TECHNICAL FIELD
[0001] The present invention concerns a construction machine, in particular an earth-moving
machine such as an excavator provided with an articulated working arm.
BACKGROUND OF THE INVENTION
[0002] Earth-moving machines such as excavators are provided with a working arm that is
hinged to vehicle's body at a first extremity and that is provided with a working
element, e.g. a bucket, at its opposite extremity.
[0003] Such working arm may be a single arm or, more frequently, comprises a pair of booms
hinged one to the other between the working element and the vehicle's body as shown
in patent application
EP0607483A1.
[0004] Such articulated working arm and the working element are actuated by substantially
simple hydraulic circuits, e.g. via three cylinders and may reach a high digging depth.
However, the working elements cannot be lifted up to reach high working heights.
[0005] Indeed, a different typology of vehicles is used in such conditions, called "demolition
vehicles". Usually, such demolition vehicles cannot dig except thanks to very expensive
modification to the arm design.
[0006] Therefore, the need is felt to provide a construction vehicle which can be used for
both working operations, i.e. allowing high digging depth and at the same time allowing
the work at high heights.
[0007] An aim of the present invention is to satisfy the above mentioned needs in an economic
and optimized way.
SUMMARY OF THE INVENTION
[0008] The aforementioned aim is reached by a construction vehicle as claimed in the appended
set of claims.
BRIEF DESCRIPTION OF DRAWINGS
[0009] For a better understanding of the present invention, a preferred embodiment is described
in the following, by way of a non-limiting example, with reference to the attached
drawings wherein:
- Figure 1 is a schematic lateral view of a construction vehicle according to the present
invention;
- Figures 2A-2B are schematic lateral views of the construction vehicle according to
the present invention in first operative conditions;
- Figures 3A-3B are schematic lateral views of the construction vehicle according to
the present invention in second operative conditions; and
- Figures 4A and 4B are schematic section views through line IV-IV of figure 2A of a
portion of the vehicle according to the present invention in two different operative
conditions.
DETAILED DESCRIPTION OF THE INVENTION
[0010] Figure 1 discloses a construction vehicle 1, e.g. an excavator, comprising a body
2 carried in movable way by an undercarriage 3 movable with respect to the ground,
e.g. thanks to a crawler belt.
[0011] Vehicle 1 further comprises a working arm 4 carried in movable manner by body 2 and
provided with a working element 5, such as a bucket, at an extremity of the working
arm 4 opposite to the connection with body 2.
[0012] According to an aspect of the invention, working arm 4 comprises three booms 4a,
4b, 4c, hinged one with respect to the other between the working element 5 and the
body 2 of the vehicle 1.
[0013] In greater particular, a first boom 4a is hinged at a first extremity 4a' via a first
hinge 6 to vehicle's body 2 and at a second extremity 4a'' via a second hinge 7 to
a first extremity 4b' of a second boom 4b. A second extremity 4b'' of second boom
4b is then hinged via a third hinge 8 to a first extremity 4c' of a third boom 4c
whose a second extremity 4c'' is hinged via a fourth hinge 9 to the working element
5.
[0014] Each boom 4a, 4b, 4c can be operated thanks to a plurality of actuators, e.g. hydraulic
cylinders. In particular, vehicle 1 comprises a first hydraulic cylinder 11a hinged
between vehicle's body 2 and the firs extremity 4b' of the second boom, a second hydraulic
cylinder 11b hinged between the first extremity 4b' of second boom 4b and the first
extremity of third boom 4c and a third hydraulic cylinder 11c hinged between the first
extremity of third boom 4c and the working element 5.
[0015] According to a further aspect of the invention, the vehicle comprises locking means
12 configured to selectively lock the first and the second hinges 6, 7, thereby selectively
coupling together, respectively, first boom 4a to vehicle's body 2 and first boom
4a to second boom 4b.
[0016] In particular locking means 12 may be realized according to any typology of means
configured to lock the rotation of two relative rotation elements.
[0017] Accordingly, locking means 12 may be alternatively manually actuated means, e.g.
a pin to be inserted manually into a hole, or automatically actuated means, i.e. comprising
an actuator (electro-mechanical, pneumatic or hydraulic) controller by a related control
unit to selectively lock or unlock the two relative rotational elements.
[0018] Furthermore, locking means 12 may alternatively be integrated into the respective
hinge 6, 7 or realized as separate elements with respect to this latter.
[0019] According to the embodiment of figures 4A- 4B, locking means 12 are mechanically
manually operated locking means which are not integrated into the hinge 6 and comprising
a pin 13 configured to be inserted into holes 14 realized in a protrusion carried
by body 2 and a protrusion carried by first boom 4.
