarn winding
in the yarn supply bobbin as the information on the condition for completing spinning.
The automatic winder may include, in a bobbin transfer unit configured to transfer
the yarn supply bobbin from the spinning frame to the automatic winder, a bobbin preparation
unit configured to perform preliminary preparation for processing yarn of the yarn
supply bobbin. The control unit may, based on the information on the end of yarn winding,
control bobbin preparing operation for the yarn supply bobbin in the bobbin preparation
unit. By this configuration, based on the state at the end of yarn winding in the
yarn supply bobbin formed by the spinning frame (e.g., information indicating the
presence of bunch winding and indicating that the bobbin is a partial bobbin), the
automatic winder can appropriately control the bobbin preparing operation in the bobbin
preparation unit.
[0010] The spinning information may include timing information for identifying timing when
the yarn supply bobbin has been formed. A tray configured to transfer the yarn supply
bobbin may be provided with a storage unit configured to store therein the timing
information. The bobbin preparation unit may include a reading unit configured to
read the timing information stored in the storage unit provided to the tray configured
to transfer the yarn supply bobbin when the yarn supply bobbin is supplied to the
bobbin preparation unit. The control unit may control operation of the bobbin preparation
unit, based on spinning information including timing information that is the same
as the timing information read by the reading unit. For example, in some cases, the
condition for completing spinning of a yarn supply bobbin differs depending on timing
when a yarn supply bobbin is formed, and yarn supply bobbins that have been formed
at different timings are transferred in a mixed manner to the bobbin preparation unit.
By the configuration described above, even in such cases, based on conditions for
completing spinning that have been applied to yarn supply bobbins to be processed,
operation of the bobbin preparation unit can be appropriately controlled.
[0011] A spinning frame according to one aspect of the present invention is a spinning frame
configured to form a yarn supply bobbin. The spinning frame includes: a generating
unit configured to generate spinning information including information on at least
one of a processing status of forming the yarn supply bobbin and a condition for completing
spinning of the yarn supply bobbin; and a transmission unit configured to transmit
the spinning information generated by the generating unit to an automatic winder configured
to wind yarn from the yarn supply bobbin to form a package.
[0012] In the spinning frame, the spinning information is transmitted to the automatic winder,
whereby the automatic winder can grasp the information on at least one of the processing
status of forming the yarn supply bobbin and the condition for completing spinning
of the yarn supply bobbin. Thus, in the automatic winder, operation control of the
automatic winder based on the spinning information can be optimized.
[0013] An automatic winder according to one aspect of the present invention is an automatic
winder configured to wind yarn from a yarn supply bobbin to form a package. The automatic
winder includes: a receiving unit configured to receive, from a spinning frame configured
to form the yarn supply bobbin, spinning information including information on at least
one of a processing status of forming the yarn supply bobbin and a condition for completing
spinning of the yarn supply bobbin; and a control unit configured to control operation
of the automatic winder based on the spinning information received by the receiving
unit.
[0014] In the automatic winder, operation of the automatic winder is controlled based on
the spinning information received from the spinning frame, whereby operation control
of the automatic winder can be optimized.
[0015] A yarn winding method according to one aspect of the present invention is a yarn
winding method performed by a spinning frame configured to form a yarn supply bobbin
and an automatic winder configured to wind yarn from the yarn supply bobbin to form
a package. The yarn winding method includes: a generating step of generating spinning
information including information on at least one of a processing status of forming
the yarn supply bobbin and a condition for completing spinning of the yarn supply
bobbin in the spinning frame; a transmitting step of transmitting the spinning information
generated at the generating step to the automatic winder; a receiving step of receiving
the spinning information in the automatic winder; and a control step of controlling
operation of the automatic winder based on the spinning information received at the
receiving step in the automatic winder.
[0016] In this yarn winding method, to begin with, the spinning information including information
on at least one of the processing status of forming the yarn supply bobbin and the
condition for completing spinning of the yarn supply bobbin is transmitted from the
spinning frame to the automatic winder. Subsequently, in the automatic winder, based
on the spinning information received from the spinning frame, operation of the automatic
winder is controlled. By controlling the operation of the automatic winder on the
basis of the spinning information received from the spinning frame in this manner,
operation control of the automatic winder can be optimized.
Advantageous Effects of Invention
[0017] According to one aspect of the present invention, operation control of the automatic
winder can be optimized.
