[0001] The invention relates to the mechanized and remotely controlled excavation of the
working chamber under a, preferably pneumatic, caisson or shaft, with the purpose
of forming the caisson or shaft, which is a structure such as a building with, for
example, accommodation spaces and, as a rule, a height of at least 5 or 10 or 25 or
50 meters, to sink, for example where the structure moves vertically downwards during
sinking over a distance of at least 5 or 10 or 25 or 50 meters. One could also call
this invention "unmanned" or "without diver" sinking. In this document the term "caisson"
also means "shaft". Although the invention is particularly intended for a pneumatic
caisson, it could also be applicable to a non-pneumatic caisson. This document mainly
discusses the application for a pneumatic caisson.
[0002] In this document, a distinction is made between a water jet and a water spray. A
water jet is supplied by a water cannon and is thick and powerful. A water spray is
thin and less powerful. A water jet is independently capable of eroding the soil sufficiently.
A water jet system is used to support a mechanical eroding the ground element, such
as a milling or cutter head.
[0003] A pneumatic caisson is used in an area with relatively high water level or groundwater
level. At the under side of the bottom (which, with a view to generating a pneumatic
vacuum in the working chamber, is sufficiently and preferably completely airtight,
possibly with the exception of slight air leaks due to, for example, functional penetrations)
of the caisson, there is a downwardly projecting cutting edge which laterally delimits
sufficiently and preferably completely airtight a working chamber. The caisson bottom
forms the ceiling and the soil the bottom of the work room. By digging out the work
room, the caisson sinks under its own weight in the soil and becomes a fully or partly
underground or underwater structure, such as building. The caisson bottom drops below
the local water level, for example ground water level, below and around the caisson
By introducing air, the (pneumatic) air pressure in the workroom is increased and
the water level under the caisson is thus temporarily reduced, so that the workroom
remains dry and therefore accessible to people.
[0005] The object of the invention is versatile. In one aspect, the aim is to avoid having
workers in the work room present during sinking. In one aspect the goal is a mechanization
such that outside the workroom, for example on top of the caisson, the process of
excavating in the workroom can be followed reliably, so that the process can be controlled
outside the workroom. In one aspect, the aim is to make the soil pumpable not only
by means of spraying loose, but also by means of mechanical cutting. Loosening has
the advantage that soil can be pumped away and removed in larger chunks, so that the
separation of the water outside the caisson can take place more quickly and effectively.
This is particularly important for extremely fine granular materials such as silt,
malm and clay. In one aspect, the goal is to be able to measure the process of loosening
and discharging soil so as to be able to control the process on efficiency. Other
aspects will be apparent from the foregoing or the following.
[0006] According to the invention, in the working chamber an excavation technique, such
as a dredge technique, is used, so in the working chamber there is a layer of water
and an in the water protruding element, such as a dredge element, for example dredge
pump. This element forms part of, for example, a device comprising the following:
A rotating central attachment, an adjustable arm construction, for example sliding
or articulating several parts for a flexible range of the free end with a soil removing
tool such as a dredge pump with sprays, a cutting or milling head. This earth removing
device is preferably suspended from the ceiling. The excavation element excavates
and/or erodes the water bottom
[0007] According to the invention, liquid (such as water) is used for excavating the soil,
and the excavation takes place under wet conditions and the material released from
the soil is made pumpable by mixing with this liquid, and the material released is
pumped out of the work chamber. and flows away from the work room by a pipe extending
from the work room.
[0008] Preferably, an air layer is present in the work chamber above the layer of water
(the usual English term for this is "head space"), preferably this air layer has a
height from the ceiling of the workroom such that the view in the workroom is optimally
free, the dredge pump is sufficient under water and quick switching is possible for
specific situations between completely dry working chamber (supply of extra air, pumping
of water), and completely under water (removal of air, the supply of water). For example,
the air layer has a height of 0.5 or 1.0 or 2 meters or a height of at least 0.5 or
1.0 or 2.0 meters.