[0020] Such pin 13 is dimensioned to be inserted between such two set of holes 14 and it
can be fixed axially into such position thanks to an axial locking element 15 such
as a spline or a split pin, as shown. In such condition, the first boom 4 cannot move
with respect to body 2, being locked by the coupling defined by pin 13 into holes
14.
[0021] The operation of the above described construction vehicle 1 is the following.
[0022] In a first operative condition, shown in figures 2A-2B, the first hinge 6 is locked
while second hinge 7 is not locked. Accordingly, the first boom 4a has a preset fixed
position with respect to vehicle's body 2 and the remaining booms 4b, 4c can be actuated
independently so that they can reach a great working high (as shown in figure 2B).
[0023] In a second operative condition, shown in figures 3A-3B, the first hinge 6 is not
locked while second hinge 7 is locked. Accordingly, the first and second booms 4a,
4b are locked together with respect to vehicle's body 2 and first cylinder 11a actuates
the movement of both first and second booms 4a, 4b. In the meanwhile, third boom 4c
can be actuated independently so that the vehicle can reach a high digging depth (See
figure 3B).
[0024] In view of the above it is clear that the present invention is furthermore directed
to a method for operating a construction vehicle 1 and that can be implemented into
a control unit configured to control locking means 12 as described above when they
are automatically actuated.
[0025] In such a case, the construction vehicle 1 may comprise sensors configured to detect
the preset position of first boom 4a in order to proceed with the locking/unlocking
of hinges 6, 7.
Such method comprises the phases of:
- selecting a working mode of the construction vehicle 1; and
- alternatively locking first and second hinges 6, 7 according to the selected working
mode.
[0026] In view of the foregoing, the advantages of a construction vehicle 1 according to
the invention are apparent.
[0027] Thanks to the presence of the three booms 4a, 4b, 4c and the two selectively locking
hinges 6, 7 the proposed construction vehicle maintains the same, high, depth of excavation
of a normal excavator while improves its performances in reaching great heights. Accordingly,
the construction vehicle 1 is more versatile.
[0028] Furthermore, the control of the construction vehicle 1 via cylinders 11 is simpler
both for its manufacturing both for the user which need to control only two cylinders
in each working operation to move the booms (obviously the third cylinder is always
present but it's voted for moving the working element 5).
[0029] Furthermore, compared to current demolition vehicles, the proposed construction vehicle
has a less complex structure from both mechanical and hydraulic points of view, thereby
allowing to reduce manufacturing time and costs.
[0030] It is clear that modifications can be made to the described construction vehicle
1 which do not extend beyond the scope of protection defined by the claims.
[0031] For example, it is clear that the proposed shapes and typology of booms 4 and vehicle
1 are merely indicatives and may vary according to the typology of construction vehicle.
[0032] Furthermore, locking means 12, hinges 6, 7, 8, 9 or actuators 11 may be of any typology
provided that they have the same operation and scope as described in the preceding.
1. Construction vehicle (1) provided with a body (2) carried by an undercarriage (3)
configured to move on ground, said construction vehicle (1) further comprising a working
arm (4) carried by said body (2) and a working element (5) carried by said working
arm (4) in a position opposite with respect to the coupling of said working arm (4)
to said body (2), said working arm (4) comprising a plurality of booms (4a, 4b, 4c)
hinged one with respect to the other via respective hinges (6, 7, 8, 9) between said
working element (5) and said body (2), said construction vehicle (1) further comprising
locking means (12) configured to lock at least two among said hinges (6, 7, 8, 9)
thereby coupling together two among said booms (4a, 4b, 4c) or one among said booms
(4a) and said body (2);
wherein said working arm (4) comprises three booms (4a, 4b, 4c), a first boom (4a)
being hinged via a first hinge (6) to said body (2), a second boom (4b) being hinged
via a second hinge (7) to said first boom (4a) and via a third hinge (8) to a third
boom (4c), this latter being further hinged via a fourth hinge (9) to said working
element (5),
said construction vehicle (1) further comprising a first actuator cylinder (11a) between
said second boom (4b) and said body (2), a second actuator cylinder (11b) between
said second boom (4b) and said third boom (4c) and a third actuator cylinder (11c)
between said third boom (4c) and said working element (5),
said construction vehicle (1) comprising locking means (12) configured to lock said
second boom (4b) to said first boom (4a) and being characterized in that it further comprises locking means (12) configured to selectively lock said first
boom (4a) to said body (2)
2. Construction vehicle according to claim 1, wherein said locking means (12) are integrated
into the respective hinge (6, 7, 8, 9) .