Brief Description of Drawings
[0018]
FIG. 1 is a front view of a yarn winding system according to one embodiment;
FIG. 2 is a perspective view of trays, an empty bobbin, and a yarn supply bobbin that
are conveyed in the yarn winding system in FIG. 1;
FIG. 3 is a side view of a spinning unit of the yarn winding system in FIG. 1;
FIG. 4 is a side view of a winder unit of the yarn winding system in FIG. 1;
FIG. 5 is a schematic block diagram illustrating a functional configuration of the
yarn winding system in FIG. 1; and
FIG. 6 is a flowchart illustrating an operation performed by the yarn winding system
in FIG. 1.
Description of Embodiments
[0019] One embodiment of the present invention will now be described in detail with reference
to the drawings. In the drawings, like or equivalent elements are designated by like
numerals, and duplicate description is omitted.
[0020] As depicted in FIG. 1, a yarn winding system 1 includes a roving frame 2, a spinning
frame 3, and an automatic winder 4. The roving frame 2 generates roved yarn from a
sliver, and winds the roved yarn to form a roved yarn bobbin. The spinning frame 3
generates yarn from the roved yarn, and winds the yarn to form a yarn supply bobbin
11. The automatic winder 4 winds the yarn from the yarn supply bobbin 11 to form a
package. The automatic winder 4 has a bobbin transfer device (bobbin transfer unit)
5. The bobbin transfer device 5 transfers the yarn supply bobbin 11 from the spinning
frame 3 to the automatic winder 4, and transfers an empty bobbin 12 (bobbin around
which yarn is not wound) from the automatic winder 4 to the spinning frame 3. The
bobbin transfer device 5 is provided with a bobbin preparation device (bobbin preparation
unit) 7 and a residual yarn processing device, for example. The bobbin preparation
device 7 performs preliminary preparation for the automatic winder 4 to process the
yarn of the yarn supply bobbin 11. When yarn remains on the bobbin 12 that has been
discharged from the yarn supply bobbin 11, the residual yarn processing device removes
the yarn to form an empty bobbin 12. For this purpose, the bobbin transfer device
5 has a complicated conveyance path having many curves.
[0021] The yarn supply bobbin 11 and the empty bobbin 12 are transferred in a manner being
set on respective trays 6. As depicted in FIG. 2, each of the trays 6 has a disk-like
base portion 61, a pin 62 protruding upward from the base portion 61, and a radio
frequency (RF) tag 63 embedded in the base portion 61. The bottom portion 12a of each
of the bobbins 12 is inserted into the pin 62, whereby the yarn supply bobbin 11 and
the empty bobbin 12 are set on the respective trays 6 with the top portions 12b of
the bobbins 12 facing upward. The RF tag (storage unit) 63 stores therein information
on the yarn supply bobbin 11 set on the tray 6. In the yarn winding system 1, the
status of the yarn supply bobbin 11 set on the tray 6 is managed by a radio frequency
identification (RFID: individual identification using radio waves) technology.
[0022] As depicted in FIG. 1, the roving frame 2 includes a control device 21 configured
to control operation of the roving frame 2 and a plurality of roving units 22 each
configured to form a roved yarn bobbin. The control device 21 includes a display unit
21a such as a display and an operation unit 21b such as input keys. The display unit
21a displays, for example, an operating status of each of the roving units 22. The
operation unit 21b is an entity to which an operator sets operating conditions, for
example, of each of the roving units 22.
[0023] The spinning frame 3 includes a control device 31 configured to control operation
of the spinning frame 3 and a plurality of spinning units 32 each configured to form
a yarn supply bobbin 11. The control device 31 includes a display unit 31a such as
a display and an operation unit 31b such as input keys. The display unit 31a displays,
for example, an operating status of each of the spinning units 32. The operation unit
31b is an entity to which the operator sets operating conditions, for example, of
each of the spinning unit 32.
[0024] As depicted in FIG. 3, the spinning unit 32 includes a drafting device 33 and a twisting
device 34.
[0025] The drafting device 33 includes a back roller pair 33a, a middle roller pair 33b,
and a front roller pair 33c. Each pair of the back roller pair 33a, the middle roller
pair 33b, and the front roller pair 33c are configured with a bottom roller and a
top roller. Around the rollers constituting the middle roller pair 33b, apron belts
are each wound. In the drafting device 33, the back roller pair 33a, the middle roller
pair 33b, and the front roller pair 33c are rotated at a predetermined speed ratio,
whereby a roved yarn 13 that has been unwound from a roved yarn bobbin is drafted.
[0026] The twisting device 34 includes a spindle shaft 35, a ring rail 36, a ring 37, and
a traveller 38. The spindle shaft 35 holds the bottom portion 12a of a bobbin 12 with
the top portion 12b of the bobbin 12 facing upward, and rotates the bobbin 12. The
ring rail 36 is movable in the axial direction of the bobbin 12. The ring 37 is fixed
to the ring rail 36. The traveller 38 is supported by the ring 37, and is movable
along the ring 37.
