Technical Field
[0001] The present invention relates to an elevator renewal construction method for replacing
an existing elevator with a new elevator and to an elevator control panel to be used
for renewal of an elevator.
Background Art
[0002] In order to cope with aging degradation of a device or to improve performance such
as energy saving performance, elevator renewal for replacing an existing elevator
with a new elevator is performed. During an elevator renewal construction period,
an operation of the elevator is required to be continuously suspended for a long period
of time.
[0003] Thus, for example, especially in a condominium or a hospital with a large number
of elderly people, a long elevator out-of-service period has been a major obstacle
to the renewal. Accordingly, in the renewal of the elevator, a continuous elevator
out-of-service period is required to be shortened as much as possible in view of convenience
of a user.
[0004] In order to shorten the continuous elevator out-of-service period, there is proposed
an elevator controller including a new transmission control unit and a new/old transmission
conversion unit. The new transmission control unit uses a new serial transmission
system different from an old serial transmission system at least in data transmission
speed. The new/old transmission conversion unit includes a new transmission control
CPU, an old transmission control CPU, and a dual-port memory. The new transmission
control CPU is connected to the new transmission control unit. The old transmission
control CPU is connected to an old transmission control unit of the old serial transmission
system, which is provided on a hall side. The dual-port memory is connected to both
of the new transmission control CPU and the old transmission control CPU. The dual-port
memory stores data of the old serial transmission system, which is transmitted from
an old transmission conversion unit provided on the hall side, via the old transmission
control CPU and retains the thus stored data so that the stored data is accessible
from the new transmission control unit via the new transmission control CPU. Meanwhile,
the dual-port memory stores data of the new serial transmission system, which is transmitted
from the new transmission control unit, via the new transmission control CPU and retains
the thus stored data so that the stored data is accessible from the old transmission
control unit provided on the hall side via the old transmission control CPU (see,
for example, Patent Literature 1) .
Citation List
Patent Literature
Summary of Invention
Technical Problem
[0006] In the elevator renewal construction method using the elevator controller, which
is described in Patent Literature 1, however, time required for renewal of an elevator
control panel is shortened with continuous use of components used in an existing elevator
without replacement thereof. Thus, there is a problem in that the above-mentioned
elevator renewal construction method does not contribute to the shortening of the
continuous elevator out-of-service period in the elevator renewal for replacing the
existing elevator with the new elevator.
[0007] Further, in the elevator controller described in Patent Literature 1, the elevator
control panel is required to include the new transmission control CPU, the old transmission
control CPU, and the dual-port memory so that the elevator controller converts transmission
signals to be transmitted in the different transmission systems and retains the converted
transmission signals. Hence, there are problems in that a configuration becomes complex
and that cost increases.
[0008] The present invention has been made to solve the problems described above, and has
an object to provide an elevator renewal construction method, with which a continuous
elevator out-of-service period in an elevator renewal construction period can be shortened,
and an elevator control panel having a simple configuration, with which cost can be
reduced.
Solution to Problem
[0009] The elevator renewal construction method according to one embodiment of the present
invention, for renewing at least one device in an existing elevator, includes the
steps of: dividing a process of renewal construction work into a series of divided
construction work steps, each being determined as such a unit that the elevator operation
becomes normally possible after finishing of each of the divided construction work
steps; and executing the renewal construction work in accordance with the series of
divided construction work steps, in which one of the series of the divided construction
work steps includes the steps of: replacing an old control panel of the existing elevator
with a new control panel; connecting an old cable for an old car device, which has
connected the old car device and the old control panel of the existing elevator to
each other, to a communication conversion unit, which is provided in the new control
panel, and is configured to mutually convert a communication method between an old
communication system for the old control panel and a new communication system for
the new control panel, which has a higher communication speed than a communication
speed of the old communication system to enable transmission and reception of a larger
capacity of data; and converting a new serial communication system to an old serial
communication system by the new control panel via the communication conversion unit
and the old cable to control the old car device through the old serial communication
system.
