BACKGROUND OF THE INVENTION
Field of the Invention
[0001] The present invention relates to a control device, an air conditioner, a control
method, and a program.
Description of Related Art
[0003] When a heating operation of an air conditioner is performed in an environment in
which outdoor air temperature is low, an outdoor unit may be frosted. In order to
prevent the reduction of heating capacity due to frosting, a defrosting operation
is performed to remove the frost of the outdoor unit. In general, conditions of an
elapsed time from the end of a previous defrosting operation or outdoor air temperature
and the temperature of an outdoor unit heat exchanger are set, and when the conditions
are established, a defrosting operation is started in many cases.
[0004] In contrast, Patent Document 1 discloses a technology for deciding the start of a
de-icing operation (a defrosting operation) with two conditional expressions including
a linear equation employing the temperature of an outdoor unit heat exchanger and
outdoor air temperature as variables. In the technology disclosed in Patent Document
1, values of parameters of the two conditional expressions are adjusted on the basis
of an operation time of a previous de-icing operation. In this way, it is possible
to start the de-icing operation at an appropriate timing according to a frosted state
of the outdoor unit heat exchanger.
[Patent Documents]
[0005] [Patent Document 1] Japanese Unexamined Patent Application, First Publication No.
2008-14593
SUMMARY OF THE INVENTION
[0006] However, even though a start condition of the defrosting operation is established
during a prohibition period of the defrosting operation, the start condition may not
be established at the end of the prohibition period due to a sudden decrease and the
like in the outdoor air temperature due to a change and the like in weather. In such
a case, the defrosting operation may not be performed or the start of the defrosting
operation may be delayed. Therefore, since the outdoor unit heat exchanger is frosted,
there is a possibility that the performance of a heating operation is reduced or it
is not possible to remove frost in a next defrosting operation.
[0007] Therefore, an object of the present invention is to provide a control device, an
air conditioner, a control method, and a program, by which it is possible to solve
the above problems.
[Solution to Problem]
[0008] According to an aspect of the present invention, the control device includes an operation
executing unit that performs a defrosting operation after a prohibition period of
the defrosting operation ends on the basis of an establishment state of a start condition
of the defrosting operation during the prohibition period regardless of whether the
start condition is established at an end time point of the prohibition period.
[0009] According to an aspect of the present invention, when a total time, for which the
start condition is established during the prohibition period, is equal to or more
than a predetermined threshold value, the operation executing unit is configured to
start the defrosting operation even though the start condition is not established
at the end time point of the prohibition period.
[0010] According to an aspect of the present invention, when the start condition is established
with a predetermined time before the prohibition period ends, the operation executing
unit is configured to start the defrosting operation even though the start condition
is not established at the end time point of the prohibition period.
[0011] According to an aspect of the present invention, the control device further includes
a parameter setting unit that is configured to set a parameter related to an operational
maintenance of the defrosting operation on the basis of a trend of operation times
of defrosting operations performed in the past.
[0012] According to an aspect of the present invention, when the operation times become
shorter than an operation time of an immediately previous defrosting operation more
than a predetermined number of consecutive times, the parameter setting unit is configured
to increase the length of the prohibition period.
[0013] According to an aspect of the present invention, when the operation times become
longer than an operation time of an immediately previous defrosting operation more
than a predetermined number of consecutive times, the parameter setting unit is configured
to decrease the length of the prohibition period.
[0014] According to an aspect of the present invention, when the operation times reach a
predetermined upper limit value, which has been set for the defrosting operation,
more than a predetermined number of consecutive times, the parameter setting unit
is configured to increase the upper limit value.
[0015] According to an aspect of the present invention, an air conditioner includes the
control device according to any one of the above.
[0016] According to an aspect of the present invention, a control method includes a step
of calculating an establishment state of a start condition of a defrosting operation
during a prohibition period of the defrosting operation, and a step of determining
whether to perform the defrosting operation after the prohibition period ends on the
basis of the establishment state regardless of whether the start condition is established
at an end time point of the prohibition period.
[0017] According to an aspect of the present invention, a program causes a computer to serve
as a means that is configured to calculate an establishment state of a start condition
of a defrosting operation during a prohibition period of the defrosting operation,
and a means that is configured to determine whether to perform the defrosting operation
after the prohibition period ends on the basis of the establishment state regardless
of whether the start condition is established at an end time point of the prohibition
period.
[0018] According to the aforementioned control device, air conditioner, control method,
and program, it is possible to prevent non-execution of a defrosting operation.
BRIEF DESCRIPTION OF THE DRAWINGS
[0019]
FIG. 1 is an overall view showing an example of an air conditioner in an embodiment
of the present invention.
FIG. 2 is a diagram showing a start condition of a defrosting operation in an embodiment
of the present invention.
FIG. 3 is a functional block diagram showing an example of a control device of an
air conditioner in an embodiment of the present invention.