[0027] In the twisting device 34, roved yarn 13 that has been drafted by the drafting device
33 is inserted into a space between the ring 37 and the traveller 38, and an end portion
of the roved yarn 13 is fixed to the bobbin 12. In this state, when the spindle shaft
35 rotates the bobbin 12, the traveller 38 moves along the ring 37 in a manner being
pulled by the roved yarn 13. At this time, the ring rail 36 gradually moves from the
bottom portion 12a side to the top portion 12b side while reciprocating within a predetermined
range along the axial direction of the bobbin 12. In the twisting device 34, rotation
of the traveller 38 lags behind rotation of the bobbin 12, whereby the roved yarn
13 is twisted to form yarn 14, and the yarn 14 is wound by the bobbin 12 to form a
yarn supply bobbin 11.
[0028] The spinning frame 3 including the spinning units 32 each configured as described
above is of what is called a simultaneous doffing type. Specifically, the spinning
frame 3 stocks a plurality of empty bobbins 12 transferred from the automatic winder
4 by the bobbin transfer device 5, simultaneously sets the empty bobbins 12 on the
respective spinning units 32, and simultaneously starts yarn winding. When winding
of yarn has been completed in the respective spinning units 32 and yarn supply bobbins
11 have been formed, the spinning frame 3 simultaneously doffs all of the yarn supply
bobbins 11. Subsequently, the spinning frame 3 pulls empty bobbins 12 that have been
already stocked out of the corresponding trays 6 and simultaneously sets the empty
bobbins on the respective spinning units 32 again and, instead, simultaneously sets
the doffed yarn supply bobbins 11 on the trays 6.
[0029] As depicted in FIG. 1, the automatic winder 4 includes a control device 41 configured
to control operation of the automatic winder 4, a plurality of winder units 42 each
configured to form a package, and the bobbin transfer device 5. The control device
41 includes a display unit 41a such as a display and an operation unit 41b such as
input keys. The display unit 41a displays, for example, an operating status of each
of the winder units 42. The operation unit 41b is an entity to which the operator
sets operating conditions, for example, of each of the winder unit 42. The control
device 41 also controls operation of the bobbin transfer device 5.
[0030] As depicted in FIG. 4, the winder unit 42 includes a winding device 43, a tension
applying device 44, a yarn monitoring device 45, an upper yarn catching device 46,
a lower yarn catching device 47, and a splicing device 48.
[0031] The winding device 43 includes a cradle 43a and a winding drum 43b. The cradle 43a
supports a package 15. The winding drum 43b rotates the package 15 while traversing
the yarn 14. Thus, the yarn 14 is wound from a yarn supply bobbin 11 set at a predetermined
position to form the package 15. The tension applying device 44 applies a predetermined
tension to the yarn 14 that is travelling from the yarn supply bobbin 11 to the package
15.
[0032] The yarn monitoring device 45 monitors the travelling yarn 14 to detect a yarn defect
(thickness abnormality of yarn 14, mixing of foreign matter into yarn 14, etc.). When
a yarn defect has been detected, the yarn 14 is cut by a cutter separately provided.
When the yarn 14 has been cut, the upper yarn catching device 46 catches a yarn end
of the yarn 14 on the package 15 side, and guides the yarn end to the splicing device
48. When the yarn 14 has been cut, the lower yarn catching device 47 catches a yarn
end of the yarn 14 on the yarn supply bobbin 11 side, and guides the yarn end to the
splicing device 48. The splicing device 48 splices the yarn ends that have been guided
by the upper yarn catching device 46 and the lower yarn catching device 47 to each
other.
[0033] As depicted in FIG. 1, the bobbin transfer device 5 includes an RF writer 51. When
a yarn supply bobbin 11 is transferred from the spinning frame 3 to the automatic
winder 4, the RF writer 51 writes information on the yarn supply bobbin 11 on the
RF tag 63 of the tray 6 on which the yarn supply bobbin 11 is set. The information
on the yarn supply bobbin 11 includes unit identification information for identifying
a spinning unit 32 that has formed the yarn supply bobbin 11 and doffing information
(timing information) for identifying timing of simultaneous doffing. More specifically,
the doffing information is information indicating the timing of doffing, for example,
the time when the simultaneous doffing was performed, the total number of doffing
having been performed after the time set as a reference, and so on. The RF writer
51 may be provided to an exit of the spinning frame 3 in the transfer direction of
the yarn supply bobbin 11. Alternatively, the RF writer 51 may be provided to every
spinning unit 32.