[0010] The elevator control panel according to one embodiment of the present invention includes
an elevator control unit configured to control a car device and a hall device of an
elevator through the new communication system having the higher communication speed
than the communication speed of the old communication system to enable the transmission
and the reception of the larger capacity of data, and the communication conversion
unit, which is connected to the elevator control unit, and is configured to mutually
convert the communication system between the old communication system and the new
communication system, in which the communication conversion unit includes one CPU
and one memory and is provided so as to be removable from the elevator control panel.
Advantageous Effects of Invention
[0011] The elevator renewal construction method according to one embodiment of the present
invention includes the steps of: dividing a process of renewal construction work into
a series of divided construction work steps, each being determined as such a unit
that the elevator operation becomes normally possible after finishing of each of the
divided construction work steps; and executing the renewal construction work in accordance
with the series of divided construction work steps, in which one of the series of
the divided construction work steps includes the steps of: replacing an old control
panel of the existing elevator with a new control panel; connecting an old cable for
an old car device, which has connected the old car device and the old control panel
of the existing elevator to each other, to a communication conversion unit, which
is provided in the new control panel, and is configured to mutually convert a communication
method between an old communication system for the old control panel and a new communication
system for the new control panel, which has a higher communication speed than a communication
speed of the old communication system to enable transmission and reception of a larger
capacity of data; and converting a new serial communication system to an old serial
communication system by the new control panel via the communication conversion unit
and the old cable to control the old car device through the old serial communication
system.
[0012] Moreover, the elevator control panel according to one embodiment of the present invention
includes an elevator control unit configured to control a car device and a hall device
of an elevator through the new communication system having the higher communication
speed than the communication speed of the old communication system to enable the transmission
and the reception of the larger capacity of data, and the communication conversion
unit, which is connected to the elevator control unit, and is configured to mutually
convert the communication system between the old communication system and the new
communication system, in which the communication conversion unit includes one CPU
and one memory and is provided so as to be removable from the elevator control panel.
[0013] Thus, the elevator renewal construction method, with which the elevator can be used
even during the elevator renewal construction period so that the continuous elevator
out-of-service period in the elevator renewal construction period is shortened, and
the elevator control panel having the simple configuration, with which the cost can
be reduced, can be obtained.
Brief Description of Drawings
[0014]
FIG. 1 is a configuration view for illustrating an elevator device to which an elevator
renewal construction method according to a first embodiment of the present invention
is to be applied.
FIG. 2 is an explanatory table for showing details of renewal and main devices to
be replaced in divided construction work steps in the elevator renewal construction
method according to the first embodiment of the present invention.
FIG. 3 is a block configuration diagram for illustrating an initial state in the elevator
device to which the elevator renewal construction method according to the first embodiment
of the present invention is to be applied.
FIG. 4 is a block configuration diagram for illustrating a state after replacement
of a control panel in the elevator device to which the elevator renewal construction
method according to the first embodiment of the present invention is applied.
FIG. 5 is a hardware configuration diagram for illustrating a communication conversion
board in the elevator control panel according to the first embodiment of the present
invention.
FIG. 6 is a block configuration diagram for illustrating a state after replacement
of a hall device and a car device in the elevator device to which the elevator renewal
construction method according to the first embodiment of the present invention is
applied.
FIG. 7 is an explanatory diagram for illustrating a connection relationship of a cable
in the elevator device to which the elevator renewal construction method according
to the first embodiment of the present invention is applied.
FIG. 8 is an explanatory diagram for illustrating a relationship between a new elevator
device to which the elevator renewal construction method according to the first embodiment
of the present invention is applied and an old battery device panel.
Description of Embodiments
[0015] A description is now given of an elevator renewal construction method and an elevator
control panel to be used for renewal of an elevator according to preferred embodiments
of the present invention referring to the accompanying drawings, and throughout the
drawings, like or corresponding components are denoted by like reference symbols to
describe those components. The elevator control panel is hereinafter simply referred
to also as "control panel".