FIG. 4 is a diagram showing a control method of a defrosting operation in an embodiment
of the present invention.
FIG. 5 is a diagram showing an adjustment method of parameters related to operational
maintenance of a defrosting operation in an embodiment of the present invention.
FIG. 6 is a flowchart showing an example of a control method in an embodiment of the
present invention.
DETAILED DESCRIPTION OF THE INVENTION
<Embodiment>
[0020] Hereinafter, defrost control in an air conditioner according to an embodiment of
the present invention will be described with reference to FIG. 1 to FIG. 6.
[0021] FIG. 1 is an overall view showing an example of an air conditioner in an embodiment
of the present invention.
[0022] An air conditioner 1 according to a first embodiment includes a refrigerant circuit
10. The refrigerant circuit 10 includes a compressor 2, an indoor heat exchanger 3,
an expansion valve 4, an outdoor heat exchanger 5, a two way valve 6, and a four way
valve 7. The compressor 2, the indoor heat exchanger 3, the expansion valve 4, the
outdoor heat exchanger 5, the two way valve 6, and the four way valve 7 are connected
to a refrigerant pipe 20 capable of circulating a refrigerant.
[0023] The refrigerant circuit 10 includes a main circuit 100 used in a heating operation,
a positive cycle defrosting operation, and a reverse cycle defrosting operation, and
a bypass pipe 200 used only in the positive cycle defrosting operation.
[0024] The main circuit 100 includes a heat exchanger-side main circuit 110 connected to
a first terminal 7A and a second terminal 7B of terminals of the four way valve 7,
and a compressor-side main circuit 120 connected to a third terminal 7C and a fourth
terminal 7D of the terminals of the four way valve 7 when starting from the four way
valve 7. In other words, the heat exchanger-side main circuit 110 and the compressor-side
main circuit 120 are connected to each other via the four way valve 7.
[0025] The heat exchanger-side main circuit 110 is provided with the indoor heat exchanger
3, the expansion valve 4, the outdoor heat exchanger 5. The compressor-side main circuit
120 is provided with the compressor 2.
[0026] In the four way valve 7, four pipelines connected to the terminals can be connected
by two pairs or these pairs can be switched. Specifically, the four way valve 7 can
connect a pair of the first terminal 7A and the fourth terminal 7D and a pair of the
second terminal 7B and the third terminal 7C. Furthermore, the four way valve 7 can
connect a pair of the first terminal 7A and the third terminal 7C and a pair of the
second terminal 7B and the fourth terminal 7D.
[0027] In this way, it is possible to switch a connection relation between the heat exchanger-side
main circuit 110 and the compressor-side main circuit 120. When the second terminal
7B and the third terminal 7C of the four way valve 7 are connected to each other,
a high temperature and high pressure refrigerant discharged from the compressor 2
flows through a path (a cooling path) from the second terminal 7B to the outdoor heat
exchanger 5. When the first terminal 7A and the third terminal 7C of the four way
valve 7 are connected to each other, the high temperature and high pressure refrigerant
discharged from the compressor 2 flows through a path (a heating path) from the first
terminal 7A to the indoor heat exchanger 3.
[0028] The refrigerant circuit 10 of the air conditioner 1 is provided with the bypass pipe
200 as described above. The bypass pipe 200 is a refrigerant pipe that connects between
the compressor 2 and the four way valve 7 (between a bypass start point 20A and a
bypass end point 20B provided between the expansion valve 4 and the outdoor heat exchanger
5 of the heat exchanger-side main circuit 110) at a discharge side of the compressor
2 of the compressor-side main circuit 120. The bypass pipe 200 is provided with the
two way valve 6, so that it is possible to open and close the bypass pipe 200. In
the normal heating operation, the cooling operation, and the reverse cycle defrosting
operation, the two way valve 6 is closed.
[0029] Circulation of a refrigerant in a heating operation will be described. In the heating
operation, the four way valve 7 is in the connection relation of the heating path.
The refrigerant is compressed by the compressor 2 to reach high temperature and high
pressure, enters the third terminal 7C of the four way valve 7, and then flows from
the first terminal 7A to the indoor heat exchanger 3. In the indoor heat exchanger
3, the refrigerant is cooled and condensed by heat exchange, and instead, heat is
given to indoor air outside the indoor heat exchanger 3. The indoor air is blown by
an indoor-side blower 13. The condensed refrigerant flows into the expansion valve
4 and reaches low temperature and low pressure. The refrigerant exiting the expansion
valve 4 flows into the outdoor heat exchanger 5, is heated by outdoor air, and is
evaporated and vaporized in the outdoor heat exchanger 5. The vaporized refrigerant
returns to the compressor 2 through the second terminal 7B and the fourth terminal
7D of the four way valve 7. By continuously repeating the above cycle, the air conditioner
1 performs the heating operation.