[0034] When the yarn supply bobbin 11 has been set on the winder unit 42 of the automatic
winder 4, the information written on the RF tag 63 by the RF writer 51 is read by
an RF reader (reading unit) 49 provided to each of the winder units 42, and is transmitted
to the control device 41 of the automatic winder 4. Based on this information, the
control device 41 can identify the spinning unit 32 that has formed the yarn supply
bobbin 11 and the timing of simultaneous doffing for the yarn supply bobbin 11 set
on the winder unit 42.
[0035] The following describes, with reference to FIG. 5 and FIG. 6, a mechanism in which
the spinning frame 3 transmits spinning information (described later in detail) to
the automatic winder 4, and the automatic winder 4 controls operation of the automatic
winder 4 (i.e., operation of each of the winder units 42 and the bobbin preparation
device 7) on the basis of the spinning information.
[0036] As depicted in FIG. 5, the spinning frame 3 includes the control device (generating
unit) 31 and a transmission unit 31c as functional elements constituting the mechanism
described above. The automatic winder 4 includes the control device (control unit)
41, a receiving unit 41c, the respective winder units 42, and the bobbin transfer
device 5. The bobbin transfer device 5 is provided with the bobbin preparation device
7. The bobbin preparation device 7 is provided with an RF reader 7a.
[0037] The control device 31 is an electronic control unit including a central processing
unit (CPU), a read only memory (ROM), a random access memory (RAM), and so on. The
control device 31 loads a program stored in the ROM into the RAM, and causes the CPU
to execute the program, thereby performing various controls . The control device 31
may include a plurality of electronic control units. The control device 31 functions
as a generating unit configured to generate spinning information including information
on at least one of a processing status of forming a yarn supply bobbin 11 and a condition
for completing spinning of the yarn supply bobbin 11.
[0038] The information on the processing status of forming a yarn supply bobbin 11 (hereinafter
called "processing status information") is, for example, information indicating remaining
time until yarn supply bobbins 11 are simultaneously doffed in a plurality of spinning
units 32 by simultaneous doffing. The control device 31 can obtain the processing
status information described above by, for example, monitoring the operating status
of each of the spinning units 32, or referring to settings for operation of each of
the spinning units 32.
[0039] The information on the condition for completing spinning of a yarn supply bobbin
11 (hereinafter called "completion condition information") is, for example, information
on a condition that needs to be satisfied when a yarn supply bobbin 11 is doffed in
each of the spinning units 32 (doffing condition) . The completion condition information
is, for example, information on a state at the end of yarn winding in the yarn supply
bobbin 11. Examples of the information on a state at the end of yarn winding include
information indicating whether what is called bunch winding has been performed in
the state at the end of yarn winding in the yarn supply bobbin 11 and information
indicating whether the yarn supply bobbin has been formed into a partial bobbin in
the state thereof.
[0040] In the present embodiment, as one example, the control device 31 generates, as the
spinning information, data including the processing status information, the completion
condition information, and doffing information for identifying timing when the yarn
supply bobbin 11 has been formed, and transmits the spinning information to the automatic
winder 4 via the transmission unit 31c. The timing when the control device 31 generates
and transmits the spinning information to the automatic winder 4 may be optionally
set. In the present embodiment, as one example, the control device 31 periodically
generates spinning information at predetermined intervals that are set in advance,
and transmits the spinning information to the automatic winder 4. By this setting,
the automatic winder 4 can grasp the processing status of the spinning frame 3 in
a timely manner, and every time the automatic winder grasps the status, the winding
speed of each of the winder units 42 can be appropriately controlled (details thereof
will be described later).
[0041] The transmission unit 31c transmits the spinning information generated by the control
device 31 to the automatic winder 4. Transmission by the transmission unit 31c may
be performed through wired communication using a cable, for example, or may be performed
through wireless communication. When the transmission by the transmission unit 31c
is performed through wireless communication, radio waves, infrared rays, or light
may be used as a conveyance medium. In FIG. 5, the transmission unit 31c is illustrated
as an element separate from the control device 31. However, the transmission unit
31c may be included in the control device 31. In other words, the transmission unit
31c may be a communication function implemented in the control device 31.
[0042] The receiving unit 41c receives the spinning information transmitted from the spinning
frame 3. Reception by the receiving unit 41c may be performed through wired communication
using a cable, for example, or may be performed through wireless communication. When
the reception by the receiving unit 41c is performed through wireless communication,
radio waves, infrared rays, or light may be used as a conveyance medium. In FIG. 5,
the receiving unit 41c is illustrated as an element separate from the control device
41. However, the receiving unit 41c may be included in the control device 41. In other
words, the receiving unit 41c may be a communication function implemented in the control
device 41.