First Embodiment
[0016] FIG. 1 is a configuration view for illustrating an elevator device to which an elevator
renewal construction method according to a first embodiment of the present invention
is to be applied. In FIG. 1, in a machine room 1, there are provided a hoisting machine
2 including a hoisting motor, a control panel 3, and a speed governor 4. In a hoistway
5, there are provided a car 6, a counterweight 7, a main rope 8, guide rails 9, and
a terminal slowdown switch 10. The main rope 8 is configured to connect the car 6
and the counterweight 7. A door driving device 11, which includes a door motor, and
a car operating panel 12 are provided to the car 6. A hall operating panel 14 is provided
at a hall 13. Buffers 16 are provided in a pit 15. The control panel 3 and an on-car
station 18 are connected to each other through a traveling cable 17. The on-car station
18 and a car device are connected to each other. The on-car station 18 has a door
opening/closing control function and a relaying function with another car device.
[0017] In this case, the "car device" denotes a device provided to and around the car, such
as the door driving device 11, the car operating panel 12, and the on-car station
18. The "hall device" denotes a device provided at and around the hall, such as the
hall operating panel 14. A "hoistway device" denotes, for example, the terminal slowdown
switch 10 and a hoistway cable not shown in FIG. 1.
[0018] In the first embodiment of the present invention, in order to shorten a continuous
elevator out-of-service period in an elevator renewal construction period, renewal
construction work is divided into a plurality of divided construction work steps.
At the same time, there is developed the elevator control panel capable of controlling,
for example, both of a new hoisting machine and an old hoisting machine so that the
elevator is available after completion of each of the divided construction work steps.
[0019] Specifically, the shortening of the continuous elevator out-of-service period in
the elevator renewal construction period presupposes the availability of the elevator
at the time of completion of each of the divided construction work steps of the renewal
construction work. For example, in a condominium, the elevator is required to be available
in morning and night hours in which a large number of users use the elevator for,
for example, commuting to and from work and school. In a restaurant tenant building,
the elevator is required to be available in evening and night business hours.
[0020] Thus, work time that can be ensured for one day is set. Based on a result of analysis
of details of work and time required for each part of work, the details of work, which
can be completed within the time, are set for each of the divided construction work
steps. The details of renewal and main devices to be replaced in the divided construction
work steps are shown in FIG. 2. In FIG. 2, the renewal construction work is divided
mainly into five divided construction work steps. However, the divided construction
work steps are required to be organized into groups depending on specifications of
the elevator.
[0021] More specifically, after a series of the divided construction work steps of replacing
old devices with new devices are organized into groups, between which an elevator
available time period is set, the renewal construction work is carried out. Further,
the elevator available time period is determined in accordance with a frequency of
activation of the elevator before the renewal and a purpose of use of a building.
Further, the renewal construction work is carried out after the divided construction
work steps are organized into the divided construction work step groups, each of which
is completed in the least work time ensured for one day and after which the elevator
is available. Specifically, a normal operation mode and an installation work mode
are set. Each time the divided construction work step is completed, the installation
work mode is switched to the normal operation mode to bring the elevator into a service
available state so as to perform a normal operation for providing elevator service
to a passenger.
(Renewal construction Method)
[0022] Subsequently, with reference to FIG. 3 to FIG. 8 together with FIG. land FIG. 2,
an elevator renewal construction method according to the first embodiment of the present
invention is described. FIG. 3 is a block configuration diagram for illustrating an
initial state in the elevator device to which the elevator renewal construction method
according to the first embodiment of the present invention is to be applied.
[0023] In FIG. 3, when the elevator device is in the initial state, an old hall device 200
and an old hall device 300 are connected to an old control panel 100 before replacement,
through an old serial communication system. The old control panel 100 includes an
old elevator control board 110 configured to control, for example, operations of the
old hall device 200, the old car device 300, and the old hoisting machine (not shown).
(Divided Construction work Step 1: Machine Room Improvement)
[0024] For the elevator device, in a divided construction work step 1 shown in FIG. 2, the
elevator control panel is replaced. FIG. 4 is a block configuration diagram for illustrating
a state after the replacement of the control panel in the elevator device to which
the elevator renewal construction method according to the first embodiment of the
present invention is applied.
[0025] The reason why the elevator control panel is first replaced in the divided construction
work step 1 is as follows. When the hall device or the car device is first replaced,
exchange of information with the replaced device increases. Thus, it becomes difficult
to deal with the exchange of the information with the existing elevator control panel
to give rise to the need of modification. Thus, when the hall device or the car device
is replaced after the elevator control panel is first replaced in the divided construction
work step 1, a new elevator control panel, which is provided after the replacement,
can deal with the exchange of the information with a new hall device or a new car
device.