[0030] During the heating operation, since the temperature of the air outside the outdoor
heat exchanger 5 is deprived of heat by the refrigerant and becomes lower as described
above, the temperature of the surface of the outdoor heat exchanger 5 is lowered to
a subzero temperature range, and therefore frost may occur and may form layers. Therefore,
heat conduction of the heat exchanger may be disturbed and thus heat exchange efficiency
may be reduced.
[0031] In order to remove the frost, two types of defrosting operations are known. That
is, there are a positive cycle defrosting operation (a bypass cycle defrosting operation,
hereinafter, referred to as DfP) and a reverse cycle defrosting operation (hereinafter,
referred to as DfR).
[0032] The DfP indicates a defrosting operation for defrosting the outdoor heat exchanger
5 by circulating the refrigerant via the bypass pipe 200 that sends some of refrigerant
gas discharged from the compressor 2 to the outdoor heat exchanger 5 during the heating
operation. By opening the two way valve 6, the DfP is performed.
[0033] The circulation of the refrigerant during the DfP will be described. During the DfP,
the connection relation of the heating path is maintained in the four way valve 7,
so that the refrigerant circulation during the aforementioned heating operation is
maintained. In addition, the two way valve 6 is opened and the refrigerant also flows
through the bypass pipe 200, so that some of the high temperature and high pressure
refrigerant discharged from the compressor 2 is sent to the outdoor heat exchanger
5 without passing through the indoor heat exchanger 3. In this way, heat is applied
to the outdoor heat exchanger 5 to perform defrosting.
[0034] In addition, in the DfP, since some of the high temperature and high pressure refrigerant
to be originally sent to the indoor heat exchanger 3 is sent to the outdoor heat exchanger
5, it is possible to continue the heating operation while performing the defrosting,
but the heating capability is reduced to about 1/3 as compared with the normal heating
operation. Furthermore, since the amount of the refrigerant sent to the outdoor heat
exchanger 5 is a part of the total refrigerant, the defrosting capability becomes
lower as compared with the DfR to be described later.
[0035] On the other hand, the DfR indicates a defrosting operation in which defrosting is
performed by circulating the refrigerant in the heat exchanger-side main circuit 1
10 in a direction opposite to that of the heating operation. The refrigerant is circulated
in the direction opposite to that of the heating operation, so that all of the refrigerant
gas discharged from the compressor 2 is sent to the outdoor heat exchanger 5. In this
way, in the DfR, it is possible to strongly melt frost as compared with the DfP. However,
since the DfR is performed by switching the four way valve 7 to the connection relation
of the cooling path, substantially the same refrigerant circulation as that in the
cooling operation is performed except that air is not blown to the indoor heat exchanger
3. Therefore, during the DfR, since the heating operation is stopped and indoor heat
deprived, the room temperature drops.
[0036] The circulation of the refrigerant during the DfR will be described. The refrigerant
is compressed by the compressor 2 to reach high temperature and high pressure, enters
the third terminal 7C of the four way valve 7, and then flows from the second terminal
7B to the outdoor heat exchanger 5. In the outdoor heat exchanger 5, the refrigerant
is cooled and condensed by heat exchange, and instead, heat is given to outdoor air
outside the outdoor heat exchanger 5. Therefore, the condensed refrigerant flows into
the expansion valve 4 and reaches low temperature and low pressure. The refrigerant
exiting the expansion valve 4 flows into the indoor heat exchanger 3, is heated by
indoor air, and is evaporated and vaporized in the indoor heat exchanger 3. At this
time, heat is taken away from indoor air outside the indoor heat exchanger 3. In the
cooling operation, the indoor air that has reached low temperature is blown by the
indoor-side blower 13 and is used for indoor cooling, but in the DfR, no air is blown.
The vaporized refrigerant enters the first terminal 7A of the four way valve 7, and
returns to the compressor 2 through the fourth terminal 7D.
[0037] The aforementioned cycle is continuously repeated.
[0038] In the present embodiment, the air conditioner 1 is further provided with an outside
air temperature sensor 25 and a heat exchanger temperature sensor 35, and further
includes a control device 201 for switching the three operation modes of the aforementioned
heating operation, DfP and DfR. A start condition M of the defrosting operation (DfP
or DfR) will be described using FIG. 2.
[0039] FIG. 2 is a diagram showing the start condition of the defrosting operation in an
embodiment of the present invention. A line L1 shown in FIG. 2 denotes the start condition
M of the defrosting operation when an outdoor heat exchanger temperature ThoR is set
as a vertical axis and an outside air temperature ThoA is set as a horizontal axis.
This relation, for example, can be expressed by α (=outside air temperature ThoA-outdoor
heat exchanger temperature ThoR) (α is a predetermined constant). The outdoor heat
exchanger temperature ThoR is a temperature measured by the heat exchanger temperature
sensor 35. The outside air temperature ThoA is a temperature measured by the outside
air temperature sensor 25.