3. Construction vehicle according to any of the preceding claims, wherein said locking
means (12) are realized separated with respect to the respective hinge (6, 7, 8, 9).
4. Construction vehicle according to any of the preceding claims, wherein said locking
means (12) are manually operated.
5. Construction vehicle according to any of the preceding claims, wherein said locking
means (12) are automatically operated.
6. Construction vehicle according to claim 5, further comprising a control unit configured
to control said locking means (12) on the base of preset configurations of said working
arm (4).
7. Construction vehicle according to claim 6, further comprising sensor means configured
to communicate with said control unit, which is configured to control the movement
of said booms (4a, 4b, 4c) automatically in order to reach said preset configurations
of said working arm (4).
8. Method for controlling a construction vehicle according to any of claims 5 to 7, comprising
the phases of:
• selecting a working mode of the construction vehicle (1); and
• alternatively locking said hinges according to a selected preset configurations
of said working arm (4).
1. Baufahrzeug (1) mit einem Oberwagen (2), der von einem Unterwagen (3) getragen wird,
der dazu eingerichtet ist, sich am Boden zu bewegen, wobei das Baufahrzeug (1) weiterhin
einen Arbeitsarm (4), der von dem Oberwagen (2) getragen wird, und ein Arbeitselement
(5) aufweist, das von dem Arbeitsarm (4) in einer Position gegenüber der Kopplung
des Arbeitsarmes (4) mit dem Oberwagen (2) getragen wird, wobei der Arbeitsarm (4)
eine Mehrzahl von Auslegerarmen (4a, 4b, 4c) aufweist, die jeweils zueinander über
entsprechende Gelenkeinrichtungen (6, 7, 8, 9) zwischen dem Arbeitselement (5) und
dem Oberwagen (2) schwenkverbunden sind, wobei das Baufahrzeug (1) weiterhin Arretiermittel
(12) umfasst, die dazu eingerichtet sind, mindestens zwei der Gelenkeinrichtungen
(6, 7, 8, 9) zu arretieren, sodass zwei der Auslegerarme (4a, 4b, 4c) oder einer der
Auslegerarme (4a) und der Oberwagen (2) miteinander verbunden sind;
wobei der Arbeitsarm (4) drei Auslegerarme (4a, 4b, 4c) aufweist, nämlich einen ersten
Auslegerarm (4a), der über eine erste Gelenkeinrichtung (6) mit dem Oberwagen (2)
schwenkverbunden ist, einen zweiten Auslegerarm (4b), der über eine zweite Gelenkeinrichtung
(7) mit dem ersten Auslegerarm (4a) und über eine dritte Gelenkeinrichtung (8) mit
einem dritten Auslegerarm (4c) schwenkverbunden ist, wobei letzterer weiterhin über
eine vierte Gelenkeinrichtung (9) mit dem Arbeitselement (5) schwenkverbunden ist,
wobei das Baufahrzeug (1) weiterhin einen ersten Betätigungszylinder (11a) zwischen
dem zweiten Auslegerarm (4b) und dem Oberwagen (2), einen zweiten Betätigungszylinder
(11b) zwischen dem zweiten Auslegerarm (4b) und dem dritten Auslegerarm (4c) und einen
dritten Betätigungszylinder (11c) zwischen dem dritten Auslegerarm (4c) und dem Arbeitselement
(5) aufweist,
wobei das Baufahrzeug (1) Arretiermittel (12) aufweist, die dazu eingerichtet sind,
den zweiten Auslegerarm (4b) an dem ersten Auslegerarm (4a) zu arretieren, und das
dadurch gekennzeichnet ist, dass es weiterhin Arretiermittel (12) aufweist, die dazu eingerichtet sind, wahlweise
den ersten Auslegerarm (4a) an dem Oberwagen (2) zu arretieren.
2. Baufahrzeug nach Anspruch 1, wobei die Arretiermittel (12) in den entsprechenden Gelenkeinrichtungen
(6, 7, 8, 9) integriert sind.
3. Baufahrzeug nach einem der vorhergehenden Ansprüche, wobei die Arretiermittel (12)
bezüglich der entsprechenden Gelenkeinrichtungen (6, 7, 8, 9) getrennt vorgesehen
sind.
4. Baufahrzeug nach einem der vorhergehenden Ansprüche, wobei die Arretiermittel (12)
manuell betätigbar sind.
5. Baufahrzeug nach einem der vorhergehenden Ansprüche, wobei die Arretiermittel (12)
automatisch betätigbar sind.