[0026] In FIG. 4, as a result of the replacement of the old control panel 100 with a new
control panel 100A, the old hall device 200 and the old car device 300 are connected
to the new control panel 100A. The new control panel 100A includes a new elevator
control board 110A in place of the old elevator control board 110 illustrated in FIG.
3.
[0027] The new elevator control board 110A has not only a function of controlling operations
of, for example, a new hall device, a new car device, and a new hoisting machine,
which are described later, but also a function of controlling operations of the old
hall device 200, the old car device 300, and the old hoisting machine with change
of setting of parameters in accordance with each of the divided construction work
steps shown in FIG. 2.
[0028] However, the new elevator control board 110A communicates with the car device through
a new serial communication system, for example, a controller area network (CAN) communication
system, which enables transmission and reception of a larger capacity of data than
that through an old serial communication system. Thus, the new elevator control board
110A and the old car device 300 cannot directly communicate with each other. As an
example of the old serial communication system, a communication speed of 4, 800 bps
is given. As an example of the CAN communication system, a communication speed of
122.88 kbps is given. Thus, a data transmission speed of the new serial communication
system is about 10 times or higher than a data transmission speed of the old serial
communication system.
[0029] Further, a larger capacity of data can be transmitted and received through communication
through the CAN communication system than through the old serial communication system.
Thus, a display device mounted in the new car device has the effect of displaying
a larger capacity of data than on a display device mounted in the old car device.
A new function, which is not provided to the old car device, for example, a touch-type
car operating function integral with the display device, can be achieved in the new
car device.
[0030] The data to be transmitted and received through the communication between the new
elevator control board 110A and the old car device 300 includes, for example, state
information of the door driving device 11, a display command for the car operating
panel 12, operation information of, for example, a button or a switch of the car operating
panel 12, and an announce command.
[0031] Thus, the new control panel 100A further includes a communication conversion board
120A serving as a communication conversion unit configured to mutually convert the
communication system between the old serial communication system and the CAN communication
system. FIG. 5 is a hardware configuration diagram for illustrating the communication
conversion board in the elevator control panel according to the first embodiment of
the present invention. In FIG. 5, the communication conversion board 120A includes
a CPU 121 and a RAM 122.
[0032] The CPU 121 is configured to convert a format of data transmitted from the new elevator
control board 110A to a format of data compatible with the old car device 300 and
store the data in the RAM 122. Further, the CPU 121 is configured to convert a format
of data transmitted from the old car device 300 to a format of data compatible with
the new elevator control board 110A and store the data in the RAM 122. The format
refers to a data structure such as the number of bits.
[0033] Further, the CPU 121 is configured to extract and output the format-converted data
from the RAM 122 in accordance with a request from the new elevator control board
110A. The CPU 121 is also configured to extract and output the format-converted data
from the RAM 122 in accordance with a request from the old car device 300. As a result,
the new elevator control board 110A and the old car device 300 can communicate with
each other via the communication conversion board 120A.
[0034] With use of the communication conversion board 120A, even when, for example, a transmission
cycle is not changed, the communication speed increases. Therefore, a data amount
transmittable per cycle increases. Further, with the increase in data amount, an error
check function can be enhanced.
[0035] The communication conversion board 120A is provided so as to be removable from the
new control panel 100A. Specifically, after the replacement of a hall device and a
car device described later, the above-mentioned devices and the new elevator control
board 110A can directly communicate with each other without using the communication
conversion board 120A. Thus, the communication conversion board 120A is not required
after the replacement.
[0036] Accordingly, through the removal of the communication conversion board 120A from
the new control panel 100A, the communication conversion board 120A can be reused
at another place. Thus, cost can be reduced. The communication conversion board may
be provided between the new elevator control board 110A and the old hall device 200
as needed.