[0040] When the relation between the outdoor heat exchanger temperature ThoR and the outside
air temperature ThoA is in a region below the line L1 (outside air temperature ThoA-outdoor
heat exchanger temperature ThoR≥α), for example, when the outside air temperature
ThoA and the outdoor heat exchanger temperature ThoR are in a relation indicated by
a point P1, the start condition M of the defrosting operation is established.
[0041] When the relation between the outdoor heat exchanger temperature ThoR and the outside
air temperature ThoA is in a region above the line L1 (outside air temperature ThoA-outdoor
heat exchanger temperature ThoR<α), for example, when they are in a relation indicated
by a point P2, the start condition M of the defrosting operation is not established.
[0042] During the heating operation, when the relation between the outdoor heat exchanger
temperature ThoR and the outside air temperature ThoA satisfies the start condition
M of the defrosting operation, the control device 201 stops the heating operation
and starts the defrosting operation of the DfP or the DfR. When the defrosting operation
is started and a predetermined stop condition of the defrosting operation is established,
the control device 201 stops the defrosting operation and resumes the heating operation.
The stop condition of the defrosting operation, for example, is that the temperature
difference (ThoA-ThoR) is within a predetermined threshold value. Furthermore, an
upper limit value is set for the operation time of the defrosting operation. When
the upper limit value passes from the start of the defrosting operation, the control
device 201 ends the defrosting operation. Furthermore, as described above, since the
defrosting operation reduces the capability of the original heating operation, when
the defrosting operation is performed once, execution is prohibited for a while (a
predetermined prohibition period). That is, even though the start condition M of the
defrosting operation is established during this prohibition period, the control device
201 performs no defrosting operation during the prohibition period.
[0043] For example, it is assumed that the relation between the outdoor heat exchanger temperature
ThoR and the outside air temperature ThoA is the relation indicated by the point P1
during the prohibition period of the defrosting operation. When the same relation
is maintained after the prohibition period passes, the control device 201 starts the
defrosting operation after the end of the prohibition period. However, it is assumed
that when the outside air temperature suddenly decreases before the end of the prohibition
period, the relation between the outdoor heat exchanger temperature ThoR and the outside
air temperature ThoA is changed to a relation indicated by a point P3 and is maintained.
Then, even though the prohibition period passes, since the start condition M of the
defrosting operation is not established, the control device 201 performs no defrosting
operation. In such a case, while the start condition M of the defrosting operation
is established during the prohibition period, there is a possibility that the outdoor
heat exchanger 5 is frosted. However, in the related control, until the outdoor heat
exchanger temperature ThoR decreases due to the outside air temperature ThoA, for
example, they are in a relation as indicated by a point P4, since the control device
201 performs no defrosting operation, the heating operation is in an operation state
with low efficiency during that time period. In contrast, the control device 201 of
the present embodiment has a function of starting the defrosting operation according
to the establishment state of a frost formation condition during the prohibition period
after the end of the prohibition period of the defrosting operation.
[0044] Next, the function of the control device 201 will be described using FIG. 3.
[0045] FIG. 3 is a functional block diagram showing an example of the control device of
the air conditioner in an embodiment of the present invention.
[0046] As shown in FIG. 3, an outdoor unit 1A includes the control device 201. The control
device 201, for example, is a computer including a central processing unit (CPU) and
the like. The control device 201 includes an outside air temperature acquiring unit
41, an outdoor heat exchanger temperature acquiring unit 42, an operation executing
unit 43, a parameter setting unit 44, a storage unit 45, and a timer 46.
[0047] The outside air temperature acquiring unit 41 acquires the outside air temperature
(outside air temperature ThoA) of the outdoor unit 1A through the outside air temperature
sensor 25.
[0048] The outdoor heat exchanger temperature acquiring unit 42 acquires the temperature
(outdoor heat exchanger temperature ThoR) of the outdoor heat exchanger 5 of the outdoor
unit 1A through the heat exchanger temperature sensor 35.
[0049] The operation executing unit 43 performs the heating operation and the defrosting
operation. The operation executing unit 43 switches the heating operation and the
defrosting operation by mainly controlling the two way valve 6 and the four way valve
7. For example, when the start condition M of the defrosting operation is established,
the operation executing unit 43 switches the heating operation to the defrosting operation.
Furthermore, for example, when the end condition of the defrosting operation is established,
the operation executing unit 43 switches the defrosting operation to the heating operation.
As described above, the operation executing unit 43 can perform the defrosting operation
of the DfP or the DfR. The operation executing unit 43, for example, may select the
DfP or the DfR in accordance with the temperature difference between the outdoor heat
exchanger temperature ThoR and the outside air temperature ThoA, and perform the selected
type of defrosting operation. In addition, since a control method for preventing the
non-execution of the defrosting operation according to the present embodiment can
be applied without distinction between the DfP and the DfR, the defrosting operation
will be described without particular distinction in the following description. On
the basis of the establishment state of the start condition M of the defrosting operation
during the prohibition period of the defrosting operation, the operation executing
unit 43 performs the defrosting operation regardless of whether the start condition
M is established at the end time point of the prohibition period.