[0043] The control device 41 is an electronic control unit including a CPU, a ROM, and a
RAM. The control device 41 loads a program stored in the ROM into the RAM, and causes
the CPU to execute the program to perform various controls . The control device 41
may include a plurality of electronic control units. Based on the spinning information
received by the receiving unit 41c, the control device 41 controls operation of the
automatic winder 4. Specifically, the control device 41 determines operation of each
of the winder units 42 on the basis of the spinning information, and transmits a control
signal indicating the determined operation to the winder unit 42 in a timely manner,
thereby controlling the operation of the winder unit 42.
[0044] Based on the processing status information included in the spinning information,
the control device 41 determines a winding speed when each of the winder units 42
winds yarn from the corresponding yarn supply bobbin 11, and controls operation of
the winder unit 42 so as to wind yarn from the yarn supply bobbin 11 at the determined
winding speed.
[0045] As described above, while yarn supply bobbins 11 are transferred from the spinning
frame 3 to the automatic winder 4, empty bobbins 12 are transferred from the automatic
winder 4 to the spinning frame 3. Herein, the fact that a pace (supply pace) at which
each of the yarn supply bobbins 11 is transferred from the spinning frame 3 to the
automatic winder 4 in a unit time is slower than a pace (discharge pace) at which
each of the empty bobbins 12 is transferred from the automatic winder 4 to the spinning
frame 3 in a unit time means that the automatic winder 4 has enough processing capacity.
This means that the winding speed of each of the winder units 42 can be reduced. In
contrast, the fact that the supply pace is faster than the discharge pace means that
the automatic winder 4 does not have enough processing capacity. This means that the
winding speed of each of the winder units 42 needs to be increased in order to balance
the processing speeds of the spinning frame 3 and the automatic winder 4.
[0046] In view of this, the control device 41 calculates the supply pace of each of the
yarn supply bobbins 11 on the basis of the processing status information included
in the spinning information, and determines the winding speed of each of the winder
units 42 such that the supply pace and the pace of a winding process in the winder
unit 42 (i.e., discharge pace of the empty bobbin 12) are balanced. Thus, when the
supply pace is faster than the discharge pace, the control device 41 can balance the
processing of the spinning frame 3 and the processing of the automatic winder 4 by
increasing the winding speed of each of the winder units 42. When the supply pace
is slower than the discharge pace, the control device 41 can improve the winding quality
(i.e., quality of a package 15) of each of the winder units 42 by reducing the winding
speed of the winder unit 42.
[0047] Furthermore, based on the information on the end of yarn winding included in the
spinning information, the control device 41 controls bobbin preparing operation for
each of the yarn supply bobbins 11 in the bobbin preparation device 7 provided to
the bobbin transfer device 5. For example, the control device 41 determines whether
the bunch winding has been performed in the yarn supply bobbin 11 on the basis of
the information on the end of yarn winding. If it is determined that the bunch winding
has been performed in a yarn supply bobbin 11, the control device 41 controls operation
of the bobbin preparation device 7 so as to omit operations that are unnecessary when
the bunch winding has been performed (e.g., operations such as cutting of a yarn end
of the yarn supply bobbin 11 by a yarn-end cutting device (not depicted) provided
to the bobbin preparation device 7 and suctioning of the yarn end of the yarn supply
bobbin 11 by a yarn-end suction device (not depicted) provided to the bobbin preparation
device 7). Consequently, unnecessary operations can be prevented from being performed
in the bobbin preparation device 7.
[0048] Furthermore, for example, the control device 41 determines whether each of the yarn
supply bobbins 11 has been formed into a partial bobbin, based on the information
on the end of yarn winding. If it is determined that a yarn supply bobbin 11 has been
formed into a partial bobbin, the control device 41 controls operation of the bobbin
preparation device 7 such that, for example, search operation (operation for searching
a yarn end of the yarn supply bobbin 11) by the yarn-end cutting device and the yarn-end
suction device described above is performed within a range corresponding to the partial
bobbin (e.g., a predetermined range on the bottom portion 12a side). Consequently,
the search operation can be prevented from being performed in an unnecessary range,
and also the yarn end can be found quickly. By controlling the bobbin preparing operation
in the bobbin preparation device 7 in accordance with the state at the end of yarn
winding in each of the yarn supply bobbins 11 as described above, operation of the
bobbin preparation device 7 can be optimized.