[0037] In the above-mentioned manner, after the step of replacing the old control panel
of an existing elevator with the new control panel, the new control panel 100A controls
the old car device 300 via the communication conversion unit (communication conversion
board 120A). As a result, the normal operation for providing the elevator service
to the passenger can be performed. Thus, the passenger can use the elevator between
the steps of the renewal construction work. Accordingly, the continuous elevator out-of-service
period in the elevator renewal construction period can be shortened.
(Divided Construction work Step 2: Car Improvement) and (Divided Construction work
Step 3: Hoistway and Hall Improvement)
[0038] Next, for the elevator device, the car device is replaced in a divided construction
work step 2 shown in FIG. 2, and the hall device and the hoistway device are replaced
in the divided construction work step 3 shown in FIG. 2. In the divided construction
work step 3, only representative hall devices are described. Any of the divided construction
work step 2 and the divided construction work step 3 may be first carried out. FIG.
6 is a block configuration diagram for illustrating a state after the replacement
of the hall device and the car device in the elevator device to which the elevator
renewal construction method according to the first embodiment of the present invention
is applied.
[0039] In FIG. 6, the old hall device 200 is replaced by a new hall device 200A, and the
old car device 300 is replaced by a new car device 300A. As a result, the new hall
device 200A and the new car device 300A are connected to the new control panel 100A.
[0040] In the divided construction work step 1, a cable for old devices to be connected
to the new control panel 100A is continuously used in accordance with continuous use
of the old hall device 200 and the old car device 300. However, a kind of a connector
for a cable for the old hall device 200 and the old car device 300 and a circuit thereof
are different from those of a connector for the new control panel 100A. Hence, the
connectors cannot be directly connected to each other.
[0041] Thus, as illustrated in FIG. 7, a relay harness 130A is connected to the new control
panel 100A. FIG. 7 is an explanatory diagram for illustrating a connection relationship
of a cable in the elevator device to which the elevator renewal construction method
according to the first embodiment of the present invention is applied.
[0042] In FIG. 7, in the divided construction work step 1, an old cable is connected to
the relay harness 130A. After that, when the hall device and the car device are replaced
in the divided construction work step 2 and the divided construction work step 3,
the old cable and the relay harness 130A are removed so that a new cable is connected
to the new control panel 100A.
[0043] Hence, with the relay harness 130A, the cable for old devices can be connected to
the new control panel 100A. Accordingly, the renewal with the continuous use of the
cable for old devices can be achieved. The relay harness 130A may be formed integrally
with the communication conversion board 120A.
(Divided Construction work Step 4: Replacement of Hoisting Machine) and (Divided Construction
work Step 5: Work for Earthquake Safety)
[0044] Subsequently, for the elevator device described above, the hoisting machine is replaced
in a divided construction work step 4 shown in FIG. 2. Work for earthquake safety
is carried out as a divided construction work step 5 as needed to thereby complete
the renewal of the elevator.
[0045] The representative renewal construction method from the divided construction work
step 1 to the divided construction work step 5 has been described above. Besides,
a power failure emergency automatic hall device, which may be affected by a difference
in power supply specifications of the elevator in the divided construction work step
1, is described.
[0046] The power failure emergency automatic hall device is a device configured to move
a car to the nearest floor with a battery power supply to rescue a passenger in case
of power failure. When a power failure is detected by the power failure emergency
automatic hall device, power is supplied from an old battery device panel to the old
control panel and a car control circuit in an old on-car station in an old elevator
device and power is supplied from a battery in the new control panel to the new elevator
control board and a car control circuit in a new on-car station in a new elevator
device.
[0047] Accordingly, also in the divided construction work step 1, the car control circuit
of the old on-car station is continuously used. Thus, the power is required to be
supplied from the battery in the new control panel. However, power supply specifications
are different due to a difference between the new control panel and the old control
panel. Thus, the power cannot be supplied from the battery in the new control panel
to the car control circuit in the old on-car station. Further, when the battery, which
has the power supply specifications compatible with the car control circuit in the
old on-car station, is used in the new control panel, the power supply cannot be supplied
after the car control circuit in the old on-car station is replaced by the car control
circuit in the new on-car station in the divided construction work step 2.
[0048] Thus, only for the power for the car control circuit in the old on-car station, a
system configured to supply the power from the old battery device is constructed.