[0009] The air layer gives one or more of the following advantages: protection of parts
of the workroom and/or tools or parts thereof located therein against the groundwater
located in the workroom and substances therein, such as sand; better monitoring with
cameras which are located above water in the working chamber and of which the vision
is not impeded by the turbidity of water; provides the possibility to work efficiently
with water jets directed at the bottom from a high level, for example from the ceiling.
[0010] In order to support the range or efficiency of the excavating element, one or more
water jets are used in the working chamber, preferably from a water cannon in the
working chamber, preferably suspended from the ceiling. The water jets preferably
process the soil in areas that are unreachable for the excavation element/dredge element.
The suspension points of the water cannons are located mutually and/or in relation
to the suspension point of the excavating element at a distance, preferably measured
parallel to the caisson bottom, for instance at least 0.5 or 2 meters (mutually) respectively
3 or 5 meters (excavation element).
[0011] Excavation element and/or water cannons/water jets are preferably controlled in distance
from their suspension point and/or in direction to cover a bottom area and thus to
be excavated over the entire range.
[0012] A possible procedure is as follows: during operation of the water jets, the water
layer is minimal or missing so that the water jets can work the soil as good as possible.
[0013] During operation of the excavating element/dredge element, the water layer is sufficiently
deep to be able to dredge properly, for example at least 0.5 or 1.0 meters. Preferably,
one or more of the following applies: during the sinking, the caisson rests directly
or interposed with one or more shape solid bodies on the ground and/or does not float
on a liquid such as water; the method or apparatus is suitable for all in a delta
area, such as Holland, common types of soil, such as peat, clay, loam, sand, gravel,
and that, in consistencies of loosely to very solid, or where appropriate consolidated;
cohesieve types of soil, such as clay, are in small chunks dredged/excavated, for
example, in order to allow fast settling after discharge; an excavation or dredge
element, such as a dredge pump, possibly loosening the soil, such as one or more of
water sprays, cutting head or milling head for excavating and possibly pumping the
soil as a groundwater suspension as a discharge system; the excavation/dredge element
is part of a, preferably spatially, movable support arm, for example, attached to
a central, preferably rotating, attachment point of the caisson, for example an attachment
point situated at the caisson bottom; a rotatable and/or slidable support arm under
the caisson bottom/work space ceiling; the supporting arm has a length of at least
5 meters, for example, about 8 meters, which length relates to the fully extended
supporting arm in the case of a supporting arm of adjustable length, for instance
by telescoping means; the supporting arm drive is located above the caisson bottom
and/or the ceiling of the work room; application of remote-controlled water jets independent
of the excavating element, which preferably cover the area to be excavated in the
work area where the excavation element can not enter; the attachment of the suspension
structure of the carrying arm is on top of the caisson bottom; a guiding slide structure
for the supporting arm, preferably for sliding in the longitudinal direction, with
the required drive; a fixed length of the support arm, preferably mounted on sliding
means for shifting the support arm longitudinally; a straight arm over at least 80%
or 90% of its length; a drive for directing the excavating/dredge element/pump housing;
a dredge pump with a connection for sand hive with, optionally, water sprays or cutter
head with water sprays if necessary; measure and control technology for monitoring
attitude pump house/excavation/dredge element; swivel connection soil for example
dredge sludge discharge line of the dredge pump/excavation element, possibly with
remote-controlled emergency shut-off valve; swivel connection water supply line of
the dredge pump, possibly with remote-controlled emergency shut-off valve; remote-controlled
water canons, which supply water jets, mounted on the ceiling of the work space; monitoring
and recording systems for air pressures and air purity in the work space; dredge element
capacity at least 10 or 20 or 30 or 60 m3/hour dry matter net for loose-grained materials,
such as sand, which in practice usually corresponds to at least 15 or 30 or 45 or
50 or 100 m3/hour of gross excavated soil (a sandy bottom usually has a pore content
of between 30 and 40%; thus, for example, at a pore content of 40% at a capacity of
50 m3/h gross excavation 30 m3/hour of dry matter net is excavated); dredge element