[0050] The parameter setting unit 44 sets parameters related to the operational maintenance
of the defrosting operation. The parameters related to the operational maintenance,
for example, include a length of the prohibition period, the upper limit value of
the operation time of the defrosting operation, and the like. On the basis of the
trend of operation times of defrosting operations performed in the past, the parameter
setting unit 44 appropriately adjusts the parameters related to the operational maintenance
of the defrosting operation.
[0051] The storage unit 45 stores various types of information of the outside air temperature
ThoA, the outdoor heat exchanger temperature ThoR, the parameters such as the length
of the prohibition period and the upper limit value of the operation time of the defrosting
operation, and the like.
[0052] The timer 46 measures time.
[0053] Next, start control of the defrosting operation based on the establishment state
of the defrosting operation start condition during the prohibition period according
to the present embodiment will be described.
[0054] FIG. 4 is a diagram showing the control method of the defrosting operation in an
embodiment of the present invention. FIG. 4 (a) shows related defrost control. The
time T1 to the time T2 is the prohibition period of the defrosting operation. It is
assumed that at the time T4 to the time T4' of the prohibition period, the start condition
M is established and then the prohibition period ends due to the non-establishment
of the start condition M. At the end of the prohibition period, the start condition
M is not established. In such a case, in the related control, the defrosting operation
is not performed immediately after the end of the prohibition period. Thereafter,
when the start condition M is established at the time T3, the defrosting operation
is started. In the case of such control, frost formation may occur from the time T1
to the time T2, and in the heating operation from the time T2 to the time T3, heating
capacity may be reduced.
[0055] FIG. 4 (b) to FIG. 4 (d) show the defrost control of the present embodiment. FIG.
4 (b) shows a control method of the defrosting operation when the control device 201
of the present embodiment has operated the air conditioner 1 in the same operation
state as that of FIG. 4 (a). That is, at the time T4 to the time T4' of the prohibition
period, the start condition M of the defrosting operation is established, and then
the prohibition period ends due to the non-establishment of the start condition M.
The operation executing unit 43 calculates the period of time between the time T4
and the time T4', in which the start condition M of the defrosting operation is established,
by using the timer 46. When the calculated period of time is equal to or more than
a predetermined period of time "h1", the operation executing unit 43 starts the defrosting
operation after the end of the prohibition period of the defrosting operation (the
time T2). In such a case, it is irrelevant whether the start condition M is established
at the time T2.
[0056] FIG. 4 (c) shows a case where the start condition M of the defrosting operation has
been established at each of the times T5 to T5', the times T6 to T6', and the times
T7 to T7' of the prohibition period and the prohibition period has ended with the
start condition M not being established. In such a case, the operation executing unit
43 calculates each period of time between the times T5 to T5', the times T6 to T6',
and the times T7 to T7', in which the start condition M of the defrosting operation
has been established, by using the timer 46, and calculates the sum of the three time
zones in which the start condition M has been established. When the calculated total
time is equal to or more than the predetermined period of time "h1", the operation
executing unit 43 starts the defrosting operation at the time T2 even though the start
condition M has not been established at the time T2 at which the prohibition period
ends.
[0057] FIG. 4 (d) shows a case where the start condition M of the defrosting operation has
been established once within a predetermined period of time "h2" immediately before
the prohibition period ends and the prohibition period has ended with the start condition
M not being established. In such a case, by using the timer 46, the operation executing
unit 43 confirms whether the start condition M has been established after the time
T8 before "h2" with reference to the time T2 at which the prohibition period ends.
When the start condition M has been established even once in this time zone, the operation
executing unit 43 starts the defrosting operation even though the start condition
M is not established at the time T2.
[0058] According to the control method of the defrosting operation shown in FIG. 4 (b) to
FIG. 4 (d), (A) when the total time in which the start condition M is established
during the prohibition period is equal to or more than the predetermined period of
time "h1" or (B) when the start condition M is established even once within the predetermined
period of time "h2" before the end of the prohibition, the defrosting operation is
started immediately after the prohibition period ends regardless of whether the start
condition M is established at the end time point of the prohibition period. In this
way, even in a state in which frost formation is proceeding during the prohibition
period, it is possible to quickly perform defrosting after the end of the prohibition
period and to prevent the reduction of heating capability. In addition, the length
of the prohibition period, for example, is 35 minutes, the predetermined period of
time "h1", for example, is 20 minutes, and the predetermined period of time "h2",
for example, is 3 minutes.
[0059] Next, a method for adjusting the parameters related to the operational maintenance
of the defrosting operation according to the present embodiment will be described.