[0049] In some cases, the condition for completing spinning of a yarn supply bobbin 11 differs
depending on timing of simultaneous doffing in the spinning frame 3. For example,
there are cases in which the condition for completing spinning is set such that the
bunch winding is performed in yarn supply bobbins 11 in simultaneous doffing at the
first timing and the bunch winding is not performed in yarn supply bobbins 11 in simultaneous
doffing at the second timing later than the first timing. Examples of a factor contributing
the case in which the bunch winding is not performed in yarn supply bobbins 11 in
simultaneous doffing at the second timing include a case in which roved yarns wound
around roved yarn bobbins set on the spinning frame 3 have been completely consumed
in many spinning units 32, and a case in which doffing has to be performed in an unfinished
state due to trouble with the spinning frame 3. There is a case in which yarn supply
bobbins 11 that have been formed at the first and second timings at which the conditions
for completing spinning are different as described above are transferred in a mixed
manner to the bobbin preparation device 7. In this case, when preparatory work is
performed for yarn supply bobbins 11 formed at the first timing, the control device
41 needs to control operation of the bobbin preparation device 7 on the basis of completion
condition information (i.e., completion condition information applied to the yarn
supply bobbins 11 formed at the first timing) included in first spinning information
including doffing information indicating the first timing. Similarly, when preparatory
work is performed for yarn supply bobbins 11 formed at the second timing, the control
device 41 needs to control operation of the bobbin preparation device 7 on the basis
of completion condition information (i.e., completion condition information applied
to the yarn supply bobbins 11 formed at the second timing) included in second spinning
information including doffing information indicating the second timing. The automatic
winder 4 is configured to be able to implement this control. The following describes
this mechanism.
[0050] To begin with, the control device 41 periodically receives spinning information from
the spinning frame 3 via the receiving unit 41c, thereby accumulating the first spinning
information including doffing information indicating the first timing and the second
spinning information including doffing information indicating the second timing. When
each of the yarn supply bobbins 11 is supplied to the bobbin preparation device 7,
the RF reader 7a provided to the bobbin preparation device 7 reads information written
on an RF tag 63 provided to the corresponding tray 6 transferring the yarn supply
bobbin 11, and transmits the information to the control device 41. Thus, the control
device 41 acquires doffing information indicating timing when the yarn supply bobbin
11 supplied to the bobbin preparation device 7 has been formed.
[0051] Subsequently, the control device 41 extracts, from among the accumulated pieces of
spinning information, spinning information including doffing information that is the
same as the doffing information (doffing information indicating timing when the yarn
supply bobbin 11 has been formed, which is, for example, information for identifying
in what number doffing the yarn supply bobbin 11 has been doffed.) received from the
RF reader 7a, and controls operation of the bobbin preparation device 7 on the basis
of this spinning information. Specifically, when the doffing information received
from the RF reader 7a indicates the first timing (e.g., the first doffing), the control
device 41 controls the bobbin preparing operation of the bobbin preparation device
7 on the basis of completion condition information included in the first spinning
information. When the doffing information received from the RF reader 7a indicates
the second timing (e.g., the second doffing), the control device 41 controls the bobbin
preparing operation of the bobbin preparation device 7 on the basis of completion
condition information included in the second spinning information. Thus, based on
the condition for completing spinning that has been applied to each of the yarn supply
bobbins 11 supplied to the bobbin preparation device 7 (e.g., information on the end
of yarn winding, such as whether the bunch winding has been performed and whether
the yarn supply bobbin has been formed into a partial bobbin), the bobbin preparing
operation of the bobbin preparation device 7 can be appropriately controlled.
[0052] The following describes operation of the yarn winding system 1 (operation including
a yarn winding method according to the present embodiment) with reference to FIG.
6. As depicted in FIG. 6, to begin with, the control device 31 of the spinning frame
3 generates spinning information including at least one of processing status information
and completion condition information (step S1, generating step) . Subsequently, the
transmission unit 31c of the spinning frame 3 transmits the spinning information generated
at step S1 to the automatic winder 4 (step S2, transmitting step).
[0053] Subsequently, the receiving unit 41c of the automatic winder 4 receives the spinning
information (step S3, receiving step) . The spinning information received by the receiving
unit 41c is delivered to the control device 41. Based on the processing status information
included in the spinning information, the control device 41 controls the winding speed
of each of the winder units 42 (step S4, control step) . Specifically, the control
device 41 calculates the supply pace of each of the yarn supply bobbins 11 on the
basis of the processing status information included in the spinning information, and
determines the winding speed of each of the winder units 42 such that the supply pace
and the pace of a winding process in the winder unit 42 (i.e., discharge pace of the
empty bobbin 12) are balanced. The control device 41 then controls operation of each
of the winder units 42 so as to wind yarn from the corresponding yarn supply bobbin
11 at the determined winding speed.