capacity for cohesive soil types net minimum 10 or 20 or 30 m3/h; dredge pump capacity
at least 50 or 100 m3/hour and/or at most 500 or 1000 m 3/hour, for example 400 m3/hour;
the liquid mixture which is pumped away from the working chamber, for example, by
the dredge pump, contains at least 10% and/or at most 35 or 40 or 50% dry matter,
preferably between 20 and 30%, such as about 25% dry matter (too little dry matter
is inefficient, too much leads to clogging of the from the workroom extending drain
pipe); in the work room, depending of the prevailing water pressure, a pneumatic overpressure,
preferably at least 0.01 or 0.25 or 0.5 or 1 or 2 or 2.5 or 5 or at most 5 bar (in
practice usually not higher than 3 bar) increased with respect to atmospheric pressure;
the groundwater level directly below the caisson has been temporarily artificially
lowered to a distance, preferably at least 0.5 or 1 meter, below the ceiling of the
workroom; the ground water level is inside the working chamber, in particular when
using a dredge pump, such that preferably of the dredge pump, the head is at least
0.5 or 1 meter under water; the supporting arm carries at its extremity an excavating
member, for example dredge pump with, for example, cutting head; the dredge pump/excavation
element is connected to a water supply pipe and a soil/dredge sludge pipe, which both
pipes debouch outside the working chamber; the working chamber has a maximum height
of 5 or 10 meters during the immersion of the caisson (the vertical distance between
the levelled soil (formed by the substrate to be excavated) of the workroom and the
ceiling (formed by the caisson bottom) of the workroom).
[0014] Possible alternatives for the suspension point and/or the excavation element: water
cannon or bucket or jet needles or dredge wheel or grab or plough or harrow; excavating
element on an articulated arm with, for example, fixed pivot point; the suspension
point moves along rigid arm suspended around a vertical axis; the suspension point
is movable along rails at e.g. ceiling; the suspension point is located on a chassis
running over the ground. Preferably, the movements of the excavating element become
one or more of measured, recorded and visualized with the use of an apparatus, for
example a camera, which is placed inside the workspace, for example for dimensional
representation where soil has been dredged away.
[0015] Preferably, data, for example one or more of power, speed, flow rate, fluid pressure,
flow rate and dry matter content, of one or more of the excavating element, the cutting
head and the contents of the dredge sludge pipe are measured and/or recorded, for
example to control process efficiency.
[0016] If desired, the working space can be filled with, preferably solid, filling material,
such as granular material such as sand or hardening material such as concrete, after
completion of the sinking.
[0017] The work space has, for example, seen in plan view, an elongated, for instance rectangular,
shape, for example a length at least 1.5 times the width, for example 15 meters wide
and 25 meters long. For example, a straight side is at least 10 meters long.
[0018] The dry matter content of the dredge sludge can, for example, be determined by measuring
the density of the dredge sludge.
[0019] The dredge sludge discharge pipe is preferably provided with one or more sensors
sensitive to the contents of the pipe, for instance for measuring the flow velocity
and/or pressure of the liquid inside the pipe, preferably near the pipe end debouching
into the working space. For example, the dredge sludge pipe is at least 10 or 50 or
100 meters long.
[0020] The terms "excavation element", "dredge element", "pump housing" and "dredge pump"
can be considered as synonymous with each other.
[0021] The accompanying drawing shows one of the many possible embodiments of the invention.
FIG. 1 AC schematically shows the three main phases during traditional sinking, with
people in the workspace;
FIG. 2 and 3 show perspectives view of an embodiment of the inventive dredge arm in
operation from opposite view directions;
FIG. 4 is a perspective view of a detail of FIG. 3;
FIG. 5 is a perspective view of another detail of FIG. 3, at two different times during
disassembly;
FIG. 6 schematically shows the application of the invention in the workspace;
FIG. 7 shows a water cannon as an excavating element on an articulated arm with fixed
pivot point;
FIG. 8 shows how the suspension point moves along a rigid arm suspended rotatably
about a vertical axis; the excavating element is a bucket;
FIG. 9 shows Jet needles as an alternative excavation element;
FIG. 10 shows the suspension point movable along rails on the ceiling, the dredge
wheel is excavation element;
FIG. 11 shows the suspension point on an undercarriage running over the ground, the
dredge head is excavation element;
FIG. 12 shows a gripper as excavation element; and
FIG. 13 shows a plow or harrow as an excavation element.