[0060] FIG. 5 is a diagram showing an adjustment method of the parameters related to the
operational maintenance of the defrosting operation in an embodiment of the present
invention.
[0061] FIG. 5 (a) shows a case where an execution time Dx (x: 1 to n) of the defrosting
operation has been continuously shortened n times. That is, D1>D2>···>Dn. Such a case
is considered to be an operational environment (the outside air temperature ThoA,
the outdoor heat exchanger temperature ThoR and the like) in which frost hardly occurs.
Accordingly, since the necessity to perform the defrosting operation is relatively
low, it is preferable that a long time is allocated to the heating operation as much
as possible. Accordingly, the parameter setting unit 44 sets the length of the prohibition
period longer by a predetermined period of time "h3". In this way, it is possible
to decrease the number of opportunities of performing the defrosting operation and
to prevent the heating operation from being disturbed more than necessary. In addition,
after the prohibition period is adjusted, when the execution time of the defrosting
operation is continuously shortened n times, the predetermined period of time "h3"
may be further added with a predetermined period of time "h4" for an initial value
(for example, 35 minutes) of the prohibition period as an upper limit value of an
increment. In addition, the value "h3" to be added at a time, for example, is 5 minutes
and the upper limit value "h4", for example, is 10 minutes.
[0062] FIG. 5 (b) shows a case where the execution time Dx (x: 1 to n) of the defrosting
operation has been continuously increased n times. That is, D1<D2<···<Dn. Such a case
is considered to be an operational environment in which frost easily occurs or a state
in which defrosting is not possible in a one-time defrosting operation and unmelted
frost easily occurs. Accordingly, it is preferable to increase the number of executions
of the defrosting operation and to operate the defrosting operation such that defrosting
can be reliably performed. Accordingly, the parameter setting unit 44 sets the length
of the prohibition period shorter by a predetermined period of time "h5". In this
way, it is possible to increase the number of opportunities of performing the defrosting
operation and to prevent frost formation and unmelted frost. In addition, after the
prohibition period is adjusted, when the execution time of the defrosting operation
is continuously increased n times, the predetermined period of time "h5" may be further
subtracted with a predetermined period of time "h6" for the initial value (for example,
35 minutes) of the prohibition period as an upper limit value of a decrement. In addition,
the value "h5" to be subtracted at a time, for example, is 5 minutes, and the upper
limit value "h6", for example, is 10 minutes.
[0063] FIG. 5 (c) shows a case where the execution time Dx (x: 1 to n) of the defrosting
operation has continuously expired n times. That is, D1=D2=···=Dn=upper limit value
(for example, is 15 minutes) of the execution time of the defrosting operation. Such
a case is considered to be an operational environment in which frost easily occurs
or a state in which defrosting is not possible in a one-time defrosting operation
and unmelted frost easily occurs. Accordingly, it is preferable to increase the execution
time of the defrosting operation and to operate the defrosting operation such that
defrosting can be performed without unmelted frost. Accordingly, the parameter setting
unit 44 sets the upper limit value of the operation time longer by a predetermined
period of time "h7". In this way, it is possible to increase the execution time of
the defrosting operation and to prevent frost formation and unmelted frost. In addition,
after the operation time is adjusted, when the defrosting operation has continuously
expired n times, the predetermined period of time "h7" may be further added with a
predetermined period of time "h8" for the initial value (for example, 15 minutes)
of the operation time as an upper limit value. In addition, the value "h7" to be added
at a time, for example, is 5 minutes and the upper limit value "h8", for example,
is 10 minutes.
[0064] In addition, even though the execution time of the defrosting operation has continuously
expired n times, the length of the prohibition period may be set shorter by "h5" in
the same manner as the adjustment described in FIG. 5 (b).
[0065] According to the adjustment method of the operational parameters shown in FIG. 5
(a) to FIG. 5 (c), on the basis of the trend of the operation times of the defrosting
operation, (a) when the operation time of the defrosting operation of each time has
been shorter than an operation time at the time of immediately previous execution
more than a predetermined number of consecutive times up to a defrosting operation
performed previous time, the length of the prohibition period is increased. Furthermore,
(b) when the operation time of the defrosting operation of each time has been longer
than an operation time at the time of immediately previous execution more than a predetermined
number of consecutive times up to a defrosting operation performed previous time,
the length of the prohibition period is decreased. Furthermore, (c) when the operation
time of each time has reached an upper limit value of the operation time more than
a predetermined number of consecutive times up to a defrosting operation performed
previous time, the upper limit value of the operation time is increased. In this way,
it is possible to appropriately adjust the operational maintenance of the defrosting
operation in accordance with a frosting state, and it is possible to prevent the reduction
of heating capacity by preventing the progression of frost formation and unmelted
frost.
[0066] Next, the process flow of the execution control of the defrosting operation will
be described using FIG. 6.