[0054] When each of the yarn supply bobbins 11 is supplied to the bobbin preparation device
7, the RF reader 7a provided to the bobbin preparation device 7 reads doffing information
written on the RF tag 63 provided to the corresponding tray 6 transferring the yarn
supply bobbin 11, and transmits the doffing information to the control device 41 (step
S5). Subsequently, based on spinning information including doffing information that
is the same as the doffing information received from the RF reader 7a, the control
device 41 controls the bobbin preparing operation of the bobbin preparation device
7 (step S6, control step). Specifically, as described above, the control device 41
controls operation of the bobbin preparation device 7, for example, based on information
on the end of yarn winding in the yarn supply bobbin 11 included in the spinning information.
[0055] As described in the foregoing, in the yarn winding system 1, from the spinning frame
3 to the automatic winder 4, spinning information including information on at least
one of the processing status of forming a yarn supply bobbin 11 and the condition
for completing spinning of the yarn supply bobbin 11 is transmitted. Based on the
spinning information received from the spinning frame 3, the control device 41 of
the automatic winder 4 controls operation of the automatic winder 4 (i.e., operation
of each of the winder units 42, and operation of the bobbin preparation device 7,
etc.). By controlling the operation of the automatic winder 4 on the basis of the
spinning information received from the spinning frame 3 in this manner, operation
control of the automatic winder 4 can be optimized.
[0056] In the yarn winding system 1, the spinning information includes information on the
processing status of forming the yarn supply bobbin 11. Based on the information on
the processing status of forming the yarn supply bobbin 11, the control device 41
determines the winding speed when each of the winder units 42 winds yarn from the
corresponding yarn supply bobbin 11, and controls operation of the winder unit 42
so as to wind yarn from the yarn supply bobbin 11 at the determined winding speed.
Thus, based on the processing status of forming the yarn supply bobbin 11 in the spinning
frame 3 (e.g., supply timing of the yarn supply bobbin 11 transferred from the spinning
frame 3 to the automatic winder 4), the automatic winder 4 can appropriately control
the winding speed of the winder unit 42.
[0057] In the yarn winding system 1, the spinning information includes information on a
state at the end of yarn winding in a yarn supply bobbin 11 as the information on
the condition for completing spinning. The automatic winder 4 includes, in the bobbin
transfer device 5 configured to transfer each of the yarn supply bobbins 11 from the
spinning frame 3 to the automatic winder 4, the bobbin preparation device 7 configured
to perform preliminary preparation for processing yarn of the yarn supply bobbin 11.
Based on the information on the end of yarn winding, the control device 41 controls
bobbin preparing operation for the yarn supply bobbin 11 in the bobbin preparation
device 7. Thus, based on the state at the end of yarn winding in a yarn supply bobbin
11 formed by the spinning frame 3 (e.g., information indicating the presence of the
bunch winding and indicating that the yarn supply bobbin is a partial bobbin), the
automatic winder 4 can appropriately control the bobbin preparing operation in the
bobbin preparation device 7.
[0058] In the yarn winding system 1, the spinning information includes doffing information
for identifying timing when a yarn supply bobbin 11 has been formed. Each tray 6 configured
to transfer a yarn supply bobbin 11 is provided with the RF tag 63 configured to store
therein the doffing information. The bobbin preparation device 7 has the RF reader
7a. When a yarn supply bobbin 11 is supplied to the bobbin preparation device 7, the
RF reader 7a reads the doffing information stored in the RF tag 63 provided to the
tray 6 configured to transfer the yarn supply bobbin 11. Based on spinning information
including doffing information that is the same as the doffing information read by
the RF reader 7a, the control device 41 controls operation of the bobbin preparation
device 7. For example, in some cases, the condition for completing spinning of a yarn
supply bobbin 11 differs depending on timing when a yarn supply bobbin 11 is formed,
and yarn supply bobbins 11 that have been formed at different timings are transferred
in a mixed manner to the bobbin preparation device 7. By the configuration described
above, even in such cases, based on conditions for completing spinning that have been
applied to yarn supply bobbins 11 to be processed, operation of the bobbin preparation
device 7 can be appropriately controlled.
[0059] When attention is focused on each of the spinning frame 3 and the automatic winder
4, the spinning frame 3 and the automatic winder 4 have the following effects. Specifically,
in the spinning frame 3, the spinning information is transmitted to the automatic
winder 4, whereby the automatic winder 4 can grasp the information on at least one
of the processing status of forming a yarn supply bobbin 11 and the condition for
completing spinning in the yarn supply bobbin 11. Thus, in the automatic winder 4,
operation control of each of the winder units 42 based on the spinning information
can be optimized. In the automatic winder 4, operation of the automatic winder 4 is
controlled based on the spinning information received from the spinning frame 3, whereby
operation control of the automatic winder 4 can be optimized.