[0022] FIG. 1A shows the beginning of the excavation in the workspace, where a worker is
in the workspace. An airlock is indicated by 11. In FIG. 1B the workspace is completely
excavated so that the caisson can move downwards. There are now three workers in the
workspace. In FIG. 1C, the sinking is completed, the desired final depth is achieved
with the caisson. In this example, the working space is filled with filling material,
such as hardening material such as concrete.
[0023] Meaning of the reference signs: 1 arm; 2 bottom caisson; 3 dredge head; 4 water jet;
5 camera; 6 water level; 7 level local groundwater; 8 lighting; 9 suspension point
arm 1; 10 sliding guide of suspension point 9; 11 lid; arrow X direction of slide
movement arm 1; arrow A outflowing water, for example water jet; arrow B incoming
dredge sludge.
[0024] The dredge head 3 pivots about a horizontal axis relative to the arm 1; the arm 1
pivots about a vertical axis with respect to the bottom 2 and can slide in its longitudinal
direction (arrow X).
[0025] The dredge head 3 contains a pump which emits water via the cutting head (arrow A)
and draws dredge material behind the cutting head (arrow B). The supply and discharge
lines for water and dredge sludge run from the head 3 along the arm 1 to the suspension
point 9 of the arm and from there up through the mounting hole in the caisson bottom
2 and open out of the working chamber into a water source or a water source. grout.
[0026] With disassembled arm 1 (Fig. 5, so the arm 1 is missing in Fig. 5), the sliding
guide 10 can be seen at the lower end of the vertical suspension tube 9. The suspension
tube 9 is mounted on top of the bottom 2 in Fig. 5 by mounting means (e.g. threaded
ends) and can be designed with a lifting device. The lower end of the mounting tube
can be retracted into the bottom 2. In the retracted position (right-hand image of
Fig. 5), the mounting hole can be closed airtight from below with a cover 11 so that
the mounting hole is freely accessible from above for handling the suspension tube.
When the suspension tube is installed according to the regulations, the mounting hole
is closed air-tight from above and the suspension tube can be fitted leak-free at
the bottom of the bottom 2 (left-hand picture of fig. 5). Thus, the air-tightness
of the workroom is ensured during operation and also during the assembly/disassembly
of the excavation device.
[0027] FIG. 6 shows a workspace that is partially submerged. In the flooded part the dredger
head 3 is active and is flooded. In the part where the bottom of the workroom is dry,
water jets supplied by water cannon 4 are active. The water-sand mixture made by the
water jets flows to the lower area where the dredger head is active. With a camera
5, the process inside the workspace is supervised from outside the workspace. Water
canon 4 and camera 5 are located above the liquid mirror 6 in the working chamber.
In order to keep the upper part of the workroom dry, the groundwater level is artificially
lowered directly from the level 7 to the level 6 below the caisson by using a pneumatic
pressure well above the atmospheric pressure in the workroom.
[0028] At the beginning of the process of sinking of the caisson the working chamber is
at a pneumatic pressure, for example, approximately equal to the atmospheric pressure,
it is in the course of the process of lowering elevated dependent from the local groundwater
pressure at the depth at which the caisson is located in order to control the height
of the dry space sufficiently accurately, in order to artificially and temporarily
reduce the groundwater level in the workroom. This pressure increase is as a rule
at least 0.01 or 0.25 or 0.5 bar.
[0029] The features disclosed herein can be taken together individually in any other conceivable
combination and permutation to provide an alternative to the invention. Included are
also technical equivalents and genus or generalizations of the revealed features.
A feature of an example is also generally applicable within the scope of the invention.
A feature disclosed herein, for example of an example, can be readily generalized
for inclusion in a general definition of the invention, for example to be found in
a patent claim.
[0030] The invention also relates to an apparatus for carrying out the method defined in
one of the accompanying claims.