FIG. 8 is an explanatory diagram for illustrating a relationship between the new elevator
device and the old battery device panel to which the elevator renewal construction
method according to the first embodiment of the present invention is applied.
[0049] In FIG. 8, when the power failure is detected, the new elevator control board 110A
of the new control panel 100A outputs a driving instruction (power failure emergency
automatic landing instruction) to a control circuit of the old battery device panel.
When the driving instruction is input to the control circuit of the old battery, the
power is supplied from a battery in the old battery device panel via an inverter to
the car control circuit in the old on-car station and outputs an operation signal
(power failure emergency automatic landing operation signal) to the new elevator control
board 110A.
[0050] In this manner, an operation of the new control panel 100A and an operation of the
old battery device panel are synchronized with each other. When the operation signal
is not input from the control circuit in the old battery device panel although the
new elevator control board 110A outputs the driving instruction, it is determined
that an abnormality has occurred.
[0051] After the old on-car station is replaced with the new on-car station in the divided
construction work step 2, the old battery device panel is not required and is therefore
removed.
[0052] As described above, according to the first embodiment, the elevator renewal construction
method includes the steps of: dividing the renewal construction work into the plurality
of divided construction work steps; executing corresponding part of the renewal construction
work in each of the plurality of execution steps; and normally operating the elevator
between the plurality of divided construction work steps.
[0053] According to the first embodiment, the elevator renewal construction method includes
the steps of : replacing the old control panel of the existing elevator with the new
control panel; connecting the old cable for the old car device, which has connected
the old car device and the old control panel of the existing elevator to each other,
to the communication conversion unit of the new control panel; controlling the old
car device by the new control panel via the communication conversion unit and the
old cable through the serial communication system; replacing the old car device with
the new car device; replacing the old cable with the new cable and connecting the
new control panel and the new car device to each other through the new cable; and
controlling the new car device by the new control panel through the large-capacity
communication system having a larger transmission capacity than that through the serial
communication system.
[0054] Further, according to the first embodiment, the elevator control panel includes the
elevator control unit configured to control the car device and the hall device of
the elevator through the large-capacity communication system having a larger transmission
capacity than that through the serial communication system and the communication conversion
unit, which is connected to the elevator control unit, and is configured to mutually
convert the communication system between the serial communication system and the large-capacity
communication system. The communication conversion unit includes one CPU and one memory,
and is provided so as to be removable from the elevator control panel.
[0055] Thus, the elevator renewal construction method, with which the elevator can be used
even during the elevator renewal construction period so that the continuous elevator
out-of-service period in the elevator renewal construction period is shortened, and
the elevator control panel having the simple configuration, with which the cost can
be reduced, can be obtained.
[0056] Further, in order to shorten the continuous elevator out-of-service period in the
elevator renewal construction period, the renewal construction work is divided into
the plurality of divided construction work steps. As a result, a working area for
each of the divided construction work steps can be limited to a specific area. Thus,
workability can be improved.
[0057] The communication conversion unit is configured so as to be removable from the elevator
control panel. As a result, the communication conversion unit can be removed from
the elevator control panel so as to be reused at another place. Thus, the cost can
be reduced.
[0058] In the embodiment described above, the communication conversion unit to be used in
the step of replacing the old car device with the new car device has been described.
However, the communication conversion unit may be applied, for example, when the old
hall device is replaced by the new hall device or when an old optional device is replaced
by a new optional device.
[0059] In the embodiment described above, the serial communication has been exemplified
as each of the old communication system and the new communication system. However,
the communication system is not limited to the serial communication. The present invention
is applicable to a communication system other than the serial communication.