[0060] Although one embodiment of the present invention has been described above, the present
invention is not limited to the embodiment. For example, transmission of the spinning
information from the spinning frame 3 to the automatic winder 4 does not have to be
performed directly between the spinning frame 3 and the automatic winder 4, and may
be performed via a predetermined repeating device, for example. In the embodiment,
an example has been described in which operation (winding speed) of each of the winder
units 42 is controlled based on the processing status information. However, the control
device 41 may control operation of the bobbin preparation device 7, based on the processing
status information. Similarly, in the embodiment, an example has been described in
which preparation operation of the bobbin preparation device 7 is controlled based
on the completion condition information. However, the control device 41 may control
operation of each of the winder units 42, based on the completion condition information.
Reference Signs List
[0061]
1... yarn winding system, 3... spinning frame, 4... automatic winder, 5... bobbin
transfer device (bobbin transfer unit), 7... bobbin preparation device (bobbin preparation
unit), 7a... RF reader (reading unit), 31... control device (generating unit), 31c...
transmission unit, 41... control device (control unit), 41c... receiving unit, 63...
RF tag (storage unit)
1. A yarn winding system comprising:
a spinning frame configured to form a yarn supply bobbin; and
an automatic winder configured to wind yarn from the yarn supply bobbin to form a
package, wherein
the spinning frame includes:
a generating unit configured to generate spinning information including information
on at least one of a processing status of forming the yarn supply bobbin and a condition
for completing spinning of the yarn supply bobbin; and
a transmission unit configured to transmit the spinning information generated by the
generating unit to the automatic winder, and
the automatic winder includes:
a receiving unit configured to receive the spinning information; and
a control unit configured to control operation of the automatic winder based on the
spinning information received by the receiving unit.
2. The yarn winding system according to claim 1, wherein
the spinning information includes information on the processing status of forming
the yarn supply bobbin, and
the control unit, based on the information on the processing status of forming the
yarn supply bobbin, determines a winding speed when the automatic winder winds yarn
from the yarn supply bobbin, and controls operation of the automatic winder so as
to wind yarn from the yarn supply bobbin at the determined winding speed.
3. The yarn winding system according to claim 1 or 2, wherein
the spinning information includes information on a state at the end of yarn winding
in the yarn supply bobbin as the information on the condition for completing spinning,
the automatic winder includes, in a bobbin transfer unit configured to transfer the
yarn supply bobbin from the spinning frame to the automatic winder, a bobbin preparation
unit configured to perform preliminary preparation for processing yarn of the yarn
supply bobbin, and
the control unit, based on the information on the end of yarn winding, controls bobbin
preparing operation for the yarn supply bobbin in the bobbin preparation unit.
4. The yarn winding system according to claim 3, wherein
the spinning information include timing information for identifying timing when the
yarn supply bobbin has been formed,
a tray configured to transfer the yarn supply bobbin is provided with a storage unit
configured to store therein the timing information,
the bobbin preparation unit includes a reading unit configured to read the timing
information stored in the storage unit provided to the tray configured to transfer
the yarn supply bobbin when the yarn supply bobbin is supplied to the bobbin preparation
unit, and
the control unit controls operation of the bobbin preparation unit, based on spinning
information including timing information that is the same as the timing information
read by the reading unit.
5. A spinning frame configured to form a yarn supply bobbin, the spinning frame comprising:
a generating unit configured to generate spinning information including information
on at least one of a processing status of forming the yarn supply bobbin and a condition
for completing spinning of the yarn supply bobbin; and
a transmission unit configured to transmit the spinning information generated by the
generating unit to an automatic winder configured to wind yarn from the yarn supply
bobbin to form a package.
6. An automatic winder configured to wind yarn from a yarn supply bobbin to form a package,
the automatic winder comprising:
a receiving unit configured to receive, from a spinning frame configured to form the
yarn supply bobbin, spinning information including information on at least one of
a processing status of forming the yarn supply bobbin and a condition for completing
spinning of the yarn supply bobbin; and
a control unit configured to control operation of the automatic winder based on the
spinning information received by the receiving unit.
7. A yarn winding method performed by a spinning frame configured to form a yarn supply
bobbin and an automatic winder configured to wind yarn from the yarn supply bobbin
to form a package, the yarn winding method comprising:
a generating step of generating spinning information including information on at least
one of a processing status of forming the yarn supply bobbin and a condition for completing
spinning of the yarn supply bobbin in the spinning frame;
a transmitting step of transmitting the spinning information generated at the generating
step to the automatic winder;
a receiving step of receiving the spinning information in the automatic winder; and
a control step of controlling operation of the automatic winder based on the spinning
information received at the receiving step in the automatic winder.