[0067] FIG. 6 is a flowchart showing an example of the control method in an embodiment of
the present invention. In addition, in the following description, a case where the
operation executing unit 43 performs the defrosting operation of the DfR will be described
as an example; however, the same control can also be applied to a case of performing
the defrosting operation of the DfP.
[0068] Firstly, when a user starts to use heating. Then, the control device 201 starts the
heating operation (step S11). Specifically, the operation executing unit 43 controls
the four way valve 7 such that refrigerant gas discharged from the compressor 2 circulates
the heating path (the path connecting the first terminal 7A to the third terminal
7C, connecting the second terminal 7B to the fourth terminal 7D, and allowing the
refrigerant gas to flow from the compressor 2 to the indoor heat exchanger 3), and
closes the two way valve 6. Next, the operation executing unit 43 determines whether
the outside air temperature ThoA and the outdoor heat exchanger temperature ThoR satisfy
the defrosting start condition M (for example, outside air temperature ThoA-outdoor
heat exchanger temperature ThoR>α) (step S12). In addition, at the start of the heating
operation, the operation executing unit 43 may continue the heating operation without
performing this determination during a predetermined prohibition period (for example,
35 minutes).
[0069] When the temperature difference (ThoA-ThoR) does not exceed the predetermined constant
α (step S12: No), the operation executing unit 43 continues the process of step S11
and continuously performs the heating operation.
[0070] When the temperature difference (ThoA-ThoR) exceeds α (step S12: Yes), the operation
executing unit 43 determines that the outdoor heat exchanger 5 is frosted. Next, the
operation executing unit 43 determines whether the present time is the prohibition
period of the defrosting operation (step S13). When the present time is not the prohibition
period of the defrosting operation (step S13: No), the operation executing unit 43
performs the defrosting operation (step S14). Specifically, the operation executing
unit 43 switches the four way valve 7 to the connection relation of the cooling path
while keeping the two way valve 6 closed, and performs an operation. In this way,
the discharged refrigerant gas is sent to the outdoor heat exchanger 5, so that defrosting
is performed. The timer 46 measures an elapsed time after the start of the defrosting
operation. The operation executing unit 43 records the start time of the defrosting
operation in the storage unit 45 by using the timer 46. Next, the operation executing
unit 43 determines whether defrosting of the outdoor heat exchanger 5 has been achieved,
and stops the defrosting operation when it is determined that the defrosting has been
achieved. In relation to the determination regarding whether the defrosting has been
achieved, for example, it may be determined that the defrosting has been achieved
when the temperature difference (ThoA-ThoR) is within a predetermined threshold value.
When a predetermined upper limit value has passed from the start of the defrosting
operation, the operation executing unit 43 stops the defrosting operation. In addition,
when the upper limit value of the operation time of the defrosting operation is updated
in step S16 to be described later, the operation executing unit 43 performs determination
of time-up with the updated value. When the defrosting operation ends, the operation
executing unit 43 switches the four way valve 7 to the connection relation of the
heating path and resumes the heating operation. Furthermore, the operation executing
unit 43 records the end time of the defrosting operation in the storage unit 45 by
using the timer 46. When the defrosting operation ends, the prohibition period of
the defrosting operation is reached. The timer 46 measures an elapsed time since entering
the prohibition period.
[0071] Next, the operation executing unit 43 calculates the operation time of the defrosting
operation by subtracting the start time of the defrosting operation from the end time
of the defrosting operation, and records the calculated operation time in the storage
unit 45 in correlation with the start time or the end time of a defrosting operation
of this time (step S15).
[0072] Next, the parameter setting unit 44 adjusts the parameters related to the operational
maintenance of the defrosting operation (step S16). For example, when the operation
time of the defrosting operation recorded in the storage unit 45 has become short
a predetermined number of consecutive times, the parameter setting unit 44 adds h3
(for example, 5 minutes) to a current prohibition period (for example, 35 minutes)
and updates the prohibition period with the added value (for example, 40 minutes).
Furthermore, when the operation time of the defrosting operation has become long a
predetermined number of consecutive times, the parameter setting unit 44 subtracts
h5 (for example, 5 minutes) from the current prohibition period (for example, 35 minutes)
and updates the prohibition period with the subtracted value (for example, 30 minutes).
Furthermore, when the operation time of the defrosting operation has expired a predetermined
number of consecutive times, the parameter setting unit 44 adds h7 (for example, 5
minutes) to an upper limit value (for example, 15 minutes) of a current operation
time and updates the upper limit value of the operation time with the added value
(for example, 20 minutes).
[0073] On the other hand, when the present time is the prohibition period of the defrosting
operation (step S13: Yes) or when the defrosting operation ends and the prohibition
period is reached, the operation executing unit 43 continuously performs the same
determination as that of step S12. Then, when the start condition M is established,
the operation executing unit 43 records the established time in the storage unit 45,
and when the start condition M is not established, the operation executing unit 43
records the unestablished time in the storage unit 45 (step S17). Furthermore, the
operation executing unit 43 determines whether the prohibition period has ended (step
S18). For example, when the elapsed time from the start of the prohibition period
measured by the timer 46 reaches a predetermined setting value (for example, 35 minutes),
the operation executing unit 43 determines that the prohibition period has ended.