6. Baufahrzeug nach Anspruch 5, das des Weiteren eine Steuereinheit aufweist, die dazu
eingerichtet ist, die Arretiermittel (12) auf Basis von voreingestellten Konfigurationen
des Arbeitsarms (4) zu steuern.
7. Baufahrzeug nach Anspruch 6, das des Weiteren Sensormittel aufweist, die dazu eingerichtet
sind, mit der Steuereinheit in Kommunikationsverbindung zu sein, die dazu eingerichtet
ist, die Bewegung der Auslegerarme (4a, 4b, 4c) automatisch zu steuern, um die voreingestellten
Konfigurationen des Arbeitsarms (4) anzunehmen.
8. Verfahren zum Steuern eines Baufahrzeugs nach einem der Ansprüche 5 bis 7, mit den
folgenden Schritten:
Auswählen eines Arbeitsmodus des Baufahrzeugs (1); und
wahlweises Arretieren der Gelenkeinrichtungen gemäß einer ausgewählten voreingestellten
Konfiguration des Arbeitsarms (4).
1. Engin de chantier (1) muni d'un corps (2) porté par un châssis (3) configuré pour
se déplacer sur le sol, ledit engin de chantier (1) comprenant en outre un bras de
travail (4) porté par ledit corps (2) et un élément de travail (5) porté par ledit
bras de travail (4) dans une position opposée par rapport au couplage dudit bras de
travail (4) audit corps (2), ledit bras de travail (4) comprenant une pluralité de
flèches (4a, 4b, 4c) articulées l'une par rapport à l'autre par des charnières respectives
(6, 7, 8, 9) entre ledit élément de travail (5) et ledit corps (2), ledit engin de
chantier (1) comprenant en outre des moyens de verrouillage (12) configurés pour verrouiller
au moins deux desdites charnières (6, 7, 8, 9) couplant ainsi ensemble deux desdites
flèches (4a, 4b, 4c) ou un parmi lesdites flèches (4a) et ledit corps (2) ;
dans lequel ledit bras de travail (4) comprend trois flèches (4a, 4b, 4c), une première
flèche (4a) étant articulée par une première charnière (6) audit corps (2), une deuxième
flèche (4b) étant articulée par une deuxième charnière (7) à ladite première flèche
(4a) et par une troisième charnière (8) à une troisième flèche (4c), cette dernière
étant en outre articulée par une quatrième charnière (9) audit élément de travail
(5),
ledit engin de chantier (1) comprenant en outre un premier cylindre d'actionnement
(11a) entre ladite deuxième flèche (4b) et ledit corps (2), un deuxième cylindre d'actionnement
(11b) entre ladite deuxième flèche (4b) et ladite troisième flèche (4c) et un troisième
cylindre d'actionnement (11c) entre ladite troisième flèche (4c) et ledit élément
de travail (5),
ledit engin de chantier (1) comprenant des moyens de verrouillage (12) configurés
pour verrouiller ladite deuxième flèche (4b) à ladite première flèche (4a) et étant
caractérisé en ce qu'il comprend en outre des moyens de verrouillage (12) configurés pour verrouiller sélectivement
ladite première flèche (4a) audit corps (2).
2. Engin de chantier selon la revendication 1, dans lequel lesdits moyens de verrouillage
(12) sont intégrés dans les charnières respectives (6, 7, 8, 9).
3. Engin de chantier selon l'une quelconque des revendications précédentes, dans lequel
lesdits moyens de verrouillage (12) sont réalisés séparément par rapport à la charnière
respective (6, 7, 8, 9).
4. Engin de chantier selon l'une quelconque des revendications précédentes, dans lequel
lesdits moyens de verrouillage (12) sont actionnés manuellement.
5. Engin de chantier selon l'une quelconque des revendications précédentes, dans lequel
lesdits moyens de verrouillage (12) sont actionnés automatiquement.
6. Engin de chantier selon la revendication 5, comprenant en outre une unité de commande
configurée pour commander lesdits moyens de verrouillage (12) sur la base de configurations
prédéfinies dudit bras de travail (4).
7. Engin de chantier selon la revendication 6, comprenant en outre des moyens de détection
configurés pour communiquer avec ladite unité de commande, qui est configurée pour
commander le mouvement desdites flèches (4a, 4b, 4c) automatiquement afin d'atteindre
lesdites configurations prédéfinies dudit bras de travail (4).
8. Procédé de commande d'un engin de chantier selon l'une quelconque des revendications
5 à 7, comprenant les étapes consistant à :
• sélectionner un mode de travail de l'engin de chantier (1) ; et
• verrouiller alternativement lesdites charnières en fonction d'une configuration
prédéfinie sélectionnée dudit bras de travail (4).