1. Method of mechanized and remote, from outside the workspace, controlled, digging out
of the workroom under a structure, such as pneumatic caisson, with the aim to sink
the caisson for example where the caisson is at least 5 meters high and moves vertically
downwards during sinking over a distance of at least 5 meters, whereby the method
is used in an area with relatively high local water level and during the sinking the
caisson with its complete weight rests directly or with the interposition of one or
more form-retaining bodies on the ground and does not float on a liquid such as water;
wherein at the underside of the at least substantially airtight bottom of the caisson
there is a downwardly extending cutting edge which laterally delimits the at least
substantially airtight working chamber; and the caisson bottom forms the ceiling of
the workroom and the ground forms the bottom of the workroom, and by excavating the
workroom the caisson sinks under its own weight in the soil and becomes a complete
or partial underground or underwater construction work; the caisson bottom sinks below
the local water level below and around the caisson; by introducing air the air pressure
in the working chamber is increased and the water level below the caisson is thus
temporarily reduced, so that the working chamber remains at least partly dry;
the air pressure in the workroom is increased in the course of the sinking process
depending on the locally prevailing water pressure at the depth at which the caisson
is located in order to control the height of the dry space inside the workroom with
sufficient accuracy, in order to maintain the artificially and temporarily reduced
water level in the work room;
the substrate that is excavated in the workspace is preferably sandy soil;
in the working chamber a wet excavation technique, such as a dredge technique, is
used, so in the working chamber there is a layer of water and an excavating member
protruding into the water, such as a dredge element, is employed in the working chamber,
wherein this excavating element is part of an excavating device.
2. Method according to claim 1, wherein the excavating device comprises one or more of
the following: a rotating central attachment; an adjustable arm construction with
a length of at least 5 meters in the fully extended state, for instance from several
parts sliding or articulating, for example articulated, for a flexible range of the
free end with the excavating element thereby spatially movable; the excavating device
is suspended by its rotating central fixing to the ceiling of the working chamber
and/or excavates and erodes the ground, such as water bottom, of the working chamber
with the purpose of making the excavated soil pumpable.
3. Method as claimed in claim 1 or 2, the excavating element is equipped with soil loosening
provisions, comprising one or more of: one or more water sprays; a mechanically ground
eroding element, such as a milling or cutting head, and a dredge pump, for excavating
and pumping the soil as dredge spoil of soil and water.
4. Method according to one of claims 1 - 3, one works with water jets coming from the
ceiling of the working chamber and directed to the substrate, and the water jets come
from a water cannon, which is arranged in the working chamber, for example is suspended
from the ceiling, these water jets treat the soil in areas which are unreachable for
the dredge element, in which a water jet is relatively thick and powerful and is capable
of independently eroding the soil; and/or
the dredge element is controlled in distance from its suspension point and pivotally
around its suspension point and the water cannon is controlled in direction, depending
on the image shown on the screen, and thus at least substantially the entire bottom
area is covered and thus the entire bottom area is excavated, and this management
takes place from outside the workspace.
5. Method according to one of Claims 1 - 4, with one or more of the following:
- the excavation element removes at least 10 m3/hour net of dry matter, such as sand,
from the work room;
- the water level directly below the caisson is temporarily artificially lowered to
a distance of at least 0.5 meters below the ceiling of the work room so that an air
layer with a height of at least 0.5 meters is located in the work room above the layer
of water;
- the excavating element is connected to a water supply pipe and a dredge sludge discharge
pipe, which both pipes discharge outside the working chamber;
- to the water cannon, and via the water-supply pipe to the excavating element, water
is supplied from outside the working chamber and a dredge sludge of soil and water
is made inside the working chamber by the action of the excavating element and the
water cannon and the dredge sludge is brought via the sludge drain pipe, which is
connected to the excavation element, outside the working chamber;
- in the area where the from the water cannon coming jets are active the water layer
is absent so that the water jets are able to process the bottom as well as possible,
in the area where the excavating element is operable, the water layer is at least
0.5 meters deep in order to properly dredge;
- at the end of the process, the working space is filled with filling material, such
as hardening concrete.