When the length of the prohibition period has been updated in the process of step
S16, the operation executing unit 43 performs determination with the updated value.
[0074] When the prohibition period has not ended (step S18; No), the operation executing
unit 43 continuously performs the process of step S17.
[0075] When the prohibition period has ended (step S18; Yes), the operation executing unit
43 determines whether to perform the defrosting operation on the basis of the establishment
state of the start condition M during the prohibition period (step S19). For example,
on the basis of the established time and the unestablished time of the start condition
M recorded in the storage unit 45, the operation executing unit 43 calculates the
sum of the times during which the start condition M is established during the prohibition
period. When the total time exceeds h1 (for example, 20 minutes), the operation executing
unit 43 determines to perform the defrosting operation. Furthermore, when the start
condition M has been established even once between the time before h2 after the end
of the prohibition period and the end time, the operation executing unit 43 determines
to perform the defrosting operation. When it is determined to perform the defrosting
operation (step S19; Yes), the operation executing unit 43 starts the defrosting operation
immediately after the end of the prohibition period. That is, after the end of the
prohibition period, the operation executing unit 43 performs the process of step S14
within a predetermined time (for example, within 30 seconds). When it is determined
to perform no defrosting operation (step S19; No), the operation executing unit 43
continues the heating operation.
[0076] According to the present embodiment, even though the start condition M of the defrosting
operation is established during the prohibition period of the defrosting operation,
even when the start condition M is not established at the end of the prohibition period
due to a subsequent sudden change in outside air temperature, it is possible to avoid
non-execution of the defrosting operation, to perform the defrosting operation after
the end of the prohibition period, and to perform defrosting. Furthermore, on the
basis of the trend of the operation times of the past defrosting operations, when
defrosting is not sufficient, it is possible to promote defrosting by shortening the
prohibition period or extending the upper limit value of the defrosting operation
time. When defrosting is performed more than necessary, it is possible to limit an
opportunity of performing the defrosting operation by extending the prohibition period.
By these functions, it is possible to realize the operational maintenance of the defrosting
operation according to the design intention of the air conditioner 1.
[0077] All functions or some functions of the control device 201, for example, may be realized
by hardware composed of a large scale integration (LSI), an application specific integrated
circuit (ASIC), a programmable logic device (PLD), a field-programmable gate array
(FPGA), an integrated circuit and the like. Furthermore, all functions or some functions
of the control device 201, for example, may be configured by a computer including
a processor such as a CPU. In such a case, the process of each processing in the control
device 201, for example, can be realized when the CPU and the like of the control
device 201 execute a program. The program executed by the control device 201 may be
recorded on a computer-readable recording medium, and the process of each processing
may be realized when the program recorded on the recording medium is read and executed.
In addition, the control device 201 is assumed to include an OS and hardware such
as a peripheral device. Furthermore, the computer-readable recording medium, for example,
is a portable medium such as a flexible disk, a magneto-optical disc, a ROM, and a
CD-ROM, and a storage device such as a hard disk embedded in the control device 201.
Furthermore, the computer-readable recording medium may also include a medium for
dynamically holding a program for a short time period such as a communication line
in the case where the program is transmitted via a network such as the Internet or
a communication line such as a telephone line, and a medium for holding the program
for a constant time period such as a volatile memory in a computer system serving
as a server or a client in that case. Furthermore, the aforementioned program may
also be a program for realizing some of the aforementioned functions, or a program
capable of realizing the aforementioned functions in combination with a program in
which the aforementioned functions have been previously recorded in the computer system.
[0078] Besides, the elements in the aforementioned embodiment can be appropriately replaced
with well-known elements without departing from the scope of the present invention.
Furthermore, the technical range of the present invention is not limited to the aforementioned
embodiment and various modifications can be made within the scope of the present invention.
[Reference Signs List]
[0079]
1 Air conditioner
1A Outdoor unit
201 Control device
2 Compressor
3 Indoor heat exchanger
4 Expansion valve
5 Outdoor heat exchanger
6 Two way valve
7 Four way valve
7A First terminal
7B Second terminal
7C Third terminal
7D Fourth terminal
10 Refrigerant circuit
20 Refrigerant pipe
20A Bypass start point
20B Bypass end point
200 Bypass pipe
100 Main circuit
110 Heat exchanger-side main circuit
120 Compressor-side main circuit
201 Control device
41 Outside air temperature acquiring unit
42 Outdoor heat exchanger temperature acquiring unit
43 Operation executing unit
44 Parameter setting unit
45 Storage unit
46 Timer