Reference Signs List
[0060] 1 machine room, 2 hoisting machine, 3 control panel, 4 speed governor, 5 hoistway,
6 car, 7 counterweight, 8 main rope, 9 guide rail, 10 terminal slowdown switch, 11
door driving device, 12 car operating panel, 13 hall, 14 hall operating panel, 15
pit, 16 buffer, 17 traveling cable, 18 on-car station, 100 old control panel, 100A
new control panel, 110 old elevator control board, 110A new elevator control board
(elevator control unit), 120A communication conversion board (communication conversion
unit), 130A relay harness, 200 old hall device, 200A new hall device, 300 old car
device, 300A new car device, 121 CPU, 122 RAM
1. An elevator renewal construction method for renewing at least one device in an existing
elevator, comprising:
dividing a process of renewal construction work into a series of divided construction
work steps, each being determined as such a unit that the elevator operation becomes
normally possible after finishing of each of the divided construction work steps;
and
executing the renewal construction work in accordance with the series of divided construction
work steps,
wherein one of the series of the divided construction work steps comprises the steps
of:
replacing an old control panel of the existing elevator with a new control panel;
connecting an old cable for an old car device, which has connected the old car device
and the old control panel of the existing elevator to each other, to a communication
conversion unit provided in the new control panel; and
converting a new serial communication system to an old serial communication system
by the new control panel via the communication conversion unit and the old cable to
control the old car device through the old serial communication system.
2. The elevator renewal construction method according to claim 1, wherein the series
of divided construction work steps are determined so that each of the divided construction
work steps is completed in corresponding one of a series of construction periods,
each being ensured without interruption for each renewal work day in a renewal construction
period.
3. The elevator renewal construction method according to claim 1 or 2, further comprising
the steps of:
replacing the old car device with a new car device;
replacing the old cable with a new cable and connecting the new control panel and
the new car device through the new cable; and
controlling the new car device by the new control panel through the new serial communication
system different from the old serial communication system at least in data transmission
speed.
4. The elevator renewal construction method according to claim 3,
wherein the step of connecting the old cable to the communication conversion unit
provided in the new control panel comprises the step of connecting the old cable to
connecting the communication conversion unit via a relay harness having a connector
compatible with the old cable, and
wherein the step of connecting the new control panel and the new car device through
the new cable comprises the step of removing the old cable and the relay harness and
then directly connecting the new cable to the new control panel.
5. The elevator renewal construction method according to claim 3 or 4, further comprising
the steps of:
replacing an old hall device connected to the old control panel with a new hall device
after replacing the old control panel of the existing elevator with the new control
panel; and
replacing an old hoisting machine connected to the old control panel with a new hoisting
machine after replacing the old car device with the new car device and the old hall
device with the new hall device.
6. An elevator control panel, comprising:
an elevator control unit configured to control a car device and a hall device of an
elevator using a new serial communication system different from an old serial communication
system at least in data transmission speed; and
a communication conversion unit, which is connected to the elevator control unit,
and is configured to mutually convert a communication system between the old serial
communication system and the new serial communication system,
wherein the communication conversion unit includes one CPU and one memory, and is
provided so as to be removable from the elevator control panel.
7. The elevator control panel according to claim 6, wherein the communication conversion
unit is formed integrally with a relay harness having a connector compatible with
the old cable, which is to be connected to an old cable for an old car device of an
existing elevator.
8. An elevator renewal construction method for renewing at least one device in an existing
elevator, comprising the steps of:
replacing an old control panel of the existing elevator with a new control panel;
converting a communication system from a new serial communication system to an old
serial communication system through a communication conversion unit provided in the
new control panel so as to control an old car device through the old serial communication
system;
replacing the old car device with a new car device; and
controlling the new car device by the new control panel without using the communication
conversion unit through the new serial communication system.
9. An elevator renewal construction method for renewing at least one device in an existing
elevator, comprising the steps of:
replacing an old control panel of the existing elevator with a new control panel;
connecting an old cable for an old car device, which has connected the old car device
and the old control panel of the existing elevator to each other, to a communication
conversion unit provided in the new control panel;
converting a communication system from a new serial communication system to an old
serial communication system by the new control panel via the communication conversion
unit to control the old car device via the old cable through the old serial communication
system;
replacing the old car device with a new car device;
replacing the old cable with a new cable and connecting the new control panel and
the new car device to each other through the new cable; and
controlling the new car device by the new control panel through the new serial communication
system.
10. The elevator renewal construction method according to claim 8 or 9, wherein, in the
step of controlling the old car device, the new control panel controls the old car
device via the communication conversion unit to perform a normal operation for providing
elevator service to a passenger.