6. A method according to any one of claim s 1 - 5, the excavating element (3) pivots
relative to the arm (1) around a horizontal axis; and/or the arm (1) pivots about
a vertical axis with respect to the bottom (2) and/or can slide in its longitudinal
direction (arrow X).
7. Method according to one of Claims 1 - 6, with one or more of the following: the excavation
element comprises a pump which emits water via the cutting head (arrow A) and/or draws
dredge material behind the cutting head (arrow B); the supply and discharge lines
for water and dredge sludge run from the excavation element (3) along the arm (1)
to the suspension point of the arm and from there upwards, for example into the installation
hole, through the caisson bottom (2) and debouches outside the working chamber in
a water source resp. sludge container.
8. Method according to one of claims 1 to 7, with one or more of: the arm (1) is mounted
to the lower end of a vertical suspension tube mounted on top of the bottom (2) by
mounting means and projects through a mounting hole in the bottom (2); the lower end
of the mounting tube can be retracted into the bottom (2); in the retracted position
the mounting hole can be closed airtight from below with a cover so that the mounting
hole is freely accessible from above for handling the suspension tube; when the suspension
tube is mounted, the mounting hole is sealed airtight from above and the suspension
tube can extend from below the bottom (2) leak-free; thus the air-tightness of the
working chamber is ensured during operation and also during the assembly/disassembly
of the excavation device.
9. A method according to any one of claims 1 - 8, with one or more of: the floor of the
work room shows a difference in level and the work room is partially submerged; in
the lower, flooded part, the excavation element (3) is active and is flooded; in the
upper part where the bottom of the workroom is dry, water jets supplied by the water
cannon (4) are active; the mixture of water and soil, such as sand, that is made by
the water jets flows to the lower area where the excavation element is active.
10. Method according to one of claims 1 - 9, with a camera (5), the process inside the
work room is supervised from outside the work room; and/or water cannon (4) and/or
camera (5) are located above the liquid level (6) in the workroom.
11. Method according to any one of claims 1-10, liquid such as water is used for excavating
the soil, and the excavation takes place under wet conditions and the material released
from the soil is made pumpable by mixing with this liquid, and material released is
pumped out of the workroom and flows out of the workroom by a pipe extending from
the workroom; and/or where the workroom is without any diver during sinking.
12. Method according to one of Claims 1 - 11, the suspension points of the water cannons
are located mutually and/or in relation to the suspension point of the excavating
element at a distance, preferably measured parallel to the caisson bottom, for instance
at least 0.5 meters mutually respectively 3 meters to the excavation element; and/or
the excavation element and/or water cannons/water jets are controlled in distance
to their suspension point and/or in direction to cover a bottom area and thus to be
able to excavate over the entire range.
13. Method according to one of Claims 1 - 12, with one or more of: the dredge pump pumping
at least 50 and/or at most 1000 m3/h; the liquid mixture that is pumped out of the
working chamber contains a minimum of 10% and/or a maximum of 50% dry matter; in the
working chamber there is a pneumatic overpressure of at least 0.25 and/or a maximum
of 5 bar increased in relation to atmospheric pressure; the workroom has a maximum
height of 10 meters during the sinking of the caisson.
14. Method according to one or more of claims 1-13, and data, for example one or more
of power, rotational speed, flow rate, fluid pressure, flow amount and dry matter
content, of one or more of the excavation element, the cutting head and the contents
of the dredge sludge pipe are measured and/or recorded, for example to control the
process efficiency; and/or the dredge sludge discharge pipe is provided with one or
more sensors sensitive to the contents of the pipe, for instance for measuring the
flow velocity and/or pressure of the liquid inside the pipe, preferably near the pipe
end opening into the working space.
15. Method as claimed in any of the claims 1-14, with one or more of: the dredge sludge
discharge pipe is at least 10 meters long; the work space has, in plan view, an elongate,
for example rectangular, shape, for example a length at least 1.5 times the width;
of the working chamber a straight side is, at least 10 meters long.